Beam-slab system and beam-slab system connection construction method

Through the combined structure of rectangular beam frame, steel bar truss floor bearing plate and steel pipe concrete column, combined with grouting technology, the problem of insufficient bearing capacity of the modular building connection method is solved, stable and efficient beam-slab connection is achieved, and the overall building is improved Sex and bearing capacity.

CN118911286APending Publication Date: 2024-11-08UNIV OF SCI & TECH BEIJING
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411185010.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The connecting method of existing modular buildings has poor load-bearing capacity, insufficient structural stiffness and integrity, and is not suitable for connection between beams and slabs.

Method used

The combined structure of rectangular beam frame, steel bar truss floor bearing plate, base plate and steel pipe concrete column is adopted. Through holes and bolts are set in a uniform array, and the stable connection between beams and slabs is achieved in combination with grouting technology, improving the integrity and bearing capacity of the structure.

Benefits of technology

It ensures stable connection between units, improves the overall structural stability and bearing capacity of modular buildings, has high construction efficiency and low accuracy requirements, and is suitable for connection between beams and slabs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911286A_ABST
    Figure CN118911286A_ABST
Patent Text Reader

Abstract

The invention provides a beam-slab system and a beam-slab system connection construction method, and relates to the technical field of construction engineering. Each beam-slab system comprises two rectangular beam frames connected through a steel pipe concrete column, a steel bar truss floor support plate and a bottom plate are arranged in the two rectangular beam frames respectively, every two horizontally adjacent beam-slab systems are horizontally connected through horizontal connecting steel bars, every two vertically adjacent beam-slab systems are vertically connected through studs and connecting pieces, and the steel bar truss floor support plates and the bottom plates are connected through bolts. Grouting is conducted on the interior of the lower rectangular beam frame of the connected beam-slab system, the containing cabin of the concrete-filled steel tubular column and the downwards-concave platform of the bottom plate, and concrete is poured into the interior of the upper rectangular beam frame and the steel bar truss floor support plate; the integral structure is good in stability and bearing capacity, not only is high in assembling efficiency and construction speed and not high in construction precision requirement, but also has good stress performance and integrity, has certain rigidity and can be applied to connection between beams and slabs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction engineering, in particular to a beam-slab system and a beam-slab system connection construction method. Background Art

[0002] Modular construction is the process of breaking down a building into a series of modular units that can be prefabricated in a factory. These units are designed to be independent and complete, and can be used alone or in combination to form spaces of various forms and functions. After the modular units arrive at the construction site, they are assembled and connected to quickly build a complete building structure. In order to ensure the stability and reliability of modular construction, the connection between modules becomes a crucial link.

[0003] Although the module connection nodes of the prior art are convenient for on-site construction, they generally have poor bearing capacity, and the self-locking function requires high processing accuracy. In addition, the connection method of the prior art is mainly corner point connection. The results show that simply improving the bearing capacity and stiffness of the corner point connection between modules to strengthen the integrity of the modular building with a combined structure is not ideal, and the structural stiffness and integrity are insufficient. The prior art proposes a wet beam-slab connection structure for use in prefabricated buildings. Studs are used as shear connectors. Two prefabricated floor slabs are connected to steel beams through studs, extended steel bars, and post-cast concrete. Additional steel bars and reserved grooves are used to prevent the extended steel bars from being damaged. However, this construction form is not suitable for the construction method in which the beams and floor slabs of the upper and lower modules are composed of beams and slabs in modular buildings.

[0004] In general, the main disadvantages of the existing module connection are: poor bearing capacity, high requirements for processing precision, insufficient structural rigidity and integrity, and unsuitable for connection between beams and slabs. Summary of the invention

[0005] In order to solve the technical problems existing in the prior art, the embodiment of the present invention provides a beam-slab system and a beam-slab system connection construction method. The technical solution is as follows:

[0006] A beam-slab system comprises a rectangular beam frame, a steel truss floor deck, a bottom plate and a steel tube concrete column;

[0007] The two rectangular beam frames are arranged in parallel in the vertical direction and aligned in position;

[0008] Both ends of the steel tube concrete column are respectively connected to the two rectangular beam frames;

[0009] The steel bar truss floor deck is installed in the upper rectangular beam frame;

[0010] The bottom plate is installed in the rectangular beam frame below;

[0011] The outer side wall of the upper rectangular beam frame is provided with first through holes in a uniform array around the circumference;

[0012] Second bolts are arranged in a uniform array around the outer wall of the top surface of the rectangular beam frame above;

[0013] The outer side wall of the rectangular beam frame below is provided with second through holes in a uniform array around the circumference;

[0014] The bottom surface of the rectangular beam frame below is provided with third through holes in a uniform array around the circumference; the number and position of the third through holes correspond to the number and position of the second bolts;

[0015] A concave platform is arranged around the bottom plate, and grooves are arranged in a uniform array around the concave platform. The number and position of the grooves correspond to the number and position of the second through holes and are connected.

