Optimized operation method and system for multi-terminal flexible power distribution network containing micro-grid
By constructing a multi-terminal flexible distribution network model and employing the particle swarm optimization algorithm, efficient management and absorption of distributed renewable energy in the flexible distribution network are achieved, solving the management and absorption problems of distributed renewable energy in the flexible distribution network and improving the system's economy and reliability.
Patent Information
- Application Number
- CN202410754884.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-12
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2044-06-12
AI Technical Summary
How to efficiently manage and absorb distributed renewable energy in flexible distribution networks, solve the problems of variable and complex power flow, voltage exceeding limits, and power quality degradation, and achieve safe and economical operation of flexible distribution networks.
A multi-terminal flexible distribution network model is constructed, and a particle swarm optimization algorithm is used for joint optimization. Through the coordinated scheduling of microgrids and distribution networks, distributed controllable power sources, energy storage, and demand response are optimized to achieve economical and safe operation of the system.
Effectively absorb distributed renewable energy, reduce operating costs and losses, improve system reliability and power quality, and achieve line load balancing.
Smart Images

Figure CN118899823A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of distribution network operation optimization, and in particular to a method and system for optimizing the operation of a multi-terminal flexible distribution network including a microgrid. Background Art
[0002] Flexible interconnection devices based on advanced power electronics technology are the key link for multiple distributed renewable energy sources to access the distribution network. Flexible interconnection devices convert the single-radiation power supply mode of the traditional distribution network into a multi-terminal closed-loop power supply mode, and the traditional distribution network is transformed into a flexible distribution network, which can achieve continuous and flexible adjustment of the power flow. However, with the increase in the number of flexible interconnection devices connected to the flexible distribution network, how to accurately coordinate the transmission power of different flexible interconnection devices is the key to improving the operational reliability of the flexible distribution network.
[0003] The flexible distribution network connected to a large number of renewable energy sources can effectively alleviate the pressure of power supply, adjust the system flow, and achieve load balancing of each line. However, the randomness and intermittency of distributed renewable energy bring severe challenges to the operation of the power system, mainly manifested in the changeable and complex flow of system flow, voltage limit crossing and power quality degradation. Therefore, many distribution networks would rather increase operating costs than connect to distributed renewable energy, resulting in a large waste of resources.
[0004] Distributed renewable energy is characterized by sparse distribution in space and large installed capacity, which puts higher requirements on the dispatching capacity of flexible distribution networks. On the other hand, the output characteristics of distributed renewable energy vary. How to achieve the consumption of different distributed renewable energy through the output of controllable units in the system is a key issue and one of the difficulties in solving the model. Therefore, the flexible distribution network realizes the efficient management and consumption of distributed renewable energy, which is an urgent problem to be solved for the safe and economic operation of the distribution network. Summary of the invention
[0005] In view of the problems existing in the existing flexible distribution network, the present invention is proposed.
[0006] Therefore, the problem to be solved by the present invention is to achieve efficient management and consumption of distributed renewable energy through a flexible distribution network.
[0007] In order to solve the above technical problems, the present invention provides the following technical solutions:
[0008] In a first aspect, an embodiment of the present invention provides a method for optimizing operation of a multi-terminal flexible distribution network including a microgrid, which comprises:
[0009] Collecting multi-terminal flexible distribution network parameters, and constructing a multi-terminal flexible distribution network model according to the multi-terminal flexible distribution network parameters;
[0010] Solving the lower layer of the multi-terminal flexible distribution network model to obtain a dispatching plan for each unit of the microgrid;
[0011] According to the dispatching scheme, the upper layer of the multi-terminal flexible distribution network model is solved to obtain a power purchase plan for the distribution network, and the distribution network is optimized based on the dispatching scheme and the power purchase plan.
