Winter heat preservation and maintenance device and method for precast beam

By using slip parts and adjusting parts in the prefabricated beam winter insulation and maintenance device to adjust the cover area of ​​the arch skeleton, the problem of insufficient heat utilization caused by the different sizes of the prefabricated beam is solved, energy consumption is reduced, and insulation efficiency is improved.

CN118906201APending Publication Date: 2024-11-08SICHUAN ROAD & BRIDGE CONSTRUCTION GROUP CO LTD

Patent Information

Application Number
CN202411277723.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The existing prefabricated beam winter insulation and maintenance devices have small sizes of prefabricated beams, and the large area of ​​the arch skeleton cover leads to insufficient utilization of heat and high energy consumption.

Method used

By introducing a slider and adjusting member into the arch skeleton, allowing the second arch rod to slide and the insulation to fold or unfold, the cover area of ​​the arch skeleton is adjusted to accommodate the actual size of the prefabricated beam, combining the heating assembly and water spray The components are heat-insulated and maintained.

Benefits of technology

The arch skeleton cover area is adjusted according to the size of the prefabricated beam, the rational use of heat gas, the energy consumption is reduced, and the insulation efficiency is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure FT_1
    Figure FT_1
  • Figure FT_2
    Figure FT_2
  • Figure FT_3
    Figure FT_3
Patent Text Reader

Abstract

The invention relates to a precast beam winter heat preservation and maintenance device and method, and belongs to the technical field of precast beam maintenance, the precast beam winter heat preservation and maintenance device comprises a bottom plate and an arch-shaped framework arranged on the bottom plate, and the arch-shaped framework comprises a first arch-shaped rod arranged on the bottom plate and a plurality of second arch-shaped rods arranged on the bottom plate in a sliding mode; the multiple second arched rods are symmetrically distributed on the two opposite sides of the first arched rod, the multiple second arched rods are jointly covered with heat preservation cloth, the first arched rod is covered with the heat preservation cloth, and the bottom plate is provided with a sliding piece used for enabling the multiple second arched rods to synchronously slide in the direction close to or away from the first arched rod. The bottom plate is provided with an adjusting piece used for folding or unfolding the heat preservation cloth, and door cloth is arranged on the side, away from the first arch-shaped rod, of the second arch-shaped rod. The device has the advantages that the covering area of the arched framework can be adjusted according to the actual size of the precast beam, reasonable utilization of hot air is guaranteed to a certain extent, and energy consumption is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of prefabricated beam maintenance, and in particular to a device and method for prefabricated beam winter thermal insulation maintenance. Background Art

[0002] In bridge concrete construction, the maintenance of precast beams is a key link, especially under low temperature conditions in winter. In order to ensure the quality of precast beams, it is necessary not only to heat the mixing water and aggregates for construction, but also to use thermal insulation maintenance equipment for thermal insulation maintenance.

[0003] In the related art, a Chinese patent document with publication number CN220741605U discloses a device for winter heat preservation and maintenance of prefabricated beams, which includes an arch frame and a bottom plate; the bottom of the arch frame is fixedly connected to the top of the bottom plate, a fixed steel pipe is welded on the left side of the surface of the arch frame, a movable steel pipe is slidably connected to the surface of the arch frame, plastic paper is installed on the left side of the fixed steel pipe and the right side of the movable steel pipe, a heating component is arranged on the left side of the top of the bottom plate, and a water spray component is arranged on the right side of the top of the bottom plate. When in use, the movable steel pipe is located on the side of the arch frame away from the fixed steel pipe, so that the plastic paper seals the space of the arch frame, and when the temperature in the device is too low, hot air is sprayed on the prefabricated beam by the heating component to perform heat preservation on the prefabricated beam; when the prefabricated beam needs to be maintained, the prefabricated beam is subjected to water mist maintenance by the water spray component; and the movable steel pipe slides on the arch frame to open the greenhouse.

[0004] Regarding the above-mentioned related technologies, since the sizes of prefabricated beams are different under different working conditions, when the size of the prefabricated beams is much smaller than the area of ​​the arch frame, the plastic paper seals a large space, resulting in unreasonable use of hot air and high energy consumption. Summary of the invention

[0005] In order to help adjust the area of ​​the arch frame cover according to the actual size of the prefabricated beam, ensure the rational use of heat to a certain extent, and reduce energy consumption, the present application provides a winter insulation and maintenance device and method for prefabricated beams.