[0016] Optionally, first bolts are arranged in a uniform array around the circumference on the inner wall of the bottom surface of the upper rectangular beam frame, and third bolts are arranged in a uniform array around the circumference on the inner wall of the top surface of the lower rectangular beam frame.

[0017] Optionally, the rectangular beam frame includes four connecting beams connected end to end, the connecting beams of the upper rectangular beam frame are U-shaped beams, C-shaped beams or rectangular beams, and the connecting beams of the lower rectangular beam frame are rectangular beams or C-shaped beams.

[0018] Optionally, an upper accommodation chamber is provided at the bottom end of the steel tube concrete column, at least one first independent space is evenly arranged in the upper accommodation chamber, and bolts are evenly arranged on the inner wall of each first independent space; a grouting port is provided on the side wall of the upper accommodation chamber;

[0019] A lower accommodation chamber is arranged at the top of the inner part of the steel tube concrete column, at least one second independent space is evenly arranged in the lower accommodation chamber, and bolts are evenly arranged on the inner wall of each second independent space; a grouting port is arranged on the side wall of the lower accommodation chamber;

[0020] The number and size of the first independent spaces are respectively equal to the number and size of the second independent spaces.

[0021] Optionally, when the connecting beam is a C-shaped beam, the bottom surface of the concave platform overlaps the inner wall of the bottom surface of the rectangular beam frame below;

[0022] The height of the connecting beam of the rectangular beam frame above is greater than the thickness of the steel bar truss floor deck;

[0023] When the connecting beam is a C-shaped beam, a slope is provided on the edges of the steel bar truss floor deck, the bottom end of the slope is connected to the transition surface, and the bottom surface of the transition surface overlaps the inner wall of the bottom surface of the rectangular beam frame above;

[0024] When the connecting beam is a U-shaped beam or a rectangular beam, slope surfaces are provided on the four edges of the steel bar truss floor deck, the bottom end of the slope surface is connected to a transition surface, and the transition surface is welded to the bottom of the outer side wall of the upper rectangular beam frame.

[0025] A beam-slab system connection construction method, comprising the beam-slab system according to the claim, the method comprising:

[0026] The beam-slab system is prefabricated, adjacent beam-slab systems are horizontally spliced, adjacent beam-slab systems are vertically spliced, and the spliced ​​beam-slab system is grouted.

[0027] Optionally,

[0028] When the adjacent beam-slab systems are connected horizontally,

[0029] The width side of the rectangular beam frame above one beam-slab system is aligned with the width side of the rectangular beam frame above another beam-slab system, so that the first through holes on the width sides of the two beam-slab systems are aligned correspondingly, and the first horizontal connecting steel bars pass through every two aligned first through holes, and the first horizontal connecting steel bars connect two adjacent steel bar truss floor decks;

[0030] The width side of the rectangular beam frame below one beam-slab system is aligned with the width side of the rectangular beam frame below another beam-slab system, so that the second through holes on the width sides of the two beam-slab systems are aligned correspondingly, and the second horizontal connecting steel bars pass through every two aligned second through holes, and the second horizontal connecting steel bars are placed in the grooves, and the second horizontal connecting steel bars connect the two adjacent bottom plates;

[0031] When the adjacent beam-slab systems are connected longitudinally and horizontally,

[0032] The length side of the rectangular beam frame above one beam-slab system is aligned with the length side of the rectangular beam frame above another beam-slab system, so that the first through holes on the length sides of the two beam-slab systems are aligned correspondingly, and the first horizontal connecting steel bars pass through every two aligned first through holes, and the first horizontal connecting steel bars connect two adjacent steel bar truss floor decks;

[0033] The length side of the rectangular beam frame below one beam-slab system is aligned with the length side of the rectangular beam frame below another beam-slab system, so that the second through holes on the length sides of the two beam-slab systems are aligned accordingly, and a second horizontal connecting steel bar passes through every two aligned second through holes, and the second horizontal connecting steel bar is placed in the groove, and the second horizontal connecting steel bar connects the two adjacent bottom plates.

[0034] Optionally,

[0035] When the adjacent beam-slab systems are connected vertically,

[0036] The rectangular beam frame below the upper beam-slab system is aligned with the rectangular beam frame above the lower beam-slab system, so that each second bolt passes through each third through hole respectively, and the second bolt connects adjacent rectangular beam frames;

[0037] The upper accommodation chamber of the steel tube concrete column of the upper beam-slab system is connected to the lower accommodation chamber of the steel tube concrete column of the lower beam-slab system through a connecting piece.