[0012] As a preferred solution of the multi-terminal flexible distribution network optimization operation method containing a microgrid described in the present invention, wherein: the multi-terminal flexible distribution network model includes an upper distribution network, a lower microgrid and safe operation constraints;
[0013] The microgrid takes the minimum operating cost as the objective function, as shown in the following formula:
[0014] min f=C MG =C DG +C ESS +C DNtoMG +C DR
[0015]
[0016] Among them, C MG is the total operating cost of the microgrid; C DG is the power generation cost of distributed controllable power source; C ESS is the charging and discharging cost of energy storage; C DNtoMG is the electricity purchase cost of the microgrid; C DR is the cost of demand response; N T is the scheduling period; is the cost coefficient of distributed controllable power supply; P DG,t is the power generation of the distributed controllable power source at time t; is the energy storage charging and discharging cost coefficient; η is the energy storage charging and discharging efficiency; and are the discharge power and charging power of energy storage at time t respectively; and are the unit electricity prices of microgrid electricity purchase and sales respectively; P MG,t is the electricity purchase amount at time t, when P MG,t ≥0 indicates electricity purchase, otherwise it indicates electricity sale; is the cost coefficient of demand response; ΔP load,t is the transferable load at time t.
[0017] As a preferred solution of the method for optimizing the operation of a multi-terminal flexible distribution network containing a microgrid according to the present invention, the distribution network takes the minimum operation loss as the objective function, as shown in the following formula:
[0018]
[0019]
[0020] Among them, P loss is the operating loss of the system; is the operating loss of the distribution network; is the operating loss of the medium voltage DC bus; is the operating loss of MMC; N is the number of nodes in the distribution network; M is the number of nodes in the DC line; R ij is the line resistance between node i and node j; P ij,t and Q ij,t are the active power and reactive power flowing from node i to node j at time t; V i,t is the voltage amplitude of node i at time t; R kl is the line resistance between node k and node l; P kl,t is the active power flowing from node k to node l at time t; V k,t is the voltage amplitude of node k at time t; N MMC is the number of MMCs; is the loss coefficient of the sth MMC; and are the active power and reactive power absorbed by the sth MMC from the access node at time t respectively.
[0021] As a preferred solution of the method for optimizing operation of a multi-terminal flexible distribution network containing a microgrid according to the present invention, wherein: the distribution network and the microgrid are interconnected via a 10kV medium voltage DC bus;
[0022] The distribution network is connected to the upper power grid and interconnected with the medium voltage DC bus through a modular multilevel converter MMC;
[0023] The microgrid is interconnected with the medium voltage DC bus through a flexible interconnection device.
[0024] As a preferred solution of the multi-terminal flexible distribution network optimization operation method containing a microgrid described in the present invention, wherein: the safe operation constraints include distributed controllable power supply operation constraints, energy storage operation constraints, microgrid power exchange constraints, demand response operation constraints, AC distribution network flow equation constraints, DC line flow equation constraints and MMC operation constraints;
[0025] The distributed controllable power supply operation constraints are as follows:
[0026]
[0027] in, and The upper and lower limits of the distributed controllable power supply ramp rate; and It is the upper and lower limits of the active power of the distributed controllable power source.
[0028] As a preferred solution of the method for optimizing the operation of a multi-terminal flexible distribution network containing a microgrid according to the present invention, the energy storage operation constraint is as follows:
[0029]
[0030]
[0031] Among them, E ESS is the maximum charging and discharging power of energy storage; U ESS,t When it is 1, it means charging, and when it is 0, it means discharging; and is the maximum and minimum value of the remaining energy storage capacity; E 0,n is the capacity of energy storage at the initial moment;
[0032] The AC distribution network power flow equation constraint is as follows:
[0033]
[0034] Among them, P j,t and Q j,t are respectively the active power and reactive power of the net load of node j at time t; I ij,t is the current amplitude between node i and node j at time t; P m,t is the active load of node m at time t; and are the active load and reactive load of node j at time t respectively.
[0035] As a preferred scheme of the method for optimizing the operation of a multi-terminal flexible distribution network containing a microgrid described in the present invention, the demand response operation constraint is a transferable demand response, and the load transferred by the user should satisfy the total load demand within the scheduling period. At the same time, the load is only allowed to be transferred in or out, and it is not allowed to exceed the maximum transferable load.