[0006] In the first aspect, the present application provides a prefabricated beam winter insulation and maintenance device, which adopts the following technical solution: A winter thermal insulation and maintenance device for prefabricated beams comprises a base plate and an arched frame arranged on the base plate, the arched frame comprising a first arched rod arranged on the base plate and a plurality of second arched rods slidably arranged on the base plate, the plurality of second arched rods being symmetrically distributed on opposite sides of the first arched rod, the plurality of second arched rods being commonly covered with a thermal insulation cloth, the thermal insulation cloth covering the first arched rod, the base plate being provided with a sliding member for making the plurality of second arched rods synchronously slide toward or away from the first arched rod, the base plate being provided with an adjusting member for folding or unfolding the thermal insulation cloth, and the second arched rod on the side away from the first arched rod being provided with a door cloth for opening or closing the inside of the arched frame.

[0007] Preferably, the sliding member includes a bidirectional screw rotatably arranged on the base plate and a driving motor arranged on the base plate, the rotation axis of the bidirectional screw is parallel to the sliding direction of the second arch rod, the ends of the second arch rod located on opposite sides of the first arch rod are respectively threadedly connected to the two ends of the bidirectional screw, and the driving motor is used to drive the bidirectional screw to rotate.

[0008] Preferably, the adjusting member includes an adjusting rope arranged on the thermal insulation cloth and adjusting strips at opposite ends of a plurality of second arch rods on the same side of the first arch rod, the adjusting rope is arranged on the edges on both sides of the thermal insulation cloth along the length direction of the arch frame, and guide wheels are arranged on the two adjusting strips at the same end of the second arch rods on both sides of the first arch rod, the spacing between the two guide wheels on the same side of the first arch rod is smaller than the spacing between the two guide wheels on the other side, the two ends of the adjusting rope are respectively arranged at the ends of the two adjustment strips close to one side that are far away from each other, and the middle part of the adjusting rope is slidably overlapped on the two guide wheels close to one side in sequence.

[0009] Preferably, connecting strips are provided at both ends of the first arched rod, the adjusting strip is slidably connected to the connecting strip close to one side, and the sliding direction of the adjusting strip is parallel to the sliding direction of the second arched rod.

[0010] Preferably, the connecting strip on any one side is slidably connected to the first arched rod along the bending direction of the first arched rod, and two adjustment strips on the connecting strip slidably connected to the first arched rod are slidably sleeved on the corresponding plurality of second arched rods.

[0011] Preferably, a lock buckle is provided on the connecting strip slidably connected to the first arch rod, and a buckle ring for buckling with the lock buckle is provided on the bottom plate. When the lock buckle is buckled with the buckle ring, the thermal insulation cloth covers the arch frame.

[0012] Preferably, a plurality of the first arched rods are provided, and the plurality of the first arched rods are arranged at intervals between the plurality of the second arched rods on both sides.

[0013] Preferably, the two ends of the insulation cloth in the length direction are connected to the second arched rods located at the two ends by a zipper.

[0014] In the second aspect, the present application provides a method for winter heat preservation and maintenance of prefabricated beams, which adopts the following technical solution: A method for prefabricated beam winter heat preservation and maintenance, using the prefabricated beam winter heat preservation and maintenance device, further comprising the following steps: The sliding member drives a plurality of second arched rods on both sides of the first arched rod to slide synchronously toward or away from the first arched rod; The heat preservation cloth is folded or unfolded by the adjusting piece to shorten or lengthen the length of the arch frame and adjust the area covered by the arch frame; Lift the prefabricated beam onto the bottom plate and close the door cloth to seal the inside of the arch frame; When the temperature inside the arch frame is too low, hot air is sprayed onto the precast beams through the heating assembly; When the precast beam needs to be cured, water mist curing is performed on the precast beam through the water spray assembly.

