Construction method for inner guide hole of steel pipe pile in super-thick pebble bed
By introducing a rotary drilling mechanism and disassembly and assembly mechanism into the steel pipe pile pipe, combined with a servo motor and a suction pump, the problem of low pile sinking efficiency of steel pipe piles in the pebble layer is solved, and efficient drilling and pile sinking is achieved. Reduce costs and improve construction quality.
Patent Information
- Application Number
- CN202410950596.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-16
- Publication Date
- 2024-11-08
AI Technical Summary
The existing steel pipe piles are inefficient and costly on hard ground such as pebble layers, and cannot effectively ensure construction quality.
The construction method of the pipe lead holes of the steel pipe piles is adopted, and the rotary drilling mechanism is connected to the vehicle body. The drive motor, servo motor and suction pump are used to achieve rapid breaking and depth extension of the steel pipe piles, combined with Disassembly and assemble the mechanism and slag discharge system to improve drilling efficiency and quality.
The pile sinking efficiency and drilling depth of steel pipe piles in super-thick pebbles are improved, construction costs are reduced, and construction quality and efficiency are ensured.
Smart Images

Figure CN118911134A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel pipe pile construction, in particular to a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer. Background Art
[0002] The steel pipe pile inner hole construction method is an engineering technology that drills holes inside the steel pipe pile to form a space inside the steel pipe pile to facilitate subsequent construction operations, such as installing steel cages and pouring concrete. This method is usually used in pile foundation construction for projects such as bridges, high-rise buildings, and port facilities.
[0003] However, when using existing steel pipe piles, they are generally hoisted to a predetermined position by a crane, and then sunk into the soil layer by a vibrating hammer or a static pressure hammer until the designed elevation is reached. However, this method is costly to use, and it is not possible to effectively sink the piles on hard soil layers such as pebble layers, resulting in slow construction efficiency and inability to ensure construction quality. Therefore, a method for constructing a steel pipe pile with an inner hole in an ultra-thick pebble layer is proposed. Summary of the invention
[0004] Based on the above-mentioned existing technical problems, the present invention proposes a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer.
[0005] The invention provides a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer, comprising the following construction steps:
[0006] S1. Steel pipe pile sinking: The steel pipe pile is connected to the vehicle body through a connecting mechanism, so that the movement of the vehicle body drives the steel pipe pile to be transported to a predetermined position.
[0007] S2. Drilling holes in steel pipe piles: A rotary drilling mechanism is installed in the steel pipe piles, and the rotary drilling mechanism is connected to the vehicle body to break the pebble layer.
[0008] S3. Drilling construction: The disassembly and assembly mechanism on the rotary drilling mechanism makes it easy to extend the length and continue to drive the steel pipe pile into the next section of the driving depth when the soil is taken.
[0009] S4. Deslagging: During the drilling process, use a suction pump to regularly discharge the drill cuttings, and use an air pump to blow air into the borehole to ensure smooth drilling.
[0010] S5. End of drilling: When the drill bit reaches the designed depth, stop drilling and pull the drill bit out of the steel pipe pile.
[0011] Preferably, a support frame is hinged to the surface of the vehicle body through a hydraulic arm, a groove is opened on the surface of the support frame, a first screw is installed on the inner wall of the groove through a bearing, a driving motor is fixedly installed on the inner wall of the support frame, an output shaft of the driving motor is fixedly sleeved on one end of the first screw, a moving block is threadedly sleeved on the surface of the first screw, the surface of the moving block is slidably engaged with the inner wall of the groove, and a mounting shell is fixedly installed on the surface of the moving block.
[0012] Through the above technical solution, the rotation of the output shaft of the driving motor drives the first screw connected thereto to rotate, and the rotation of the first screw drives the moving block connected thereto to move along the inner wall of the groove, and the movement of the moving block drives the installation shell to move.
[0013] Preferably, the connecting mechanism includes guide grooves distributed in a circular array on the lower surface of the mounting shell, the inner wall of the guide groove is installed with a second screw through a bearing, the outer surface of the mounting shell is installed with a servo motor distributed in a circular array, the output shaft of the servo motor is fixedly sleeved with one end of the second screw, a slider is fixedly sleeved on the surface of the second screw, the surface of the slider is slidably engaged with the inner wall of the guide groove, the lower surface of the slider is fixedly connected to an arc-shaped clamping plate, and the arc-shaped clamping plate is in contact with the steel pipe pile.
