Excavation construction method for underground passage close to existing building
By dividing sections according to the geological conditions of the underground passage address area and the location of the building, the three-step method or the three-step temporary arch method is used for blasting and excavation, the impact of underground passage construction on existing buildings is solved and construction safety is achieved , efficient and low cost effects.
Patent Information
- Application Number
- CN202411023518.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-29
- Publication Date
- 2024-11-05
AI Technical Summary
When building underground passages, how to design a reasonable excavation construction method to avoid affecting existing buildings, especially in the presence of different levels of surrounding rock sections and complex geological conditions, to ensure construction safety and efficiency.
According to the geological conditions of the underground passage address area and the location of existing buildings, the sections are divided and the three-step method or the three-step temporary arch method is used to perform blasting excavation. The blasting parameters are calculated and real-time dynamic monitoring is adjusted to ensure blasting Safe distance and quality.
It realizes precise control of blasting technology while ensuring the safety of existing buildings, reduces the impact of blasting vibration, improves construction efficiency and investment efficiency, and ensures that the project volume is small, the cost is low and the quality of crushing is good.
Smart Images

Figure CN118895978A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of underground passage construction, and in particular to a construction method for excavating an underground passage adjacent to an existing building. Background Art
[0002] When constructing an underground passage, if there are existing buildings nearby, a reasonable excavation construction method should be designed to avoid affecting the existing buildings. For example, the underground passage to be excavated is parallel to the existing buildings without intersection. The distance between the entrance and the building is 201.3m, the distance between the exit and the building is 191.1m, and the distance between the middle section varies from 201.3m to 210.7m to 191.1m. The relationship between the geological conditions of the site of the underground passage to be built and the location of the existing buildings is as follows: Figure 1 As shown, the total length of the IV-level surrounding rock section is 165m, the distance between the IV-level surrounding rock blasting section and the existing buildings is: 194.7m~210.7m, the total length of the V-level surrounding rock section is 132m, and the distance between the V-level surrounding rock blasting section and the existing buildings is: 191.1m~210.7m; no active faults were found in the site of the underground passage to be built, and there was no strong earthquake record in modern times. The basic seismic peak acceleration of the Class II site in this area is 0.05g, and the basic seismic response spectrum characteristic period is 0.35s. The property is a relatively stable plot, the terrain at the entrance and exit of the underground passage is relatively flat, and the natural slope is about 10°~35°. There is an artificial excavation platform on the right side of the exit of the underground passage site, and a large amount of loose artificial abandoned soil is piled up. The main component is clay soil, with a large number of boulders in some parts. The height of the abandoned soil is about 8m~10m, which is piled in two layers. The surface layer of the underground passage site is Q el+dl Silty clay, yellowish brown, hard plastic, mainly clay, followed by a small amount of breccia; the underlying bedrock is tuff, which is completely weathered: tuff, completely weathered, gray, gray-brown, the core is sandy, with strongly weathered fragments, and a layer thickness of 0.5 to 1.5m; tuff, strongly weathered, gray, with developed joints and fissures, the rock mass is broken and in fragments, and the layer thickness is 1.5 to 3.0m; tuff, slightly weathered, gray, blue-gray, the rock mass is relatively complete, and the core is short columnar and blocky. In view of the above-mentioned underground passage site conditions, determining what excavation construction method to use to excavate the underground passage to be built, and how to avoid affecting the safety of existing buildings during the excavation construction of the underground passage to be built have become technical issues that need to be solved urgently. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a construction method for excavating an underground passage adjacent to an existing building, so as to overcome the deficiencies in the above-mentioned prior art.
[0004] The technical solution of the present invention to solve the above technical problem is as follows: A construction method for excavating an underground passage near an existing building comprises the following steps:
[0005] The steps include:
[0006] S1. According to the geological conditions of the underground passage site and its position relationship with the existing buildings, the entire underground passage is divided into sections: Class IV surrounding rock section and Class V surrounding rock section. The Class IV surrounding rock section adopts the three-step method of blasting and excavation, and the Class V surrounding rock section adopts the three-step temporary invert method of blasting and excavation;
[0007] S2. Design the blasting parameters of the IV-level surrounding rock section and the V-level surrounding rock section in turn according to the geological conditions, the cross-sectional dimensions of the underground passage, the distance of the riprap, the blasting air shock wave, the particle vibration velocity, and the distance between the blasting source and the existing buildings;
[0008] The relationship between the maximum allowable charge amount, blasthole arrangement, allowable value of particle vibration velocity and the distance between the blast source and the existing building in the blasting parameters is calculated by the following formulas:
[0009] Q max =R 3 (V / K) 3 / α →→V=K(Q max 1 / 3 / R) α →→R=(K / V) 1 / α Q max 1 / 3
[0010] Where:
[0011] R is the distance from the blasting point to the protected object;
[0012] Q max It is the maximum amount of explosives in a single stage, the total amount for simultaneous blasting, and the maximum amount for delayed blasting;
[0013] V is the safe permissible vibration velocity of the mass point where the protected object is located;
[0014] K and α are coefficients and attenuation indexes related to the topography and geological conditions between the blasting point and the existing buildings. If the lithology is hard rock, K is 50-150 and α is 1.3-1.5. If the lithology is medium-hard rock, K is 150-250 and α is 1.5-1.8. If the lithology is soft rock, K is 250-350 and α is 1.8-2.0.
[0015] S3. According to the construction sequence, test blast at least three blasting points at the minimum unit consumption during the construction of each section, and adjust the blasting parameters through real-time dynamic monitoring of the impact of the test blasting on existing buildings and the test blasting effects of different rock formations to obtain the optimal blasting parameters;
[0016] S4. Implement the blasting procedure in sequence according to the optimal blasting parameters to complete the excavation of the entire underground passage.
[0017] Based on the above technical solution, the present invention can also be improved as follows.
[0018] Furthermore, for the IV level surrounding rock section, the depth of each footage is 1.5m, and for the V level surrounding rock section, the depth of each footage is 0.6m.
