High pile pier type wharf fabricated abutment structure and construction method thereof

By adopting a combination of thin-wall reinforced concrete structure and truss in the high-pile pier pier platform, the problems of long construction time, high cost and continuous laying of steel bars are solved, efficient installation and construction are achieved, and the stability of the structure is ensured. and durability.

CN118911067APending Publication Date: 2024-11-08CHINA COMM CONSTR FIRST HARBOR CONSULTANTS +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411090679.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

During the construction process, there are problems such as long time, high cost, and easy to cause shrinkage cracks. Prefabricated piers are difficult to achieve during lifting and installation, and continuous laying of steel bars is difficult, and the connection between pile foundation and pier is limited. , affects the quality and durability of the overall structure.

Method used

Thin-wall reinforced concrete structure is combined with trusses, connected with prefabricated piles to form a hollow structure, and lifted onto the pile foundation for measurement, positioning and reinforcement, forming a stable platform, and then bottom plate construction and concrete pouring are carried out to reduce the site Rebar binding and mold erecting improve overall stability and construction efficiency.

Benefits of technology

It realizes efficient prefabricated installation, reduces on-site workload and expenses, improves component quality and construction progress, avoids shrinkage and crack problems, ensures the quality and durability of concrete, and is suitable for winter construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911067A_ABST
    Figure CN118911067A_ABST
Patent Text Reader

Abstract

The invention provides a high-pile pier type wharf fabricated abutment structure and a construction method thereof.The high-pile pier type wharf fabricated abutment structure comprises a thin-wall reinforced concrete structure, a truss and a plurality of prefabricated piles, and the thin-wall reinforced concrete structure is a circumferential closed structure defined by a plurality of thin-wall reinforced concrete plates; a connecting piece used for being connected with a truss is pre-buried in the inner wall of the circumferential closed structure, the truss is arranged in the circumferential closed structure and effectively connected with the inner wall of the circumferential closed structure through the connecting piece, and profile steel used for being effectively connected with the truss is pre-buried in the precast pile. The truss is effectively connected with the section steel, the precast piles and the truss are integrated through concrete pouring, the top and the bottom of the circumferential sealing structure are sealed through a poured reinforced concrete top plate and a poured reinforced concrete bottom plate respectively, a reinforced concrete middle plate is poured in the middle of the circumferential sealing structure, and a plurality of reinforced concrete columns are arranged in the circumferential sealing structure. The two ends of the reinforced concrete column are effectively connected with the reinforced concrete top plate, the middle plate and the reinforced concrete bottom plate respectively.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of dock construction, and in particular to an assembled pier structure of a high-pile pier type dock and a construction method thereof. Background Art

[0002] Conventional high-pile pier-type wharf pier structures mainly include pile foundations and cast-in-place piers. However, there are a large number of problems in the construction of conventional piers as follows: (1) The piers are made of large-volume cast-in-place concrete. During the construction of this structure, it is necessary to build a enclosure system based on the pile foundation, set up the bottom formwork and side formwork for pouring, which is time-consuming and requires high costs for load-bearing hoops or inverted steel beams, wooden planks, formwork and other measures. (2) When pouring the pier concrete, it is necessary to wait for the tide level when constructing in water level fluctuation areas and wave splash zones. The construction time is limited and the newly poured concrete is at risk of being submerged by the tide. (3) Large-volume piers involve layered pouring. After each layer is poured, it is necessary to wait for the strength to be reached before pouring the next layer of concrete. Negative bending reinforcements must also be arranged, which takes a long time and is costly. Expansion and contraction cracks are prone to occur between the upper and lower layers of concrete, affecting the overall quality and durability of the structure.

[0003] Chinese patent CN102943482A discloses a prefabricated pier pretightening water-stopping cofferdam, which includes a prefabricated pier consisting of a pier body and a pier seat, a cofferdam wall body connected to the prefabricated pier, a circumferential ring beam arranged on the prefabricated pier, and an expansion water-stop strip arranged between the prefabricated pier and the circumferential ring beam; the cofferdam wall body is assembled from cofferdam blocks, and the cofferdam wall body is tightened horizontally by a tensioning system; multiple internal support systems are arranged between the inner wall of the cofferdam wall body and the pier body of the prefabricated pier, and a bottom tightening device is arranged between the bottom inner wall of the cofferdam wall body and the pier seat of the prefabricated pier; the cofferdam wall body is tightened longitudinally by a vertical hanging device. The cofferdam wall body is clamped on the prefabricated pier after achieving self-stabilization through various pretightening structures, and the cofferdam wall body is a tool-type assembly combination. After loosening each pretightening device, the steel cofferdam can be dismantled as a whole, and can be repeatedly used after inspection and repair, which greatly reduces the labor intensity, effectively speeds up the construction progress, and further reduces the construction cost.