[0015] In summary, this application includes the following beneficial technical effects: The sliding member drives the multiple second arch rods at both ends of the first arch rod to slide in a direction close to or away from the first arch rod. At the same time, the adjusting member folds or unfolds the insulation cloth, thereby shortening or lengthening the length of the arch frame and adjusting the area covered by the arch frame to suit the actual size of the prefabricated beam, thereby ensuring the rational use of hot air and reducing energy consumption to a certain extent. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application.

[0017] Figure 2 It is an exploded view of the first overall structure of an embodiment of the present application.

[0018] Figure 3 It is an exploded view of the second overall structure of the embodiment of the present application.

[0019] Figure 4 yes Figure 2 Enlarged view of part A.

[0020] Explanation of the accompanying drawings: 1. Base plate; 2. Arch frame; 21. First arch rod; 22. Second arch rod; 3. Insulation cloth; 4. Sliding piece; 41. Bidirectional screw; 42. Driving motor; 5. Door cloth; 6. Adjustment rope; 7. Adjustment strip; 8. Guide wheel; 9. Connecting strip; 10. Lock buckle; 11. Buckle; 12. Slide groove; 13. Connecting block. DETAILED DESCRIPTION

[0021] The following is combined with Figure 1-4 This application is described in further detail.

[0022] The present application embodiment discloses a prefabricated beam winter heat preservation and maintenance device. Figure 1 and Figure 2 The prefabricated beam winter heat preservation and maintenance device comprises a bottom plate 1 and an arch frame 2, wherein the arch frame 2 comprises a first arch rod 21 and a second arch rod 22, wherein the first arch rod 21 is fixed to the bottom plate 1, and a plurality of first arch rods 21 are provided, and the plurality of first arch rods 21 are arranged at intervals along the length direction of the bottom plate 1, so as to facilitate the installation of the connecting frame in the water spraying assembly and the connecting ring in the heating assembly, and improve the installation stability. In the embodiment of the present application, three first arch rods 21 are provided, and in other embodiments, the number of first arch rods 21 can be set as required.

[0023] Reference Figure 2 , a plurality of second arch rods 22 are provided, and the plurality of second arch rods 22 are slidably arranged on the base plate 1, and sliding grooves 12 slidably matched with the second arch rods 22 are provided on opposite sides of the base plate 1, and the sliding direction of the second arch rods 22 is parallel to the arrangement direction of the plurality of first arch rods 21, and the plurality of second arch rods 22 are symmetrically distributed on opposite sides of the plurality of first arch rods 21; the opposite sides of the first arch rod 21 refer to the two ends in the length direction of the base plate 1; in the embodiment of the present application, there are two second arch rods 22 on both sides of the plurality of first arch rods 21, and the two second arch rods 22 on each side are arranged at intervals along the length direction of the base plate 1.

[0024] Reference Figure 1 and Figure 2 A plurality of second arch rods 22 are commonly covered with a heat preservation cloth 3, and the heat preservation cloth 3 covers the first arch rod 21; a sliding member 4 is provided on the bottom plate 1 for making the plurality of second arch rods 22 slide synchronously toward or away from the first arch rod 21, and an adjusting member is provided on the bottom plate 1 for folding or unfolding the heat preservation cloth 3; and a door cloth 5 for opening or closing the inside of the arch frame 2 can be removably provided on the second arch rod 22 away from the first arch rod 21 on each side of the first arch rod 21.

[0025] When in use, the sliding member 4 drives the multiple second arched rods 22 at both ends of the bottom plate 1 to slide in the direction close to or away from the first arched rod 21, and the adjusting member folds or unfolds the heat preservation cloth 3, thereby shortening or lengthening the length of the arched frame 2, and adjusting the area covered by the arched frame 2 to be suitable for the actual size of the prefabricated beam, to a certain extent ensuring the reasonable use of hot air and reducing energy consumption. The heat preservation cloth 3 and the door cloth 5 block and seal the inside of the arched frame 2, and the prefabricated beam is insulated and maintained in winter through the cooperation of the adding component and the water spraying component; when the operator needs to enter, the door cloth 5 is opened to open the inside of the arched frame 2, so that people can enter and exit conveniently.