[0038] Optionally, the connecting member includes a horizontal connecting plate, at least one first cross-shaped plate is arranged on the upper plate surface of the horizontal connecting plate, bolts are evenly arranged on the plate surface of each first cross-shaped plate, and the number of the first cross-shaped plates is equal to the number of the first independent spaces; the position size of each first cross-shaped plate is respectively corresponding to the position size of each first independent space; at least one second cross-shaped plate is arranged on the lower plate surface of the horizontal connecting plate, bolts are evenly arranged on the plate surface of each second cross-shaped plate, the number of the second cross-shaped plates is equal to the number of the second independent spaces, and the position size of each second cross-shaped plate is respectively corresponding to the position size of each second independent space.

[0039] Optionally,

[0040] When the first horizontal steel bars and the second horizontal steel bars connect the horizontally adjacent beam-slab systems, concrete is poured in the rectangular beam frame on the steel bar truss floor deck and above the beam-slab system, and grouting is poured in the rectangular beam frame on the concave platform and below the beam-slab system;

[0041] When the connecting member and the second bolt connect the upper and lower adjacent beam-slab systems, the upper accommodation chamber and the lower accommodation chamber are grouted through the grouting port, concrete is poured into the upper rectangular beam frame of each beam-slab system, and grouting is performed in the lower rectangular beam frame of each beam-slab system. The technical solution provided by the embodiment of the present invention brings at least the following beneficial effects:

[0042] The present invention can ensure stable connection between units in the horizontal and vertical directions. The vertical connection is achieved by welding bolts to the upper rectangular beam frame, and after grouting, the upper and lower steel beams and floor slabs are combined together with the concrete tenons in the third through holes of the upper beam-slab system. Holes are opened on the web of the connecting beam to place horizontal connecting steel bars. The steel bars and the concrete tenons in the holes are used to combine the beams of the left and right units and the horizontal steel bar truss floor slab and floor to achieve horizontal connection between units. The steel tube concrete columns of the lower beam-slab system are placed with connectors and then grouting is performed. Then the steel tube concrete columns of the upper beam-slab system are placed and grouting is performed again to achieve column-column connection. This design enables adjacent units to be stressed in coordination, thereby improving the overall structural stability and bearing capacity performance of modular buildings. The present invention not only has high assembly efficiency and fast construction speed, but also has low requirements on construction precision and has good stress-bearing performance and integrity. It has a certain rigidity and can be applied to the connection between beams and slabs. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0044] Figure 1 A structural schematic diagram of the beam-slab system provided by the present invention;

[0045] Figure 2 A schematic diagram of a horizontal connection of the beam-slab system provided by the present invention;

[0046] Figure 3 This is a schematic diagram of the beam-slab system provided by the present invention after the bottom plate is grouted and the top plate is poured with concrete;

[0047] Figure 4 A schematic diagram of the beam-slab system provided by the present invention after the connector is installed;

[0048] Figure 5 A schematic diagram of a cushion layer of a beam-slab system provided by the present invention;

[0049] Figure 6 A schematic diagram of the vertical connection of the beam-slab system provided by the present invention;

[0050] Figure 7 A detailed view of the connection between the bottom plate and the connecting beam of the beam-slab system when the connecting beam is a C-beam provided by the present invention;

[0051] Figure 8 A detailed view of the connection between the steel truss floor deck and the connection beam of the beam-slab system provided by the present invention when the connection beam is a C-beam;

[0052] Fig. 9 A detailed view of the vertical connection of the beam-slab system provided by the present invention;

[0053] Fig.10 A schematic diagram of a connecting piece provided by the present invention;

[0054] Fig.11 A top view of the connector provided by the present invention;

[0055] Fig.12 A schematic diagram of the connection between the upper rectangular beam frame and the lower rectangular beam frame when the connecting beam of the upper rectangular beam frame provided by the present invention is a C-shaped beam;

[0056] Fig.13 A schematic diagram of the connection between the upper rectangular beam frame and the lower rectangular beam frame when the connecting beam of the upper rectangular beam frame provided by the present invention is a U-shaped beam;

[0057] Fig.14 The present invention provides a schematic diagram of the connection between the upper rectangular beam frame and the lower rectangular beam frame when the connecting beam of the upper rectangular beam frame is a rectangular beam.