[0036] In a second aspect, an embodiment of the present invention provides a multi-terminal flexible distribution network optimization operation system including a microgrid, which includes:
[0037] The model building module is used to collect the parameters of the multi-terminal flexible distribution network and build a multi-terminal flexible distribution network model including a microgrid according to the collected parameters;
[0038] Microgrid optimization module, used to solve the microgrid model of the lower layer of the multi-terminal flexible distribution network, obtain the optimal scheduling plan of each unit in the microgrid, and the amount of electricity purchased by the microgrid;
[0039] The distribution network optimization module is used to solve the upper distribution network model of the multi-terminal flexible distribution network according to the power purchase amount output by the microgrid optimization module, and obtain the optimal dispatching plan of the distribution network.
[0040] In a third aspect, an embodiment of the present invention provides a computer device, comprising a memory and a processor, wherein the memory stores a computer program, wherein: when the processor executes the computer program, it implements any step of the above-mentioned method for optimizing operation of a multi-terminal flexible distribution network containing a microgrid.
[0041] In a fourth aspect, an embodiment of the present invention provides a computer-readable storage medium having a computer program stored thereon, wherein: when the computer program is executed by a processor, any step of the above-mentioned method for optimizing operation of a multi-terminal flexible distribution network containing a microgrid is implemented.
[0042] The beneficial effect of the present invention is that a multi-terminal flexible distribution network model is constructed based on microgrid technology and flexible interconnection technology. The upper layer of the model is the distribution network, and the objective function is to minimize the operating loss; the lower layer of the model is the microgrid, and the objective function is to minimize the operating cost. Under the premise of considering the system's safe operation constraints, the particle swarm optimization algorithm is used to jointly optimize and solve the upper and lower models to obtain the power purchase plan of the distribution network and the scheduling plan of the microgrid, which can effectively absorb distributed renewable energy and realize the economic and safe operation of the multi-terminal flexible distribution network. At the same time, the present invention solves the model by partitioning joint solution, the calculation process is simple, and it has high engineering practical value. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. Among them:
[0044] Figure 1 Flowchart of the method for optimizing the operation of a multi-terminal flexible distribution network containing microgrids.
[0045] Figure 2 A schematic diagram of the structure of a multi-terminal flexible distribution network containing microgrids and an optimization operation method of a multi-terminal flexible distribution network containing microgrids.
[0046] Figure 3 The load curve diagram, distributed photovoltaic power and distributed wind power diagram before and after optimization of the optimal operation method of the multi-terminal flexible distribution network containing microgrids.
[0047] Figure 4 The optimized microgrid dispatching scheme diagram for the optimal operation method of a multi-terminal flexible distribution network containing a microgrid.
[0048] Figure 5 This is a diagram of the power distribution of the optimized MMC transmitted to the microgrid partitions in the multi-terminal flexible distribution network optimization operation method containing microgrids. DETAILED DESCRIPTION
[0049] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the drawings of the specification. Obviously, the described embodiments are part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary persons in the art without creative work should fall within the scope of protection of the present invention.
[0050] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.
[0051] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.
[0052] The present invention is described in detail with reference to schematic diagrams. When describing the embodiments of the present invention, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.