[0026] Reference Figure 2 and Figure 3 , in order to facilitate the sliding of multiple second arch rods 22 in the direction of approaching or moving away from the first arch rod 21, the sliding member 4 includes a bidirectional screw 41 and a driving motor 42, the bidirectional screw 41 is rotatably penetrated on the base plate 1, and two bidirectional screws 41 are provided, and the two bidirectional screws 41 are located at both ends of the second arch rod 22, and the two ends of the second arch rod 22 refer to the two ends in the width direction of the base plate 1, and the rotation axis of the bidirectional screw 41 is parallel to the sliding direction of the second arch rod 22, and the bidirectional screw 41 passes through the slide groove 12 on the corresponding side, and the two ends of the second arch rod 22 are fixed with connecting blocks 13, and the connecting blocks 13 slide in the slide groove 12, and the connecting blocks 13 on the second arch rod 22 on the opposite sides of the first arch rod 21 are respectively threadedly sleeved on the two ends of the bidirectional screw 41, and the driving motor 42 is fixedly installed on the base plate 1, and the driving motor 42 corresponds to the bidirectional screw 41 one by one, and the bidirectional screw 41 is coaxially fixed with the output shaft of the corresponding driving motor 42.

[0027] When it is necessary to adjust the covering area of ​​the arch frame 2, the two driving motors 42 are started. The driving motors 42 drive the corresponding bidirectional screws 41 to rotate. The rotation of the bidirectional screws 41 drives the connecting blocks 13 to slide toward or away from the first arch rod 21, thereby causing the connecting blocks 13 on both sides to drive the corresponding second arch rods 22 to move, which helps to shorten or increase the distance between the second arch rods 22 at both ends of the base plate 1, thereby adjusting the length of the arch frame 2. When the length of the prefabricated beam is much smaller than the length of the base plate 1, the internal space of the arch frame 2 can be reduced, which ensures the rational use of hot air to a certain extent and reduces energy consumption.

[0028] Reference Figure 2 and Figure 4 In order to facilitate folding or unfolding the insulation cloth 3, the two ends of the multiple first arched rods 21 are commonly connected with a connecting strip 9, the connecting strip 9 is in contact with the bottom plate 1, and the connecting strip 9 extends along the length direction of the bottom plate 1. The adjusting member includes an adjusting rope 6 and an adjusting strip 7. The adjusting rope 6 is fixed to the edges of the insulation cloth 3 on both sides along the length direction of the arched frame 2. The adjusting strips 7 are respectively sleeved on the two ends of the multiple second arched rods 22 on the same side of the first arched rod 21. The cross-section of the adjusting strip 7 is L-shaped. The distances between the two adjusting strips 7 at the same end of the multiple second arched rods 22 and the center line of the bottom plate 1 are unequal. A guide wheel 8 is installed at one end of the two adjusting strips 7 at the same end of the multiple second arched rods 22 that are close to each other. The spacing between the two guide wheels 8 on the same side of the first arched rod 21 is smaller than the spacing between the two guide wheels 8 on the other side, so that the two adjusting strips 7 at the same end of the multiple second arched rods 22 are staggered, one is located on the inside and the other is located on the outside. The adjusting bar 7 is slidably connected to the connecting bar 9 near one side through a slider (not shown in the figure), and the sliding direction of the adjusting bar 7 is parallel to the sliding direction of the second arch rod 22, so that the adjusting bar 7 and the connecting bar 9 near one side will not be separated.

[0029] Reference Figure 2 and Figure 4 The two ends of the adjusting rope 6 are respectively fixed near the ends of the two adjusting bars 7 on one side that are away from each other. The adjusting rope 6 passes through the middle of the first arched rod 21 and is separated from the adjusting bar 7. The middle of the adjusting rope 6 is sequentially slid and overlapped on the two guide wheels 8 on the corresponding side. Specifically, one end of the adjusting rope 6 enters the guide wheel 8 on the outside from the outer edge of the adjusting bar 7 on the outside, and then passes through the guide wheel 8 on the inside and extends out from the inner edge of the adjusting bar 7 on the inside. Since the two guide wheels 8 at the same end of the second arched rod 22 are staggered inside and outside, the adjusting rope 6 is bent in a Z shape at the positions of the two guide wheels 8.