[0014] Through the above technical scheme, the rotation of the servo motor output shaft drives the second screw connected to it to rotate, and the rotation of the second screw drives the slider connected to it to move along the inner wall of the guide groove, and the movement of the slider drives the arc clamping plate to move, so that the steel pipe pile is clamped by the relative movement of the four arc clamping plates.
[0015] Preferably, the rotary drilling mechanism comprises a rotary motor fixedly mounted in the mounting housing, one end of the output shaft of the rotary motor passes through the mounting housing and is fixedly sleeved with a connecting rod, and the connecting rod is mounted on the lower surface of the mounting housing through a bearing.
[0016] Through the above technical solution, the rotation of the output shaft of the rotating motor drives the connecting rod connected thereto to rotate, and at the same time the connecting rod is installed under the mounting housing through a bearing, so that the rotation stability of the connecting rod is improved.
[0017] Preferably, a guard rod is provided at the lower end of the connecting rod, a grinding drill bit is fixedly mounted on the lower surface of the guard rod, and an impact drill bit is mounted on the lower surface of the grinding drill bit.
[0018] Through the above technical solution, the rotation of the connecting rod drives the guard rod to rotate, and the rotation of the guard rod drives the grinding drill bit and the impact drill bit to rotate.
[0019] Preferably, the disassembly and assembly mechanism includes a fixing ring fixedly sleeved on the outer surface of the guard rod, the inner surface of the fixing ring is slidably connected to the surface of the guard rod, the outer surface of the fixing ring is fixedly installed with a supporting ring, the outer surface of the supporting ring is installed with pushing cylinders distributed in an annular array, one end of the piston rod of the pushing cylinder extends into the fixing ring and is fixedly connected with a clamping column, the inner surface of the fixing ring is provided with limiting grooves distributed in an annular array, the surface of the guard rod is provided with clamping grooves distributed in an annular array, and the surface of the clamping column is clamped with the inner wall of the clamping groove.
[0020] Through the above technical solution, the cylinder piston rod is pushed out to drive the clamping column connected thereto to be inserted into the clamping slot along the inner wall of the limiting slot.
[0021] Preferably, a stepper motor is fixedly mounted on the inner wall of the clamping column, and an adjusting disk is fixedly sleeved on one end of the output shaft of the stepper motor.
[0022] Through the above technical solution, the rotation of the output shaft of the stepping motor drives the adjusting disk connected thereto to rotate.
[0023] Preferably, springs are fixedly installed on the outer surface of the adjustment disk in a circular array, a clamping plate is fixedly installed on the free end of the spring, and sliding grooves are opened on the outer surface of the clamping column in a circular array, and the surface of the clamping plate is slidably engaged with the inner wall of the sliding groove.
[0024] Through the above technical solution, as the adjusting disk rotates, the card plate is driven to move along the inner wall of the slide slot. In order to facilitate the reset of the card plate moved out of the slide slot, the elastic force of the spring drives the card plate to reset when the adjusting disk rotates.
[0025] Preferably, the inner wall of the steel pipe pile is provided with slag discharge pipes in a circular array, the lower end of the slag discharge pipe extends out of the lower end of the steel pipe pile, and the upper end of the slag discharge pipe extends out of the upper end of the steel pipe pile and is connected to a suction pump.
[0026] Through the above technical solution, the suction pump allows the broken drill cuttings to be discharged from the steel pipe pile through the slag discharge pipe.
[0027] Preferably, an air blowing pipe is provided on the inner wall of the guard rod, the lower end of the air blowing pipe extends to the inner wall of the grinding drill bit, the outer surface of the grinding drill bit is provided with air outlets distributed in a circular array, the air outlets are connected to the air blowing pipe, and the upper end of the air blowing pipe extends out of the steel pipe pile and is connected to the air pump.
[0028] Through the above technical solution, the air pump allows the gas to extend to the grinding drill bit through the air blowing pipe and be discharged from the grinding drill bit through the air outlet, thereby preventing drill cuttings from adhering to the grinding drill bit and facilitating the slag discharge pipe to absorb the drill cuttings.