[0053] At the same time, in the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "upper, lower, inner and outer" are based on the directions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first, second or third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0054] In the present invention, unless otherwise clearly specified and limited, the terms "install, connect, connect" should be understood in a broad sense, for example: it can be a fixed connection, a detachable connection or an integral connection; it can also be a mechanical connection, an electrical connection or a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0055] Example 1
[0056] Reference Figure 1 to Figure 5 , which is the first embodiment of the present invention, and provides a method for optimizing operation of a multi-terminal flexible distribution network including a microgrid, comprising:
[0057] S1: Collect multi-terminal flexible distribution network parameters, and build a multi-terminal flexible distribution network model according to the multi-terminal flexible distribution network parameters;
[0058] Extract distribution network data, microgrid data and load point data, and summarize system information, including: distribution network line parameters, load conditions, distributed photovoltaic power, distributed wind power and operating constraints of each unit;
[0059] According to the multi-terminal flexible distribution network parameters provided above, a multi-terminal flexible distribution network model including a microgrid is constructed, including: setting the distribution network to minimize operating losses as the objective function, setting the microgrid to minimize operating costs as the objective function, and considering the system safety operation constraints;
[0060] The multi-terminal flexible distribution network model with microgrid is divided into upper and lower models. The upper model is the distribution network, which is composed of an improved IEEE 33-node standard system; the lower model is the microgrid, which is composed of distributed controllable power supplies, energy storage, demand response, photovoltaic and wind power. The distribution network and the microgrid are interconnected through a 10kV medium-voltage DC bus: the distribution network is connected to the upper grid at node 1, and is interconnected with the medium-voltage DC bus through two modular multilevel converters (MMCs) with a capacity of 1MW. The two MMCs are connected to nodes 18 and 22 respectively; the microgrid is interconnected with the medium-voltage DC bus through a flexible interconnection device.
[0061] Microgrids are mainly composed of distributed controllable power sources, energy storage, demand response, photovoltaic and wind power. The load demand of the microgrid itself is met through the coordinated scheduling of various units within the system and the support of the upper distribution network. The optimization goal of the microgrid is to maximize the consumption of distributed renewable energy while reducing its own operating costs under the constraints of meeting the safe operation of the system. Therefore, the operating cost includes the power generation cost of distributed controllable power sources, the charging and discharging cost of energy storage, the power purchase cost of the microgrid and the cost of demand response:
[0062] min f=C MG =C DG +CESS +C DNtoMG +C DR
[0063]
[0064]
[0065] Among them, C MG is the total operating cost of the microgrid; C DG is the power generation cost of distributed controllable power source; C ESS is the charging and discharging cost of energy storage; C DNtoMG is the electricity purchase cost of the microgrid; C DR is the cost of demand response; N T is the scheduling period; is the cost coefficient of distributed controllable power supply; P DG,t is the power generation of the distributed controllable power source at time t; is the energy storage charging and discharging cost coefficient; η is the energy storage charging and discharging efficiency; and are the discharge power and charging power of energy storage at time t respectively; and are the unit electricity prices of microgrid electricity purchase and sales respectively; P MG,t is the electricity purchase amount at time t, when P MG,t ≥0 indicates electricity purchase, otherwise it indicates electricity sale; is the cost coefficient of demand response; ΔP load,t is the transferable load at time t.
[0066] The distribution network objective function is expressed as follows:
[0067] The distribution network is the upper layer of the model. The improved IEEE 33-node standard system is selected as the distribution network, and its own load demand is met through the support of the upper power grid. The optimization goal of the microgrid is to minimize the system operation loss under the constraint of meeting the safe operation of the system. Therefore, the operation loss includes the operation loss of the distribution network, the operation loss of the medium-voltage DC bus, and the operation loss of the MMC:
[0068]
[0069] Among them, P loss is the operating loss of the system; is the operating loss of the distribution network; is the operating loss of the medium voltage DC bus; is the operating loss of MMC; N is the number of nodes in the distribution network; M is the number of nodes in the DC line; R ij is the line resistance between node i and node j; P ij,t and Qij,t are the active power and reactive power flowing from node i to node j at time t; V i,t is the voltage amplitude of node i at time t; R kl is the line resistance between node k and node l; P kl,t is the active power flowing from node k to node l at time t; V k,t is the voltage amplitude of node k at time t; N MMC is the number of MMCs; is the loss coefficient of the sth MMC; and are the active power and reactive power absorbed by the sth MMC from the access node at time t respectively.
[0070] Furthermore, the system safety operation constraints are constructed, and the constraints are expressed as follows:
[0071] 1) Operation constraints of distributed controllable power sources
[0072]
[0073]
[0074] 2) Energy storage operation constraints
[0075]
[0076] 3) Microgrid power exchange constraints
[0077]
[0078] 4) Demand response operation constraints
[0079] Considering transferable demand response, the load transferred by the user should satisfy the total load demand within the scheduling period. At the same time, the load is only allowed to be transferred in or out, and it is not allowed to exceed the maximum transferable load.