[0019] Furthermore, the number of blastholes and their arrangement in the IV-level surrounding rock section are determined according to the size of each section of the underground passage, and the number of blastholes and their arrangement in the V-level surrounding rock section are determined according to the size of each section of the underground passage; the blastholes include: groove holes, auxiliary holes, peripheral holes and bottom plate holes.
[0020] Furthermore, the detonation sequence during blasting is that the groove holes explode first, the auxiliary holes second, and the peripheral holes explode last. The spacing between the bottom plate holes is appropriately reduced, and the amount of explosives is appropriately increased.
[0021] Furthermore, the groove hole is located in the middle and lower part of the section, and a straight hole is used for groove cutting, and the groove hole is 0.2-0.3m deep; the opening of the peripheral hole and the bottom plate hole is 0.05-0.1m away from the edge of the section contour, and the bottom of the eye falls 0.05-0.1m outside the edge of the contour;
[0022] The drilling error of peripheral holes and slot holes is 3cm to 5cm. When drilling peripheral holes, the drill rod is kept horizontal and parallel to the axis of the underground passage, with an external 3° angle. The hole is positioned on the contour line with a deviation of no more than 5cm. The excavation step is within 10cm. The drilling accuracy error of slot holes is within 3cm. The spacing, depth and angle of blastholes are controlled. It is strictly forbidden to drill through or intersect blastholes.
[0023] The auxiliary holes are evenly distributed, the drilling holes are slightly upward, but the inclination is not greater than 1°, and the auxiliary holes are kept parallel to each other;
[0024] The bottom hole is tilted downward, and the bottom of the hole shall not exceed 10cm from the contour line. Before drilling, the residual explosives on the working surface shall be cleaned up, and it is strictly forbidden to continue drilling on the residual hole;
[0025] If the rock is incomplete, the eye depth is 0.6m to 1.2m, and if the rock is complete, the eye depth is 1.2m to 3m;
[0026] The eye spacing is 0.4m~1.0m. If the rock is hard and intact, take a smaller value. If the rock is soft and broken, take a larger value. At the same time, adjust the eye spacing according to the size of the excavation section.
[0027] Furthermore, the explosive consumption is 0.6kg / m 3 ~2kg / m 3 , if the rock layer is hard, take a large value, if the rock layer is soft, take a small value;
[0028] The charging coefficient of the groove eye is 0.6~0.8, the charging coefficient of the peripheral eye is 0.2~0.3, and the charging coefficient of the auxiliary eye is 0.5~0.7.
[0029] Furthermore, the safe distance calculation formula for blasting flying rocks is: R = 20kn 2 w;
[0030] Where:
[0031] R——the required safety distance;
[0032] 20——Experience calculation coefficient;
[0033] K——safety factor, take 1.5;
[0034] n——The action index of the largest drug package, take 1.5,
[0035] W——minimum resistance line, take W=0.8m.
[0036] Furthermore, the calculation formula of blasting air shock wave is:
[0037] Where:
[0038] Kn——coefficient related to blasting index and damage state 15~20;
[0039] ——Total amount of medicine in the largest section.
[0040] Furthermore, when charging each blast hole, high-pressure air is first used to clear the hole, and then the charge is loaded, and the charge rolls must be loaded to the bottom without leaving any gaps between the charge rolls. Then, wooden blast sticks are used to block the clay, and the blocking length is not less than 30 cm. In the interval charging, detonating cord detonators and detonating cords are used for detonation, and the interval charge bags and detonating cords are tied with bamboo pieces with thin ropes or wrapped with electrical tapes. The peripheral holes are charged at intervals, that is, the explosive rolls are tied to the bamboo pieces / strips at the designed intervals and the detonating cord is passed through the entire length. The bottom plate hole slightly increases the amount of charge and adopts forward detonation. The remaining blast holes all adopt continuous uncoupled charging, reverse detonation, and out-of-hole delay.
[0041] Furthermore, the detonating network during blasting adopts the cluster connection method, and the blasting surface is divided into several areas, with no more than 20 blastholes in each area. The tails of the detonating cord detonators in all the blastholes in the area are collected and connected into a bunch. First, two detonating cord detonators are used as detonating detonators for connection. The detonating detonators of all areas use detonators of the same grade, and the micro-difference detonation sequence of the original blasting design is not changed. The detonating detonator and the blasting detonator are connected in reverse to prevent damage to the blasting detonating cord detonator. Then, the detonating detonators of each area are collected into a bunch and detonated with two No. 8 electric detonators. Finally, the detonating wire is laid out from the working surface. The clustered network should be in a loose state, and there should be no dead knots, folds, or thinning in the network. Try to avoid network crossing, and the detonating cord should not be placed on the detonating detonator, or even close to the detonating detonator.
[0042] The beneficial effects of the present invention are:
[0043] The underground tunnel construction adopts precise control blasting technology for excavation, with short advance and multiple steps for excavation. Blasting should adopt shallow drilling, dense holes, small charge, interval detonation and other measures to reduce the impact of blasting vibration on existing buildings. While ensuring that the existing buildings are not affected, the investment can be saved as much as possible, the excavation volume is small, the project progress is fast, the blasting cost is low, the blasting volume and crushing quality can be guaranteed, the shape and distribution of the blasting pile meet the requirements, the large block rate is reduced, the amount of under-excavation of the slope is reduced, the bottom plate of the blasting area is flat, which is conducive to loading and unloading, and the slope and contour can be protected from damage. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] Figure 1 A diagram showing the relationship between the underground passage to be excavated and the existing buildings in the present invention;
[0045] Figure 2 Excavation construction drawing for the three-step construction method;
[0046] Figure 3 This is the construction drawing for excavation using the three-step temporary invert method;
[0047] Figure 4 This is a schematic diagram of the blasthole arrangement of the three-step method used for Grade IV surrounding rock;
[0048] Figure 5 This is a schematic diagram of the blasthole arrangement of the three-step method used for Class V surrounding rock;
[0049] Figure 6 This is a schematic diagram of the detonation network connection. DETAILED DESCRIPTION
[0050] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0051] Example 1
[0052] A construction method for excavating an underground passage near an existing building comprises the following steps:
[0053] S1. Divide the entire underground passage into sections according to the geological conditions of the underground passage site and its location relationship with existing buildings, such as Figure 1 As shown, they are: IV-level surrounding rock section and V-level surrounding rock section, and the more detailed divisions are: V-level surrounding rock section, IV-level surrounding rock section, V-level surrounding rock section, IV-level surrounding rock section and V-level surrounding rock section. For the IV-level surrounding rock section, the three-step method is used for blasting and excavation, while for the V-level surrounding rock section, the three-step temporary invert method is used for blasting and excavation. The lining type for the three-step method is IVb type lining, while the lining type for the three-step temporary invert method is Vc type lining.