[0004] Chinese patent CN114775516A discloses an assembled pier structure for dock engineering and its use method: its structure includes pile foundation, slotted modular pier, connecting steel frame, and ancillary facilities; the pile foundation is connected to the lower end of the slotted modular pier, the connecting steel frame is located in the notch at the upper end of the slotted modular pier, and the ancillary facilities are prefabricated on the slotted modular pier; the slotted modular pier includes a berthing module and a mooring module, the notch is located at the connection between the berthing module and the mooring module, the notch is composed of a prefabricated notch of the berthing module and a prefabricated notch of the mooring module, and the notches are evenly distributed on the slotted modular pier; the pile foundation includes steel pipe piles and corrugated steel, and the corrugated steel is welded to the top of the steel pile. This application connects different modules into one by connecting the steel frame and the notch post-casting strip, which ensures the integrity and force transmission effectiveness of the pier structure, and improves the component quality and construction progress by prefabrication.

[0005] Although the above patents provide a technical method for using prefabricated piers, they also give rise to related key technical problems that need to be overcome, including: (1) The piers of the wharf project need to bear huge ship / process equipment loads, there are a large number of lower load-bearing pile foundations, and the plane dimensions of the piers are generally large. It is difficult for general crane equipment to lift and install the prefabricated piers, so they should be split and the piers should be split into multiple modules according to actual use requirements and lifting capacity and prefabricated and installed separately; (2) Conventional cast-in-place piers are equipped with steel bars in all directions of up, down, left, and right, and the concrete is poured continuously on the plane, so that when the entire pier is locally stressed, the rest of the force is transmitted through the pier interior, and the pier is lifted and installed together. Participate in bearing the load and transfer the load to all pile foundations. However, after the pier is modularized and prefabricated separately, continuous laying of steel bars is impossible, so innovative means should be used to connect multiple modules; (3) The steel piles of conventional cast-in-place piers extend into the cast-in-place piers, and the upper and lower parts are reliably connected through the pile core steel cage and pile core concrete. When prefabricated piers are used, the pile foundation and the prefabricated pier can generally only be connected by grouting after reserving pile holes. Limited by the size of the reserved pile holes, the pile foundation needs to be connected and strengthened with the prefabricated pier by innovative means; at the same time, in order to improve the construction efficiency and give full play to the advantages of prefabrication, it should be avoided as much as possible: the pile hole deviation affects the installation of the pile core structure. Summary of the invention

[0006] The idea of ​​the present invention is to design a hollow thin-walled structure of the pier to be fixed with a concrete truss to improve its overall stability, and then the crane ship will hoist the entire structure onto the pile foundation, measure and locate it, and then reinforce it to form a stable construction platform on the water, and then carry out the bottom plate construction, steel bar tying, and concrete pouring.

[0007] In order to solve the above technical problems, the technical solution adopted by the present invention is: an assembled pier structure of a high-pile pier type wharf, comprising a thin-walled reinforced concrete structure, a truss and a plurality of precast piles, wherein the thin-walled reinforced concrete structure is a circumferentially closed structure surrounded by a plurality of thin-walled reinforced concrete plates, the inner wall of the circumferentially closed structure is pre-embedded with a connecting piece for connecting with the truss, the truss is arranged in the circumferentially closed structure, the truss is effectively connected to the inner wall of the circumferentially closed structure through the connecting piece, a steel section for effectively connecting with the truss is pre-embedded in the precast pile, the truss is effectively connected to the steel section, and the precast pile and the truss are formed into one by concrete pouring, the top and bottom of the circumferentially closed structure are respectively closed by a poured reinforced concrete top plate and a reinforced concrete bottom plate, a reinforced concrete middle plate is poured in the middle of the circumferentially closed structure, a plurality of reinforced concrete columns are arranged in the circumferentially closed structure, and the two ends of the reinforced concrete column are respectively effectively connected to the reinforced concrete top plate, the middle plate and the reinforced concrete bottom plate.

