Spring-floor elevator system of integrated steel platform and construction method of spring-floor elevator system
By installing an integrated steel platform elevator system with screw guide rails and gear drives in the elevator shaft, the problem of shaking of the elevator machine room and car is solved, and the safety and stability of elevators during construction are improved.
Patent Information
- Application Number
- CN202410902341.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-06
- Publication Date
- 2024-11-08
Smart Images

Figure CN118908018A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building construction, and in particular to a split-level elevator system with an integrated steel platform and a construction method thereof. Background Art
[0002] Elevators are a type of vertical transportation equipment used to transport people or goods vertically within a building. The development of elevators has an important impact on the design and living of high-rise buildings. Especially during construction, elevators are often needed to transport building materials.
[0003] In the related art, a Chinese patent document with publication number CN109436985A discloses a formwork for lifting an elevator and a construction method thereof. A formwork for lifting an elevator includes an elevator shaft, a machine room lifting device, an elevator machine room and an elevator car. The inner wall of the elevator shaft is provided with a plurality of support holes in the vertical direction, and the length direction of the support holes is in the horizontal direction. The machine room lifting device includes a steel platform, a first winch, a second winch, a lifting beam and a fixed beam. The first winch is installed on the steel platform, and the first winch is connected to the lifting beam through a steel cable. The lifting beam is fixedly connected to a lifting ring. The second winch is installed in the elevator machine room, and the steel cable of the second winch is passed through the lifting ring and connected to the fixed beam. The fixed beam is fixedly connected to the elevator machine room. The lifting beam and the fixed beam are both installed with telescopic brackets, and the moving direction of the output end of the telescopic bracket is in the horizontal direction. The first winch is hoisted with a lifting beam through a steel cable, and a traction machine is installed in the elevator machine room, and the traction machine is connected to the elevator car through a steel cable.
[0004] A construction method for a formwork frame for lifting an elevator comprises the following steps: S1, a self-climbing device moves to a designated position, then a first hoist drives a lifting beam to move to a designated support hole, then a telescopic bracket on the lifting beam is inserted into the support hole, so that the lifting beam is fixed to the inner wall of the elevator shaft through the telescopic bracket; S2, a second hoist reels a steel cable, so that a fixed beam drives an elevator room to be lifted to a designated support hole, then the telescopic bracket on the fixed beam is inserted into the support hole, so that the fixed beam is fixed to the inner wall of the elevator shaft through the telescopic bracket, and at this time, a traction machine can lift or lower the elevator car by reeling in or unreeling the steel cable; S 3. After the upper elevator shaft is poured, the self-climbing device moves upward to the designated position, and then the telescopic bracket of the lifting beam is separated from the support hole, and the first winch reels the steel cable, so that the lifting beam moves upward to the designated support hole, and then the telescopic bracket of the lifting beam is inserted into the support hole, so that the lifting beam is fixed to the inner wall of the elevator shaft through the telescopic bracket; S4. The telescopic bracket of the fixed beam is separated from the support hole, and then the second winch reels the steel cable, so that the fixed beam drives the elevator room and the elevator car to move upward to the designated support hole at the same time, and the telescopic bracket of the fixed beam is inserted into the support hole, so that the fixed beam is fixed to the inner wall of the elevator shaft. In this way, the elevator can be climbed without occupying the tower crane, saving the tower crane's transportation capacity while improving the safety of the elevator during lifting and operation.
[0005] However, in a related art formwork for lifting an elevator and a construction method thereof, an elevator machine room and an elevator car are prone to shaking, causing the elevator machine room and the elevator car to collide with the elevator shaft and cause an accident. Summary of the invention
[0006] In order to reduce the shaking of the elevator machine room and the elevator car, the present application provides a split-level elevator system with an integrated steel platform and a construction method thereof.
