Regulation and control method of power system in energy station, electronic equipment and storage medium
By constructing a power load model and setting constraints for power flow calculations, the power system safety issues of integrated refueling, gas filling, and battery swapping energy stations were solved, achieving safe configuration and efficient utilization of equipment.
Patent Information
- Application Number
- CN202310485862.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-02
- Publication Date
- 2024-11-05
AI Technical Summary
Existing technologies lack dedicated power system analysis methods for integrated energy stations that combine refueling, gas filling, and battery swapping, which fails to improve power system safety and ensure the safe operation of energy stations.
Construct power load models for refueling, gas filling, and battery swapping equipment, set inequality and equality constraints for the power network nodes, perform power flow calculations and parameter adjustments until the constraints are met, and achieve safe configuration of the equipment.
This improves the safety of the power system in integrated energy stations that combine refueling, gas filling, and battery swapping, ensuring the safe operation of the energy stations.
Smart Images

Figure CN118899853A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of integrated energy technology integrating refueling, gas filling and power exchange, and in particular to a control method, device, electronic equipment and storage medium for an electric power system in an energy station. Background Art
[0002] With the construction and application of integrated energy stations integrating refueling, gas (hydrogen) and battery replacement, the mutual development of different types of vehicles in the transportation field has been greatly promoted. However, it also brings certain safety hazards, especially after a large number of electrical equipment are involved in various links, the requirements for the use of flammable and explosive gases and power supply safety are constantly increasing. For this reason, the commonly used means and methods currently mainly use the capacity of the power grid as the main assessment indicator. There is a lack of dedicated power system analysis means for integrated energy stations integrating refueling, gas (hydrogen) and battery replacement, which cannot improve the power system safety of integrated energy stations integrating refueling, gas and battery replacement, and ensure the safe operation of energy stations. Summary of the invention
[0003] In view of the problems existing in the prior art, the present invention provides a control method, device, electronic equipment and storage medium for an electric power system in an energy station.
[0004] The present invention provides a control method for an electric power system in an energy station, comprising:
[0005] Constructing a fueling equipment power load model, a gas filling equipment power load model, and a battery exchange equipment power load model belonging to the target energy station; each power load model includes power parameters;
[0006] Constructing inequality constraints and equality constraints for each electrical network node under the target energy station; the electrical network node is the electrical connection point between each device and the power supply line;
[0007] Obtaining power consumption data of each power load model, performing power flow calculation according to the power consumption data, and determining a power flow result corresponding to a preset power flow item;
[0008] When it is determined that the flow result does not satisfy the inequality constraint and the equality constraint, the power parameters in each power load model are adjusted until the flow result determined based on the power consumption data of the power load model after the power parameters are adjusted satisfies the inequality constraint and the equality constraint.
[0009] According to a method for controlling a power system in an energy station provided by the present invention, the method further includes:
[0010] When it is determined that the power flow result satisfies the inequality constraint and the equality constraint, the inequality constraint and the equality constraint are adjusted according to a preset adjustment rule, and the power flow result is kept to satisfy the adjusted inequality constraint and the equality constraint.
[0011] According to a control method for an electric power system in an energy station provided by the present invention, the electric power load model of the refueling equipment and the electric power load model of the gas filling equipment select the same inequality constraint conditions, including:
[0012]
[0013] Among them, S k , S k,max is the current power and power upper limit obtained by power flow calculation; U k , U k,min , U k,max The current bus voltage, voltage lower limit and voltage upper limit obtained by power flow calculation; I k ,I k,max is the current line circuit and current upper limit obtained by power flow calculation; f k 、f k,min 、f k,max are the current system frequency, lower frequency limit and upper frequency limit obtained by power flow calculation; k is 1 and 2, 1 represents the power load model of refueling equipment, and 2 represents the power load model of gas filling equipment.
[0014] According to a control method for a power system in an energy station provided by the present invention, the inequality constraint conditions of the power load model of the power exchange equipment include:
[0015]
[0016] Among them, S k , S k,max is the current power and power upper limit obtained by power flow calculation; U k , U k,min , U k,max The current bus voltage, voltage lower limit and voltage upper limit obtained by power flow calculation; I k ,I k,max is the current line circuit and current upper limit obtained by power flow calculation; k is 3, and 3 represents the power load model of the battery replacement equipment.