[0008] Optionally, the truss is a double-layer structure.

[0009] A prefabricated pier structure of a high-pile pier type wharf, characterized in that it includes a thin-walled reinforced concrete structure, a truss and a plurality of precast piles, the thin-walled reinforced concrete structure is a circumferentially closed structure surrounded by a plurality of thin-walled reinforced concrete slabs, the inner wall of the circumferentially closed structure is pre-embedded with connecting pieces for connecting to the truss, the truss is arranged in the circumferentially closed structure, the truss is effectively connected to the inner wall of the circumferentially closed structure through the connecting pieces, the precast piles are pre-embedded with steel sections for effectively connecting to the truss, the truss is effectively connected to the steel sections, and the precast piles and the truss are formed into one body through concrete pouring, the bottom of the circumferentially closed structure is closed by a poured reinforced concrete bottom plate, and the circumferentially closed structure is filled with reinforced concrete.

[0010] A construction method of the above-mentioned high-pile pier type wharf assembled pier structure comprises the following steps:

[0011] ⑴ Prefabricated thin-wall reinforced concrete structure;

[0012] ⑵ Prefabricate trusses according to the location of piles and the size of thin-walled concrete structures;

[0013] ⑶ Effectively connect the thin-walled reinforced concrete structure to the truss through the connection points on the side of the truss and the connectors inside the thin-walled reinforced concrete structure;

[0014] (4) The on-site pile foundation is cut to the designed elevation, and the assembly connecting the thin-walled reinforced concrete structure and the truss in step (3) is hoisted onto the pile foundation, and is effectively connected to the truss in the assembly through the steel embedded in the prefabricated pile;

[0015] (5) Use the trusses, the steel plates embedded in the side walls of the thin-walled reinforced concrete structure and the composite steel beams to hang the bottom formwork for pouring the concrete bottom slab, tie the steel bars, install the reinforced concrete columns and fix them, and then pour the bottom slab concrete;

[0016] (6) Tie up the steel bars around the piles, support the formwork, and pour concrete;

[0017] ⑺Lift the top formwork for pouring concrete middle slab, tie the steel bars, and then pour the top slab concrete.

[0018] ⑻Lift the top formwork for pouring the concrete top slab, tie the steel bars, and then pour the top slab concrete.

[0019] ⑼ Cover and cure the concrete.

[0020] A construction method of the above-mentioned high-pile pier type wharf assembled pier structure comprises the following steps:

[0021] ⑴ Prefabricated thin-wall reinforced concrete structure;

[0022] ⑵ Prefabricate trusses according to the location of piles and the size of thin-walled concrete structures;

[0023] ⑶ Effectively connect the thin-walled reinforced concrete structure to the truss through the connection points on the side of the truss and the connectors inside the thin-walled reinforced concrete structure;

[0024] (4) The on-site pile foundation is cut to the designed elevation, and the assembly connecting the thin-walled reinforced concrete structure and the truss in step (3) is hoisted onto the pile foundation, and is effectively connected to the truss in the assembly through the steel embedded in the prefabricated pile;

[0025] (5) Use the truss, the steel plate embedded in the side wall of the thin-wall reinforced concrete structure and the composite steel beam to hang the bottom formwork for pouring the concrete bottom plate, tie the steel bars, and then pour the bottom plate concrete;

[0026] (6) Tie up the steel bars and pour the remaining concrete in steps according to the load-bearing conditions of the bottom slab;

[0027] ⑺Cover and cure the concrete.

[0028] The advantages and positive effects of the present invention are:

[0029] 1. The present invention combines the advantages of high efficiency and good quality of prefabricated installation and the advantages of good integrity of cast-in-place concrete, which reduces the workload of on-site steel bar binding, formwork erection and cast-in-place concrete to the greatest extent. It is no longer necessary to build enclosure systems and formwork on site, which can improve the quality of components, speed up construction progress and reduce the cost of measures;

[0030] 2. The prefabricated reinforced concrete thin-walled structure is lighter in weight and has a hollow bottom design, which is no longer affected by piles, making installation more efficient. It can also be used as a construction platform, which is less affected by wind and waves, making construction safer and quality more guaranteed.