[0030] When the thermal insulation cloth 3 needs to be folded or unfolded, the multiple second arch rods 22 on both sides of the first arch rod 21 are driven to slide synchronously in the direction close to or away from the first arch rod 21. Since the adjusting strips 7 are sleeved on the multiple second arch rods 22 on the same side, the multiple second arch rods 22 drive the adjusting strips 7 at the corresponding two ends to move, so that the two adjusting strips 7 at the same end of the second arch rod 22 are close to or away from each other. When the two adjusting strips 7 at the same end are close to each other, the two adjusting strips 7 gradually overlap, and the guide wheels 8 on the two adjusting strips 7 move away from each other, driving the adjusting rope 6 to slide relative to each other, increasing the folding length, thereby realizing the folding of the thermal insulation cloth 3; when the two adjusting strips 7 at the same end move away from each other, the two adjusting strips 7 gradually move away from each other, reducing the overlap, and the guide wheels 8 on the two adjusting strips 7 gradually move toward each other, driving the adjusting rope 6 to slide relative to each other, reducing the folding length, thereby realizing the unfolding of the thermal insulation cloth 3, which helps to adapt to the length change of the arch frame 2 and ensure the reasonable use of hot air.

[0031] Reference Figure 1 and Figure 2 The door cloth 5 and the corresponding second arch rod 22 are detachably connected by a zipper, which facilitates the opening or closing of the door cloth 5 and the entry and exit of workers and prefabricated beams; the two ends of the insulation cloth 3 in the length direction are detachably connected to the second arch rods 22 located at the two ends by a zipper, which helps to ensure the sealing inside the arch frame 2, making it difficult for hot air to overflow from the edge of the insulation cloth 3, thereby reducing energy consumption.

[0032] Reference Figure 2 and Figure 4, the connecting strip 9 on any one side is slidably connected to the first arched rod 21 along the bending direction of the first arched rod 21, and the connecting strip 9 on the remaining side is fixed on the first arched rod 21 and abuts against the bottom plate 1; a guide rail (not shown in the figure) is fixed on the top wall of the first arched rod 21, and the guide rail is slidably matched with the sliding connecting strip 9, so that the connecting strip 9 is not easy to affect the suspension rod installed on the first arched rod 21 when sliding; the two adjustment strips 7 on the sliding connecting strip 9 are slidably sleeved on the corresponding multiple second arched rods 22, so that the corresponding two adjustment strips 7 can slide along the corresponding second arched rods 22. And the hole diameters of the two adjustment strips 7 are larger than the diameters of the corresponding second arched rods 22, which are not easy to affect the installation of the zipper on the second arched rod 22.

[0033] When winter is over and there is no need to perform insulation operation, the door cloth 5 is removed, and then the insulation cloth 3 and the corresponding zipper on the second arch rod 22 are opened, and the slidable connecting strip 9 is moved toward the direction close to the other end of the first arch rod 21, so that the connecting strip 9 moves along the guide rail on the first arch rod 21, and the connecting strip 9 drives the corresponding two adjustment strips 7 to slide along the corresponding second arch rod 22, so that the two connecting strips 9 can be moved to the same end of the first arch rod 21, so that the insulation cloth 3 is no longer covered on the arch frame 2, so that the ordinary maintenance of the prefabricated beam can be performed, which can be applied to different scenes. When insulation maintenance is required in winter, the slidable connecting strip 9 drives the corresponding two adjustment strips 7 to move to the other end of the first arch rod 21, so that the insulation cloth 3 covers the arch frame 2, and then the insulation cloth 3 is connected to the second arch rods 22 at both ends by zippers, and the door cloth 5 is installed on the second arch rod 22 at the end, so as to facilitate the insulation operation of the prefabricated beam.

[0034] Reference Figure 2 and Figure 4 A lock buckle 10 is installed on the connecting strip 9 slidably connected to the first arch rod 21, and a buckle 11 for buckling with the lock buckle 10 is fixed on the bottom plate 1. The buckle 11 is located on the side of the bottom plate 1 away from the connecting strip 9 fixed on the first arch rod 21. When the lock buckle 10 is buckled with the buckle 11, the insulating cloth 3 covers the arch frame 2. The buckle 10 and the buckle 11 are buckled to ensure that the connecting strip 9 of the insulating cloth 3 is not easy to slide during use; when the insulating cloth 3 needs to be put away, the lock buckle 10 is removed from the buckle 11, and the connecting strip 9 can be slid.