[0017] According to a control method for the power system in an energy station provided by the present invention, the equation constraints of the fueling equipment power load model, the gas filling equipment power load model and the battery exchange equipment power load model include:
[0018]
[0019] Among them, P j , Q j is the power and electricity balance equation constraint, where j is 1, 2 and 3, 1 represents the power load model of the refueling equipment, 2 represents the power load model of the gas filling equipment, and 3 represents the power load model of the battery replacement equipment.
[0020] The present invention also provides a control device for an electric power system in an energy station, comprising:
[0021] The first processing module is used to construct a fueling equipment power load model, a gas filling equipment power load model and a battery exchange equipment power load model belonging to the target energy station; each power load model includes power parameters;
[0022] The second processing module is used to construct inequality constraints and equality constraints of each electrical network node under the target energy station; the electrical network node is the electrical connection point between each device and the power supply line;
[0023] A calculation module, used to obtain power consumption data of each power load model, perform power flow calculation according to the power consumption data, and determine the power flow result corresponding to the preset power flow item;
[0024] The control module is used to adjust the power parameters in each power load model when it is determined that the power flow result does not satisfy the inequality constraint and the equality constraint, until the power flow result determined based on the power consumption data of the power load model after the power parameters are adjusted satisfies the inequality constraint and the equality constraint.
[0025] According to a control device for a power system in an energy station provided by the present invention, the control module is also used for:
[0026] When it is determined that the power flow result satisfies the inequality constraint and the equality constraint, the inequality constraint and the equality constraint are adjusted according to a preset adjustment rule, and the power flow result is kept to satisfy the adjusted inequality constraint and the equality constraint.
[0027] The present invention also provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the steps of the method for controlling the power system in the energy station as described above are implemented.
[0028] The present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of the method for controlling the power system in the energy station as described above.
[0029] The embodiments of the present invention provide a control method, device, electronic device and storage medium for the power system in an energy station. The control method, device and storage medium construct a refueling equipment power load model, a gas filling equipment power load model and a battery exchange equipment power load model under the target energy station, and construct inequality constraints and equality constraints for each electrical network node under the target energy station, and perform flow calculations based on the power consumption data of each power load model. When it is determined that the flow result corresponding to the preset flow item does not satisfy the inequality constraints and the equality constraints, the power parameters in each power load model are adjusted until the flow result determined based on the power consumption data of the power load model after the power parameters are adjusted satisfies the inequality constraints and the equality constraints, thereby achieving safe configuration of the equipment, improving the power system safety of the integrated energy station integrating refueling, gas filling and battery exchange, and ensuring the safe operation of the energy station. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0031] Figure 1 This is a flow chart of an embodiment of a method for controlling a power system in an energy station of the present invention;
[0032] Figure 2 This is a structural diagram of an embodiment of a control device for a power system in an energy station of the present invention;
[0033] Figure 3 It is a structural diagram of an electronic device embodiment of the present invention. DETAILED DESCRIPTION
[0034] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0035] Combine the following Figure 1-Figure 3 The present invention describes a control method, device, electronic device and storage medium for an electric power system in an energy station.
[0036] Figure 1 A schematic diagram showing a flow chart of a method for controlling a power system in an energy station provided by the present invention is shown in FIG. Figure 1 , the method comprises the following steps:
[0037] 11. Construct the power load model of the refueling equipment, the power load model of the gas filling equipment and the power load model of the battery replacement equipment under the target energy station; each power load model contains power parameters;
[0038] 12. Construct inequality constraints and equality constraints for each electrical network node under the target energy station; the electrical network node is the electrical connection point between each device and the power supply line;
[0039] 13. Obtain the power consumption data of each power load model, perform power flow calculation based on the power consumption data, and determine the power flow results corresponding to the preset power flow items;
[0040] 14. When it is determined that the flow result does not satisfy the inequality constraint and the equality constraint, the power parameters in each power load model are adjusted until the flow result determined based on the power consumption data of the power load model after the power parameters are adjusted satisfies the inequality constraint and the equality constraint.
[0041] Regarding steps 11 to 14, it should be noted that in the present invention, with the construction and application of integrated energy stations integrating refueling, gas filling (hydrogen) and battery replacement, the mutual promotion and development of different types of automobiles in the field of transportation has been greatly promoted. However, it also brings certain safety hazards, especially after a large number of electrical equipment are involved in various links, the requirements for the use of flammable and explosive gases and power supply safety are constantly increasing. To this end, it is necessary to reasonably configure the power parameters of multiple refueling equipment, gas filling equipment and battery replacement equipment arranged under each energy station, so as to realize the efficient use of refueling, gas filling and battery replacement by the energy station.