[0031] 3. The utilization rate of ship machinery is greatly improved, the construction period is controlled, and the project cost is reduced;

[0032] 4. Prefabricated reinforced concrete thin-walled structures are all prefabricated in land factories, with better quality assurance. The concrete is poured in layers inside the piers, which effectively solves the problem of expansion and contraction cracks that are easily generated between the upper and lower layers of concrete on traditional piers, affecting the overall quality and durability of the structure.

[0033] 5. The hollow thin-wall structure is conducive to concrete maintenance and winter concrete construction insulation, ensuring the quality of cast-in-place concrete. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 It is a structural schematic diagram of a specific implementation mode 1 of the present invention;

[0035] Figure 2 yes Figure 1 Schematic diagram of the structure without the top plate and bottom plate;

[0036] Figure 3 yes Figure 2 Top view without top and bottom plates;

[0037] Figure 4 yes Figure 1 Top view of the middle truss well frame;

[0038] Figure 5 yes Figure 4 1-1 is a schematic diagram of the cross section;

[0039] Figure 6 yes Figure 4 2-2 is a schematic diagram of the cross section;

[0040] In the figure: 1. Thin-walled reinforced concrete structure; 1-1. Reinforced concrete top plate; 1-2. Reinforced concrete middle plate; 1-3. Reinforced concrete bottom plate; 2. Truss; 3. Connection point; 3-1. Pin hole position; 4. Pile core concrete; 5. Steel section; 6. Steel plate; 7. Reinforced concrete column; 8. Position for pouring concrete around precast piles. DETAILED DESCRIPTION

[0041] The present invention is further described in detail below in conjunction with specific embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention. In the description of the present invention, it should be understood that the orientation or position relationship indicated by the terms "center", "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. is based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention. In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be a connection between the two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood by specific circumstances. Specific implementation method one:

[0043] like Figures 1 to 6 As shown, the present invention provides an assembled pier structure of a high-pile pier type wharf, comprising a thin-walled reinforced concrete structure 1, a truss 2 and a plurality of precast piles, wherein the thin-walled reinforced concrete structure 1 is a circumferentially closed structure surrounded by a plurality of thin-walled reinforced concrete plates, the inner wall of the circumferentially closed structure is pre-embedded with a connecting piece for connecting with the truss 2, the truss 2 is arranged in the circumferentially closed structure, the truss 2 is effectively connected to the inner wall of the circumferentially closed structure through the connecting piece, a profile pipe 5 for effectively connecting with the truss 2 is pre-embedded in the precast pile 4, the truss 2 is effectively connected to the profile pipe 5, and the precast pile and the truss 2 are formed into one by concrete pouring, the top and bottom of the circumferentially closed structure are respectively closed by pouring a reinforced concrete top plate 1-1 and a reinforced concrete bottom plate 1-3, a reinforced concrete intermediate plate 1-2 is poured in the middle of the circumferentially closed structure, a plurality of reinforced concrete columns 7 are arranged in the circumferentially closed structure, and the two ends of the reinforced concrete column 7 are respectively effectively connected to the reinforced concrete top plate 1-1 and the reinforced concrete bottom plate 1-3.

[0044] The truss 2 is a double-layer structure. Some holes are reserved on the truss 2 for hoisting the bottom formwork. The truss 2 can be a steel truss or a reinforced concrete truss.

[0045] The pier structure is a hollow thin-walled structure, in which the upper and lower parts of the thin-walled reinforced concrete structure 1 are both cavity structures. The overall stability of the pier is improved by fixing it with the truss 2 in the middle of the thin-walled reinforced concrete structure 1. The truss 2 is reliably connected to the pile foundation. A plurality of reinforced concrete columns 7 are arranged in the thin-walled reinforced concrete structure 1 to strengthen the internal structure. When the pier of this design structure is subjected to force, it is mainly transmitted to the truss 2, and then transmitted to the prefabricated piles through the truss 2. The overall force system is different from the existing technology and is more reasonable and safe. It effectively reduces the weight of the pier, achieves a lightweight and high-strength design structure, reduces the project cost, and effectively reduces the hydration heat of large-volume concrete.