[0029] The beneficial effects of the present invention are:
[0030] 1. By setting up the disassembly and assembly mechanism, it is convenient to connect the connecting rod and the guard rod together, so that the rotation of the output shaft of the driving motor drives the connecting rod to rotate and can drive the guard rod to move, thereby making the grinding drill bit and the impact drill bit rotate, which is convenient for quickly breaking the ultra-thick pebble layer. At the same time, the original guard rod can be extended by splicing another section of the guard rod, thereby increasing the penetration depth of the impact drill bit, facilitating pile sinking, and improving the utilization efficiency of the existing drilling holes.
[0031] 2. By setting up a connecting mechanism, it is convenient to synchronize the sinking and breaking of the steel pipe piles. The rotation of the output shaft of the servo motor drives the second screw connected to it to rotate, and the rotation of the four second screws drives the arc-shaped clamping plates connected to them to move relatively. When the four arc-shaped clamping plates gather together, the steel pipe pile is connected to the vehicle body, so that it is sleeved on the outer surface of the guard rod, which makes it easy to insert the steel pipe pile into the drill hole when the impact drill bit and the grinding drill bit are drilling, thereby improving the construction efficiency.
[0032] 3. By setting up a rotary drilling mechanism, adjust the drilling parameters, including drill bit rotation speed, drilling pressure, etc. according to the actual situation on site to ensure drilling efficiency and quality. Apply drilling pressure while rotating the impact drill bit and the grinding drill bit to press the impact drill bit into the pebble layer. During the drilling process, the suction pump and air pump are used to discharge the drill cuttings out of the steel pipe pile to ensure smooth drilling, thereby improving the drilling efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 A schematic diagram of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0034] Figure 2 A three-dimensional diagram of the first screw structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0035] Figure 3 A three-dimensional diagram of the grinding drill bit structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0036] Figure 4 A three-dimensional diagram of the guard rod structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0037] Figure 5 A three-dimensional diagram of the air outlet structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0038] Figure 6 A three-dimensional diagram of the slag discharge pipe structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0039] Figure 7A three-dimensional diagram of the arc-shaped cardboard structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0040] Figure 8 A three-dimensional diagram of the guide groove structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0041] Fig. 9 A three-dimensional diagram of the fixing ring structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0042] Fig.10 A three-dimensional diagram of the limit groove structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0043] Fig.11 A three-dimensional diagram of a column clamping structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention;
[0044] Fig.12 A three-dimensional diagram of the adjusting disk structure of a method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer proposed by the present invention.
[0045] In the figure: 1. guide groove; 101. second screw rod; 102. servo motor; 103. slider; 104. arc-shaped clamping plate; 2. steel pipe pile; 3. vehicle body; 4. rotating motor; 41. connecting rod; 42. guard rod; 43. grinding drill bit; 44. impact drill bit; 5. fixing ring; 501. support ring; 502. pushing cylinder; 503. clamping column; 504. limit groove; 505. clamping groove; 506. stepping motor; 507. adjusting disk; 508. spring; 509. clamping plate; 510. slide groove; 6. supporting frame; 7. groove; 8. first screw rod; 9. driving motor; 10. moving block; 11. mounting shell; 12. slag discharge pipe; 13. air blowing pipe; 14. air outlet. DETAILED DESCRIPTION
[0046] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0047] Reference Figure 1-Figure 12 A method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer, comprising the following construction steps:
[0048] S1. Steel pipe pile sinking: The steel pipe pile 2 is connected to the vehicle body 3 through a connecting mechanism, so that the movement of the vehicle body 3 drives the steel pipe pile 2 to be transported to a predetermined position.
[0049] S2. Drilling holes in steel pipe piles: A rotary drilling mechanism is installed in the steel pipe pile 2, and the rotary drilling mechanism is connected to the vehicle body 3 to break the pebble layer.
[0050] S3, drilling construction: the disassembly and assembly mechanism on the rotary drilling mechanism is convenient for extending and continuing to drive into the steel pipe pile 2 when taking soil to the next driving depth.
[0051] S4. Deslagging: During the drilling process, use a suction pump to regularly discharge the drill cuttings, and use an air pump to blow air into the borehole to ensure smooth drilling.