[0054] S2. Design the blasting parameters of the IV-level surrounding rock section and the V-level surrounding rock section in turn according to the geological conditions, the cross-sectional dimensions of the underground passage, the distance of the riprap, the blasting air shock wave, the particle vibration velocity, and the distance between the blasting source and the existing buildings, including at least: blasthole distribution, corrected drilling depth, angle, spacing, row spacing, and unit consumption of explosives, etc.;
[0055] The relationship between the maximum allowable charge amount, blasthole arrangement, allowable value of particle vibration velocity and the distance between the blast source and the existing building in the blasting parameters is calculated by the following formulas:
[0056] Q max =R 3 (V / K) 3 / α →→V=K(Q max 1 / 3 / R) α →→R=(K / V) 1 / α Q max 1 / 3
[0057] Where:
[0058] R is the distance from the blasting point to the protected object, in meters (m);
[0059] It is the maximum amount of explosives in a single stage, the total amount for simultaneous blasting, and the maximum amount for delayed blasting, in kilograms (kg);
[0060] V is the safe permissible vibration velocity of the geological point where the protected object is located, in centimeters per second (cm / s);
[0061] K and α are coefficients and attenuation indexes related to the topography and geological conditions between the blasting point and the existing buildings. If the lithology is hard rock, K is 50-150 and α is 1.3-1.5. If the lithology is medium-hard rock, K is 150-250 and α is 1.5-1.8. If the lithology is soft rock, K is 250-350 and α is 1.8-2.0.
[0062] S3. According to the construction sequence, test blast at least three blasting points with the lowest unit consumption in each section during construction, and adjust the blasting parameters through real-time dynamic monitoring of the impact of the test blasting on existing buildings and the test blasting effects of different rock formations, such as: blasthole distribution, correction of drilling depth, angle, spacing, row spacing and unit consumption of explosives, so as to obtain the optimal blasting parameters. The blasting effect after each blasting must be statistically analyzed to continuously optimize the blasting parameters;
[0063] S4. Implement the blasting procedure in sequence according to the optimal blasting parameters to complete the excavation of the entire underground passage.
[0064] Example 2
[0065] This embodiment is a further optimization based on Embodiment 1, and its details are as follows:
[0066] The main construction methods for underground passages are: open excavation method, three-step method and three-step temporary invert method. The construction method for underground passages should be determined based on comprehensive research on the engineering geology and hydrogeology of the underground passage, the cross-sectional dimensions of the excavated underground passage, the buried depth of the underground passage, the difficulty of conversion of construction methods, mechanical equipment configuration and environmental constraints. For underground passages with large changes in geological conditions, the selected construction method should have greater applicability. When it is necessary to change the construction method, the principle of simple process switching and less impact on construction progress is generally not suitable for multiple construction methods. According to the actual situation of the railway, the construction methods are as follows:
[0067]
[0068] Note: “●” in the table means it is recommended for use, and “○” means it can be used. It will be determined during construction based on geological data, groundwater development and other actual conditions.
[0069] According to the actual situation on site and the construction period requirements, the underground passage excavation started from the shallow buried section and two working faces were arranged for excavation construction.
[0070] At the underground tunnel entrance and open-cut section, mechanical and static blasting are used to enter the tunnel for construction. After the tunnel gate arch is completed, blasting operations are prepared. Before blasting operations, according to the cross-sectional dimensions of the underground tunnel entrance, a wheeled movable double-layer protective frame trolley is set to support the tunnel gate wall (the length, width and height of the protective frame are greater than the size of the tunnel gate). The protective frame trolley uses 20 channel steel as the skeleton, and scissor struts and pull rods are added to the skeleton to ensure overall stability. A wheel stop limit device is set on the movable pulley group to prevent rolling. The trolley is hung with wire mesh from top to bottom, and bamboo plywood and automobile rubber tires are used as a buffer layer to make the frame guard panel. Before each blasting operation, the processed protective frame trolley is fixed to the pre-embedded wall connection parts of the tunnel gate arch (three layers are set) by using the wall connection rod, and the underground tunnel entrance is checked to ensure that all flying rocks in the underground tunnel are intercepted in the underground tunnel.