[0046] The present invention also provides a construction method for the above-mentioned pier, comprising the following steps:

[0047] ⑴ Prefabricate the thin-wall reinforced concrete structure of the pier in the land prefabrication yard according to the drawings 1;

[0048] (2) According to the pile position and the structure of the pier, the metal truss of the truss 2 is designed, and the upper and lower layers are poured with reinforced concrete to form the truss 2;

[0049] ⑶ After the concrete reaches the required strength, assemble the thin-walled reinforced concrete structure 1 and the truss 2, with 4 points on each side, for a total of 16 connection points (the number of connection points can be increased according to design calculations);

[0050] (4) The on-site pile foundation is cut to the designed elevation, the thin-walled hollow structure assembled in step (3) is transported to the site, the crane ship is in place, and the installation is carried out. The surveying personnel measure and locate it to the designed position, and then the prefabricated pile 4 medium steel and the truss 2 are reliably connected;

[0051] (5) The bottom formwork for pouring the concrete bottom plate 1-3 is hung upside down through the truss 2, the steel plate embedded in the side wall of the thin-wall reinforced concrete structure 1, and the composite steel beam, and the steel bars are tied, and then the bottom plate concrete is poured;

[0052] (6) Tie up the steel bars around the precast piles, support the formwork, and pour concrete;

[0053] ⑺Lift the top formwork for pouring concrete middle slab, tie the steel bars, and then pour the top slab concrete.

[0054] ⑻Lift the top formwork for pouring the concrete top slab 1-1, tie the steel bars, and then pour the top slab concrete;

[0055] ⑼ Cover and cure the concrete. Specific implementation method 2:

[0057] In view of the situation where there are relatively many loads and the stress conditions are complicated, taking the chemical terminal as an example, large oil transfer arms, fire cannons, quick release hooks, boarding ladders, pipelines, and trenches are provided. The present invention provides a solid high-pile pier type wharf prefabricated pier structure. Specifically: a high-pile pier type wharf prefabricated pier structure, including a thin-walled reinforced concrete structure 1, a truss 2 and a plurality of precast piles, the thin-walled reinforced concrete structure 1 is a circumferentially closed structure surrounded by a plurality of thin-walled reinforced concrete slabs, the inner wall of the circumferentially closed structure is pre-embedded with a connecting piece for connecting with the truss 2, the truss 2 is arranged in the circumferentially closed structure, the truss 2 is effectively connected to the inner wall of the circumferentially closed structure through the connecting piece, the precast pile is pre-embedded with a steel section 5 for effectively connecting with the truss 2, the truss 2 is effectively connected to the steel section 5, and the precast pile and the truss 2 are formed into one by concrete pouring, the bottom of the circumferentially closed structure is closed by a poured reinforced concrete bottom plate 1-3, and the circumferentially closed structure is filled with reinforced concrete.

[0058] The pier structure is a hollow thin-walled structure. It is fixed with the truss 2 in the middle of the thin-walled reinforced concrete structure 1 to improve the overall stability of the pier. The truss 2 is reliably connected to the pile foundation and transmitted to the prefabricated pile column through the truss 2. The overall force system is different from the existing technology and is more reasonable and safe. It forms effective protection conditions and favorable construction conditions. After the bottom plate is poured, the upper concrete pouring is simpler and easier, the construction is fast, safe and reliable, the quality is more guaranteed, the cost is low, and the hydration heat of large-volume concrete is effectively reduced, which is more conducive to the construction quality of winter concrete.

[0059] The present invention also provides a construction method for the above-mentioned pier, comprising the following steps:

[0060] ⑴ Prefabricated thin-wall reinforced concrete structure;

[0061] ⑵ Prefabricate trusses according to the location of piles and the size of thin-walled concrete structures;

[0062] ⑶ Effectively connect the thin-walled reinforced concrete structure to the truss through the connection points on the side of the truss and the connectors inside the thin-walled reinforced concrete structure;

[0063] (4) The on-site pile foundation is cut to the designed elevation, and the assembly connecting the thin-walled reinforced concrete structure and the truss in step (3) is hoisted onto the pile foundation, and is effectively connected to the truss in the assembly through the steel embedded in the prefabricated pile;

[0064] (5) Use the truss, the steel plate embedded in the side wall of the thin-wall reinforced concrete structure and the composite steel beam to hang the bottom formwork for pouring the concrete bottom plate, tie the steel bars, and then pour the bottom plate concrete;

[0065] (6) Tie up the steel bars and pour the remaining concrete in steps according to the load-bearing conditions of the bottom slab;

[0066] ⑺Cover and cure the concrete.