[0007] In the first aspect, the present application provides a leap-deck elevator system with an integrated steel platform, which adopts the following technical solution: The present application provides a leap-deck elevator system with an integrated steel platform, comprising: An elevator shaft, wherein the elevator shaft is provided with a machine room hoisting device, an elevator machine room and an elevator car in sequence from top to bottom, the machine room hoisting device is used to drive the elevator machine room to move upward, and the elevator machine room is used to drive the elevator car to move in a vertical direction; A machine room guide assembly, the machine room guide assembly comprising a first connection portion, a first drive member and a plurality of first guide rails, the first guide rail being a screw and being arranged inside the elevator shaft along a vertical direction, the plurality of first guide rails being connected in sequence along a vertical direction, the first connection portion being rotatably connected to the elevator machine room and being threadedly connected to the first guide rails, and the first drive member being used to drive the first connection portion to rotate; The car guide assembly includes a second connecting portion and a plurality of second guide rails, wherein the second guide rails are vertically arranged inside the elevator shaft, the plurality of second guide rails are connected in sequence along the vertical direction, and the second connecting portion is fixedly connected to the elevator car and slidably connected to the second guide rails.
[0008] By adopting the above technical solution, when the machine room lifting device lifts the elevator machine room and the elevator car, the elevator machine room moves upward along the length direction of the first guide rail, and the elevator car moves upward along the length direction of the second guide rail, thereby reducing the shaking of the elevator machine room and the elevator car during the movement, and improving the safety and reliability of the operation of the elevator machine room and the elevator car. And when the elevator machine room is moved and when the elevator machine room is moved, the threaded connection between the first guide rail and the elevator machine room enables the first guide rail to bear part of the gravity of the elevator machine room and the elevator car, reducing the force on the inner wall of the elevator shaft and the machine room lifting device, thereby reducing the force on the inner wall of the elevator shaft and the machine room lifting device, and reducing the situation where the inner wall of the elevator shaft or the machine room lifting device fails and the accident occurs.
[0009] Optionally, the first driving member includes a rack, a first driving gear, a second driving gear and a third driving gear, the rack is vertically arranged inside the elevator shaft, the first driving gear is coaxially fixedly connected to the first connecting part, the rotation axis of the second driving gear is perpendicular to the rotation axis of the first driving gear, and the first driving gear is meshed with the second driving gear, and the third driving gear is meshed with the rack and coaxially fixedly connected to the second driving gear.
[0010] By adopting the above technical solution, when the machine room lifting device lifts the elevator machine room, the third drive gear rotates with the movement of the elevator machine room, the third drive gear drives the second drive gear to rotate, the second drive gear drives the first drive gear to rotate, and the first drive gear drives the first connecting part to rotate, so that the first connecting part is threadedly connected to the first guide rail, and the machine room lifting device can drive the elevator machine room to move along the length direction of the first guide rail.
[0011] Optionally, a locking assembly is provided at one end of the first guide rail, and a first positioning groove is opened at the other end, the locking assembly includes a first positioning portion, the cross-section of the first positioning portion is polygonal, and the first positioning portion of the adjacent first guide rail is used to be plugged into the first positioning groove.
[0012] By adopting the above technical solution, when two adjacent first guide rails are connected, the first positioning parts of the adjacent first guide rails are plugged into and matched with the positioning grooves. Because one end of the first guide rail is connected to the elevator shaft, and the cross section of the first positioning part is a polygon, the matching relationship between the first positioning part and the positioning groove can limit the rotation of the first guide rail around the length direction of the first guide rail.
[0013] Optionally, the locking assembly includes a locking part and a second driving member, the locking part is slidably connected to the first positioning part, the moving direction of the locking part is perpendicular to the length direction of the first guide rail, the second driving member is used to drive the locking part to slide, the inner wall of the first positioning groove is provided with a locking groove along a direction perpendicular to the length direction of the first guide rail, and the adjacent first guide rails are connected by the locking part and the locking groove through the plug-in cooperation.
[0014] By adopting the above technical solution, during the process of the first positioning part being inserted into the positioning groove, the second driving member drives the locking part to move and engage with the locking groove. The locking groove is opened along a length direction perpendicular to the first guide rail, so that the matching relationship between the locking part and the locking groove can limit the movement of the first guide rail along the length direction of the first guide rail.
[0015] Optionally, the second driving member includes a first magnet and a second magnet, the first magnet is fixedly connected to the bottom wall of the first positioning groove, the second magnet is fixedly connected to the locking portion, and the facing magnetic poles of the first magnet and the second magnet repel each other; When the first positioning portion moves toward the direction close to the bottom wall of the first positioning groove, the locking portion moves in the vertical direction toward the direction close to the first magnet, and the facing magnetic poles of the first magnet and the second magnet repel each other, so that the second magnet drives the locking portion to move in the horizontal direction away from the first magnet, so that the locking portion is plugged into and fits with the locking groove.
