Secondary hole entering method for long and large high-speed rail tunnel parallel guide crossing deep and large karst cave

By erecting a steel bridge on the cantilever beam between the tunnel and the palm surface, the problem of low construction efficiency of deep large caves in karst geological areas is solved, rapid and safe construction and economic benefits are achieved, and the impact of the cave on tunnel construction is reduced.

CN118911690APending Publication Date: 2024-11-08CHINA RAILWAY SEVENTH GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411054460.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

During construction in karst geological areas, the emergence of caves often leads to low tunnel construction efficiency and poor economicality, and existing backfill methods are difficult to quickly and safely deal with deep large caves.

Method used

The cantilevered steel bridge is used to pass through the cave. By erecting a cantilevered steel bridge between the tunnel and the palm surface, fixing the two ends of the cantilevered steel bridge, erecting a temporary trestle, and installing a steel frame in the guide hole to backfilling the cave slag to reduce the cave Impact on construction.

Benefits of technology

It has achieved rapid and safe crossing of the cave, improved construction efficiency and economic benefits, reduced the impact of the cave on tunnel construction, and saved construction period and material transportation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911690A_ABST
    Figure CN118911690A_ABST
Patent Text Reader

Abstract

The invention discloses a secondary hole entering method for a long and large high-speed rail tunnel to penetrate through a deep and large karst cave in a parallel guide mode. The method comprises the following steps that a bottom plate close to a tunnel portal of the karst cave is excavated and then hardened and leveled; a cantilever beam steel bridge is installed at the hardened and leveled tunnel portal, and one end of the cantilever beam steel bridge is fixed to the hardened and leveled tunnel portal through a first ground anchor; pilot tunnel excavation is conducted on the tunnel face opposite to the tunnel on the cantilever beam steel bridge by constructors, and then the other end of the cantilever beam steel bridge is fixed to the bottom of a pilot tunnel through a second ground anchor; a temporary trestle is erected on the cantilever beam steel bridge, and the road surfaces at the two ends of the temporary trestle are hardened; a steel frame is installed in the pilot tunnel, tunnel excavation is conducted on the tunnel face, and the karst cave is backfilled with tunnel slag obtained after the tunnel face is excavated; and the tunnel of the tunnel face is reinforced. According to the method, the cantilever beam steel bridge is erected between the excavated tunnel and the tunnel face, so that the karst cave can be quickly and safely spanned during construction, and the influence of the karst cave on tunnel construction is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, and in particular to a secondary tunnel entry method for a long high-speed railway tunnel to pass through a deep and large karst cave. Background Art

[0002] A tunnel is a building built underground or in a mountain for the passage of motor vehicles after laying railways or building roads. In the construction of a tunnel, various situations may be encountered, and different construction methods are usually required to carry out the construction of the tunnel.

[0003] When constructing in karst geological areas, due to various forms of dissolution, caves are often encountered during tunnel construction, and caves have a serious impact on tunnel construction and operation. At present, it is very common for tunnel projects to encounter karst geology. When caves appear at the bottom of the construction tunnel, it is often necessary to use backfilling methods to backfill the caves. However, this method of backfilling caves has low construction efficiency and poor economy. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a secondary entry method for a long high-speed railway tunnel to pass through a deep and large cave in view of the deficiencies in the above-mentioned prior art. By erecting a cantilever beam steel bridge between the excavated tunnel and the heading face, the cave can be crossed quickly and safely during construction, thereby reducing the impact of the cave on tunnel construction.

[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: a secondary cave entry method for a long high-speed railway tunnel to pass through a deep and large cave, comprising the following steps:

[0006] The bottom plate near the tunnel entrance of the cave is excavated and hardened and leveled;

[0007] Install a cantilever beam steel bridge at the hardened and leveled tunnel entrance, and fix one end of the cantilever beam steel bridge at the hardened and leveled tunnel entrance through a first ground anchor;

[0008] The construction workers excavated the pilot tunnel on the cantilever steel bridge at the opposite end of the tunnel, and then fixed the other end of the cantilever steel bridge to the bottom of the pilot tunnel through the second ground anchor;

[0009] Build a temporary trestle on the cantilever steel bridge and harden the road surface at both ends of the temporary trestle;

[0010] Install a steel frame in the pilot tunnel, excavate the tunnel face, and backfill the cave with tunnel slag after the excavation of the tunnel face;

[0011] After the cave backfill is completed, the temporary trestle is removed and the tunnel at the heading face is reinforced.

