TBM assembly hole lining construction method

By employing a construction method involving small-hole lining and sand blowing backfilling, the problems of high construction difficulty, resource waste, and safety risks associated with assembling large components inside a TBM tunnel were solved, thereby improving construction efficiency and safety.

CN118911712APending Publication Date: 2024-11-08CHINA RAILWAY TUNNEL GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410819411.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-24
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

During the TBM assembly process inside the tunnel, the secondary lining construction of the large component assembly tunnel is difficult, resulting in resource waste, long construction time, high cost, and safety risks.

Method used

The construction method of small hole lining and sand blowing backfilling was adopted. The large component assembly tunnel section was divided into 8 sections. The first seven sections were constructed using the open tunnel method, and the eighth section was constructed using the closed method. Concrete was produced by an automatic metering mixing plant and pumped, immersion vibrated, and combined with sand blowing backfilling by shotcrete truck to form small hole lining and sand blowing holes were reserved in the arch.

Benefits of technology

It shortens the construction period by 25%, reduces construction difficulty, improves safety, avoids the risks of working at height, saves resources, and improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911712A_ABST
    Figure CN118911712A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of tunnel engineering construction, in particular to a tunnel boring machine (TBM) assembly hole lining construction method which comprises the following construction steps of preparing hole lining, trailer assembly hole lining, large piece assembly hole lining, starting hole lining, small hole lining and sand blasting backfill area construction. A mold is erected in a TBM large piece assembly hole to form a small hole lining, and then sand blasting backfilling treatment is conducted on the small hole lining and the middle portion of the large piece assembly hole. The core problem that the secondary lining construction difficulty of the TBM large piece assembly hole is large is solved, and the safe, feasible, reliable and economical construction purposes are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel engineering construction, in particular to a TBM assembly hole lining construction method. Background Art

[0002] The assembly process of TBM (tunnel boring machine) can be divided into two types: TBM outside the hole assembly and TBM inside the hole assembly. TBM outside the hole assembly is generally carried out in a factory environment, according to the normal assembly procedure, and the supporting trailers are transported to the assembly site in parts, and then hoisted one by one. After all trailers are hoisted, pipeline connection and commissioning work are carried out. In contrast, TBM inside the hole assembly is the most commonly used method in large-section TBM construction, which can reduce the space required for transportation and assembly, thereby saving space outside the hole. In addition, inside the hole assembly can also reduce the risks of workers at work, such as suspension and air pressure changes, and reduce the impact on the environment with its high safety, especially in areas sensitive to noise and vibration. In addition, under tight schedules or high-cost environments, inside the hole assembly can significantly reduce construction time and cost, and the benefits are more significant; however, inside the hole assembly still has some disadvantages. For example, the maximum cross-sectional size of a TBM large-piece assembly hole in a plateau project is 23.40m high and 17.62m wide. The traditional secondary lining scheme of the assembly hole will use a large-section lining trolley for construction. The same section is only more than 100 meters, such as Figure 1 , Figure 2 As shown, a great waste of trolley resources is caused. Summary of the invention

[0003] In order to solve the above technical problems, the present invention specifically adopts the following technical solutions.

[0004] A TBM assembly hole lining construction method is designed, which includes the following construction steps: preparation hole lining, trailer assembly hole lining, large assembly hole lining, starting hole lining, small hole lining, and sand blowing backfill area construction; firstly, a small hole lining is formed by erecting a formwork in the TBM large assembly hole, and then the small hole lining and the middle part of the large assembly hole are sand blown backfilled.

[0005] Preferably, the method of forming a small hole lining by erecting a formwork comprises: firstly dividing the large assembly hole section into 8 lining sections, wherein the first seven lining sections of the small hole lining can be constructed by an open hole method, that is, using a formwork trolley as an inner formwork and a combined steel formwork as an outer formwork to pour the arch wall lining concrete at one time; the eighth section is constructed by a concealed method.

[0006] Preferably, the concrete is produced by an automatic metering mixing station, transported by tank trucks, pumped into molds, and vibrated by insert vibrators.

[0007] Preferably, the construction sequence of the concealed section includes: backfilling concrete on both sides of the arch foot, mortaring flagstones on both sides of the side wall, crushed stone filter layer, concrete arch protection, pouring arch wall lining, backfilling soil and stone or blowing sand backfill.

