Loose body structure construction disturbance monitoring and early warning device

By using a combination device of pallets, fitting vibration and shaking warnings in loose structure construction, the precise monitoring and early warning of loose structure disturbances is achieved, and the problem of insufficient detection accuracy in the prior art is solved, and the Construction safety.

CN118898889APending Publication Date: 2024-11-05HEBEI UNIV OF ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411281860.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

The detection accuracy of existing loose structures is not accurate enough, resulting in slight disturbances that may cause landslide accidents, and there is a lack of effective early warning measures.

Method used

A monitoring and early warning device including a pallet warning device, a fitted shock warning device and a shaking warning device is designed to provide more accurate disturbance monitoring through internal vibration detection and external drop detection, combined with analytical warning.

Benefits of technology

It improves construction safety, reduces construction risks, makes up for the shortcomings of traditional inspection methods being too macro and insufficient early warning sensitivity, and can detect disturbances in specific structural surfaces from multiple angles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118898889A_ABST
    Figure CN118898889A_ABST
Patent Text Reader

Abstract

The invention discloses a loose body structure construction disturbance monitoring and early warning device, and relates to the technical field of loose body structure construction early warning equipment.The loose body structure construction disturbance monitoring and early warning device comprises a bearing disc early warning device, an attached type vibration sense early warning device, a shaking early warning device, a bearing table and a control system; the lower end of the connecting column is installed on the bearing base, the shaking early warning device is installed on the connecting column, the two ends of the shaking early warning device are each connected with a connecting support, a bearing disc early warning device is installed on each connecting support, the attaching type vibration sense early warning device is installed at the upper end of the connecting column, and the attaching type vibration sense early warning device is installed at the lower end of the connecting column. The bearing disc early warning device, the attaching type vibration sense early warning device and the shaking early warning device are all electrically connected with the control system. The device is provided with the bearing disc early warning device, the attaching type vibration sense early warning device and the shaking early warning device, and the monitoring and early warning effects on the loose body structure can be achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of loose body structure construction early warning equipment, and in particular to a loose body structure construction disturbance monitoring and early warning device. Background Art

[0002] The existing construction technology, when processing and reconstructing loose body structures, mainly relies on the joint maintenance of all members during the entire construction process. In order to protect the safety of construction personnel, the commonly used detection and warning measures during construction are generally personnel planning and electronic shooting and detection with high-definition cameras. Its characteristics are that the detection range is relatively wide, but the detection accuracy is not accurate enough. The construction of loose body structures is generally seen in the construction of mountain walls and tunnel walls. During construction, the rock walls are loose and unstable, and the internal cracks and stress conditions of the structure are complex. Minor disturbances may cause landslides, resulting in irreversible consequences.

[0003] Based on the above characteristics, the safety inspection of loose structure construction requires more accurate monitoring devices to reduce the occurrence of accidents. Summary of the invention

[0004] The purpose of the present invention is to provide a loose body structure construction disturbance monitoring and early warning device to solve the problems existing in the above-mentioned prior art, which can be used to monitor and warn loose body structures, thereby ensuring the safety of construction.

[0005] To achieve the above object, the present invention provides the following solutions: The present invention discloses a loose body structure construction disturbance monitoring and early warning device, comprising a bearing tray early warning device, a close-fitting vibration early warning device, a shaking early warning device, a bearing platform and a control system, the bearing platform comprising a bearing base and a connecting column, the lower end of the connecting column is installed on the bearing base, the shaking early warning device is installed on the connecting column, the two ends of the shaking early warning device are respectively connected to a connecting bracket, each of the connecting brackets is installed with a bearing tray early warning device, the close-fitting vibration early warning device is installed at the upper end of the connecting column, the bearing tray early warning device, the close-fitting vibration early warning device and the shaking early warning device are all electrically connected to the control system.

[0006] Preferably, two connecting columns are provided.

[0007] Preferably, the tray alarm device comprises a tray body, the inner cavity of the tray body is provided with a ballast plate, a spring, a pressure sensor and a tray alarm, the ballast plate and the pressure sensor are respectively fixed to the upper and lower ends of the spring, the tray alarm is installed at the lower end of the pressure sensor, and the pressure sensor and the tray alarm are both electrically connected to the control system; A tray receiving slot is provided at the lower end of the tray receiving body, and the upper end of the connecting bracket can be inserted into the tray receiving slot.