[0071] Since the underground passage to be built is parallel to the existing buildings and the distance is relatively close, attention should be paid to the impact of blasting vibrations generated by blasting construction on the existing buildings. According to the "Safety Regulations for Blasting" GB6722-2014, the amount of single-shot explosives should be strictly controlled during blasting construction to reduce the harm of blasting earthquakes to surrounding protective structures. The safety allowance standards are as follows:
[0072] Blasting vibration safety allowable standard
[0073]
[0074]
[0075] Before construction, the existing buildings should be inspected for related defects and relevant defects should be recorded. Different construction methods should be adopted according to the surrounding rock sections of the underground passage with different properties:
[0076] 1) Design of construction scheme for blasting of level IV surrounding rock
[0077] The mileage of the IV-level surrounding rock section of the underground passage is 165m in total. According to the relationship diagram of the surrounding rock sections between the new underground passage and the existing buildings, it can be clearly seen that the distance between the IV-level surrounding rock blasting section and the existing buildings is 194.7m to 210.7m, and the blasting parameters are designed;
[0078] The blasting excavation method of the IV-level surrounding rock is adopted. The three-step method can effectively control the scale of one-time blasting. For rocks with poor rock quality, timely support can be provided to ensure the structural stability of the rock wall of the underground passage. Combined with the geological conditions and characteristics of the IV-level surrounding rock section and to ensure construction safety, the three-step construction method is proposed for the IV-level surrounding rock section. Figure 2The numbers in the figure represent the excavation order. Smooth blasting holes are arranged around the tunnel wall. The appropriate number of holes is arranged according to the actual needs of different geological lithologies. The peripheral holes are generally inclined about 10 cm toward the tunnel wall to form a flat contour surface. The blasting equipment is 2# rock emulsion explosive with a diameter of Ф32mm. The detonator is non-electric millisecond detonating cord detonator.
[0079] 2) Design of construction scheme for Ⅴ-level surrounding rock blasting
[0080] The mileage of the V-level surrounding rock section of the underground passage is 132m in total. According to the relationship diagram of the surrounding rock sections between the new underground passage and the existing buildings, it can be clearly seen that the distance between the V-level surrounding rock blasting section and the existing buildings is 191.1m to 210.7m, and the blasting parameters are designed;
[0081] The blasting excavation method for the V-level surrounding rock is the three-step temporary invert method. Figure 3 The numbers in the figure represent the excavation order. Smooth blasting holes are arranged around the tunnel wall. The appropriate number of holes is arranged according to the actual needs of different geological lithologies. The peripheral holes are generally inclined about 10 cm toward the tunnel wall to form a flat contour surface. The blasting equipment is 2# rock emulsion explosive with a diameter of Ф32. The detonator is non-electric millisecond detonating cord detonator.
[0082] In this embodiment, the depth of each penetration is 1.5m for the surrounding rock section of level IV, and 0.6m for the surrounding rock section of level V.
[0083] Example 3
[0084] This embodiment is a further optimization based on Embodiment 1 or 2, and its details are as follows:
[0085] Determine the heights of the upper step, middle step and lower step in the three-step method used in the IV-level surrounding rock section, for example: the height of the upper step is 4m, the height of the middle step is 3m, and the height of the lower step is 4m;
[0086] Determine the heights of the upper step, middle step and lower step in the three-step temporary invert method used in the V-level surrounding rock section, for example: the height of the upper step is 4m, the height of the middle step is 3m, and the height of the lower step is 4m;
[0087] Then, according to the size of each section of the underground passage, determine the number of blastholes and the arrangement of blastholes in the IV-level surrounding rock section, and according to the size of each section of the underground passage, determine the number of blastholes and the arrangement of blastholes in the V-level surrounding rock section; blastholes include: slot holes, auxiliary holes, peripheral holes and bottom plate holes;
[0088] The detonation order during blasting is that the groove hole explodes first, the auxiliary hole explodes second, and the peripheral hole explodes last. The spacing between the bottom plate holes is appropriately reduced, and the charge is appropriately increased.
[0089] The blasting parameters determined in this embodiment are as follows:
[0090] 1. Determine the layout of blastholes
[0091] Due to the different rock properties, the cross-sectional dimensions of each level of surrounding rock are also different. During construction, excavation blasting should be carried out strictly in accordance with the design plan. During blasting construction, the blasters should carry out blasting operations according to the blasting instruction sheet and blasting design regulations. Before formal blasting, test blasting must be carried out on various rock layers respectively, and the amount of explosives used should be adjusted according to the test blasting results of various rock layers;
[0092] The hole arrangement method adopted in this scheme is as follows: the groove hole is located in the middle and lower part of the section, and the groove hole is cut by straight hole. The groove hole should be 0.2-0.3m deep. The hole opening of the peripheral hole and the bottom plate hole is 0.05-0.1m away from the edge of the section contour, and the bottom of the eye falls 0.05-0.1m outside the edge of the contour.
[0093] 2. Determine the blasthole parameters
[0094] a. Determine eye depth (L)
[0095] To reduce vibration, the hole depth L of the underground passage is L = 0.6 ~ 1.2m when the rock is incomplete, and L = 1.2 ~ 3m when the rock is intact. When drilling, the hole depth error cannot be greater than 0.1m. In this plan, the hole depth of the surrounding rock of level IV is 2m, and the hole depth of the surrounding rock of level V is 1m;
[0096] b. Interocular distance (a)
[0097] The value range of hole spacing is mostly 0.4-1.0m. In actual construction, it should be determined according to the specific conditions of the blasted rock. If the rock is hard and intact, a small value is used, while if the rock is soft and broken, a large value is used. At the same time, the hole spacing should be adjusted according to the specific size of the excavation section to make the hole arrangement as uniform as possible. When drilling holes, the hole spacing error cannot be greater than 0.1m;
[0098] c. Explosive consumption per unit (q)
[0099] The value of explosive consumption is related to the size of the section, the hardness and integrity of the rock, the depth of the hole and the performance of the selected explosives. According to the actual situation of this project, q = 0.6 ~ 2kg / m 3 , take a larger value when the rock layer is hard, and take a smaller value when the rock layer is soft;
[0100] d.Blasthole diameter (D)
[0101] Use air-leg pneumatic drill to drill holes, D = 42mm;
[0102] e. Coil diameter (d)
[0103] Use ordinary packaging rolls, d = 32mm;
[0104] f. Charge quantity per unit length (△)
[0105] The diameter of the medicine roll is d = 32 mm, the length of the medicine roll is l = 200 mm, and the weight of the medicine roll is 0.2 kg. When the medicine diameter is kept at 32 mm, △ = 0.2 / 200 × 1000 = 1.0 kg / m;
[0106] g. Single hole charge
[0107] The single-hole charge is first calculated based on the charge coefficient (η), hole depth (L) and charge per unit length (△) of different blastholes, that is, Then according to the amount of medicine required for the whole section (Right now ) Make appropriate adjustments to the distribution of explosives. The average charging coefficient is 0.5-0.8. During the blasting process, reasonable adjustments should be made at any time according to the blasting effect. The charging coefficients (η) of various types of blastholes are shown in the following table:
[0108] Various types of blasthole charging coefficients (η)
[0109] Blast hole name Charge coefficient (η) Groove Eye 0.60—0.80 Auxiliary hole 0.50—0.70 Peripheral Eye 0.20—0.30
[0110] h. Number of blast holes (N)
[0111]
[0112] Where N is the number of blastholes, pieces;
[0113] f---rock strength coefficient;
[0114] s--- tunnel excavation cross-sectional area, m 2 .