[0080]
[0081] 5) AC distribution network power flow equation constraints
[0082] The AC distribution network power flow is described using the DisFlow branch power flow method.
[0083]
[0084]
[0085] 6) DC line power flow equation constraints
[0086]
[0087] 7)MMC operation constraints
[0088]
[0089] in, and The upper and lower limits of the distributed controllable power supply ramp rate; and is the upper and lower limits of the active power of the distributed controllable power supply; E ESS is the maximum charging and discharging power of energy storage; U ESS,t When it is 1, it means charging, and when it is 0, it means discharging; and is the maximum and minimum value of the remaining energy storage capacity; E 0,n is the capacity of energy storage at the initial moment; and They are the lower and upper limits of the amount of electricity that the microgrid can purchase, respectively; and are the load after and before the response at time t; τ is the allowable range of load variation at each moment; X ij is the line impedance between node i and node j; P j,t and Q j,t are respectively the active power and reactive power of the net load of node j at time t; I ij,t is the current amplitude between node i and node j at time t; P m,t is the active load of node m at time t; and are the active load and reactive load of node j at time t respectively; and are the lower and upper limits of reactive power absorbed by the sth MMC from the access node; S MMCs is the capacity of the sth MMC; P MMG,t is the active power absorbed by the microgrid from the medium voltage DC bus at time t; is the active power flowing from the sth MMC to the medium voltage DC bus at time t.
[0090] S2: Solve the lower layer of the multi-terminal flexible distribution network model to obtain the scheduling plan of each unit of the microgrid;
[0091] The microgrid includes distributed controllable power sources, energy storage, demand response, photovoltaic and wind power. It consumes distributed renewable energy by coordinating the distributed controllable power sources, energy storage and microgrid power purchase. The microgrid parameters are input and the particle swarm optimization algorithm is used to solve the microgrid model. The results after the transferable demand response optimizes the load curve are shown in Figure 2. Figure 3As shown in the figure, through the incentive of time-of-use electricity prices, users transfer part of the load during peak hours to low-peak hours, effectively alleviating the power supply pressure. The peak-to-valley difference of the load before optimization is 844kW, and the peak-to-valley difference of the load after optimization is 745kW, which is a decrease of 11.73%. The dispatch results of distributed controllable power supply, energy storage and microgrid power purchase are shown in the figure. Figure 4 As shown in the figure, the microgrid is positive when purchasing electricity and negative when selling electricity; it is positive when the energy storage is charged and negative when discharging. Through the coordinated dispatch of distributed controllable power sources, energy storage and microgrid power purchase, distributed renewable energy is effectively absorbed, and the excess power is transmitted to the distribution network through flexible interconnection devices and MMC, increasing the revenue of the microgrid while alleviating the supply and load pressure of the distribution network.
[0092] S3: According to the scheduling scheme, solve the upper layer of the multi-terminal flexible distribution network model to obtain a power purchase plan for the distribution network, and optimize the distribution network based on the scheduling scheme and the power purchase plan.
[0093] The distribution network is based on the power purchase plan of the microgrid, with the minimum system operation loss as the objective function. The line parameters and system load of the distribution network are input, and the particle swarm optimization algorithm is used to solve the distribution network model. The power distribution of the two MMC transmissions is shown in Figure 5 As shown in the figure, the power transmitted from the distribution network to the microgrid is positive, and the power transmitted from the microgrid to the distribution network is negative. Since the parameters of the distribution network lines are the same, the loads are also different, resulting in different powers transmitted by the MMC. Since the load of the line where MMC#2 is located is higher than the load of the line where MMC#1 is located, when the distribution network transmits power to the microgrid, MMC#1 is mainly used, and when the microgrid transmits power to the distribution network, MMC#2 is mainly used, which can effectively achieve line load balancing, thereby reducing line operation losses.