[0058] Reference numerals:

[0059] 11. Steel truss floor deck; 12. Bottom plate; 13. Steel tube concrete column; 111. Cushion; 112. Transition surface; 113. Slope surface; 131. Exhaust port; 132. Grouting port; 133. Grouting material;

[0060] 2. Concave platform; 21. Groove; 3. Lower rectangular beam frame; 31. Second through hole; 32. Third through hole; 33. Third bolt; 4. Upper rectangular beam frame; 41. First through hole; 42. Second bolt; 43. First bolt; 51. First horizontal connecting steel bar; 52. Second horizontal connecting steel bar; 6. Connector; 61. Horizontal connecting plate; 62. First cross-shaped plate; 63. Fourth through hole; 7. Connecting plate. DETAILED DESCRIPTION

[0061] In order to make the purpose, technical solution and advantages of the embodiment of the present invention clearer, the technical solution of the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings of the embodiment of the present invention. Obviously, the described embodiment is a part of the embodiment of the present invention, not all of the embodiments. Based on the described embodiment of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0062] Unless otherwise defined, the technical terms or scientific terms used in the present invention should be understood by people with ordinary skills in the field to which the present invention belongs. The words "first", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. Similarly, words such as "one", "one" or "the" do not indicate a quantitative limitation, but indicate the existence of at least one. Words such as "include" or "comprise" mean that the elements or objects appearing before the word include the elements or objects listed after the word and their equivalents, without excluding other elements or objects. Words such as "connect" or "connected" are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect.

[0063] It should be noted that the terms "up", "down", "left", "right", "front", "back", etc. used in the present invention are only used to indicate relative position relationships. When the absolute position of the object being described changes, the relative position relationship may also change accordingly.

[0064] like Figure 1-Figure 14 As shown, this embodiment provides a beam-slab system, including two rectangular beam frames, a steel truss floor deck 11, a bottom plate 12 and a steel tube concrete column 13; the rectangular beam frame refers to a rectangular beam frame. The two rectangular beam frames are arranged in parallel in the vertical direction and aligned; the two ends of the steel tube concrete column 13 are respectively connected to the two rectangular beam frames; the steel tube concrete column 13 is placed vertically, and the number of the steel tube concrete columns 13 is four; the tops of the four steel tube concrete columns 13 are respectively located at the four corners of the upper rectangular beam frame 4, and the bottoms of the four steel tube concrete columns 13 are respectively located at the four corners of the lower rectangular beam frame 3. The steel truss floor deck 11 is installed in the upper rectangular beam frame 4, and the bottom plate 12 is installed in the lower rectangular beam frame 3.

[0065] The upper rectangular beam frame 4 includes four connecting beams connected end to end, and the lower rectangular beam frame 3 includes four connecting beams connected end to end. The adjacent connecting beams of the upper rectangular beam frame 4 are connected through the top of the steel tube concrete column 13, and the adjacent connecting beams of the lower rectangular beam frame 3 are connected through the bottom of the steel tube concrete column 13.

[0066] A first through hole 41 is arranged in a uniform array around the circumference on the outer wall of the upper rectangular beam frame 4; a second through hole 31 is arranged in a uniform array around the circumference on the outer wall of the lower rectangular beam frame 3. A second stud 42 is arranged in a uniform array around the circumference on the outer wall of the top surface of the upper rectangular beam frame 4; a third through hole 32 is arranged in a uniform array around the circumference on the bottom surface of the lower rectangular beam frame 3; the number and position of the third through holes 32 correspond to the number and position of the second stud 42 one by one; a first stud 43 is arranged in a uniform array around the circumference on the inner wall of the bottom surface of the upper rectangular beam frame 4, and a third stud 33 is arranged in a uniform array around the circumference on the inner wall of the top surface of the lower rectangular beam frame 3.

[0067] A concave platform 2 is provided around the bottom plate 12, and grooves 21 are arranged in a uniform array around the concave platform 2. The number and position of the grooves 21 correspond to the number and position of the second through holes 31 and are connected. The extending direction of the grooves 21 on the length side of the concave platform 2 is perpendicular to the length direction of the concave platform 2, and the extending direction of the grooves 21 on the width side of the concave platform 2 is perpendicular to the width direction of the concave platform 2; the grooves 21 are provided to facilitate grouting to fill the entire concave platform 2 when connected.

[0068] like Figure 12-14 As shown, the connecting beam of the upper rectangular beam frame can be a C-beam, a U-beam or a rectangular beam, and the connecting beam of the lower rectangular beam frame can be a C-beam or a rectangular beam. C-beam, U-beam or rectangular beam is C-shaped steel, U-shaped steel and rectangular steel, which is the prior art and will not be described here. The difference between a C-beam and a U-beam is that the cross section of a C-beam is C-shaped, with an opening facing both sides, while the opening of a U-beam faces upward, and the top ends of the two side walls of the U-beam are bent inward at a right angle. When the connecting beam of the upper rectangular beam frame 4 is a U-beam, the two side walls at the opening of the connecting beam are connected by a connecting plate 7, and a second bolt 42 is provided on the connecting plate 7.