[0012] Further, the hardening and leveling comprises the following steps:

[0013] Pour C30 concrete on the excavated bottom plate to a depth of 20-40 cm from the tunnel bottom;

[0014] Leveling the poured concrete.

[0015] Further, after fixing one end of the cantilever beam steel bridge at the hardened and leveled tunnel entrance by the first ground anchor, and before the construction personnel excavate the pilot tunnel on the tunnel face opposite to the tunnel on the cantilever beam steel bridge, the following steps are included:

[0016] Edge protection of set height is installed on both sides of the cantilever beam steel bridge.

[0017] Furthermore, there are multiple first ground anchors, and the multiple first ground anchors are distributed in a plum blossom shape.

[0018] Furthermore, there are multiple second ground anchors, and the multiple second ground anchors are distributed in a plum blossom shape.

[0019] Furthermore, the pilot tunnel is excavated by means of pneumatic drilling and blasting.

[0020] Furthermore, the excavation depth of the pilot tunnel is 5-8 meters.

[0021] Further, the reinforcement of the tunnel at the face includes the following steps:

[0022] Excavate the bottom invert of the tunnel face and construct the invert reinforced concrete;

[0023] Steel mesh and steel frame are installed at the arch wall of the face tunnel, and concrete is sprayed.

[0024] Compared with the prior art, the present invention has the following advantages:

[0025] The present invention provides a secondary tunnel entry method for a long high-speed railway tunnel to pass through a deep and large karst cave. By setting up a cantilever beam steel bridge between the excavated tunnel and the heading, the karst cave can be quickly and safely crossed during construction, thereby reducing the impact of the karst cave on the tunnel construction.

[0026] The present invention provides a secondary tunnel entry method for a long high-speed railway tunnel to pass through a deep and large karst cave. Under the connection of a cantilever beam steel bridge, it can not only improve the construction efficiency, but also quickly align the tunnels at both ends of the karst cave to ensure the tunnel's flatness.

[0027] The present invention provides a secondary tunnel entry method for a long and large high-speed railway tunnel to pass through a deep and large karst cave. The slag excavated from the pilot tunnel is filled into the karst cave, so that the process of excavating the pilot tunnel and the process of filling the karst cave can be carried out simultaneously, saving construction time and improving construction efficiency. Since the karst cave is filled with the slag excavated from the pilot tunnel, there is no need to transport filling soil from the outside, and there is no need to clean the slag, thereby improving the economic benefit of the construction.

[0028] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 A schematic flow chart of a secondary tunnel entry method for a long high-speed railway tunnel provided by the present invention that passes through a deep and large karst cave;

[0030] Figure 2 It is a schematic diagram of the positional relationship of the tunnel, cave and face of the present invention;

[0031] Figure 3 It is a schematic diagram of the internal structure of the pilot tunnel after excavation of the present invention;

[0032] Figure 4 It is a schematic diagram of the overall structure of the cantilever beam steel bridge in the present invention;

[0033] Figure 5 It is a schematic cross-sectional view of the connection structure of adjacent sub-beams in the cantilever beam steel bridge of the present invention.

[0034] Description of reference numerals:

[0035] 1. First steel beam; 2. Connecting ribs; 3. Second steel beam; 4. Sub-beam; 5. Flange plate; 6. Web plate. DETAILED DESCRIPTION

[0036] like Figure 1-5 As shown, the present invention provides a secondary cave entry method for a long high-speed railway tunnel to pass through a deep and large cave, such as Figure 1 As shown, the following steps are included:

[0037] Step 1: Excavate the bottom plate near the tunnel entrance and harden and level it;

[0038] Step 2: Install a cantilever beam steel bridge at the hardened and leveled tunnel entrance, and fix one end of the cantilever beam steel bridge at the hardened and leveled tunnel entrance through a first ground anchor;

[0039] Step 3: The construction workers excavate the pilot tunnel on the cantilever beam steel bridge at the opposite end of the tunnel, and then fix the other end of the cantilever beam steel bridge to the bottom of the pilot tunnel through the second ground anchor;

[0040] Step 4: Build a temporary trestle on the cantilever beam steel bridge and harden the road surface at both ends of the temporary trestle;

[0041] Step 5: Install a steel frame in the pilot tunnel, excavate the tunnel face, and backfill the cave with the tunnel slag after the excavation of the tunnel face;

[0042] Step 6: After the cave is backfilled, the temporary trestle is removed and the tunnel at the face is reinforced.