[0067] The embodiments of the present invention are described in detail above, but the contents described are only preferred embodiments of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A prefabricated pier structure of a high pile pier type wharf, characterized by: The invention comprises a thin-walled reinforced concrete structure, a truss and a plurality of precast piles, wherein the thin-walled reinforced concrete structure is a circumferentially closed structure surrounded by a plurality of thin-walled reinforced concrete plates, the inner wall of the circumferentially closed structure is pre-embedded with a connecting piece for connecting with the truss, the truss is arranged in the circumferentially closed structure, the truss is effectively connected to the inner wall of the circumferentially closed structure through the connecting piece, a steel section for effectively connecting with the truss is pre-embedded in the precast pile, the truss is effectively connected to the steel section, and the precast pile and the truss are integrated by concrete pouring, the top and the bottom of the circumferentially closed structure are closed by respectively pouring a reinforced concrete top plate and a reinforced concrete bottom plate, a reinforced concrete middle plate is poured in the middle of the circumferentially closed structure, a plurality of reinforced concrete columns are arranged in the circumferentially closed structure, and the two ends of the reinforced concrete columns are respectively effectively connected to the reinforced concrete top plate, the middle plate and the reinforced concrete bottom plate.

2. The assembled pier structure of the high pile pier type wharf according to claim 1 is characterized by: The truss is a double-layer structure.

3. A prefabricated pier structure of a high pile pier type wharf, characterized by: The invention comprises a thin-walled reinforced concrete structure, a truss and a plurality of precast piles. The thin-walled reinforced concrete structure is a circumferentially closed structure surrounded by a plurality of thin-walled reinforced concrete plates. The inner wall of the circumferentially closed structure is pre-embedded with connecting pieces for connecting with the truss. The truss is arranged in the circumferentially closed structure. The truss is effectively connected to the inner wall of the circumferentially closed structure through the connecting pieces. The precast piles are pre-embedded with steel sections for effectively connecting with the truss. The truss is effectively connected to the steel sections, and the precast piles and the truss are integrated by concrete pouring. The bottom of the circumferentially closed structure is closed by a poured reinforced concrete bottom plate, and the circumferentially closed structure is filled with reinforced concrete.

4. The construction method of the assembled pier structure of the high-pile pier type wharf according to any one of claims 1 or 2, comprising the following steps: ⑴ Prefabricated thin-wall reinforced concrete structure; ⑵ Prefabricate trusses according to the location of piles and the size of thin-walled concrete structures; ⑶ Effectively connect the thin-walled reinforced concrete structure to the truss through the connection points on the side of the truss and the connectors inside the thin-walled reinforced concrete structure; (4) The on-site pile foundation is cut to the designed elevation, and the assembly connecting the thin-walled reinforced concrete structure and the truss in step (3) is hoisted onto the pile foundation, and is effectively connected to the truss in the assembly through the steel embedded in the prefabricated pile; (5) Use the trusses, the steel plates embedded in the side walls of the thin-walled reinforced concrete structure and the composite steel beams to hang the bottom formwork for pouring the concrete bottom slab, tie the steel bars, install the reinforced concrete columns and fix them, and then pour the bottom slab concrete; (6) Tie up the steel bars around the piles, support the formwork, and pour concrete; ⑺Lift the top formwork for pouring concrete middle slab, tie the steel bars, and then pour the top slab concrete. ⑻Lift the top formwork for pouring the concrete top slab, tie the steel bars, and then pour the top slab concrete. ⑼ Cover and cure the concrete.

5. The construction method of the assembled pier structure of the high-pile pier type wharf according to claim 3 comprises the following steps: ⑴ Prefabricated thin-wall reinforced concrete structure; ⑵ Prefabricate trusses according to the location of piles and the size of thin-walled concrete structures; ⑶ Effectively connect the thin-walled reinforced concrete structure to the truss through the connection points on the side of the truss and the connectors inside the thin-walled reinforced concrete structure; (4) The on-site pile foundation is cut to the designed elevation, and the assembly connecting the thin-walled reinforced concrete structure and the truss in step (3) is hoisted onto the pile foundation, and is effectively connected to the truss in the assembly through the steel embedded in the prefabricated pile; ⑸ Use the trusses, pre-embedded steel plates and composite steel beams in the side walls of the thin-walled reinforced concrete structure to hang the bottom formwork for pouring the concrete bottom slab, tie the steel bars, and then pour the bottom slab concrete; ⑹ According to the load-bearing conditions of the bottom slab, tie the steel bars and pour the remaining concrete in steps; ⑺ Cover and cure the concrete.