[0016] By adopting the above technical solution, when the first positioning portion is inserted into the first positioning groove, the first magnet moves toward the direction close to the second magnet, so that the second magnet drives the locking portion to insert into the locking groove.
[0017] Optionally, the machine room lifting device includes a lifting beam, and one end of the first guide rail away from the bottom wall of the elevator shaft is detachably connected to the lifting beam.
[0018] By adopting the above technical solution, the lifting beam and the elevator machine room are connected to the elevator shaft as a whole through the first guide rail, which can improve the stability of the lifting beam, the elevator machine room and the first guide rail.
[0019] Optionally, a second positioning groove is formed on the inner wall of the elevator shaft in the vertical direction, and the second guide rail is fixedly connected to the inner wall of the second positioning groove.
[0020] By adopting the above technical solution, the second positioning groove can facilitate construction workers to align adjacent second guide rails, and make the second guide rails form a whole with the elevator shaft, thereby improving the stability of the second guide rails.
[0021] In the second aspect, the community provides a construction method for a leap-level elevator system with an integrated steel platform, comprising the following steps: S1. After constructing the elevator shaft of a certain height, install the first guide rail and the second guide rail inside the elevator shaft, and then install the elevator car, the elevator machine room and the machine room lifting device inside the elevator shaft in sequence along the vertical direction; S2, the elevator car moves to the second guide rail, the construction personnel slide the second connection part to the second guide rail, and then the elevator room moves to the first guide rail, the construction personnel thread the first connection part to the first guide rail, and install the drive assembly; S3, the steel platform climbs up one floor and constructs the elevator shaft of a higher floor, then the machine room lifting device lifts the elevator machine room to a higher floor, the elevator car transports the construction personnel, the first guide rail and the second guide rail to the installation position, then the construction personnel install the first guide rail on the original first guide rail, and install the second guide rail on the original second guide rail; S4. Repeat steps S1, S2 and S3 until the elevator shaft on the highest floor is completed, then remove the machine room lifting device and fix the elevator machine room to the elevator shaft on the highest floor.
[0022] In summary, the present application includes at least one of the following beneficial effects: 1. When the machine room lifting device lifts the elevator machine room and the elevator car, the elevator machine room moves upward along the length direction of the first guide rail, and the elevator car moves upward along the length direction of the second guide rail, thereby reducing the shaking of the elevator machine room and the elevator car during the movement, and improving the safety and reliability of the operation of the elevator machine room and the elevator car. And when the elevator machine room is moved and when the elevator machine room is moving, the threaded connection between the first guide rail and the elevator machine room enables the first guide rail to bear part of the gravity of the elevator machine room and the elevator car, reducing the force on the inner wall of the elevator shaft and the machine room lifting device, thereby reducing the force on the inner wall of the elevator shaft and the machine room lifting device, and reducing the situation of accidents caused by failure of the inner wall of the elevator shaft or the machine room lifting device; 2. When the machine room lifting device lifts the elevator machine room, the third driving gear rotates with the movement of the elevator machine room, the third driving gear drives the second driving gear to rotate, the second driving gear drives the first driving gear to rotate, and the first driving gear drives the first connecting part to rotate, so that the first connecting part is threadedly connected to the first guide rail, and the machine room lifting device can drive the elevator machine room to move along the length direction of the first guide rail; 3. When two adjacent first guide rails are connected, the first positioning portions of the adjacent first guide rails are plugged into and matched with the positioning grooves. Because one end of the first guide rail is connected to the elevator shaft and the cross-section of the first positioning portion is a polygon, the matching relationship between the first positioning portion and the positioning groove can limit the rotation of the first guide rail around the length direction of the first guide rail. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application; Figure 2 It is a schematic diagram of a local structure inside an elevator shaft used to illustrate an embodiment of the present application; Figure 3 yes Figure 2 A schematic diagram of the local enlarged structure at point A in the middle; Figure 4 It is a schematic diagram of a partial structure of a single first guide rail used in an embodiment of the present application; Figure 5 is a cross-sectional structural schematic diagram of an embodiment of the present application for illustrating a connection method of two first guide rails; Figure 6 yes Figure 2 Schematic diagram of the local enlarged structure at point B in the middle.
