The invention discloses a rotary excavating
pile construction method for a
karst cave dense area capable of preventing water and
soil loss. According to the real-time
monitoring system, the sensor is installed on the
drill bit, various data such as the
drill bit position, the drilling speed and the hole wall stability in the drilling process are collected in real time, and real-time feedback is provided for construction. By means of the
system, constructors can know the drilling state in time, drilling parameters are adjusted in real time through
data analysis, and the drilling process is optimized. By means of real-time monitoring and adjusting, the construction efficiency is improved, risks caused by geological condition changes are greatly reduced, and the safety of the construction process and the drilling accuracy are guaranteed. According to the self-adaptive
slurry injection
system, the flow and pressure of
slurry can be automatically adjusted according to real-time
monitoring data, especially when a
karst cave or an easily-collapsed hole section is encountered, the
system can automatically increase the
slurry injection amount so as to maintain the stability of a hole wall, the construction efficiency is improved, and the construction cost is reduced.