[0008] Preferably, a shape measuring layer is provided at the upper end of the pressure plate, and the shape measuring layer includes a shape measuring frame, and the shape measuring frame is fixed to the upper end of the supporting tray body. A plurality of shape measuring through holes are evenly distributed on the shape measuring frame, and a shape measuring column is slidably connected in each of the shape measuring through holes.

[0009] Preferably, the fitted vibration warning device comprises a fitted warning body, on which a fitted frame, a fitted vibration sensor and a fitted warning alarm are provided, the fitted frame is provided with a plurality of fitted through holes, each of the fitted through holes is slidably connected with a fitted part, the fitted part can be used to contact with a working interface, the fitted vibration sensor is arranged at one end of the fitted frame away from the working interface, the fitted vibration sensor is in contact with the fitted frame, and the fitted vibration sensor and the fitted warning alarm are both electrically connected to the control system; A fitting warning slot is provided at the lower end of the fitting warning body, and the upper end of the connecting column is inserted into the fitting warning slot.

[0010] Preferably, a protective pad is provided on the upper ends of the fitting frame and the fitting vibration sensor, and the protective pad is made of rubber.

[0011] Preferably, the shaking warning device includes a shaking body, and the two connecting brackets are respectively fixed on both sides of the shaking body. A shaking vibration sensor and a shaking alarm are provided in the shaking body, and the shaking vibration sensor and the shaking alarm are both electrically connected to the control system.

[0012] Preferably, the receiving base includes an inner base and an outer base, and the inner base is arranged on the inner circle of the outer base; The material of the inner base is steel; the material of the outer base is concrete; The inner base is provided with a base slot, and the lower end of the connecting column is plugged into the base slot.

[0013] Preferably, the connecting column comprises an upper connecting column and a lower connecting column, and an arc-shaped groove is provided at the lower end of the upper connecting column and the upper end of the lower connecting column, and the upper connecting column and the lower connecting column are clamped together.

[0014] Preferably, the upper connecting column is provided with a connecting groove, the connecting groove is provided with a plurality of snap-in holes, the lower connecting column is hinged with a connecting clamping plate, the connecting clamping plate is provided with a plurality of snap-in protrusions, and the snap-in protrusions are snap-in with the snap-in holes.

[0015] Compared with the prior art, the present invention has achieved the following technical effects: The present invention is provided with a tray warning device, a close-fitting vibration warning device and a shaking warning device, wherein the tray warning device is used to catch falling rocks and can measure the gravity of falling rocks; the close-fitting vibration warning device has a good fit with the working interface to better transmit the vibration inside the working interface to prevent the insensitive warning effect caused by insufficient fit; the shaking warning device can be used to sense the severity of the falling rock situation.

[0016] The present invention adopts a combination of internal vibration detection, external falling object detection and analysis and warning for the detection and early warning mode of loose body structure construction disturbance. Its advantage is that it can detect the disturbance of specific structural surface from multiple angles, reduce the hidden danger of construction safety, and make up for the shortcomings of traditional detection methods that are too macroscopic and lack of early warning sensitivity. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 It is a structural schematic diagram of a loose body structure construction disturbance monitoring and early warning device according to an embodiment of the present invention; Figure 2 It is a structural schematic diagram of a support tray warning device in a loose body structure construction disturbance monitoring and warning device according to an embodiment of the present invention; Figure 3 A top view of a shape measurement layer in a loose body structure construction disturbance monitoring and early warning device according to an embodiment of the present invention; Figure 4 A bottom view of the support tray slot in the loose body structure construction disturbance monitoring and early warning device according to an embodiment of the present invention; Figure 5 It is a structural schematic diagram of a close-fitting vibration sensing warning device in a loose body structure construction disturbance monitoring and early warning device according to an embodiment of the present invention; Figure 6 It is a structural schematic diagram of a close-fitting vibration sensing warning device in a loose body structure construction disturbance monitoring and early warning device according to an embodiment of the present invention; Figure 7 It is a structural schematic diagram of a sway warning device in a loose body structure construction disturbance monitoring and early warning device according to an embodiment of the present invention; Figure 8 It is a structural schematic diagram of a receiving platform in a loose body structure construction disturbance monitoring and early warning device according to an embodiment of the present invention; In the figure: 1-tray warning device; 101-tray body; 102-shape measuring layer; 103-ballast plate; 104-spring; 105-pressure sensor; 106-tray alarm; 107-tray slot; 2-fitting vibration warning device; 201-fitting warning body; 202-fitting frame; 203-protection pad; 204-fitting vibration sensor; 205-fitting warning alarm; 206-fitting warning slot; 20 7-fitting part; 208-working interface; 3-shake warning device; 301-shake main body; 302-connecting bracket; 303-shake vibration sensor; 304-shake alarm; 4-supporting platform; 401-supporting base; 4011-inner base; 4012-outer base; 4013-base slot; 402-connecting column; 4021-connecting upper column; 4022-connecting lower column; 403-connecting groove; 404-connecting card plate. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0020] The purpose of the present invention is to provide a loose body structure construction disturbance monitoring and early warning device to solve the problems existing in the above-mentioned prior art, which can be used to monitor and warn loose body structures, thereby ensuring the safety of construction.