[0024] Explanation of the accompanying drawings: 1. elevator shaft; 2. machine room lifting device; 21. lifting beam; 22. steel platform; 3. elevator machine room; 4. elevator car; 5. machine room guide assembly; 51. first connecting part; 52. first driving member; 521. rack; 522. first driving gear; 523. second driving gear; 524. third driving gear; 53. first guide rail; 54. locking assembly; 541. first positioning part; 542. locking part; 543. second driving member; 5431. first magnet; 5432. second magnet; 55. first positioning groove; 56. locking groove; 6. car guide assembly; 61. second connecting part; 62. second guide rail; 7. second positioning groove. DETAILED DESCRIPTION
[0025] The following is combined with Figure 1-6 This application is described in further detail.
[0026] The embodiment of the present application discloses a leap-level elevator system with an integrated steel platform, referring to Figure 1 and Figure 2The inner wall of the elevator shaft 1 is provided with a plurality of support holes in the vertical direction. The elevator shaft 1 is provided with a machine room lifting device 2, an elevator machine room 3 and an elevator car 4 in the order from top to bottom. The machine room lifting device 2 comprises a steel platform 22 and a lifting beam 21. The steel platform 22 can move in the vertical direction inside the elevator shaft 1. A lifting ring is fixedly connected to the bottom of the steel platform 22. The lifting beam 21 is installed below the steel platform 22. A telescopic bracket is arranged on the lifting beam 21. When the output end of the telescopic bracket is extended and inserted into the support hole, the lifting beam 21 can be fixed to the inner wall of the elevator shaft 1. When the output end of the telescopic bracket is retracted and separated from the support hole, the lifting beam 21 can move in the vertical direction. The elevator machine room 3 is equipped with a winch, a traction machine and a telescopic bracket. The telescopic bracket is used to insert into the support beam to fix the elevator machine room 3. One end of the steel cable of the winch passes through the lifting ring and is fixedly connected to the lifting beam 21. One end of the steel cable of the traction machine is fixedly connected to the elevator car 4.
[0027] When the elevator shaft 1 is constructed to a certain height, the steel platform 22, the elevator machine room 3 and the elevator car 4 are installed in the elevator shaft 1, so that the construction workers can transport construction materials, equipment and personnel through the elevator car 4. The steel platform 22 drives the lifting beam 21 to move upward, and the lifting beam 21 is fixed to the inner wall of the elevator shaft 1 through the telescopic bracket, and then the elevator shaft 1 of a higher level is constructed, and then the winch is wound up, and the steel cable of the winch drives the elevator machine room 3 to move upward to a higher floor, and the elevator machine room 3 is fixed to the inner wall of the elevator shaft 1 at a higher level through the telescopic bracket, so that the elevator car 4 can transport construction materials to a higher floor, and the above process is repeated in sequence until the construction of the elevator shaft 1 at the highest level is completed. At this time, the elevator machine room 3 is transported to the elevator shaft 1 at the highest level, and the elevator machine room 3 is fixed to the inner wall of the elevator shaft 1, and then the machine room lifting device 2 is removed, thereby completing the construction of the elevator system.
[0028] The elevator machine room 3 in the embodiment of the present application is the elevator machine room 3 of a split-level elevator, which can also serve as a construction elevator during the structural construction process, thereby improving construction efficiency and safety.
[0029] Reference Figure 2 and Figure 3 The inner wall of the elevator shaft 1 is provided with a second positioning groove 7 in the vertical direction. A car guide assembly 6 is arranged inside the elevator shaft 1, and the car guide assembly 6 includes a second connecting portion 61 and a plurality of second guide rails 62, the second guide rails 62 are fixedly connected to the inner wall of the second positioning groove 7, and the plurality of second guide rails 62 are fixedly connected in sequence in the vertical direction, the second connecting portion 61 is two rollers arranged in parallel, the rollers are rotatably connected to the elevator car 4, and the two rollers are simultaneously in contact with the second guide rails 62, so that the elevator car 4 is slidably connected to the second guide rails 62 through the second connecting portion 61.
[0030] When the elevator car 4 moves, the cooperation relationship between the second connecting portion 61 and the second guide rail 62 can reduce the shaking of the elevator car 4, thereby improving the stability and safety of the elevator car 4 when moving.