[0042] In the present invention, the refueling, gas filling and battery replacement equipment are all composed of different device combinations. For example, the refueling equipment requires a motor and a pump, and the pump is used to output the oil. To this end, a simulation method can be used to simulate the refueling, gas filling and battery replacement equipment to obtain the refueling equipment power load model, gas filling equipment power load model and battery replacement equipment power load model corresponding to the refueling, gas filling and battery replacement equipment. These power load models all contain power parameters. These power parameters can determine the power consumption data of each power load model during the simulated use of the refueling, gas filling and battery replacement equipment. In other words, the configuration of power parameters can determine the power consumption data. In the present invention, power parameters include basic parameters of the equipment, such as the operating conditions of the electrical structure, parameters and load components of a given equipment. Usually, the given operating conditions include the power of each power source and load point in the system, the hub point voltage, the voltage and phase angle of the balance point.
[0043] In the present invention, the power supply line will supply power to each energy station, and different types of equipment under the energy station will be connected to the power supply line with different supply voltages. The electrical connection point between each device and the power supply line is called an electrical network node. Inequality constraints and equality constraints are set for each electrical network node. The constraint condition can be numerically constrained from different constraint items. The constraint item may include power, voltage, current, system frequency, etc.
[0044] In the present invention, a usage simulation is performed based on each power load model, and the power consumption data of each power load model is obtained. The power flow calculation is performed according to the power consumption data to determine the power flow result corresponding to the preset power flow item. The power flow item includes power, bus voltage, line current and system frequency. The power flow calculation is calculated downward with the energy station distribution incoming transformer as the interface, and the maximum protection capacity value of the distribution transformer is used as the maximum capacity value.
[0045] In the present invention, since the electrical connection point between each device and the power supply line becomes an electrical network node, the flow results determined for each device are compared with the corresponding inequality constraints and equality constraints. Here, the above constraints configured for each electrical network node can be the same.
[0046] When it is determined that the flow result corresponding to an electric load model does not satisfy the inequality constraint and the equality constraint, the power parameters in the electric load model are adjusted until the flow result determined based on the power consumption data of the electric load model after the power parameters are adjusted satisfies the inequality constraint and the equality constraint.
[0047] In the present invention, when it is determined that the power flow results determined according to the power consumption data of each power load model under the target energy station all meet the constraint conditions, the power parameters corresponding to each power load model are stored, and the actual equipment is configured according to the current power parameters. The configured actual equipment is applied to the actual scene of the energy station, which can realize the efficient use of refueling, gas filling and power replacement by the energy station.
[0048] The control method of the power system in the energy station provided by the present invention constructs a refueling equipment power load model, a gas filling equipment power load model and a battery exchange equipment power load model belonging to the target energy station and constructs inequality constraints and equality constraints of each electrical network node under the target energy station, and performs flow calculation according to the power consumption data of each power load model. When it is determined that the flow result corresponding to the preset flow item does not satisfy the inequality constraint and the equality constraint, the power parameters in each power load model are adjusted until the flow result determined according to the power consumption data of the power load model after the power parameters are adjusted satisfies the inequality constraint and the equality constraint, thereby realizing safe configuration of the equipment, improving the power system safety of the integrated energy station integrating refueling, gas filling and battery exchange, and ensuring the safe operation of the energy station.
[0049] In a further method of the above method, when it is determined that the flow result satisfies the inequality constraints and the equality constraints, the inequality constraints and the equality constraints are adjusted according to preset adjustment rules, and the flow result is kept to satisfy the adjusted inequality constraints and the equality constraints.
[0050] In this regard, it should be noted that in the present invention, when the flow result satisfies the inequality constraint and the equality constraint, it may be that the constraints initially set are too broad, resulting in easy satisfaction. At this time, the equipment requirements may be too high (but the actual situation does not require high-specification equipment), which is not conducive to the reasonable planning of the equipment. For this reason, it is necessary to re-adjust the inequality constraint and the equality constraint according to the preset adjustment rules, and ensure that the flow result satisfies the adjusted inequality constraint and the equality constraint. The preset adjustment rules can adjust the values in the constraints according to the configuration change ratio.