[0043] Wherein, the hardening and leveling comprises the following steps:

[0044] Pour C30 concrete on the excavated bottom plate to a depth of 20-40 cm from the tunnel bottom;

[0045] Leveling the poured concrete.

[0046] Wherein, after fixing one end of the cantilever beam steel bridge at the hardened and leveled tunnel entrance by the first ground anchor, and before the construction personnel excavate the pilot tunnel on the tunnel face opposite to the tunnel on the cantilever beam steel bridge, the following steps are included:

[0047] Edge protection of set height is installed on both sides of the cantilever beam steel bridge.

[0048] There are multiple first ground anchors, and the multiple first ground anchors are distributed in a plum blossom shape.

[0049] There are multiple second ground anchors, and the multiple second ground anchors are distributed in a plum blossom shape.

[0050] Wherein, the pilot tunnel is excavated by means of pneumatic drilling and blasting.

[0051] Wherein, the excavation depth of the pilot tunnel is 5-8 meters.

[0052] Wherein, the reinforcement of the tunnel at the face includes the following steps:

[0053] Excavate the bottom invert of the tunnel face and construct the invert reinforced concrete;

[0054] Steel mesh and steel frame are installed at the arch wall of the face tunnel, and concrete is sprayed.

[0055] In the specific construction, the steps are as follows: excavation of the base plate → hardening and leveling (step 1) → installation of cantilever beams (step 2) → excavation of the pilot tunnel (step 3) → erection of a steel temporary bridge → hardening of the road surfaces at both ends of the temporary bridge (step 4) → expansion of the pilot tunnel and installation of steel frames → excavation of the heading face → backfilling of the cave (step 5) → removal of the steel temporary bridge → construction of an invert → construction of the arch wall lining (step 6).

[0056] First, we first introduce the specific conditions of tunnels and caves, such as Figure 2Because it is necessary to cross the karst cave, a tunnel is excavated on the face on the same axis as the tunnel, so it is called secondary entry.

[0057] The specific construction procedures of each method are as follows:

[0058] Base plate excavation

[0059] The bottom plate near the tunnel entrance of the cave is excavated to about 60-70cm below the bottom of the tunnel pit.

[0060] Hardening and leveling

[0061] After the bottom plate excavation is completed, 20cm thick C30 concrete is poured, and the elevation of the concrete top surface is controlled at 40cm below the bottom of the tunnel pit.

[0062] Cantilever beam installation

[0063] The cantilever beam is made of I22a I-beam, with a length of 18m, a width of 7.1m, and an I-beam spacing of 1m. The bottom is welded to the I-beam with Φ22 steel bars at a spacing of 1.5m to form a whole, and 3 22 I-beams are set at a spacing of 5m for reinforcement. The top is laid with 8mm thick steel plates, and the I-beam joints are staggered 4.5m. The joints are reinforced with steel plates and welded. 1.2m high hard edge protection is set on both sides of the cantilever beam.

[0064] After the cantilever beam is completed, it is pushed to the top of the cave, with one end close to the rock wall and ground anchors evenly placed within 3m of the other end. The ground anchors are arranged in a plum blossom shape with Φ32 steel bars with a spacing of 1m*1m, welded to the cantilever beam I-beam, driven into a depth of not less than 3m, and anchored with M30 cement mortar. A counterweight of not less than 1t is evenly piled within 2m of the fixed end of the cantilever beam.

[0065] Pilot tunnel excavation

[0066] Use the cantilever beam as a working platform to excavate the pilot hole within the contour of the horizontal excavation. Figure 3 As shown, the suspension bridge is only for personnel to pass and work, and no more than 5 people are allowed to pass and stay at the same time. Any large mechanical equipment is strictly prohibited from disturbing or passing through.

[0067] The pilot tunnel is excavated by pneumatic drilling and blasting. The excavation height is 2m above the tunnel bottom and the width is 3.25m on both sides of the tunnel centerline. The cyclic excavation advance is not more than 2m, and the pilot tunnel excavation is terminated after 5 to 8m of excavation.

[0068] Build a temporary steel bridge

[0069] After the excavation of the pilot tunnel meets the requirements for the trestle erection, remove the ground anchor at the rear of the cantilever beam and continue to push it forward into the pilot tunnel with a length of no less than 3m. Then, re-anchor the ground anchors at both ends of the large and small mileages, and use the cantilever beam as a platform to erect a temporary trestle. The trestle is made of 40H steel, with a length of 12m and a single-span width of 1.2m. Two spans are set according to the wheel width of the wheel equipment in the tunnel.