[0035] Reference Figure 2 In order to ensure the thermal insulation effect and reduce energy consumption, thermal insulation strips (thermal insulation strips) can be placed on the bottom plate 1 along the four sides of the arched frame 2 so that the thermal insulation strips cover the gap between the thermal insulation cloth 3 and the adjustment strip 7.

[0036] The implementation principle of the winter thermal insulation and maintenance device for prefabricated beams in the embodiment of the present application is as follows: when in use, the two driving motors 42 are started, and the driving motors 42 drive the corresponding bidirectional screws 41 to rotate. The rotation of the bidirectional screws 41 drives the connecting blocks 13 to slide toward or away from the first arch rod 21, thereby causing the connecting blocks 13 on both sides to drive the corresponding second arch rods 22 to move, so as to shorten or increase the distance between the second arch rods 22 at both ends of the base plate 1, and thereby adjust the length of the arch frame 2 to suit the actual size of the prefabricated beam.

[0037] When the multiple second arched rods 22 on both sides of the first arched rod 21 slide synchronously toward or away from the first arched rod 21, since the adjustment strips 7 are sleeved on the multiple second arched rods 22 on the same side, the multiple second arched rods 22 drive the adjustment strips 7 at the corresponding two ends to move, so that the two adjustment strips 7 at the same end of the second arched rod 22 are close to or away from each other, so as to realize the folding or unfolding of the insulation cloth 3, which helps to adapt to the length change of the arched frame 2, to a certain extent ensure the reasonable use of hot air, and reduce energy consumption. Pull up the zipper of the door cloth 5 to close the inside of the arched frame 2, and realize the insulation maintenance of the prefabricated beam in winter through the cooperation of the heating component and the water spray component.

[0038] The embodiment of the present application also discloses a method for heat preservation and maintenance of prefabricated beams in winter. The method for heat preservation and maintenance of prefabricated beams in winter uses the above-mentioned heat preservation and maintenance device for prefabricated beams in winter, and further includes the following steps: Step 1: Start the two driving motors 42 to drive the bidirectional screws 41 to rotate synchronously, so that the connecting block 13 drives the corresponding second arched rods 22 to slide in a direction close to or away from the first arched rod 21; Step 2: When the second arch rod 22 slides, the corresponding adjustment strip 7 is driven to slide, so that the two adjustment strips 7 at the same end of the first arch rod 21 gradually overlap or reduce overlap, and the insulation cloth 3 is folded or unfolded with the cooperation of the adjustment rope 6 and the guide wheel 8 to shorten or lengthen the length of the arch frame 2 and adjust the area covered by the arch frame 2; Step 3: hoist the prefabricated beam onto the bottom plate 1, close the door cloth 5 and the zipper on the edge of the insulation cloth 3 to seal the inside of the arch frame 2; Step 4: When the temperature inside the arch frame 2 is too low, hot air is sprayed onto the prefabricated beam through the heating assembly; Step 5: When the precast beam needs to be cured, water mist curing is performed on the precast beam through the water spray assembly.

[0039] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A prefabricated beam winter heat preservation and maintenance device, comprising a bottom plate (1) and an arched frame (2) arranged on the bottom plate (1), characterized in that: The arch frame (2) comprises a first arch rod (21) arranged on a bottom plate (1) and a plurality of second arch rods (22) slidably arranged on the bottom plate (1); the plurality of second arch rods (22) are symmetrically distributed on opposite sides of the first arch rod (21); a heat preservation cloth (3) is commonly provided on the plurality of second arch rods (22); the heat preservation cloth (3) covers the first arch rod (21); the bottom plate (1) is provided with a sliding member (4) for making the plurality of second arch rods (22) slide synchronously in a direction approaching or away from the first arch rod (21); the bottom plate (1) is provided with an adjusting member for folding or unfolding the heat preservation cloth (3); and a door cloth (5) for opening or closing the interior of the arch frame (2) is provided on the second arch rod (22) on the side away from the first arch rod (21).