[0069] like Figure 7-Figure 8 As shown, the height of the connecting beam of the upper rectangular beam frame 3 is greater than the thickness of the steel truss floor slab 11; when the connecting beam of the lower rectangular beam frame 3 is a C-shaped beam, the bottom surface of the concave platform 2 overlaps the inner wall of the bottom surface of the lower rectangular beam frame 3; when the connecting beam of the upper rectangular beam frame 3 is a C-shaped beam, the surrounding edges of the steel truss floor slab 11 are provided with a downwardly inclined slope 113, the bottom end of the slope 113 is connected to the transition surface 112, and the bottom surface of the transition surface 112 overlaps the inner wall of the bottom surface of the upper rectangular beam frame 4, that is, the bottom surface of the transition surface 112 overlaps the inner wall of the lower flange of the connecting beam of the upper rectangular beam frame 3. When the connecting beam is a U-shaped beam or a rectangular beam, the surrounding edges of the steel truss floor slab 11 are provided with a slope 113, the bottom end of the slope is connected to the transition surface 112, and the transition surface 112 is welded to the bottom of the outer wall of the upper rectangular beam frame 3. The slope of the slope 113 can be set according to the thickness of the floor slab to save the use space of the building.

[0070] like Figure 9-10 As shown, an upper accommodation chamber is provided at the bottom end of the steel tube concrete column 13, at least one first independent space is evenly arranged in the upper accommodation chamber, and bolts are evenly arranged on the inner wall of each first independent space; a grouting port 132 and an exhaust port 131 are provided on the side wall of the upper accommodation chamber;

[0071] A lower accommodation chamber is arranged at the top of the inner part of the steel tube concrete column 13, and at least one second independent space is evenly arranged in the lower accommodation chamber, and bolts are evenly arranged on the inner wall of each second independent space; a grouting port 132 and an exhaust port 131 are arranged on the side wall of the lower accommodation chamber;

[0072] The exhaust port 131 is used to exhaust the interior of the steel tube concrete column 13 after grouting.

[0073] The number and size of the first independent spaces are respectively equal to the number and size of the second independent spaces.

[0074] like Figure 1-Figure 14 As shown, a beam-slab system connection construction method comprises:

[0075] The beam-slab system is prefabricated, adjacent beam-slab systems are horizontally spliced, adjacent beam-slab systems are vertically spliced, and the spliced ​​beam-slab systems are grouting.

[0076] When adjacent beam-slab systems are connected horizontally,

[0077] The width side of the upper rectangular beam frame 4 of one beam-slab system is aligned with the width side of the upper rectangular beam frame 4 of another beam-slab system, so that the first through holes 41 on the width sides of the two beam-slab systems are aligned correspondingly, and the first horizontal connecting steel bars 51 pass through every two aligned first through holes 41, and the first horizontal connecting steel bars 51 connect two adjacent steel bar truss floor decks 11;

[0078] The width side of the lower rectangular beam frame 3 of one beam-slab system is aligned with the width side of the lower rectangular beam frame 3 of another beam-slab system, so that the second through holes 31 on the width sides of the two beam-slab systems are aligned correspondingly, and the second horizontal connecting steel bars 52 pass through every two aligned second through holes 31, and the second horizontal connecting steel bars 52 are placed in the groove 21, and the second horizontal connecting steel bars 52 connect the two adjacent bottom plates 12;

[0079] When adjacent beam-slab systems are connected longitudinally and horizontally,

[0080] The length side of the upper rectangular beam frame 4 of one beam-slab system is aligned with the length side of the upper rectangular beam frame 4 of another beam-slab system, so that the first through holes 41 on the length sides of the two beam-slab systems are aligned correspondingly, and the first horizontal connecting steel bars 51 pass through every two aligned first through holes 41, and the first horizontal connecting steel bars 51 connect two adjacent steel bar truss floor decks 11;

[0081] The length side of the lower rectangular beam frame 3 of one beam-slab system is aligned with the length side of the lower rectangular beam frame 3 of another beam-slab system, so that the second through holes 31 on the length sides of the two beam-slab systems are aligned accordingly, and the second horizontal connecting steel bars 52 pass through every two aligned second through holes 31, and the second horizontal connecting steel bars 52 are placed in the groove 21, and the second horizontal connecting steel bars 52 connect the two adjacent bottom plates 12.