[0094] In summary, the use of particle swarm optimization algorithm to solve the operation optimization problem of multi-terminal flexible distribution network containing microgrids can effectively absorb distributed renewable energy and reduce the operating loss of the distribution system, thereby obtaining the optimal multi-terminal flexible distribution network scheduling scheme containing microgrids. It has a certain guiding role in accelerating the construction of multi-terminal flexible distribution networks containing microgrids in actual engineering practice.
[0095] Furthermore, this embodiment also provides a multi-terminal flexible distribution network optimization operation system including a microgrid, including:
[0096] A model building module is used to collect multi-terminal flexible distribution network parameters and build a multi-terminal flexible distribution network model including a microgrid based on the collected parameters;
[0097] The microgrid optimization module is used to solve the microgrid model of the lower layer of the multi-terminal flexible distribution network, obtain the optimal scheduling plan for each unit in the microgrid, and the power purchase amount of the microgrid.
[0098] The distribution network optimization module is used to solve the upper distribution network model of the multi-terminal flexible distribution network according to the power purchase amount output by the microgrid optimization module, and obtain the optimal dispatching plan of the distribution network.
[0099] This embodiment also provides a computer device, which is suitable for the case of an optimized operation method of a multi-terminal flexible distribution network containing a microgrid, and includes a memory and a processor; the memory is used to store computer-executable instructions, and the processor is used to execute computer-executable instructions to implement the optimized operation method of a multi-terminal flexible distribution network containing a microgrid as proposed in the above embodiment.
[0100] The computer device may be a terminal, and the computer device includes a processor, a memory, a communication interface, a display screen and an input device connected via a system bus. The processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The communication interface of the computer device is used to communicate with an external terminal in a wired or wireless manner, and the wireless manner can be achieved through WIFI, an operator network, NFC (near field communication) or other technologies. The display screen of the computer device may be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device may be a touch layer covering the display screen, or a key, trackball or touchpad provided on the housing of the computer device, or an external keyboard, touchpad or mouse, etc.
[0101] This embodiment also provides a storage medium on which a computer program is stored. When the program is executed by a processor, the method for optimizing the operation of a multi-terminal flexible distribution network including a microgrid as proposed in the above embodiment is implemented.
[0102] The storage medium proposed in this embodiment and the data storage method proposed in the above embodiment belong to the same inventive concept. The technical details not fully described in this embodiment can be found in the above embodiment, and this embodiment has the same beneficial effects as the above embodiment.
[0103] Example 2
[0104] This is the second embodiment of the present invention. This embodiment provides a method for optimizing the operation of a multi-terminal flexible distribution network including a microgrid. In order to verify the beneficial effects of the present invention, scientific demonstration is carried out through economic benefit calculation and simulation experiments.
[0105] In order to verify the effectiveness and superiority of the invented method, this embodiment performs a simulation test on an IEEE 33-node standard distribution network including a microgrid.
[0106] Configure the computer hardware environment and install MATLAB R2022a software.
[0107] Establish the IEEE 33-node standard distribution network model, including line parameters, node loads, etc.
[0108] Two 1MW MMCs are set at nodes 18 and 22 for interconnection with the microgrid medium-voltage DC bus.
[0109] A microgrid model is constructed, which includes a 100kW distributed controllable power supply, a 200kWh energy storage system, 100kW photovoltaic power, 50kW wind power and transferable demand response load.
[0110] Set system parameters: distributed controllable power generation cost coefficient 0.5 yuan / kWh, energy storage charging and discharging cost coefficient 0.1 yuan / kWh, energy storage efficiency 0.9, electricity purchase price 0.6 yuan / kWh, electricity selling price 0.4 yuan / kWh, demand response cost coefficient 0.8 yuan / kWh.
[0111] Implementation process:
[0112] The distribution network, microgrid and load point data are extracted to build a multi-terminal flexible distribution network model including microgrids. The distribution network target is set to minimize the operating loss, the microgrid target is set to minimize the operating cost, and various operating constraints are considered.