[0031] Reference Figure 4 and Figure 5 , a machine room guide assembly 5 is arranged inside the elevator shaft 1, and the machine room guide assembly 5 includes a plurality of first guide rails 53, one first guide rail 53 is arranged on the bottom wall of the elevator shaft 1 along the vertical direction, and the other first guide rails 53 are connected in sequence along the vertical direction, and one end of the first guide rail 53 away from the bottom wall of the elevator shaft 1 is detachably connected to the lifting beam 21. A first positioning groove 55 is provided at one end of the first guide rail 53 along its length direction, and the cross section of the first positioning groove 55 is triangular. A locking assembly 54 is arranged at the other end of the first guide rail 53, and the locking assembly 54 includes a first positioning portion 541, a locking portion 542, and a second driving member 543. The first positioning portion 541 is fixedly connected to the first guide rail 53. The first positioning portion 541 is a columnar shape with a triangular cross-section and is arranged along the length direction of the first guide rail 53. There are three locking portions 542, which are slidably connected to the three side walls of the first positioning portion 541 along the length direction perpendicular to the first guide rail 53, so that one end of the locking portion 542 can penetrate into and out of the side wall of the first positioning portion 541. One end of the first positioning portion 541 is provided with a groove along the length direction of the first guide rail 53. The second driving member 543 includes a first magnet 5431 and a plurality of second magnets 5432, the number of the second magnets 5432 is three, the second magnets 5432 are fixedly connected one by one to one end of the locking portion 542 close to the center line of the first guide rail 53, and the second magnets 5432 are slidably connected to the inside of the first positioning portion 541, the moving direction of the second magnet 5432 is the moving direction of the locking portion 542, the first magnet 5431 is fixedly connected to the bottom wall of the first positioning groove 55, and the facing magnetic poles of the first magnet 5431 and the second magnet 5432 repel each other.
[0032] When connecting two adjacent first rails 53, the first positioning portion 541 is inserted into the first positioning groove 55, so that the locking portion 542 moves in the vertical direction toward the first magnet 5431. Because the magnetic poles of the first magnet 5431 and the second magnet 5432 repel each other, the second magnet 5432 fixedly connected to the locking portion 542 will move in the direction away from the center line of the first rail 53, so that the second magnet 5432 drives the locking portion 542 to pass through the first positioning portion 541 and insert into the locking groove 56, thereby locking the two adjacent first rails 53. This connection method does not require construction workers to carry other tools to connect two adjacent first rails 53, thereby facilitating the installation of adjacent first rails 53.
[0033] The cross-sections of the first positioning portion 541 and the first positioning groove 55 are triangular, which can limit the relative rotation of two adjacent first guide rails 53 and further improve the stability of the connection between the adjacent first guide rails 53 .
[0034] Reference Figure 6 The machine room guide assembly 5 includes a first connection part 51 and a first driving member 52. The first connection part 51 is cylindrical and rotatably connected to the elevator machine room 3. The rotation axis of the first connection part 51 is arranged in the vertical direction. The first connection part 51 is threadedly connected to the first guide rail 53. The first driving member 52 includes a rack 521, a first driving gear 522, a second driving gear 523 and a third driving gear 524. The rack 521 is fixedly connected to the inner wall of the elevator shaft 1 in the vertical direction. The third driving gear 524 is rotatably connected to the elevator machine room 3 and meshes with the rack 521. The rotation axis of the third driving gear 524 is arranged perpendicular to the vertical direction. The second driving gear 523 is coaxially fixedly connected to the third driving gear 524. The first driving gear 522 is coaxially fixedly connected to the first connection part 51. The second driving gear 523 and the first driving gear 522 are bevel gears and mesh with each other.
[0035] When the machine room guide assembly 5 lifts the elevator machine room 3, the third driving gear 524 drives the second driving gear 523 to rotate, the second driving gear 523 drives the first driving gear 522 to rotate, and the first driving gear 522 drives the first connecting part 51 to rotate, so that under the condition that the first connecting part 51 is threadedly connected to the first guide rail 53, the elevator machine room 3 can move in the vertical direction.