[0115] The above calculated charge amount is the result of theoretical calculation, and no test explosion was carried out. Therefore, at the beginning of the blasting, more than three blasting points were tested for Class IV surrounding rock and Class V surrounding rock according to the minimum unit consumption. According to the real-time dynamic monitoring and evaluation results of the existing buildings during the test explosion and the test explosion results of different rock formations, the blasting parameters such as blastholes, row spacing and unit consumption of explosives were adjusted respectively.
[0116] Summary table of blasting parameters - see the table below for blasting parameters of each section:
[0117] Schematic diagram of three-step blasthole arrangement (0.6m per cycle)
[0118]
[0119]
[0120]
[0121] Schematic diagram of three-step blasthole arrangement (1.5m per cycle)
[0122]
[0123]
[0124]
[0125] The schematic diagram of blasthole arrangement for the three-step method used for Grade IV surrounding rock is as follows: Figure 4 For the three-step temporary invert method used for Grade V surrounding rock, the schematic diagram of the blasthole arrangement is as follows: Figure 5 , the blastholes must be drilled correctly according to the designed markings. The accuracy requirements for peripheral holes and slot holes are higher than those for other holes. The eye opening error must be controlled within 3 to 5 cm. When drilling peripheral holes, the drill rod must be kept horizontal and parallel to the axis of the underground passage, with an external 3° angle. The eye opening must be positioned on the contour line with a deviation of no more than 5 cm. The excavation step must be within 10 cm. The slot hole drilling accuracy must be high, with an error within 3 cm. The blasthole spacing, depth and angle must be controlled. It is strictly forbidden to penetrate or intersect blastholes. The auxiliary holes must be evenly distributed, and the holes must be drilled slightly upward, but the inclination must not exceed 1°. The auxiliary holes must be kept parallel to each other, and the bottom plate holes must be tilted downward, but the bottom of the eyes must not exceed 10 cm from the contour line. Before drilling, the residual explosives on the working surface should be cleaned up, and it is strictly forbidden to continue drilling on the residual eyes.
[0126] The relationship between the maximum allowable charge, blasthole arrangement, allowable value of particle vibration velocity, and the distance between the explosion source and the measuring point is calculated according to the following formulas:
[0127] Q max =R 3 (V / K) 3 / α →→V=K(Q max 1 / 3 / R) α →→R=(K / V) 1 / α Q max 1 / 3
[0128] Assuming that the particle vibration speed V = 3cm / s, according to the actual situation on site, the amount of explosives used at different distances can be obtained as shown in the table. Level IV surrounding rock: K = 220, α = 1.8;
[0129] IV Level Surrounding Rock Charge Control Table
[0130]
[0131]
[0132] According to the maximum single-stage charge of various surrounding rocks and the distance from existing buildings, the vibration impact value of the underground passage to be excavated can be obtained as shown in the following table:
[0133] Underground tunnel blasting vibration calculation table
[0134]
[0135] From the data in the table, it can be seen that by using the blasting parameters in the table and blasting with different step heights and numbers of holes according to different distances, the blasting vibration is less than the safe allowable vibration speed value of 3cm / s, which is reasonable. Therefore, in daily blasting, the maximum amount of explosive in a single stage should be controlled within the allowable range to ensure safety. As the distance from the blasting point to the protected object gradually increases, the allowable The value increases accordingly.
[0136] Calculation of safe distance for flying rocks during blasting
[0137] R=20kn 2 w
[0138] Where:
[0139] R——the required safety distance, m;
[0140] 20——Experience calculation coefficient;
[0141] K——safety factor, take 1.5;
[0142] n——The action index of the largest drug package, take 1.5,
[0143] W——minimum resistance line, m, take W=0.8m.
[0144] After calculation, R=54m. Under normal circumstances, the flying stone radius is within 60m, and the mechanical safety distance is double the calculated distance, that is, 120m.
[0145] Calculation of safe distance of harmful gases
[0146]
[0147] Where:
[0148] R j ——Safety distance of toxic gas, m;
[0149] ψ——ventilation coefficient, which is 0.84 when ventilated and 1 when not ventilated. This calculation takes 1;
[0150] i——value related to the number of tunnels that can be connected under the blasting working face, take 1;
[0151] b——The amount of toxic gas produced per kilogram of explosive, generally 0.9m3 / kg;
[0152] ∑ △ ——The total volume of the blasting smoke passing through the nearby underground passage, m 3 , this time we take 2.5:
[0153] S——underground passage cross-sectional area, m 2 , this time we take 54.33m 2 ;
[0154] ——Total amount of explosives in one section, kg, this time 138.64kg;
[0155] After calculation, Rj=1.9m, that is to say, there is poisonous gas within 1.9m of the smoke after the blasting operation, so exhaust ventilation work must be done well, and only after confirming safety can you enter the work area.
[0156] Blasting air shock wave
[0157]
[0158] Where:
[0159] Kn——coefficient related to blasting index and damage state, 15~20, take 15;
[0160] ——Total charge of the largest section, kg, take 138.64kg;
[0161] After calculation, R=73.61m. According to regulations, short hole blasting was carried out to evacuate all personnel in the tunnel to prevent harm from air shock waves in the underground passage and ensure personnel safety.