[0113] Solve the microgrid model and obtain the optimal distributed controllable power supply, energy storage and power purchase scheduling plan through the particle swarm optimization algorithm to absorb renewable energy and smooth the load curve.
[0114] According to the microgrid power purchase plan, the distribution network model is solved, and the optimal power allocation plan of MMC is obtained through the particle swarm optimization algorithm to achieve the minimum operation loss of the distribution network.
[0115] Record the dispatch values and distribution network operation data of each participant, generate data tables and analysis results, as shown in the following table:
[0116] Table 1 Experimental data table
[0117]
[0118]
[0119] As can be seen from the table above, by solving the two-layer optimization of the multi-terminal flexible distribution network model, the output of each device in the microgrid can be reasonably arranged, distributed renewable energy can be effectively absorbed, and the power purchase cost of the microgrid can be controlled. The specific performance is:
[0120] Renewable energy consumption: Both photovoltaic and wind power can be fully utilized during the day. For example, from 10:00 to 16:00, the photovoltaic output is 62.5-86.7 kWh, and the wind power output is 25.2-36.3 kWh. The microgrid adjusts the load curve through the energy storage system and demand response, so that more renewable energy can be consumed.
[0121] Internal coordination of microgrids: Distributed controllable power sources, energy storage systems and power purchases work together to reduce operating costs. For example, from 19:00 to 21:00, the controllable power sources are basically shut down, the energy storage system discharges a large amount of power, and sells power to the distribution network at the same time, avoiding the purchase of power during the peak period of the power grid and reducing operating costs.
[0122] Reduced distribution network losses: By optimizing the distribution network model and reasonably allocating the power transmission of the two MMCs, the line load is balanced, keeping the overall line loss of the distribution network at a low level. From the data, it can be seen that the maximum line loss of the distribution network is 16.3kWh, which is only about 2.5% of the total load.
[0123] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.
Claims
1. A method for optimizing the operation of a multi-terminal flexible distribution network including a microgrid, characterized in that: include, Collecting multi-terminal flexible distribution network parameters, and constructing a multi-terminal flexible distribution network model according to the multi-terminal flexible distribution network parameters; Solving the lower layer of the multi-terminal flexible distribution network model to obtain a dispatching plan for each unit of the microgrid; According to the dispatching scheme, the upper layer of the multi-terminal flexible distribution network model is solved to obtain a power purchase plan for the distribution network, and the distribution network is optimized based on the dispatching scheme and the power purchase plan.
2. The method for optimizing operation of a multi-terminal flexible distribution network including a microgrid according to claim 1, characterized in that: The multi-terminal flexible distribution network model includes an upper distribution network, a lower microgrid and safe operation constraints; The microgrid takes the minimum operating cost as the objective function, as shown in the following formula: min f=C MG =C DG +C ESS +C DNtoMG +C DR Among them, C MG is the total operating cost of the microgrid; C DG is the power generation cost of distributed controllable power source; C ESS is the charging and discharging cost of energy storage; C DNtoMG is the electricity purchase cost of the microgrid; C DR is the cost of demand response; N T is the scheduling period; is the cost coefficient of distributed controllable power supply; P DG,t is the power generation of the distributed controllable power source at time t; is the energy storage charging and discharging cost coefficient; η is the energy storage charging and discharging efficiency; and are the discharge power and charging power of energy storage at time t respectively; and are the unit electricity prices of microgrid electricity purchase and sales respectively; P MG,t is the electricity purchase amount at time t, when P MG,t ≥0 indicates electricity purchase, otherwise it indicates electricity sale; is the cost coefficient of demand response; ΔP load,t is the transferable load at time t.