[0082] When adjacent beam-slab systems are connected vertically,

[0083] The lower rectangular beam frame 3 of the upper beam-slab system is aligned with the upper rectangular beam frame 4 of the lower beam-slab system, so that each second bolt 42 of the lower beam-slab system passes through each third through hole 32 of the upper beam-slab system, and the second bolt 42 connects adjacent rectangular beam frames;

[0084] The upper accommodation chamber of the steel tube concrete column 13 of the upper beam-slab system is connected to the lower accommodation chamber of the steel tube concrete column 13 of the lower beam-slab system via a connecting piece 6 .

[0085] like Figure 9-11 As shown, the connecting member 6 includes a horizontal connecting plate 61, on the upper plate surface of which at least one first cross-shaped plate 62 is arranged, and bolts are evenly arranged on the plate surface of each first cross-shaped plate 62, and the number of the first cross-shaped plates 62 is equal to the number of the first independent spaces; the position and size of each first cross-shaped plate 62 are respectively adapted to the position and size of each first independent space; at least one second cross-shaped plate is arranged on the lower plate surface of the horizontal connecting plate 61, and bolts are evenly arranged on the plate surface of each second cross-shaped plate, and the number of the second cross-shaped plates is equal to the number of the second independent spaces, and the position and size of each second cross-shaped plate are respectively adapted to the position and size of each second independent space. A fourth through hole 63 is provided on the horizontal connecting plate, and when the connecting member 6 is inserted into the upper accommodation chamber, the second bolt 42 adjacent to the connecting member 6 passes through the corresponding fourth through hole 63.

[0086] like Figure 12-14 As shown, when the first horizontal steel bars 51 and the second horizontal steel bars 52 connect the horizontally adjacent beam-slab system, concrete is poured on the steel truss floor decking 11 and in the upper rectangular beam frame 4 of the beam-slab system, and grouting is performed on the recessed platform 2 and in the lower rectangular beam frame 3 of the beam-slab system; after grouting, the first horizontal connecting steel bars 51 and the concrete tenons in the first through holes 41, and the second horizontal connecting steel bars 52 and the concrete tenons in the second through holes 31 jointly combine the beams and floors of the horizontal beam-slab system to achieve horizontal connection between units.

[0087] When the connecting member 6 and the second bolt 42 connect the upper and lower adjacent beam-slab systems, the grouting material 133 is respectively poured into the upper accommodation chamber and the lower accommodation chamber through the grouting port 132, so that the adjacent units can be subjected to force in a coordinated manner, which significantly improves the force bearing performance and integrity of the building;

[0088] Concrete is poured into the upper rectangular beam frame and the steel truss floor slab 11 of each beam-slab system, and grouting material 133 is poured into the lower rectangular beam frame and the concave platform 2 of each beam-slab system, and concrete is poured into the steel truss floor slab of the uppermost beam-slab system in the vertically connected beam-slab system. After grouting, the second bolt 42 and the concrete tenon in the third through hole 32 jointly combine the steel beams and floor slabs of the upper and lower beam-slab systems to achieve vertical connection between units.

[0089] The first bolt 43, the second bolt 42 and the third bolt 33 are combined and connected with the concrete or high-strength grouting material 133 to bear the force in coordination.

[0090] Before the upper and lower beam-slab systems are vertically connected, a cushion layer 111 is provided on the steel truss floor deck 11 after pouring concrete of the lower beam-slab system. The cushion layer in this embodiment is 20 mm thick. The thickness of the cushion layer 111 is the same as that of the horizontal connection plate 61 .

[0091] Since the horizontal connecting plate 61 has thickness, there is a gap between the upper and lower beam-slab systems when they are connected. The thickness of the gap is the same as the thickness of the horizontal connecting plate 61, which is 20 mm in this embodiment. When the upper and lower beam-slab systems are connected, grouting is performed in the lower rectangular beam frame 3 of the upper beam-slab system. The high-strength grouting material 133 will pass through the third through hole 32 to fill the 20 mm gap between the rectangular beam frames of the upper and lower beam-slab systems, and will also fill the lower rectangular beam frame 3 of the upper beam-slab system to achieve a longitudinal connection between the upper and lower beam-slab systems.