[0021] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0022] like Figure 1-Figure 8As shown, the present invention provides a loose body structure construction disturbance monitoring and early warning device, including a tray early warning device 1, a fitting vibration early warning device 2, a shaking early warning device 3, a receiving platform 4 and a control system. Among them, the receiving platform 4 includes a receiving base 401 and a connecting column 402, the lower end of the connecting column 402 is installed on the receiving base 401, and the receiving platform 4 plays the role of supporting various devices. The shaking early warning device 3 is installed on the connecting column 402, and the shaking early warning device 3 is used to monitor the severity of falling rocks. The two ends of the shaking early warning device 3 are respectively connected to an L-shaped connecting bracket 302, and each connecting bracket 302 is installed with a tray early warning device 1, and the tray early warning device 1 is used to catch the falling rocks from above and measure their gravity. The fitting vibration early warning device 2 is installed at the upper end of the connecting column 402, and the fitting vibration early warning device 2 is in contact with the working interface 208, and is used to measure the vibration inside the working interface 208. The tray warning device 1, the contact vibration warning device 2 and the shaking warning device 3 are all electrically connected to the control system, and the measurement data of each device can be transmitted to the control system in time, and the control system will perform corresponding control.

[0023] In actual use, it is only necessary to install the loose body structure construction disturbance monitoring and early warning device on a side wall of an environment such as a rock wall or a mountain, ensure the stability of the device and the loose body structure construction disturbance monitoring and early warning device must be in contact with the working interface 208, so that monitoring work can be carried out. During the monitoring process, the tray early warning device 1 is used to catch the falling rocks and can measure the gravity of the falling rocks; the fitted vibration early warning device 2 has a good fit with the working interface 208 to better transmit the vibration inside the working interface 208; the shaking early warning device 3 can be used to sense the severity of the falling rocks. In addition, the tray early warning device 1, the fitted vibration early warning device 2 and the shaking early warning device 3 can transmit the corresponding monitoring data to the control system for data processing and related control.

[0024] In this embodiment, two connecting posts 402 are provided, and the two connecting posts 402 are respectively used to fix the front and rear ends of the shaking alarm 3. The reason for this arrangement is that the connecting brackets 302 are fixed at the two ends of the middle part of the shaking alarm 3. In actual use, the two connecting brackets 302 will inevitably shake, and the connecting posts 402 provided at the front and rear ends of the shaking alarm 3 will not cause any impact on the connecting brackets 302.

[0025] In this embodiment, if Figure 2As shown, the tray alarm 1 includes a tray body 101, and the tray body 101 is made of a relatively strong rigid material, including but not limited to stainless steel. The tray body 101 is provided with an inner cavity and has an upper end opening, and the inner cavity of the tray body 101 is provided with a ballast plate 103, a spring 104, a pressure sensor 105 and a tray alarm 106 from top to bottom. Specifically, the ballast plate 103 and the pressure sensor 105 are respectively fixed to the upper and lower ends of the spring 104, and the tray alarm 106 is installed at the lower end of the pressure sensor 105. The pressure sensor 105 and the tray alarm 106 are both electrically connected to the control system.