[0051] In a further method of the above method, the fueling equipment power load model and the gas filling equipment power load model select the same inequality constraint conditions, including:
[0052]
[0053] Among them, S k , S k,max is the current power and power upper limit obtained by power flow calculation; U k , U k,min , U k,max The current bus voltage, voltage lower limit and voltage upper limit obtained by power flow calculation; I k ,I k,max is the current line circuit and current upper limit obtained by power flow calculation; f k 、f k,min 、f k,maxare the current system frequency, lower frequency limit and upper frequency limit obtained by power flow calculation; k is 1 and 2, 1 represents the power load model of refueling equipment, and 2 represents the power load model of gas filling equipment.
[0054] The inequality constraints of the power load model of the battery swapping equipment include:
[0055]
[0056] Among them, S k , S k,max is the current power and power upper limit obtained by power flow calculation; U k , U k,min , U k,max The current bus voltage, voltage lower limit and voltage upper limit obtained by power flow calculation; k ,I k,max is the current line circuit and current upper limit obtained by power flow calculation; k is 3, and 3 represents the power load model of the battery replacement equipment.
[0057] The equation constraints of the fueling equipment power load model, the gas filling equipment power load model, and the battery swapping equipment power load model include:
[0058]
[0059] Among them, P j , Q j is the power and electricity balance equation constraint, where j is 1, 2 and 3, 1 represents the power load model of the refueling equipment, 2 represents the power load model of the gas filling equipment, and 3 represents the power load model of the battery replacement equipment.
[0060] The control device of the power system in the energy station provided by the present invention is described below. The control device of the power system in the energy station described below and the control method of the power system in the energy station described above can be referred to each other.
[0061] Figure 2 A schematic diagram showing the structure of a control device for an electric power system in an energy station provided by the present invention is shown in FIG. Figure 2 The device includes a first processing module 21, a second processing module 22, a calculation module 23 and a control module 24, wherein:
[0062] The first processing module 21 is used to construct a fueling equipment power load model, a gas filling equipment power load model and a battery exchange equipment power load model belonging to the target energy station; each power load model includes power parameters;
[0063] The second processing module 22 is used to construct inequality constraints and equality constraints of each electrical network node under the target energy station; the electrical network node is the electrical connection point between each device and the power supply line;
[0064] The calculation module 23 is used to obtain the power consumption data of each power load model, perform power flow calculation according to the power consumption data, and determine the power flow result corresponding to the preset power flow item;
[0065] The control module 24 is used to adjust the power parameters in each power load model when it is determined that the power flow result does not meet the inequality constraint and the equality constraint, until the power flow result determined based on the power consumption data of the power load model after the power parameter adjustment meets the inequality constraint and the equality constraint.
[0066] In a further embodiment of the above device, the control module is further used for:
[0067] When it is determined that the power flow result satisfies the inequality constraint and the equality constraint, the inequality constraint and the equality constraint are adjusted according to a preset adjustment rule, and the power flow result is kept to satisfy the adjusted inequality constraint and the equality constraint.
[0068] In a further embodiment of the above device, the fueling equipment power load model and the gas filling equipment power load model select the same inequality constraint conditions, including:
[0069]
[0070] Among them, S k , S k,max is the current power and power upper limit obtained by power flow calculation; U k , U k,min , U k,max The current bus voltage, voltage lower limit and voltage upper limit obtained by power flow calculation; I k ,I k,max is the current line circuit and current upper limit obtained by power flow calculation; f k 、f k,min 、f k,max are the current system frequency, lower frequency limit and upper frequency limit obtained by power flow calculation; k is 1 and 2, 1 represents the power load model of refueling equipment, and 2 represents the power load model of gas filling equipment.
[0071] In a further embodiment of the above device, the inequality constraint conditions of the power load model of the battery swapping equipment include:
[0072]
[0073] Among them, S k , Sk,max is the current power and power upper limit obtained by power flow calculation; U k , U k,min , U k,max The current bus voltage, voltage lower limit and voltage upper limit obtained by power flow calculation; I k ,I k,max is the current line circuit and current upper limit obtained by power flow calculation; k is 3, and 3 represents the power load model of the battery replacement equipment.
[0074] In a further device of the above device, the equality constraints of the fueling equipment power load model, the gas filling equipment power load model and the battery exchange equipment power load model include:
[0075]
[0076] Among them, P j , Q j is the power and electricity balance equation constraint, where j is 1, 2 and 3, 1 represents the power load model of the refueling equipment, 2 represents the power load model of the gas filling equipment, and 3 represents the power load model of the battery replacement equipment.