[0092] The vertical connecting bolts of this embodiment are welded to the top surface of the upper rectangular beam frame 4 of the beam-slab system. After grouting, they are combined with the concrete tenons in the third through holes 32 of the upper beam-slab system to combine the upper and lower steel beams and the floor slabs to achieve longitudinal connection between units. Holes are opened in the web of the connecting beam to place horizontal connecting steel bars. After grouting, the steel bars and the concrete tenons in the openings are combined with the connecting beams of the left and right units and the horizontal steel bar truss floor decking and the bottom plate to achieve horizontal connection between units. The steel tube concrete columns of the lower beam-slab system are placed with connecting parts and then grouted. Then the steel tube concrete columns of the upper beam-slab system are placed and grouting is performed again to achieve column-to-column connection, so as to improve the integrity and stress-bearing performance of the modular building.

[0093] This solution can ensure stable connection between units in the horizontal and vertical directions. The vertical connection is achieved by welding bolts to the upper rectangular beam frame, and after grouting, the upper and lower steel beams and floor slabs are combined together with the concrete tenons in the third through holes of the upper beam-slab system. Holes are opened on the web of the connecting beam to place horizontal connecting steel bars. The steel bars and the concrete tenons in the holes are used to combine the beams of the left and right units and the horizontal steel bar truss floor slab and floor to achieve horizontal connection between units. The steel tube concrete columns of the lower beam-slab system are placed with connectors and grouting is carried out, and then the steel tube concrete columns of the upper beam-slab system are placed and grouting is carried out to achieve column-column connection. This design enables adjacent units to be stressed in coordination, thereby improving the overall structural stability and bearing capacity performance of modular buildings. The present invention not only has high assembly efficiency and fast construction speed, but also has low requirements on construction precision and has good stress-bearing performance and integrity. It has a certain rigidity and can be applied to the connection between beams and slabs.

[0094] The following points need to be explained:

[0095] (1) The drawings of the embodiments of the present invention only involve structures related to the embodiments of the present invention. Other structures may refer to conventional designs.

[0096] (2) For the sake of clarity, in the drawings used to describe the embodiments of the present invention, the thickness of layers or regions is exaggerated or reduced, that is, these drawings are not drawn according to the actual scale. It is understood that when an element such as a layer, film, region or substrate is referred to as being "on" or "under" another element, the element may be "directly" "on" or "under" the other element or there may be intermediate elements.

[0097] (3) In the absence of conflict, the embodiments of the present invention and the features therein may be combined with each other to obtain new embodiments.

[0098] The above are only specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. The protection scope of the present invention shall be based on the protection scope of the claims.

Claims

1. A beam-slab system, characterized in that: It includes rectangular beam frame, reinforced steel truss floor deck, bottom plate and concrete-filled steel tube columns; The two rectangular beam frames are arranged in parallel in the vertical direction and aligned in position; Both ends of the steel tube concrete column are respectively connected to the two rectangular beam frames; The steel bar truss floor deck is installed in the upper rectangular beam frame; The bottom plate is installed in the rectangular beam frame below; The outer side wall of the upper rectangular beam frame is provided with first through holes in a uniform array around the circumference; Second bolts are arranged in a uniform array around the outer wall of the top surface of the rectangular beam frame above; The outer side wall of the rectangular beam frame below is provided with second through holes in a uniform array around the circumference; The bottom surface of the rectangular beam frame below is provided with third through holes in a uniform array around the circumference; the number and position of the third through holes correspond to the number and position of the second bolts; A concave platform is arranged around the bottom plate, and grooves are arranged in a uniform array around the concave platform. The number and position of the grooves correspond to the number and position of the second through holes and are connected.

2. The beam-slab system according to claim 1, characterized in that: A first array of bolts is evenly arranged on the inner wall of the bottom surface of the upper rectangular beam frame, and a third array of bolts is evenly arranged on the inner wall of the top surface of the lower rectangular beam frame.

3. The beam-slab system according to claim 1, characterized in that: The rectangular beam frame comprises four connecting beams connected end to end, the connecting beams of the upper rectangular beam frame are U-shaped beams, C-shaped beams or rectangular beams, and the connecting beams of the lower rectangular beam frame are rectangular beams or C-shaped beams.

4. The beam-slab system according to claim 1, characterized in that: An upper accommodation chamber is arranged at the bottom end of the interior of the steel tube concrete column, at least one first independent space is evenly arranged in the upper accommodation chamber, and bolts are evenly arranged on the inner wall of each first independent space; a grouting port is arranged on the side wall of the upper accommodation chamber; A lower accommodation chamber is arranged at the top of the inner part of the steel tube concrete column, at least one second independent space is evenly arranged in the lower accommodation chamber, and bolts are evenly arranged on the inner wall of each second independent space; a grouting port is arranged on the side wall of the lower accommodation chamber; The number and size of the first independent spaces are respectively equal to the number and size of the second independent spaces.