[0026] In the actual process, the ballast plate 103 can transfer the ballast force generated by the falling object to the pressure sensor 105 below through the spring 104, and can measure and analyze the instantaneous force generated by the falling object and the gravity after subsequent stabilization, and transmit the relevant measurement data to the control system. When the pressure reaches the preset value, the control system controls the tray alarm 106 to sound an alarm to remind on-site staff.

[0027] like Figure 4 As shown, a rectangular tray slot 107 is provided at the lower end of the tray body 101 , and the upper end of the connecting bracket 302 can be inserted into the tray slot 107 , so that the tray alarm 106 and the shaking warning device 3 can form a whole through the connecting bracket 302 .

[0028] In this embodiment, a shape measuring layer 102 is provided on the upper end of the pressure plate 103. The specific structure of the shape measuring layer 102 is as follows: Figure 3 As shown, the shape measurement layer 102 includes a rectangular shape measurement frame, which is fixed to the upper end of the tray body 101 so that the shape measurement frame does not move up and down during actual use. A plurality of shape measurement through holes are evenly distributed on the shape measurement frame, and a shape measurement column is slidably connected in each shape measurement through hole. The shape measurement column can slide up and down in the shape measurement through hole, and the cross-sectional shape of the shape measurement column is the same as the cross-sectional shape of the shape measurement through hole, which can be circular, rectangular or other shapes.

[0029] When there is a falling object, the falling object will first fall onto the shape measuring layer 102, and the shape measuring columns corresponding to the shape of the falling object in the shape measuring layer 102 will move downward and transfer the pressure to the ballast plate 103. The shape measuring layer 102 is provided for the following purposes: firstly, the shape and volume of the falling object can be measured; secondly, it is used to buffer the falling object to prevent it from damaging the ballast plate 103 or even the pressure sensor 105 due to excessive impact force.

[0030] In this embodiment, if Figure 5As shown, the fitted shock warning device 2 includes a fitted warning body 201, and a step structure is provided at the upper end of the fitted warning body 201. The stepped structure on the fitted warning body 201 is provided with a fitted frame 202, a fitted vibration sensor 204 and a fitted warning alarm 205. The fitted frame 202 is provided with a plurality of horizontally fitted through holes, and each of the fitted through holes is slidably connected with a fitting member 207, and the fitting member 207 is a columnar structure with a cross section identical to that of the fitted through hole, including but not limited to a cylinder or a rectangular column. When the fitting member 207 is actually used, one end can be used to contact with a working interface 208, and the working interface 208 can be a mountain side wall or a rock wall. The fitted vibration sensor 204 is arranged at one end of the fitted frame 202 away from the working interface 208, and the fitted vibration sensor 204 is in contact with the fitted frame 202. When the fitted frame 202 has a sense of shock, it will be transmitted to the fitted vibration sensor 204. The lamination vibration sensor 204 and the lamination early warning alarm 205 are both electrically connected to the control system.

[0031] When the bonded vibration warning device 2 is working, firstly all the bonded parts 207 are pulled out in the direction away from the bonded vibration sensor 204, and then the whole device is attached to the working interface 208 for installation. Figure 2 As shown, each of the bonding pieces 207 may be longer or shorter, thus ensuring that each of the bonding pieces 207 is tightly bonded to the working interface 208. When there is a vibration transmission inside the working interface 208, the vibration will be transmitted to the bonding vibration sensor 204 through the bonding piece 207 and the bonding frame 202, and the bonding vibration sensor 204 will collect and transmit it to the control system. When the vibration is greater than the preset value in the control system, the control system will control the bonding early warning alarm 205 to sound an alarm to remind the on-site staff.

[0032] The lower end of the fitting warning body 201 is provided with two fitting warning slots 206 , and the upper ends of the two connecting columns 402 are respectively inserted into the two fitting warning slots 206 , thereby achieving the fixation of the fitting type shock sensing warning device 2 .