[0077] Since the principle of the device described in the embodiment of the present invention is the same as that of the method described in the above embodiment, a more detailed explanation will not be repeated here.
[0078] It should be noted that, in the embodiment of the present invention, the relevant functional modules can be implemented by a hardware processor.
[0079] The control device of the power system in the energy station provided by the present invention constructs a fueling equipment power load model, a gas filling equipment power load model and a battery exchange equipment power load model belonging to the target energy station and constructs inequality constraints and equality constraints of each electrical network node under the target energy station, and performs flow calculation according to the power consumption data of each power load model. When it is determined that the flow result corresponding to the preset flow item does not satisfy the inequality constraints and the equality constraints, the power parameters in each power load model are adjusted until the flow result determined according to the power consumption data of the power load model after the power parameters are adjusted satisfies the inequality constraints and the equality constraints, thereby realizing safe configuration of the equipment, improving the power system safety of the integrated energy station integrating fueling, gas filling and battery exchange, and ensuring the safe operation of the energy station.
[0080] Figure 3 An example of a physical structure diagram of an electronic device is shown in FIG. Figure 3As shown, the electronic device may include: a processor 31, a communication interface 32, a memory 33 and a communication bus 34, wherein the processor 31, the communication interface 32 and the memory 33 communicate with each other via the communication bus 34. The processor 31 may call the logic instructions in the memory 33 to execute the following method:
[0081] Constructing a fueling equipment power load model, a gas filling equipment power load model, and a battery exchange equipment power load model belonging to the target energy station; each power load model includes power parameters;
[0082] Construct inequality constraints and equality constraints for each electrical network node under the target energy station; the electrical network node is the electrical connection point between each device and the power supply line;
[0083] Obtain the power consumption data of each power load model, perform power flow calculation based on the power consumption data, and determine the power flow results corresponding to the preset power flow items;
[0084] When it is determined that the power flow result does not satisfy the inequality constraint condition and the equality constraint condition, the power parameters in each power load model are adjusted until the power flow result determined based on the power consumption data of the power load model after the power parameter adjustment satisfies the inequality constraint condition and the equality constraint condition.
[0085] In addition, the logic instructions in the above-mentioned memory 33 can be implemented in the form of a software functional unit and can be stored in a computer-readable storage medium when it is sold or used as an independent product. Based on such an understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk and other media that can store program codes.
[0086] On the other hand, the present invention further provides a computer program product, the computer program product comprising a computer program stored on a non-transitory computer-readable storage medium, the computer program comprising program instructions, when the program instructions are executed by a computer, the computer can perform the method provided by the above methods, the method comprising:
[0087] Constructing a fueling equipment power load model, a gas filling equipment power load model, and a battery exchange equipment power load model belonging to the target energy station; each power load model includes power parameters;
[0088] Construct inequality constraints and equality constraints for each electrical network node under the target energy station; the electrical network node is the electrical connection point between each device and the power supply line;
[0089] Obtain the power consumption data of each power load model, perform power flow calculation based on the power consumption data, and determine the power flow results corresponding to the preset power flow items;
[0090] When it is determined that the power flow result does not satisfy the inequality constraint condition and the equality constraint condition, the power parameters in each power load model are adjusted until the power flow result determined based on the power consumption data of the power load model after the power parameter adjustment satisfies the inequality constraint condition and the equality constraint condition.
[0091] In another aspect, the present invention further provides a non-transitory computer-readable storage medium having a computer program stored thereon, which is implemented when the computer program is executed by a processor to perform the methods provided in the above embodiments, for example, including:
[0092] Constructing a fueling equipment power load model, a gas filling equipment power load model, and a battery exchange equipment power load model belonging to the target energy station; each power load model includes power parameters;
[0093] Construct inequality constraints and equality constraints for each electrical network node under the target energy station; the electrical network node is the electrical connection point between each device and the power supply line;
[0094] Obtain the power consumption data of each power load model, perform power flow calculation based on the power consumption data, and determine the power flow results corresponding to the preset power flow items;
[0095] When it is determined that the power flow result does not satisfy the inequality constraint condition and the equality constraint condition, the power parameters in each power load model are adjusted until the power flow result determined based on the power consumption data of the power load model after the power parameter adjustment satisfies the inequality constraint condition and the equality constraint condition.