[0162] To sum up, all equipment within 200m from the blasting point should be moved to a safe range, the support within 73.61m should be ensured to be firm and reliable, and the personnel in the cave should be evacuated to a secluded place outside the cave to ensure their safety. The design data of the blasting plan is only the result of theoretical calculation. Before the actual construction on site, the geological conditions, the cross-sectional profile dimensions of the underground passage, the distance of the stone throwing, the blasting air shock wave, the particle vibration speed and the distance between the blasting source and the existing buildings should be used to ensure the safety and effect of the blasting.
[0163] In order to ensure the driving safety of existing buildings, the preliminary parameters of the blasting design need to be tested on site before the blasting construction. The test blasting follows the principle of from small to large, from weak to strong. At the same time, the existing underground passages are monitored and evaluated in real time, the parameters obtained from the test blasting are analyzed, and the blasting design is further adjusted and optimized.
[0164] According to the actual situation of the parallel construction of the new underground passage and the existing buildings, and taking into account various safety factors of the project construction, the test explosion work was arranged to be carried out during the skylight period. On the one hand, it ensures the safety of train operation, and on the other hand, it reasonably adjusts and matches the maximum controlled charge design based on the safety impact data monitored on site.
[0165] Combined with the actual situation on site, the test explosion is an in-tunnel blasting. The in-tunnel test explosion is carried out 8 meters into the tunnel at the junction of the light and dark parts of the newly built underground passage. According to the changes in the surrounding rock grade and the analysis of the changes in the monitoring data of the existing railway, the test explosion work in different sections is reasonably arranged and organized. According to the requirements of the blasting design plan, various protective measures are strictly implemented. The test explosion is carried out in three times. The first test explosion is filled with 60% of the pre-designed charge, the second test explosion is filled with 80% of the pre-designed charge, and the third test explosion is filled with the pre-designed charge. Monitoring work is carried out while the test explosions are carried out.
[0166] Example 4
[0167] This embodiment is a further optimization based on Embodiment 1, 2 or 3, and its details are as follows:
[0168] The explosives used are No. 2 rock emulsion explosives, with a diameter of 32m, a length of 200mm, a single roll weight of 0.2kg, millisecond delay detonator (for inside the hole), and detonator instantaneous detonator (for network connection outside the hole). The main millisecond detonator delay time and segment mark are as follows:
[0169]
[0170]
[0171] Charge structure
[0172] The peripheral holes use spaced charging, that is, the explosive rolls are tied to bamboo pieces (strips) at designed intervals and the detonating cord is passed through the entire length. The amount of explosives is slightly increased at the bottom of the hole, and forward detonation is used. The remaining blast holes use continuous uncoupled charging (coupled charging can be used when necessary), reverse detonation, and outside-hole delay.
[0173] Detonation sequence
[0174] The groove holes will explode first, followed by the auxiliary holes, and finally the peripheral holes. The spacing between the bottom plate holes can be appropriately reduced, and the amount of explosives can be appropriately increased to play the role of "turning over slag" to facilitate slag removal and transportation.
[0175] The detonation network adopts the cluster connection method, dividing the blasting surface into several areas, with no more than 20 blastholes in each area. The tails of the detonating cord detonators in all the blastholes in the area are collected and connected into a bundle. First, two detonating cord detonators are used as priming detonators for connection. The priming detonators of all areas use the same segment detonators, and the micro-difference detonation sequence of the original blasting design is not changed. The priming detonator and the blasting detonator are reversely connected to prevent damage to the blasting detonating cord detonator. Then, the priming detonators of each area are collected into a bundle and detonated with two No. 8 electric detonators. Finally, the detonating wire is laid out from the working surface.
[0176] The cluster network should be in a relaxed state, without any dead knots, folds or thinning in the network, and try to avoid network crossing. The detonating cord should not be placed on the detonating fuse, or even close to the detonating fuse;
[0177] During the processing of explosive packages, according to the cross-sectional dimensions and network connection requirements, sufficient length is reserved for the detonator of the detonating cord in advance. This time, multiple groups of clusters are connected in one working section. Instantaneous detonators (reverse installation) are used as detonating detonators. They are wrapped with adhesive tape at a distance of more than 15 cm from the free end of a cluster of detonating cords. After filling according to the sections of various types of blastholes, clusters of 10 rounds are connected in parallel. See the network connection diagram Figure 6 .
[0178] Blast hole blockage
[0179] After all the blastholes are charged, the orifices of the powder bags should be filled and blocked with gun mud. The blocking material should be made of materials with large internal friction, easy to compact and airtight, and sufficient blocking length should be ensured, which should generally be 10% to 15% greater than the length of the resistance line. The blockage should be dense, and the direction of the blasthole should be at an angle of 30 degrees to the vertical air surface. Gun mud can be made of clay (or loess) without fine stone particles. The moisture content should be enough to be shaped by hand. It is best to use a mixed sand mixture of 1:2 to 1:3 (clay: coarse sand) with a water content of about 20%, and gently press it in layers.
[0180] During the underground passage blasting construction, the underground passage blasting design and hole layout should be used as the basis. The blaster should report to the on-site blasting technicians to make reasonable adjustments to the parameters based on the actual situation of the working face (mainly including the cross-sectional dimensions and geological conditions, etc.) and combined with the effect of the previous cycle blasting. During the blasting, the on-site blasting technicians should make reasonable arrangements for the depth of each advance, the size of each cross-sectional area, the detonation sequence and sections based on the adjusted parameters and the maximum amount of explosives allowed for one detonation obtained from the blasting seismic verification. Controlled blasting should be used during the underground passage blasting construction, the amount of explosives should be strictly controlled, and effective measures should be taken to prevent or reduce the occurrence of blasting accidents.