[0033] In this embodiment, a protective pad 203 is provided on the upper end of the bonding frame 202 and the bonding vibration sensor 204 to protect the bonding vibration sensor 204 below and prevent damage. The material of the protective pad 203 includes but is not limited to rubber material.

[0034] In this embodiment, if Figure 7As shown, the shaking alarm 3 includes a shaking body 301, and the shaking body 301 is in the shape of a dumbbell as a whole, with large diameters of the cylinders at both ends and small diameters of the cylinders in the middle. Two connecting brackets 302 are respectively fixed on both sides of the shaking body 301, and a shaking vibration sensor 303 and a shaking alarm 304 are arranged in the shaking body 301. Specifically, the shaking vibration sensor 303 is installed at the center of the shaking body 301, and the shaking alarm 304 is arranged at one end of the shaking body 301. And the shaking vibration sensor 303 and the shaking alarm 304 are both electrically connected to the control system.

[0035] In actual use, the control system monitors the value of the shaking vibration sensor 303. If the detection value of the shaking vibration sensor 303 is large, it means that the falling objects at the tray warning device 1 on both sides are many and frequent; on the contrary, if the value is small, it means that the falling objects are few. If the value is greater than the preset value, the control system controls the shaking alarm 304 to issue an alarm to remind the on-site staff. Of course, corresponding early warning alarms can also be given for different shaking cycles.

[0036] In this embodiment, if Figure 8 As shown, the receiving base 401 includes an inner base 4011 and an outer base 4012 , the inner base 4011 is a rectangular structure, the outer base 4012 is a U-shaped structure, and the inner base 4011 is arranged on the inner circle of the outer base 4012 .

[0037] Furthermore, the material of the inner base 4011 is steel, and the material of the outer base 4012 is concrete, specifically a concrete grouting block.

[0038] Two base slots 4013 are provided on the inner base 4011 , and the lower ends of the two connecting posts 402 are respectively plugged into the two base slots 4013 , so as to fix the connecting posts 402 .

[0039] In this embodiment, if Figure 8 As shown, the connecting column 402 includes an upper connecting column 4021 and a lower connecting column 4022. The lower end of the upper connecting column 4021 and the upper end of the lower connecting column 4022 are both provided with an arc groove. When the upper connecting column 4021 and the lower connecting column 4022 are connected, the two arc grooves just form a circular channel, and the circular channel is used to fix the middle cylindrical part of the shaking alarm 3. For the connection relationship between the upper connecting column 4021 and the lower connecting column 4022, the upper connecting column 4021 and the lower connecting column 4022 can be connected by a conventional clamping method.

[0040] In this embodiment, a rectangular connection groove 403 is provided on both sides of the lower end of the upper column 4021, and a plurality of clamping holes are provided on each connection groove 403. Correspondingly, a rectangular connection clamping plate 404 is hingedly connected to both sides of the two ends of the lower column 4022 through hinges, and the area of ​​the connection clamping plate 404 is the same as that of the connection groove 403. A plurality of clamping protrusions are provided on the connection clamping plate 404, and the shape, number and distribution of the clamping protrusions correspond to the shape, number and distribution of the clamping holes one by one, so that the clamping protrusions and the clamping holes can be clamped.

[0041] When installing the shaking alarm 3, it is only necessary to place the shaking alarm 3 on the two arc-shaped grooves connecting the lower columns 4022, and then place the upper connecting columns 4021 on top of them respectively, and pull the connecting clamp 404 so that the clamping protrusions on the connecting clamp 404 are engaged with the clamping holes on the connecting grooves 403, thereby realizing the clamping connection between the upper connecting column 4021 and the lower connecting column 4022, thereby fixing the shaking alarm 3.

[0042] According to the looseness of the working interface 208, a loose body structure construction disturbance monitoring and early warning device is placed at the bottom of the loose body structure surface at intervals. The interval depends on the specific project situation. The greater the looseness, the denser the device arrangement. After leveling, the loose body structure construction disturbance monitoring and early warning device is placed in close contact with the bottom edge of the working interface 208. Its function is to facilitate the transmission of vibration and the falling of stone chips from above onto the gravity platform. When the vibration transmission or gravity sensing reaches a certain level, each early warning device alarms, and the alarm value is determined according to the site requirements of different projects.