2. A prefabricated beam winter heat preservation and maintenance device according to claim 1, characterized in that: The sliding member (4) comprises a bidirectional screw (41) rotatably arranged on the base plate (1) and a driving motor (42) arranged on the base plate (1); the rotation axis of the bidirectional screw (41) is parallel to the sliding direction of the second arch rod (22); the ends of the second arch rod (22) located on opposite sides of the first arch rod (21) are respectively threadedly connected to the two ends of the bidirectional screw (41); and the driving motor (42) is used to drive the bidirectional screw (41) to rotate.

3. The winter heat preservation and maintenance device for prefabricated beams according to claim 1 is characterized by: The adjusting member comprises an adjusting rope (6) arranged on the heat preservation cloth (3) and adjusting strips (7) sleeved on opposite ends of a plurality of second arch rods (22) on the same side of the first arch rod (21); the adjusting rope (6) is arranged on the edges of both sides of the heat preservation cloth (3) along the length direction of the arch frame (2); guide wheels (8) are arranged on the two adjusting strips (7) at the same end of the second arch rods (22) on both sides of the first arch rod (21); the spacing between the two guide wheels (8) on the same side of the first arch rod (21) is smaller than the spacing between the two guide wheels (8) on the other side; the two ends of the adjusting rope (6) are respectively arranged at the ends of the two adjusting strips (7) on one side that are far away from each other; the middle part of the adjusting rope (6) is slidably overlapped on the two guide wheels (8) on the one side in sequence.

4. A winter heat preservation and maintenance device for prefabricated beams according to claim 3, characterized in that: Connecting strips (9) are provided at both ends of the first arched rod (21), the adjusting strip (7) is slidably connected to the connecting strip (9) close to one side, and the sliding direction of the adjusting strip (7) is parallel to the sliding direction of the second arched rod (22).

5. The winter heat preservation and maintenance device for prefabricated beams according to claim 4 is characterized by: The connecting strip (9) on either side is slidably connected to the first arch rod (21) along the bending direction of the first arch rod (21), and the two adjustment strips (7) on the connecting strip (9) slidably connected to the first arch rod (21) are slidably sleeved on the corresponding plurality of second arch rods (22).

6. The winter heat preservation and maintenance device for prefabricated beams according to claim 5, characterized in that: A lock buckle (10) is provided on a connecting strip (9) slidably connected to the first arch rod (21), and a buckle ring (11) for buckling with the lock buckle (10) is provided on the bottom plate (1). When the lock buckle (10) and the buckle ring (11) are buckled, the heat-insulating cloth (3) covers the arch frame (2).

7. The winter heat preservation and maintenance device for prefabricated beams according to claim 1 is characterized by: A plurality of the first arched rods (21) are provided, and the plurality of the first arched rods (21) are arranged at intervals between the plurality of second arched rods (22) on both sides.

8. A winter heat preservation and maintenance device for prefabricated beams according to any one of claims 1 to 7, characterized in that: The two ends of the insulation cloth (3) in the length direction are connected to the second arched rods (22) located at the two ends via a zipper.

9. A method for heat preservation and maintenance of precast beams in winter, using the heat preservation and maintenance device for precast beams in winter according to any one of claims 1 to 8, characterized in that: The following steps are also included: A plurality of second arched rods (22) on both sides of the first arched rod (21) are driven by a sliding member (4) to slide synchronously in a direction approaching or moving away from the first arched rod (21); The heat-insulating cloth (3) is folded or unfolded by means of an adjusting piece to shorten or lengthen the length of the arch frame (2) and adjust the area covered by the arch frame (2); The prefabricated beam is hoisted onto the bottom plate (1), and the door cloth (5) is closed to seal the interior of the arch frame (2); When the temperature inside the arch frame (2) is too low, hot air is sprayed onto the prefabricated beam through the heating assembly; When the precast beam needs to be cured, water mist curing is performed on the precast beam through the water spray assembly.

Citation Information

Patent Citations

  • Winter heat preservation and maintenance device for precast beam

    CN220741605U

Cited By

  • Winter heat preservation and maintenance device for construction beams and slabs

    CN120925673A