[0181] Shallow hole blasting blind shot treatment:
[0182] ⑴ When the detonation network is confirmed to be intact after inspection, it can be re-detonated;
[0183] (2) Parallel holes can be drilled for charging and blasting, and the distance between parallel holes and blind shots should not be less than 0.3m;
[0184] ⑶ You can use tools made of wood, bamboo or other materials that do not produce sparks to gently remove the fillings in the blasthole and use explosive bags to induce explosion;
[0185] (4) Blind shell fillings and explosives can be blown out from a safe location using a remotely controlled wind and water nozzle, but measures should be taken to recover the detonators;
[0186] ⑸ Blind shots should be handled during the shift. If the shift cannot handle it or has not completed the handling, the blind shot situation (number of blind shots, direction of the borehole, amount of explosives and location of the explosive package, handling method and handling opinions) should be clearly handed over on site and the next shift will continue to handle it.
[0187] After dealing with a blind shot, the blast pile should be carefully checked and the remaining blasting materials should be collected and destroyed. Before it can be confirmed that there is no residual blasting material in the blast pile, preventive measures should be taken. The handler should fill out a registration card or submit a report to explain the cause of the blind shot, the method and result of the treatment, and the preventive measures. After each blast, the blaster should fill out the blasting record, and the construction team should promptly clean up the rubble on the traffic channel to ensure smooth traffic.
[0188] After all the charging work is completed, the network is connected and the detonation network adopts the cluster connection method, that is, a duplex network, to ensure the reliability and accuracy of detonation.
[0189] In order to reduce the impact of blasting vibration on buildings around the blasting area, the following measures should be taken in a targeted manner according to the relative position, distance and distribution of the protected target and the blasting point:
[0190] 1) Adopt multi-stage micro-difference detonation technology to change energy release from one time to multiple releases, reduce the energy of each blast, and change the seismic wave with large amplitude into multiple seismic waves with small amplitude, thereby reducing the intensity of blasting vibration. The more segments, the smaller the amplitude and the smaller the blasting vibration. The intensity of seismic waves of micro-difference blasting depends on the amount of the largest segment;
[0191] 2) Strictly load and segment according to the maximum explosive quantity of one section (time) determined by the earthquake resistance of the protected target and its relative distance from the explosion point, and control the vibration speed of the ground particles caused by the blasting vibration to be below the vibration speed allowed by the surrounding facilities to be protected (i.e., the safe vibration speed), so as to ensure the safety of the protected target;
[0192] 3) Reasonable selection of blasting parameters and unit explosive consumption. Too high unit explosive consumption will produce strong vibration and air shock waves, while too low unit explosive consumption will cause rock breakage and loosening, and most of the energy will be consumed in vibration. Therefore, reasonable blasting parameters and unit explosive consumption should be determined through on-site tests.
[0193] Air supply, water supply and power supply are three essential facilities for underground tunnel excavation. Pressure, ventilation and drainage must be guaranteed to be smooth and meet supply needs;
[0194] ①、Pressure air
[0195] Install 20m away from the shallow open excavation of the underground passage 100m away 3 / min fixed air compressor, connected to seamless high-pressure steel pipe and entering the underground passage, a three-way or four-way valve is installed 50m to 100m away from the blasting face to connect to the high-pressure soft air duct, which is used for drilling holes by the rock drill and for temporary support of wet shotcrete;
[0196] ② Water supply
[0197] Since rock drilling and temporary anchor spraying support in underground passages require wet rock drills and wet shotcrete, the water supply pipe should be connected to the underground passage 50 to 60 meters away from the tunnel face, and a joint should be installed to supply water for rock drilling and anchor spraying;
[0198] ③. Power supply
[0199] The power distribution box of the power supply line should be installed 300m away from the blasting face. When supplying electricity to various equipment, it should be "three-phase five-wire, one machine, one switch, one leakage, one box, and one lock". The metal shell of all electrical equipment should be grounded for protection. The lighting voltage in the underground passage is 36V, and the line should be connected to the fixed hooks on both sides of the underground passage.
[0200] ④. Ventilation
[0201] According to the actual situation of the underground passage, natural ventilation can be adopted without fans;
[0202] ⑤. Drainage
[0203] For drainage outside the tunnel, intercepting ditches are dug at an appropriate distance above the tunnel entrance and exit to connect to the drainage ditch outside the tunnel. The drainage inside the tunnel is mainly industrial sewage, fissure water in the surrounding rock, and water gushing from the rock strata in some areas. These water flows are discharged through the drainage ditches temporarily dug on both sides of the underground passage during the excavation process and the longitudinal slope of the underground passage. A sedimentation tank is set at the entrance of the underground passage, and the water is discharged after sedimentation. The reverse slope construction is used. During excavation, sufficient pumping equipment should be equipped according to the actual water gushing requirements of the tunnel body, and good pumping work should be done during construction to ensure that there is no water accumulation on the working surface.
[0204] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.
Claims
1. A construction method for excavating an underground passage near an existing building, characterized in that: The steps include: S1. According to the geological conditions of the underground passage site and its position relationship with the existing buildings, the entire underground passage is divided into sections: Class IV surrounding rock section and Class V surrounding rock section. The Class IV surrounding rock section adopts the three-step method of blasting and excavation, and the Class V surrounding rock section adopts the three-step temporary invert method of blasting and excavation; S2. Design the blasting parameters of the IV-level surrounding rock section and the V-level surrounding rock section in turn according to the geological conditions, the cross-sectional dimensions of the underground passage, the distance of the riprap, the blasting air shock wave, the particle vibration velocity, and the distance between the blasting source and the existing buildings; The relationship between the maximum allowable charge amount, blasthole arrangement, allowable value of particle vibration velocity and the distance between the blast source and the existing building in the blasting parameters is calculated by the following formulas: Q max =R 3 (V / K) 3 / α →→V=K(Q max 1 / 3 / R) α →→R=(K / V) 1 / α Q max 1 / 3 Where: R is the distance from the blasting point to the protected object; Q max It is the maximum amount of explosives in a single stage, the total amount for simultaneous blasting, and the maximum amount for delayed blasting; V is the safe permissible vibration velocity of the mass point where the protected object is located; K and α are coefficients and attenuation indexes related to the topography and geological conditions between the blasting point and the existing buildings. If the lithology is hard rock, K is 50-150 and α is 1.3-1.