[0036] The first guide rail 53 can reduce the shaking of the elevator machine room 3 when it moves, thereby improving the reliability and safety of the elevator machine room 3 during operation, and when the elevator machine room 3 is fixed to the inner wall of the elevator shaft 1 and when the elevator machine room 3 moves, the first guide rail 53 can bear part of the gravity of the elevator machine room 3 and the elevator car 4, thereby reducing the load of the winch, reducing the failure of the winch and the failure of the telescopic bracket of the elevator machine room 3, thereby further improving the reliability and safety of the operation of the elevator machine room 3.
[0037] The implementation principle of a leap-level elevator system with an integrated steel platform and its construction method in an embodiment of the present application is as follows: the first guide rail 53 can limit the shaking of the elevator machine room 3 when it moves, and the first guide rail 53 can bear part of the gravity of the elevator machine room 3 and the elevator car 4, and the second guide rail 62 can limit the shaking of the elevator car 4 when it moves, thereby improving the reliability and safety of the leap-level elevator system during operation.
[0038] The present application also discloses a construction method of a leap-level elevator system with an integrated steel platform, comprising the following steps: S1, construct the elevator shaft 1 to a certain height, and then install the first guide rail 53, the second guide rail 62 and the rack 521 of the corresponding height on the inner wall of the elevator shaft 1; S2. Install the elevator car 4, the elevator machine room 3 and the machine room lifting device 2 in the elevator shaft 1 in sequence, so that the first connecting part 51 is threadedly connected with the first guide rail 53, the third driving gear 524 is meshed with the rack 521, and the second connecting part 61 is slidably connected with the second guide rail 62, so that the elevator machine room 3 can drive the elevator car 4 to move to transport construction personnel and building materials. When the elevator machine room 3 moves, the third driving gear 524 can drive the first connecting part 51 to rotate through the second driving gear 523 and the first driving gear 522, so that the first connecting part 51 can move with the elevator machine room 3, the first guide rail 53 can improve the reliability and safety of the operation of the elevator machine room 3, and the second guide rail 62 can improve the reliability and safety of the elevator car 4; S3, the steel platform 22 climbs up one floor, so that the machine room lifting device 2 moves to a higher floor and transports the elevator machine room 3 to a higher floor, and the elevator machine room 3 is fixed to the inner wall of the elevator shaft 1 at a higher floor by a telescopic bracket, and then the elevator car 4 transports the construction personnel, the first guide rail 53, the second guide rail 62 and the rack 521 to the installation position, and the construction personnel install the first guide rail 53 on the existing first guide rail 53, the second guide rail 62 on the existing second guide rail 62, and the rack 521 on the existing rack 521, so that the elevator car 4 can move to the elevator shaft 1 at a higher floor; S4, repeat steps S1, S2 and S3 until the construction of the elevator shaft 1 on the highest floor is completed, then remove the machine room lifting device 2, and fix the elevator machine room 3 to the elevator shaft 1 through a concrete structure.
[0039] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A leap-deck elevator system with integrated steel platform, characterized in that: include: An elevator shaft (1), wherein the elevator shaft (1) is provided with a machine room lifting device (2), an elevator machine room (3) and an elevator car (4) in sequence from top to bottom, the machine room lifting device (2) being used to drive the elevator machine room (3) to move upward, and the elevator machine room (3) being used to drive the elevator car (4) to move in a vertical direction; A machine room guide assembly (5), the machine room guide assembly (5) comprising a first connecting portion (51), a first driving member (52) and a plurality of first guide rails (53), the first guide rails (53) being screws and being arranged inside the elevator shaft (1) along a vertical direction, the plurality of first guide rails (53) being connected in sequence along a vertical direction, the first connecting portion (51) being rotatably connected to the elevator machine room (3) and being threadedly connected to the first guide rails (53), and the first driving member (52) being used to drive the first connecting portion (51) to rotate; A car guide assembly (6), the car guide assembly (6) comprising a second connecting portion (61) and a plurality of second guide rails (62), the second guide rails (62) being arranged inside the elevator shaft (1) along a vertical direction, the plurality of second guide rails (62) being connected in sequence along a vertical direction, the second connecting portion (61) being fixedly connected to the elevator car (4) and slidably connected to the second guide rails (62).