[0052] S5, drilling end: when the drill bit reaches the designed depth, drilling is stopped and the drill bit is pulled out of the steel pipe pile 2.
[0053] In order to cooperate with the rotary drilling mechanism to facilitate the sinking of the steel pipe pile 2, a support frame 6 is hinged on the surface of the vehicle body 3 through a hydraulic arm, and a groove 7 is opened on the surface of the support frame 6. The inner wall of the groove 7 is installed with a first screw 8 through a bearing, and a driving motor 9 is fixedly installed on the inner wall of the support frame 6. The output shaft of the driving motor 9 is fixedly sleeved with one end of the first screw 8, and a moving block 10 is threadedly sleeved on the surface of the first screw 8. The surface of the moving block 10 is slidably engaged with the inner wall of the groove 7, and a mounting shell 11 is fixedly installed on the surface of the moving block 10. The rotation of the output shaft of the driving motor 9 drives the first screw 8 connected thereto to rotate, and the rotation of the first screw 8 drives the moving block 10 connected thereto to move along the inner wall of the groove 7, and the movement of the moving block 10 drives the mounting shell 11 to move.
[0054] In order to connect the steel pipe pile 2 with the vehicle body 3, the connecting mechanism includes a guide groove 1 distributed in a circular array on the lower surface of the mounting shell 11, the inner wall of the guide groove 1 is installed with a second screw 101 through a bearing, and the outer surface of the mounting shell 11 is installed with a servo motor 102 distributed in a circular array, the output shaft of the servo motor 102 is fixedly sleeved with one end of the second screw 101, and a slider 103 is fixedly sleeved on the surface of the second screw 101, and the surface of the slider 103 is slidably engaged with the inner wall of the guide groove 1, and the lower surface of the slider 103 is fixedly connected with an arc clamping plate 104, and the arc clamping plate 104 is in contact with the steel pipe pile 2. The rotation of the output shaft of the servo motor 102 drives the second screw 101 connected thereto to rotate, and the rotation of the second screw 101 drives the slider 103 connected thereto to move along the inner wall of the guide groove 1, and the movement of the slider 103 drives the arc clamping plate 104 to move, so that the steel pipe pile 2 is clamped by the relative movement of the four arc clamping plates 104.
[0055] By setting up a connecting mechanism, it is convenient to synchronize the sinking and breaking of the steel pipe pile 2. The rotation of the output shaft of the servo motor 102 drives the second screw 101 connected thereto to rotate. The rotation of the four second screws 101 respectively drives the arc-shaped clamping plates 104 connected thereto to move relatively. When the four arc-shaped clamping plates 104 are gathered together, the steel pipe pile 2 is connected to the vehicle body 3, so that it is sleeved on the outer surface of the guard rod 42, which makes it convenient for the steel pipe pile 2 to be inserted into the drill hole when the impact drill bit 44 and the grinding drill bit 43 are drilling, thereby improving the construction efficiency.
[0056] In order to break the pebble layer, the rotary drilling mechanism includes a rotary motor 4 fixedly installed in the mounting shell 11. One end of the output shaft of the rotary motor 4 passes through the mounting shell 11 and is fixedly sleeved with a connecting rod 41. The connecting rod 41 is installed on the lower surface of the mounting shell 11 through a bearing. The rotation of the output shaft of the rotary motor 4 drives the connecting rod 41 connected thereto to rotate. At the same time, the connecting rod 41 is installed under the mounting shell 11 through a bearing, so that the rotation stability of the connecting rod 41 is improved.
[0057] In order to break the ultra-thick pebble layer, a guard rod 42 is provided at the lower end of the connecting rod 41, a grinding drill bit 43 is fixedly installed on the lower surface of the guard rod 42, and an impact drill bit 44 is installed on the lower surface of the grinding drill bit 43. The rotation of the connecting rod 41 drives the guard rod 42 to rotate, and the rotation of the guard rod 42 drives the grinding drill bit 43 and the impact drill bit 44 to rotate.