5. The beam-slab system according to claim 3, characterized in that: When the connecting beam is a C-shaped beam, the bottom surface of the concave platform overlaps the inner wall of the bottom surface of the rectangular beam frame below; The height of the connecting beam of the rectangular beam frame above is greater than the thickness of the steel bar truss floor deck; When the connecting beam is a C-shaped beam, a slope is provided on the edges of the steel bar truss floor deck, the bottom end of the slope is connected to the transition surface, and the bottom surface of the transition surface overlaps the inner wall of the bottom surface of the rectangular beam frame above; When the connecting beam is a U-shaped beam or a rectangular beam, slope surfaces are provided on the four edges of the steel bar truss floor deck, the bottom end of the slope surface is connected to a transition surface, and the transition surface is welded to the bottom of the outer side wall of the upper rectangular beam frame.

6. A beam-slab system connection construction method, characterized in that: The beam-slab system comprising any one of claims 1 to 5, wherein the method comprises: The beam-slab system is prefabricated, adjacent beam-slab systems are horizontally spliced, adjacent beam-slab systems are vertically spliced, and the spliced ​​beam-slab system is grouted.

7. The beam-slab system connection construction method according to claim 6, characterized in that: When the adjacent beam-slab systems are connected horizontally, The width side of the rectangular beam frame above one beam-slab system is aligned with the width side of the rectangular beam frame above another beam-slab system, so that the first through holes on the width sides of the two beam-slab systems are aligned correspondingly, and the first horizontal connecting steel bars pass through every two aligned first through holes, and the first horizontal connecting steel bars connect two adjacent steel bar truss floor decks; The width side of the rectangular beam frame below one beam-slab system is aligned with the width side of the rectangular beam frame below another beam-slab system, so that the second through holes on the width sides of the two beam-slab systems are aligned correspondingly, and the second horizontal connecting steel bars pass through every two aligned second through holes, and the second horizontal connecting steel bars are placed in the grooves, and the second horizontal connecting steel bars connect the two adjacent bottom plates; When the adjacent beam-slab systems are connected longitudinally and horizontally, The length side of the rectangular beam frame above one beam-slab system is aligned with the length side of the rectangular beam frame above another beam-slab system, so that the first through holes on the length sides of the two beam-slab systems are aligned correspondingly, and the first horizontal connecting steel bars pass through every two aligned first through holes, and the first horizontal connecting steel bars connect two adjacent steel bar truss floor decks; The length side of the rectangular beam frame below one beam-slab system is aligned with the length side of the rectangular beam frame below another beam-slab system, so that the second through holes on the length sides of the two beam-slab systems are aligned accordingly, and a second horizontal connecting steel bar passes through every two aligned second through holes, and the second horizontal connecting steel bar is placed in the groove, and the second horizontal connecting steel bar connects the two adjacent bottom plates.

8. The beam-slab system connection construction method according to claim 7, characterized in that: When the adjacent beam-slab systems are connected vertically, The rectangular beam frame below the upper beam-slab system is aligned with the rectangular beam frame above the lower beam-slab system, so that each second bolt passes through each third through hole respectively, and the second bolt connects adjacent rectangular beam frames; The upper accommodation chamber of the steel tube concrete column of the upper beam-slab system is connected to the lower accommodation chamber of the steel tube concrete column of the lower beam-slab system through a connecting piece.

9. The beam-slab system connection construction method according to claim 8, characterized in that: The connecting member includes a horizontal connecting plate, at least one first cross-shaped plate is arranged on the upper plate surface of the horizontal connecting plate, bolts are evenly arranged on the plate surface of each first cross-shaped plate, and the number of the first cross-shaped plates is equal to the number of the first independent spaces; the position size of each first cross-shaped plate is respectively corresponding to the position size of each first independent space; at least one second cross-shaped plate is arranged on the lower plate surface of the horizontal connecting plate, bolts are evenly arranged on the plate surface of each second cross-shaped plate, the number of the second cross-shaped plates is equal to the number of the second independent spaces, and the position size of each second cross-shaped plate is respectively corresponding to the position size of each second independent space.

10. The beam-slab system connection construction method according to claim 9, characterized in that: When the first horizontal steel bars and the second horizontal steel bars connect the horizontally adjacent beam-slab systems, concrete is poured in the rectangular beam frame on the steel bar truss floor deck and above the beam-slab system, and grouting is poured in the rectangular beam frame on the concave platform and below the beam-slab system; When the connecting member and the second bolt connect the upper and lower adjacent beam-slab systems, the upper accommodating chamber and the lower accommodating chamber are grouted respectively through the grouting port, concrete is poured into the upper rectangular beam frame of each beam-slab system, and grouting is performed in the lower rectangular beam frame of each beam-slab system.