[0070] 1.2m high guardrails are set on both sides, and the access tunnel length is not less than 1m. The guardrails are composed of Φ48 steel pipe + dense mesh safety net. The vertical pole spacing is 1.5m, firmly welded to the steel plate, and the horizontal bar is set at a distance of 50cm from 20cm from the bottom. There are 3 lines welded or fastened to the vertical poles, and the inside is fully hung with dense mesh safety net.

[0071] Harden the road surface at both ends of the temporary bridge

[0072] After the trestle is erected, the road surface within 10m at both ends of the trestle is hardened and poured using C30 plain concrete formwork. The pouring height is 40 to 60cm and is flush with the top surface of the trestle to ensure a smooth connection between the top surface of the trestle and the hardened road surface, allowing mechanical equipment to pass smoothly.

[0073] Expansion of pilot tunnel and installation of steel frame

[0074] After the road surface is hardened, auxiliary holes and peripheral holes are set up using the excavation rig for smooth blasting to expand the small guide tunnel to the designed excavation section. The cycle advance shall not be greater than 2m (the distance between 2 steel frames). The initial arch frame shall be installed in time for support.

[0075] Face excavation

[0076] After entering the tunnel, excavation and support construction shall be carried out according to the original excavation and support plan.

[0077] Cave backfill

[0078] The cave is backfilled with cave slag. After filling to 2m below the invert arch, backfill, roll and compact every 1m layer until it reaches 1.5m below the bottom of the flat pilot pit.

[0079] Removal of steel temporary bridge

[0080] After the cave is backfilled to a position 1.5m below the bottom of the pit, backfilling is stopped, the hardened road surface is broken, and the steel temporary bridge is dismantled. It is gradually dismantled and dismantled in accordance with the principle of first build and then dismantle, or last build and first dismantle. After dismantling, a 12m long inverted arch trestle is erected to meet the transportation needs in the cave.

[0081] Make an inverted arch

[0082] Excavate the invert at the bottom of the tunnel and construct the invert reinforced concrete.

[0083] Arch wall lining

[0084] After the construction of the invert is completed, steel mesh and steel frame are set at the arch wall and concrete is sprayed.

[0085] In addition, if Figure 4-5 As shown, the cantilever beam steel bridge provided by the present invention comprises a plurality of first steel beams 1 arranged in parallel along the length direction of the tunnel, one end of the first steel beam 1 is fixed to the bottom plate of the tunnel end by a first ground anchor, and the other end of the first steel beam 1 is fixed to the surrounding rock of the excavated face by a second ground anchor, and a steel plate is laid above the first steel beam 1.

[0086] In the present invention, the first steel beam 1 is an I-beam, which is light in weight and high in strength, and can also bear a large load, so it can be effectively fixed in the cave and has a certain load capacity, meeting the safety requirements of construction personnel.

[0087] The present invention further comprises connecting ribs 2, which are vertically crossed and connected to the plurality of first steel beams 1. The connecting ribs 2 are wound and connected to the first steel beams 1. The connecting ribs 2 can not only ensure the connection strength between the plurality of first steel beams 1, but also determine the distance between two parallel adjacent first steel beams 1.

[0088] In the present invention, the first steel beam 1 is composed of a plurality of sub-beams 4 welded end to end in sequence. The head ends of two parallel adjacent sub-beams 4 are not located in a straight line. A flange plate 5 and / or a web plate 6 are arranged between the two sub-beams 4 connected end to end, and the two ends of the flange plate 5 and / or the web plate 6 are respectively welded to the two sub-beams 4 connected end to end. The flange plate 5 and the web plate 6 can wrap the end portions of the two sub-beams 4 adjacent end to end and fix them by welding, so that there are multiple welding points, which increases the connection strength of the two sub-beams 4 adjacent end to end.

[0089] The present invention further comprises a second steel beam 3, which is vertically cross-connected at the bottom of the plurality of first steel beams 1. The second steel beam 3 is also an I-beam. The second steel beam 3 can increase the stability of the first steel beam 1.