[0096] Through the description of the above implementation methods, those skilled in the art can clearly understand that each implementation method can be implemented by means of software plus a necessary general hardware platform, and of course, it can also be implemented by hardware. Based on this understanding, the above technical solution is essentially or the part that contributes to the prior art can be embodied in the form of a software product, and the computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, a disk, an optical disk, etc., including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each embodiment or some parts of the embodiments.
[0097] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for regulating the power system in an energy station, characterized in that: include: Constructing a fueling equipment power load model, a gas filling equipment power load model, and a battery exchange equipment power load model belonging to the target energy station; each power load model includes power parameters; Constructing inequality constraints and equality constraints for each electrical network node under the target energy station; The electrical network nodes are electrical connection points between various devices and power supply lines; Obtaining power consumption data of each power load model, performing power flow calculation according to the power consumption data, and determining a power flow result corresponding to a preset power flow item; When it is determined that the flow result does not satisfy the inequality constraint and the equality constraint, the power parameters in each power load model are adjusted until the flow result determined based on the power consumption data of the power load model after the power parameters are adjusted satisfies the inequality constraint and the equality constraint.
2. The control method of the power system in the energy station according to claim 1, characterized in that: The method further comprises: When it is determined that the power flow result satisfies the inequality constraint and the equality constraint, the inequality constraint and the equality constraint are adjusted according to a preset adjustment rule, and the power flow result is kept to satisfy the adjusted inequality constraint and the equality constraint.
3. The control method of the power system in the energy station according to claim 1, characterized in that: The fueling equipment power load model and the gas filling equipment power load model select the same inequality constraints, including: Among them, S k , S k,max is the current power and upper power limit obtained by power flow calculation; U k , U k,min , U k,max The current bus voltage, voltage lower limit and voltage upper limit obtained by power flow calculation; I k ,I k,max is the current line circuit and current upper limit obtained by power flow calculation; f k 、f k,min 、f k,max are the current system frequency, lower frequency limit and upper frequency limit obtained by power flow calculation; k is 1 and 2, 1 represents the power load model of refueling equipment, and 2 represents the power load model of gas filling equipment.
4. The method for controlling the power system in an energy station according to claim 1, characterized in that: The inequality constraints of the power load model of the battery swapping equipment include: Among them, S k , S k,max is the current power and upper power limit obtained by power flow calculation; U k , U k,min , U k,max The current bus voltage, voltage lower limit and voltage upper limit obtained by power flow calculation; I k ,I k,max is the current line circuit and current upper limit obtained by power flow calculation; k is 3, and 3 represents the power load model of the battery replacement equipment.
5. The control method of the power system in the energy station according to claim 1, characterized in that: The equation constraints of the refueling equipment power load model, the gas filling equipment power load model and the battery exchange equipment power load model include: Among them, P j , Q j is the power and electricity balance equation constraint, where j is 1, 2 and 3, 1 represents the power load model of the refueling equipment, 2 represents the power load model of the gas filling equipment, and 3 represents the power load model of the battery replacement equipment.
6. A control device for the power system in an energy station, characterized in that: include: The first processing module is used to construct a fueling equipment power load model, a gas filling equipment power load model and a battery exchange equipment power load model belonging to the target energy station; each power load model includes power parameters; A second processing module is used to construct inequality constraints and equality constraints of each electrical network node under the target energy station; The electrical network nodes are electrical connection points between various devices and power supply lines; A calculation module, used to obtain power consumption data of each power load model, perform power flow calculation according to the power consumption data, and determine the power flow result corresponding to the preset power flow item; The control module is used to adjust the power parameters in each power load model when it is determined that the power flow result does not satisfy the inequality constraint and the equality constraint, until the power flow result determined based on the power consumption data of the power load model after the power parameters are adjusted satisfies the inequality constraint and the equality constraint.
7. The control device for the power system in the energy station according to claim 6, characterized in that: The control module is also used for: When it is determined that the power flow result satisfies the inequality constraint and the equality constraint, the inequality constraint and the equality constraint are adjusted according to a preset adjustment rule, and the power flow result is kept to satisfy the adjusted inequality constraint and the equality constraint.
8. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the steps of the method for controlling the power system in the energy station as described in any one of claims 1 to 5 are implemented.
9. A non-transitory computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method for controlling the power system in an energy station as claimed in any one of claims 1 to 5 are implemented.
Citation Information
Cited By
Multi-loop power supply abnormity cooperative regulation and control system for oil storage station
CN121939638A