[0058] In order to facilitate the discharge of drill cuttings from the steel pipe pile 2, slag discharge pipes 12 are arranged in a circular array on the inner wall of the steel pipe pile 2. The lower end of the slag discharge pipe 12 extends out of the lower end of the steel pipe pile 2, and the upper end of the slag discharge pipe 12 extends out of the upper end of the steel pipe pile 2 and is connected to a suction pump. The suction pump allows the crushed drill cuttings to be discharged from the steel pipe pile 2 through the slag discharge pipe 12.
[0059] In order to prevent the grinding drill bit 43 from adhering to drill cuttings, an air blowing pipe 13 is provided on the inner wall of the guard rod 42, and the lower end of the air blowing pipe 13 extends to the inner wall of the grinding drill bit 43, and the outer surface of the grinding drill bit 43 is provided with air outlets 14 distributed in a circular array, and the air outlets 14 are connected to the air blowing pipe 13, and the upper end of the air blowing pipe 13 extends out of the steel pipe pile 2 and is connected to the air pump. The air pump allows the gas to extend to the grinding drill bit 43 through the air blowing pipe 13, and discharge the grinding drill bit 43 through the air outlet 14, thereby preventing drill cuttings from adhering to the grinding drill bit 43, and also facilitating the slag discharge pipe 12 to absorb the drill cuttings.
[0060] By setting up a rotary drilling mechanism, the drilling parameters, including the drill bit rotation speed, drilling pressure, etc., are adjusted according to the actual situation on site to ensure the drilling efficiency and quality. The drilling pressure is applied while the impact drill bit 44 and the grinding drill bit 43 are rotating to press the impact drill bit 44 into the pebble layer. During the drilling process, the drill cuttings are discharged outside the steel pipe pile 2 through the suction pump and the air pump to ensure smooth drilling, thereby improving the drilling efficiency.
[0061] In order to increase the drilling depth, the disassembly and assembly mechanism includes a fixing ring 5 fixedly sleeved on the outer surface of the guard rod 42, the inner surface of the fixing ring 5 is slidably connected to the surface of the guard rod 42, the outer surface of the fixing ring 5 is fixedly installed with a support ring 501, the outer surface of the support ring 501 is installed with a pushing cylinder 502 distributed in an annular array, one end of the piston rod of the pushing cylinder 502 extends into the fixing ring 5 and is fixedly connected with a clamping column 503, the inner surface of the fixing ring 5 is provided with a limiting groove 504 distributed in an annular array, the surface of the guard rod 42 is provided with a clamping groove 505 distributed in an annular array, the surface of the clamping column 503 is clamped with the inner wall of the clamping groove 505, and the clamping column 503 connected thereto is driven by the extension and retraction of the piston rod of the pushing cylinder 502 to be inserted into the clamping groove 505 along the inner wall of the limiting groove 504.
[0062] In order to make the connection between the card column 503 and the card slot 505 tighter, a stepper motor 506 is fixedly installed on the inner wall of the card column 503, and an adjusting disk 507 is fixedly sleeved on one end of the output shaft of the stepper motor 506. The outer surface of the adjusting disk 507 is fixedly installed with springs 508 distributed in an annular array, and a clamping plate 509 is fixedly installed on the free end of the spring 508. The outer surface of the card column 503 is provided with a slide groove 510 distributed in an annular array. The surface of the clamping plate 509 is slidably engaged with the inner wall of the slide groove 510. The rotation of the output shaft of the stepper motor 506 drives the adjusting disk 507 connected thereto to rotate. As the adjusting disk 507 rotates, the clamping plate 509 is driven to move along the inner wall of the slide groove 510. In order to facilitate the reset of the clamping plate 509 moved out of the slide groove 510, the elastic force of the spring 508 drives the clamping plate 509 to reset when the adjusting disk 507 rotates.
[0063] By setting up the disassembly and assembly mechanism, it is convenient to connect the connecting rod 41 and the guard rod 42 together, so that the rotation of the output shaft of the driving motor 9 drives the connecting rod 41 to rotate and can drive the guard rod 42 to move, thereby making the grinding drill bit 43 and the impact drill bit 44 rotate, so as to quickly break the ultra-thick pebble layer. At the same time, the original guard rod 42 can be extended by splicing another section of the guard rod 42, so as to increase the driving depth of the impact drill bit 44, facilitate pile sinking, and improve the utilization efficiency of the existing drilling holes.