3. The method for optimizing operation of a multi-terminal flexible distribution network including a microgrid according to claim 2, characterized in that: The distribution network takes the minimum operating loss as the objective function, as shown in the following formula: Among them, P loss is the operating loss of the system; is the operating loss of the distribution network; is the operating loss of the medium voltage DC bus; is the operating loss of MMC; N is the number of nodes in the distribution network; M is the number of nodes in the DC line; R ij is the line resistance between node i and node j; P ij,t and Q ij,t are the active power and reactive power flowing from node i to node j at time t; V i,t is the voltage amplitude of node i at time t; R kl is the line resistance between node k and node l; P kl,t is the active power flowing from node k to node l at time t; V k,t is the voltage amplitude of node k at time t; N MMC is the number of MMCs; is the loss coefficient of the sth MMC; and are the active power and reactive power absorbed by the sth MMC from the access node at time t respectively.
4. The method for optimizing operation of a multi-terminal flexible distribution network including a microgrid as claimed in claims 2 and 3, characterized in that: The distribution network and the microgrid are interconnected via a 10kV medium voltage DC bus; The distribution network is connected to the upper power grid and interconnected with the medium voltage DC bus through a modular multilevel converter MMC; The microgrid is interconnected with the medium voltage DC bus through a flexible interconnection device.
5. The method for optimizing operation of a multi-terminal flexible distribution network including a microgrid as claimed in claim 3, characterized in that: The safety operation constraints include distributed controllable power supply operation constraints, energy storage operation constraints, microgrid power exchange constraints, demand response operation constraints, AC distribution network power flow equation constraints, DC line power flow equation constraints and MMC operation constraints; The distributed controllable power supply operation constraints are as follows: in, and The upper and lower limits of the distributed controllable power supply ramp rate; and It is the upper and lower limits of the active power of the distributed controllable power source.
6. The method for optimizing operation of a multi-terminal flexible distribution network including a microgrid according to claim 5, characterized in that: The energy storage operation constraints are as follows: Among them, E ESS is the maximum charging and discharging power of energy storage; U ESS,t When it is 1, it means charging, and when it is 0, it means discharging; and is the maximum and minimum value of the remaining energy storage capacity; E 0,n is the capacity of energy storage at the initial moment; The AC distribution network power flow equation constraint is as follows: Among them, P j,t and Q j,t are respectively the active power and reactive power of the net load of node j at time t; I ij,t is the current amplitude between node i and node j at time t; P m,t is the active load of node m at time t; and are the active load and reactive load of node j at time t respectively.
7. The method for optimizing operation of a multi-terminal flexible distribution network including a microgrid according to claim 6, characterized in that: The demand response operation constraint is a transferable demand response. The load transferred by the user should satisfy the total load demand within the scheduling period. The load is only allowed to be transferred in or out at the same time, and is not allowed to exceed the maximum transferable load.
8. A multi-terminal flexible distribution network optimization operation system including a microgrid, based on the multi-terminal flexible distribution network optimization operation method including a microgrid according to any one of claims 1 to 7, characterized in that: include, The model building module is used to collect the parameters of the multi-terminal flexible distribution network and build a multi-terminal flexible distribution network model including a microgrid according to the collected parameters; Microgrid optimization module, used to solve the microgrid model of the lower layer of the multi-terminal flexible distribution network, obtain the optimal scheduling plan of each unit in the microgrid, and the amount of electricity purchased by the microgrid; The distribution network optimization module is used to solve the upper distribution network model of the multi-terminal distribution network according to the purchased electricity output by the power grid optimization module, and obtain the optimal dispatching plan for the distribution network.
9. A computer device comprising a memory and a processor, wherein the memory stores a computer program, wherein: When the processor executes the computer program, the steps of the method for optimizing operation of a multi-terminal flexible distribution network containing a microgrid as described in any one of claims 1 to 7 are implemented.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method for optimizing operation of a multi-terminal flexible distribution network containing a microgrid as described in any one of claims 1 to 7 are implemented.
Citation Information
Patent Citations
Flexible interconnection AC / DC power distribution system optimization scheduling method and system
CN112290601A
Power distribution network collaborative planning method and device considering multiple types of flexible resources
CN116683534A
Multi-microgrid power distribution system optimization scheduling method and device based on energy sharing
CN117578622A
Flexible interconnection and energy storage planning method and system for photovoltaic absorption low-voltage distribution network
CN117639077A