5. If the lithology is medium-hard rock, K is 150-250 and α is 1.5-1.
8. If the lithology is soft rock, K is 250-350 and α is 1.8-2.
0. S3. According to the construction sequence, test blast at least three blasting points at the minimum unit consumption during the construction of each section, and adjust the blasting parameters through real-time dynamic monitoring of the impact of the test blasting on existing buildings and the test blasting effects of different rock formations to obtain the optimal blasting parameters; S4. Implement the blasting procedure in sequence according to the optimal blasting parameters to complete the excavation of the entire underground passage.
2. The method for excavating an underground passage near an existing building according to claim 1, characterized in that: For the IV grade surrounding rock section, the depth of each advancement is 1.5m, and for the V grade surrounding rock section, the depth of each advancement is 0.6m.
3. A construction method for excavating an underground passage near an existing building according to claim 1 or 2, characterized in that: According to the size of each section of the underground passage, the number of blastholes and the blasthole arrangement form of the Grade IV surrounding rock section are determined, and according to the size of each section of the underground passage, the number of blastholes and the blasthole arrangement form of the Grade V surrounding rock section are determined; the blastholes include: groove holes, auxiliary holes, peripheral holes and bottom plate holes.
4. A construction method for excavating an underground passage near an existing building according to claim 1, 2 or 3, characterized in that: During blasting, the detonation sequence is that the groove hole explodes first, followed by the auxiliary hole, and the peripheral hole explodes last. The spacing between the bottom plate holes is appropriately reduced, and the amount of explosives is appropriately increased.
5. A construction method for excavating an underground passage near an existing building according to claim 3 or 4, characterized in that: The cutout hole is located in the middle and lower part of the section, and is cut by straight holes. The cutout hole is 0.2-0.3m deep. The openings of the peripheral holes and the bottom plate holes are 0.05-0.1m away from the edge of the section contour, and the bottom of the eyes is 0.05-0.1m outside the edge of the contour. The drilling error of peripheral holes and slot holes is 3cm to 5cm. When drilling peripheral holes, the drill rod is kept horizontal and parallel to the axis of the underground passage, with an external 3° angle. The hole is positioned on the contour line with a deviation of no more than 5cm. The excavation step is within 10cm. The drilling accuracy error of slot holes is within 3cm. The spacing, depth and angle of blastholes are controlled. It is strictly forbidden to drill through or intersect blastholes. The auxiliary holes are evenly distributed, the drilling holes are slightly upward, but the inclination is not greater than 1°, and the auxiliary holes are kept parallel to each other; The bottom hole is tilted downward, and the bottom of the hole shall not exceed 10cm from the contour line. Before drilling, the residual explosives on the working surface shall be cleaned up, and it is strictly forbidden to continue drilling on the residual hole; If the rock is incomplete, the eye depth is 0.6m to 1.2m, and if the rock is complete, the eye depth is 1.2m to 3m; The eye spacing is 0.4m~1.0m. If the rock is hard and intact, take a smaller value. If the rock is soft and broken, take a larger value. At the same time, adjust the eye spacing according to the size of the excavation section.
6. The method for excavating an underground passage near an existing building according to claim 5, characterized in that: The unit consumption of explosives is 0.6kg / m 3 ~2kg / m 3 , if the rock layer is hard, take a large value, if the rock layer is soft, take a small value; The charging coefficient of the groove eye is 0.6~0.8, the charging coefficient of the peripheral eye is 0.2~0.3, and the charging coefficient of the auxiliary eye is 0.5~0.
7.
7. The method for excavating an underground passage near an existing building according to claim 1, characterized in that: The safe distance calculation formula for blasting flying rocks is: R = 20kn 2 w; Where: R——the required safety distance; 20——Experience calculation coefficient; K——safety factor, take 1.5; n——The action index of the largest drug package, take 1.5, W——minimum resistance line, take W=0.8m.
8. The method for excavating an underground passage near an existing building according to claim 1, characterized in that: The calculation formula of blasting air shock wave is: Where: Kn——coefficient related to blasting index and damage state 15~20; ——Total amount of medicine in the largest section.
9. The method for excavating an underground passage near an existing building according to claim 1, characterized in that: When charging each blast hole, first use high-pressure air to clear the hole, then load the explosives, and the explosive rolls must be loaded to the bottom without leaving any gaps between the rolls. Then use wooden sticks to block the clay, and the length of the blockage should not be less than 30 cm. In the interval charging, use detonating cord detonators and detonating cords for detonation. The interval explosive bags and detonating cords are tied with bamboo strips with thin ropes or wrapped with electrical tape. The peripheral holes use interval charging, that is, the explosive rolls are tied to the bamboo strips / strips at the designed intervals and the detonating cord is passed through the entire length. The bottom plate hole slightly increases the amount of explosives and adopts forward detonation. The remaining blast holes use continuous uncoupled charging, reverse detonation, and out-of-hole delay.
10. The method for excavating an underground passage near an existing building according to claim 1, characterized in that: The detonation network in blasting adopts the cluster connection method, dividing the blasting surface into several areas, with no more than 20 blastholes in each area. The tails of the detonating cord detonators in all the blastholes in the area are collected and connected into a bundle. First, two detonating cord detonators are used as priming detonators for connection. The priming detonators of all areas use the same segment detonators, and the micro-difference detonation sequence of the original blasting design is not changed. The priming detonator and the blasting detonator are reversely connected to prevent damage to the blasting detonating cord detonator. Then, the priming detonators of each area are collected into a bundle and detonated with two No. 8 electric detonators. Finally, the detonating wire is laid out from the working surface; The clustered network should be in a relaxed state, without any knots, folds or thinning in the network, and network crossing should be avoided as much as possible. The detonating cord should not be placed against the detonating cap, or even close to the detonating cap.