[0064] Working principle: When in use, insert the guard rod 42 into the fixing ring 5 to align and contact with the connecting rod 41, start the push cylinder 502, and drive the clamping column 503 connected to it to be inserted into the clamping groove 505 along the inner wall of the limit groove 504 by extending the piston rod of the push cylinder 502, and then start the stepper motor 506, and drive the adjustment disk 507 connected to it to rotate by the rotation of the output shaft of the stepper motor 506. As the adjustment disk 507 rotates, the protrusion on the adjustment disk 507 drives the clamping plate 509 to move out along the inner wall of the slide groove 510 and contact the inner wall of the guard rod 42, so that the connecting rod 41 and the guard rod 42 are connected together;
[0065] Then, the steel pipe pile 2 is sleeved on the outer surface of the guard rod 42, so that the grinding drill bit 43 and the impact drill bit 44 are located outside the steel pipe pile 2, and the servo motor 102 is started. The clockwise rotation of the output shafts of the four servo motors 102 respectively drives the second screws 101 connected thereto to rotate clockwise, and the clockwise rotation of the four second screws 101 respectively drives the sliders 103 connected thereto to move together along the inner wall of the guide groove 1, and the movement of the sliders 103 drives the arc clamping plate 104 to move, so that the outer surface of the upper end of the steel pipe pile 2 is clamped by the gathering movement of the four arc clamping plates 104;
[0066] Then, the slag discharge pipe 12 is inserted into the steel pipe pile 2, so that the lower end of the slag discharge pipe 12 extends out of the lower end of the steel pipe pile 2, the upper end of the slag discharge pipe 12 extends out of the upper end of the steel pipe pile 2 and is connected to a suction pump, and the upper end of the air pipe on the guard rod 42 extends out of the upper end of the steel pipe pile 2 and is connected to an air pump;
[0067] Then, the rotating motor 4 is started, and the rotation of the output shaft of the rotating motor 4 drives the connecting rod 41 connected thereto to rotate, and the rotation of the connecting rod 41 drives the guard rod 42 to rotate, and the rotation of the guard rod 42 drives the grinding drill bit 43 and the impact drill bit 44 to rotate, and at the same time, the driving motor 9 is started, and the clockwise rotation of the output shaft of the driving motor 9 drives the first screw rod 8 connected thereto to rotate clockwise, and the clockwise rotation of the first screw rod 8 drives the moving block 10 connected thereto to move downward along the inner wall of the groove 7, and the downward movement of the moving block 10 drives the installation shell 11 to move downward, so as to facilitate breaking the pebble layer and allow the steel pipe pile 2 to be inserted;
[0068] At the same time, the suction pump and the air pump are started. The crushed drill cuttings are discharged from the steel pipe pile 2 through the slag discharge pipe 12 by the suction pump, and the gas is extended to the grinding drill bit 43 through the air blowing pipe 13 by the air pump, and discharged from the grinding drill bit 43 through the air outlet 14, thereby preventing the drill cuttings from adhering to the grinding drill bit 43 and facilitating the slag discharge pipe 12 to absorb the drill cuttings.
[0069] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer, characterized in that: The construction steps include: S1. Transportation of steel pipe piles: connecting the steel pipe piles (2) to the vehicle body (3) through a connecting mechanism, so that the movement of the vehicle body (3) drives the steel pipe piles (2) to be transported to a predetermined position; S2, drilling a hole in the steel pipe pile: installing a rotary drilling mechanism in the steel pipe pile (2), and the rotary drilling mechanism is connected to the vehicle body (3) to break the pebble layer; S3, drilling construction: rotating the disassembly and assembly mechanism on the drilling mechanism, so that when the soil is taken to the next driving depth, the pile can be extended and continued to be driven into the steel pipe pile (2); S4. Deslagging: During the drilling process, use a suction pump to regularly discharge the drill cuttings, and use an air pump to blow air into the borehole to ensure smooth drilling; S5, end of drilling: when the drill bit reaches the designed depth, the drilling is stopped and the drill bit is pulled out of the steel pipe pile (2).