[0090] In summary, in actual construction, in one of the specific embodiments, the first steel beam 1 of the cantilever steel bridge is made of I22a I-beam, with a length of 18m, a width of 7.1m, an I-beam spacing of 1m, and a Φ22 connecting rib with a spacing of 1.5m at the bottom, welded to the I-beam to form a whole, the connecting rib is a steel bar, and 3 second steel beams 3 are provided with a spacing of 5m for reinforcement connection. The second steel beam 3 is made of 22a I-beam, and an 8mm thick steel plate is laid on the top. The I-beam joints of the adjacent parallel first steel beams 1 are staggered by 4.5m, and the joints are reinforced with steel plates. See Figure 2 , 1.2m high hard edge protection is set on both sides of the cantilever beam steel bridge.

[0091] After the cantilever steel bridge is completed, it is pushed above the cave, with one end close to the rock wall and ground anchors evenly placed within 3m of the other end. The ground anchors are arranged in a plum blossom shape with Φ32 steel bars with a spacing of 1m*1m, and are welded to the I-beam of the cantilever steel bridge. The depth of the anchor is not less than 3m, and M30 cement mortar is poured for anchoring. A counterweight of not less than 1t is evenly piled within 2m of the fixed end of the cantilever steel bridge.

[0092] In summary, when a wide and deep cave is encountered at the bottom of the tunnel before tunnel excavation, the present invention can quickly and safely cross the cave by quickly constructing a cantilever beam-steel temporary bridge structure, thereby reducing the impact of the cave on the construction; the invention clarifies the construction steps when the tunnel construction quickly crosses the cave, and the construction method fully guarantees the construction safety and construction quality.

[0093] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any way. Any simple modification, change and equivalent structural change made to the above embodiment based on the technical essence of the present invention still falls within the protection scope of the technical solution of the present invention.

Claims

1. A secondary cave entry method for a long high-speed railway tunnel through a deep and large cave, characterized in that: The following steps are involved: The bottom plate near the tunnel entrance of the cave is excavated and hardened and leveled; Install a cantilever beam steel bridge at the hardened and leveled tunnel entrance, and fix one end of the cantilever beam steel bridge at the hardened and leveled tunnel entrance through a first ground anchor; The construction workers excavated the pilot tunnel on the cantilever steel bridge at the opposite end of the tunnel, and then fixed the other end of the cantilever steel bridge to the bottom of the pilot tunnel through the second ground anchor; Build a temporary trestle on the cantilever steel bridge and harden the road surface at both ends of the temporary trestle; Install a steel frame in the pilot tunnel, excavate the tunnel face, and backfill the cave with tunnel slag after the excavation of the tunnel face; After the cave backfill is completed, the temporary trestle is removed and the tunnel at the heading face is reinforced.

2. A secondary cave entry method for a long high-speed railway tunnel with a flat guide passing through a deep and large cave according to claim 1, characterized in that: The hardening and leveling comprises the following steps: Pour C30 concrete on the excavated bottom plate to a depth of 20-40 cm from the tunnel bottom; Leveling the poured concrete.

3. A secondary cave entry method for a long high-speed railway tunnel with a flat guide passing through a deep and large cave according to claim 1, characterized in that: After fixing one end of the cantilever beam steel bridge to the hardened and leveled tunnel entrance through the first ground anchor, and before the construction personnel excavate the pilot tunnel on the tunnel face opposite to the tunnel on the cantilever beam steel bridge, the following steps are included: Edge protection of set height is installed on both sides of the cantilever beam steel bridge.

4. A secondary cave entry method for a long high-speed railway tunnel with a flat guide passing through a deep and large cave according to claim 1, characterized in that: There are multiple first ground anchors, and the multiple first ground anchors are distributed in a plum blossom shape.

5. A secondary cave entry method for a long high-speed railway tunnel with a flat guide passing through a deep and large cave according to claim 1, characterized in that: There are multiple second ground anchors, and the multiple second ground anchors are distributed in a plum blossom shape.

6. A secondary cave entry method for a long high-speed railway tunnel with a flat guide passing through a deep and large cave according to claim 1, characterized in that: The pilot tunnel is excavated by means of pneumatic drilling and blasting.

7. A secondary cave entry method for a long high-speed railway tunnel with a flat guide passing through a deep and large cave according to claim 1, characterized in that: The excavation depth of the pilot tunnel is 5-8 meters.

8. A secondary cave entry method for a long high-speed railway tunnel with a flat guide passing through a deep and large cave according to claim 1, characterized in that: The reinforcement of the tunnel at the face comprises the following steps: Excavate the bottom invert of the tunnel face and construct the invert reinforced concrete; Steel mesh and steel frame are installed at the arch wall of the face tunnel, and concrete is sprayed.