[0043] The present invention uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core ideas of the present invention. At the same time, for those skilled in the art, according to the ideas of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.

Claims

1. A loose body structure construction disturbance monitoring and early warning device, characterized in that: It includes a support tray warning device, a close-fitting vibration warning device, a shaking warning device, a supporting platform and a control system. The supporting platform includes a supporting base and a connecting column. The lower end of the connecting column is installed on the supporting base. The shaking warning device is installed on the connecting column. The two ends of the shaking warning device are respectively connected to a connecting bracket. Each connecting bracket is equipped with a support tray warning device. The close-fitting vibration warning device is installed on the upper end of the connecting column. The support tray warning device, the close-fitting vibration warning device and the shaking warning device are all electrically connected to the control system.

2. The loose body structure construction disturbance monitoring and early warning device according to claim 1 is characterized by: There are two connecting columns.

3. The loose body structure construction disturbance monitoring and early warning device according to claim 1 is characterized by: The tray alarm device includes a tray body, the inner cavity of the tray body is provided with a ballast plate, a spring, a pressure sensor and a tray alarm, the ballast plate and the pressure sensor are respectively fixed to the upper and lower ends of the spring, the tray alarm is installed at the lower end of the pressure sensor, and the pressure sensor and the tray alarm are both electrically connected to the control system; A tray receiving slot is provided at the lower end of the tray receiving body, and the upper end of the connecting bracket can be inserted into the tray receiving slot.

4. The loose body structure construction disturbance monitoring and early warning device according to claim 3 is characterized by: A shape measuring layer is provided at the upper end of the pressure plate, and the shape measuring layer includes a shape measuring frame. The shape measuring frame is fixed to the upper end of the tray body, and a plurality of shape measuring through holes are evenly distributed on the shape measuring frame. A shape measuring column is slidably connected in each of the shape measuring through holes.

5. The loose body structure construction disturbance monitoring and early warning device according to claim 1 is characterized by: The fitted vibration sensing warning device comprises a fitted warning body, on which a fitted frame, a fitted vibration sensor and a fitted warning alarm are arranged, the fitted frame is provided with a plurality of fitted through holes, each of the fitted through holes is slidably connected with a fitted part, the fitted part can be used to contact with a working interface, the fitted vibration sensor is arranged at one end of the fitted frame away from the working interface, the fitted vibration sensor is in contact with the fitted frame, and the fitted vibration sensor and the fitted warning alarm are both electrically connected to the control system; A fitting warning slot is provided at the lower end of the fitting warning body, and the upper end of the connecting column is inserted into the fitting warning slot.

6. The loose body structure construction disturbance monitoring and early warning device according to claim 5 is characterized by: The upper ends of the fitting frame and the fitting vibration sensor are provided with protection pads, and the protection pads are made of rubber material.

7. The loose body structure construction disturbance monitoring and early warning device according to claim 1 is characterized by: The shaking warning device includes a shaking body, and the two connecting brackets are respectively fixed on both sides of the shaking body. A shaking vibration sensor and a shaking alarm are arranged in the shaking body, and the shaking vibration sensor and the shaking alarm are both electrically connected to the control system.

8. The loose body structure construction disturbance monitoring and early warning device according to claim 1 is characterized by: The receiving base includes an inner base and an outer base, and the inner base is arranged on the inner circle of the outer base; The material of the inner base is steel; the material of the outer base is concrete; The inner base is provided with a base slot, and the lower end of the connecting column is plugged into the base slot.

9. The loose body structure construction disturbance monitoring and early warning device according to claim 1 is characterized by: The connecting column comprises an upper connecting column and a lower connecting column. An arc-shaped groove is provided at the lower end of the upper connecting column and the upper end of the lower connecting column. The upper connecting column and the lower connecting column are clamped together.

10. The loose body structure construction disturbance monitoring and early warning device according to claim 9, characterized in that: The upper connecting column is provided with a connecting groove, and the connecting groove is provided with a plurality of clamping holes. The lower connecting column is hinged with a connecting clamping plate, and the connecting clamping plate is provided with a plurality of clamping protrusions, and the clamping protrusions are clamped with the clamping holes.