2. The method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer according to claim 1, characterized in that: The surface of the vehicle body (3) is hinged with a support frame (6) through a hydraulic arm, and a groove (7) is opened on the surface of the support frame (6). A first screw rod (8) is installed on the inner wall of the groove (7) through a bearing. A driving motor (9) is fixedly installed on the inner wall of the support frame (6). The output shaft of the driving motor (9) is fixedly sleeved with one end of the first screw rod (8). A moving block (10) is threadedly sleeved on the surface of the first screw rod (8). The surface of the moving block (10) is slidably engaged with the inner wall of the groove (7), and a mounting shell (11) is fixedly installed on the surface of the moving block (10).
3. The method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer according to claim 2, characterized in that: The connection mechanism comprises guide grooves (1) arranged in an annular array on the lower surface of the installation shell (11); a second screw (101) is installed on the inner wall of the guide groove (1) via a bearing; a servo motor (102) is installed on the outer surface of the installation shell (11) in an annular array; an output shaft of the servo motor (102) is fixedly sleeved with one end of the second screw (101); a slider (103) is fixedly sleeved on the surface of the second screw (101); a surface of the slider (103) is slidably clamped with the inner wall of the guide groove (1); an arc-shaped clamping plate (104) is fixedly connected to the lower surface of the slider (103); and the arc-shaped clamping plate (104) is in contact with the steel pipe pile (2).
4. The method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer according to claim 2, characterized in that: The rotary drilling mechanism comprises a rotary motor (4) fixedly mounted in the mounting housing (11); one end of an output shaft of the rotary motor (4) passes through the mounting housing (11) and is fixedly sleeved with a connecting rod (41); the connecting rod (41) is mounted on the lower surface of the mounting housing (11) via a bearing.
5. The method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer according to claim 4, characterized in that: A guard rod (42) is provided at the lower end of the connecting rod (41), a grinding drill bit (43) is fixedly mounted on the lower surface of the guard rod (42), and an impact drill bit (44) is mounted on the lower surface of the grinding drill bit (43).
6. The method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer according to claim 5, characterized in that: The disassembly and assembly mechanism comprises a fixing ring (5) fixedly sleeved on the outer surface of the guard rod (42); the inner surface of the fixing ring (5) is slidably connected to the surface of the guard rod (42); a supporting ring (501) is fixedly installed on the outer surface of the fixing ring (5); a pushing cylinder (502) is installed on the outer surface of the supporting ring (501) in an annular array; one end of the piston rod of the pushing cylinder (502) extends into the fixing ring (5) and is fixedly connected to a clamping column (503); the inner surface of the fixing ring (5) is provided with limiting grooves (504) in an annular array; the surface of the guard rod (42) is provided with clamping grooves (505) in an annular array; the surface of the clamping column (503) is clamped with the inner wall of the clamping groove (505).
7. The method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer according to claim 6, characterized in that: A stepper motor (506) is fixedly mounted on the inner wall of the clamping column (503), and an adjusting disk (507) is fixedly sleeved on one end of the output shaft of the stepper motor (506).
8. The method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer according to claim 7, characterized in that: The outer surface of the adjustment disk (507) is fixedly mounted with springs (508) in an annular array, and a clamping plate (509) is fixedly mounted on the free end of the spring (508). The outer surface of the clamping column (503) is provided with sliding grooves (510) in an annular array, and the surface of the clamping plate (509) is slidably engaged with the inner wall of the sliding groove (510).
9. The method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer according to claim 1, characterized in that: The inner wall of the steel pipe pile (2) is provided with slag discharge pipes (12) in a circular array, the lower end of the slag discharge pipe (12) extends out of the lower end of the steel pipe pile (2), and the upper end of the slag discharge pipe (12) extends out of the upper end of the steel pipe pile (2) and is connected to a suction pump.
10. The method for constructing a hole in a steel pipe pile in an ultra-thick pebble layer according to claim 5, characterized in that: The inner wall of the guard rod (42) is provided with an air blowing pipe (13), the lower end of the air blowing pipe (13) extends to the inner wall of the grinding drill bit (43), the outer surface of the grinding drill bit (43) is provided with air outlets (14) distributed in a circular array, the air outlets (14) are connected to the air blowing pipe (13), and the upper end of the air blowing pipe (13) extends out of the steel pipe pile (2) and is connected to an air pump.