2. The leap-deck elevator system with integrated steel platform according to claim 1, characterized in that: The first driving member (52) comprises a rack (521), a first driving gear (522), a second driving gear (523) and a third driving gear (524); the rack (521) is arranged inside the elevator shaft (1) along the vertical direction; the first driving gear (522) is coaxially fixedly connected to the first connecting portion (51); the rotation axis of the second driving gear (523) is perpendicular to the rotation axis of the first driving gear (522); the first driving gear (522) is meshed with the second driving gear (523); the third driving gear (524) is meshed with the rack (521) and is coaxially fixedly connected to the second driving gear (523).
3. The leap-deck elevator system with integrated steel platform according to claim 1, characterized in that: A locking assembly (54) is provided at one end of the first guide rail (53), and a first positioning groove (55) is provided at the other end; the locking assembly (54) comprises a first positioning portion (541); the cross section of the first positioning portion (541) is polygonal; the first positioning portion (541) adjacent to the first guide rail (53) is used for plugging into the first positioning groove (55).
4. The leap-deck elevator system with integrated steel platform according to claim 3, characterized in that: The locking assembly (54) comprises a locking portion (542) and a second driving member (543); the locking portion (542) is slidably connected to the first positioning portion (541); the moving direction of the locking portion (542) is perpendicular to the length direction of the first guide rail (53); the second driving member (543) is used to drive the locking portion (542) to slide; a locking groove (56) is formed on the inner wall of the first positioning groove (55) along a direction perpendicular to the length direction of the first guide rail (53); adjacent first guide rails (53) are connected by plugging and fitting the locking portion (542) with the locking groove (56).
5. The leap-deck elevator system with integrated steel platform according to claim 4, characterized in that: The second driving member (543) comprises a first magnet (5431) and a second magnet (5432), the first magnet (5431) being fixedly connected to the bottom wall of the first positioning groove (55), the second magnet (5432) being fixedly connected to the locking portion (542), and the facing magnetic poles of the first magnet (5431) and the second magnet (5432) repel each other; When the first positioning portion (541) moves toward the direction approaching the bottom wall of the first positioning groove (55), the locking portion (542) moves in the vertical direction toward the direction approaching the first magnet (5431), and the opposing magnetic poles of the first magnet (5431) and the second magnet (5432) repel each other, so that the second magnet (5432) drives the locking portion (542) to move in the horizontal direction away from the first magnet (5431), so that the locking portion (542) is plugged into and fitted with the locking groove (56).
6. The leap-deck elevator system with integrated steel platform according to claim 1, characterized in that: The machine room lifting device (2) comprises a lifting beam (21), and one end of the first guide rail (53) away from the bottom wall of the elevator shaft (1) is detachably connected to the lifting beam (21).
7. The leap-deck elevator system with integrated steel platform according to claim 1, characterized in that: The inner wall of the elevator shaft (1) is provided with a second positioning groove (7) in the vertical direction, and the second guide rail (62) is fixedly connected to the inner wall of the second positioning groove (7).
8. A construction method for a split-level elevator system with an integrated steel platform, using the split-level elevator system with an integrated steel platform as claimed in any one of claims 1 to 7, characterized in that: The following steps are involved: S1. After constructing an elevator shaft (1) of a certain height, a first guide rail (53) and a second guide rail (62) are installed inside the elevator shaft (1), and then an elevator car (4), an elevator machine room (3), and a machine room lifting device (2) are installed inside the elevator shaft (1) in sequence along a vertical direction; S2, the elevator car (4) moves to the second guide rail (62), the construction personnel slide the second connection part (61) and the second guide rail (62) together, then the elevator room (3) moves to the first guide rail (53), the construction personnel threadably connect the first connection part (51) and the first guide rail (53), and install the drive assembly; S3, the steel platform (22) climbs up one floor and constructs the elevator shaft (1) of a higher floor, then the machine room lifting device (2) lifts the elevator machine room (3) to a higher floor, the elevator car (4) transports the construction personnel, the first guide rail (53) and the second guide rail (62) to the installation location, then the construction personnel install the first guide rail (53) on the original first guide rail (53), and install the second guide rail (62) on the original second guide rail (62); S4, repeating steps S1, S2 and S3 until the construction of the elevator shaft (1) on the highest floor is completed, then removing the machine room lifting device (2) and fixing the elevator machine room (3) to the elevator shaft (1) on the highest floor.