[0008] Preferably, when backfilling and sand blowing, in order to ensure the dense backfill, after the first seven linings are completed, two shotcrete trucks are set up at the eighth lining position for sand blowing. After the first seven linings are completed, the eighth lining is cast using a blind method, and sand blowing holes are reserved on the arch for backfilling.

[0009] Preferably, the lining of the large assembly hole is constructed after the TBM starts. Before starting, the precast blocks of the invert are laid on the floor of the large assembly hole, and C30 fine stone concrete is backfilled in the 50 cm area on both sides of the precast blocks of the invert to meet the TBM stepping conditions. After starting, C25 concrete is used for backfilling to make the floor of the assembly hole uniform in elevation.

[0010] The beneficial effects of the present invention are as follows: compared with the existing TBM assembly hole lining construction method, the present invention proposes a TBM assembly hole lining construction method with small hole lining and blown sand as the core; it solves the core problem of the difficulty of secondary lining construction of large TBM assembly holes, and achieves the construction purpose of safety, feasibility, reliability and economy. Compared with traditional large hole lining, the construction period can be shortened by 25%, the construction difficulty is reduced, the construction safety is improved, and the risk of high-altitude operations is avoided. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a schematic diagram of the overall structure of the structure of the present invention;

[0012] Figure 2 It is a traditional trailer assembly hole lining construction diagram;

[0013] Figure 3 This is a schematic diagram of the traditional assembly hole lining construction;

[0014] Figure 4 It is a schematic diagram of the construction of the trailer assembly hole lining in the present invention;

[0015] Figure 5 It is a schematic diagram of the large-scale assembly hole lining construction in the present invention.

[0016] The numbers in the figure are: 1 trailer assembly hole, 2 large component assembly hole, 3 starting hole, 4 small hole lining, 5 sand blowing backfill area. DETAILED DESCRIPTION

[0017] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0018] Example 1

[0019] A TBM assembly hole lining construction method, such as Figures 1 to 5As shown, the following construction steps are included: lining of the preparatory hole, lining of the trailer assembly hole 1, lining of the large assembly hole 2, lining of the starting hole 3, lining of the small hole 4, and construction of the sand blowing backfill area 5. In order to ensure the rapid start of the TBM, the lining of the large assembly hole 2 is constructed after the TBM starts. Before the start, the invert precast blocks are laid on the bottom plate of the large assembly hole 2, and C30 fine stone concrete is backfilled in the 50cm area on both sides of the invert precast blocks to meet the TBM stepping conditions. After the start, C25 concrete is used for backfilling to make the bottom plate of the assembly hole uniform in elevation.

[0020] In the TBM large-scale assembly tunnel 2, a small-hole lining 4 is first formed by a formwork. The method of forming the small-hole lining 4 by a formwork includes: firstly, the large-scale assembly tunnel 2 is divided into 8 linings, among which the first seven linings of the small-hole lining 4 can be constructed by an open tunnel method, that is, a formwork trolley is used as an inner formwork, and a combined steel formwork is used as an outer formwork to pour the arch wall lining concrete at one time. The concrete is produced by an automatic metering mixing station, transported by a tank truck, pumped into the mold, and vibrated by an inserted vibrator; since the total length of the assembly tunnel of this section is 80m, if a small-section lining is used The whole section cannot be constructed in an open hole, so the eighth plate is constructed in a hidden way. The construction sequence of the hidden section includes: backfilling concrete on both sides of the arch foot, mortaring slabs on both sides of the side wall, crushed stone filter layer, concrete arch protection, pouring arch wall lining, backfilling soil and stone or backfilling by blowing sand. When backfilling and blowing sand, in order to ensure the backfill is dense, after the first seven plates of lining are completed, two spraying vehicles are set up at the eighth plate lining position for sand blowing. After the first seven plates of sand blowing are completed, the eighth plate lining is cast in a hidden way, and sand blowing holes are reserved on the arch top for backfilling. Then the small hole lining 4 and the middle part of the large assembly hole 2 are backfilled with sand blowing.

[0021] In the above embodiments, there is no need to customize the template trolley additionally. By using the preparation hole template trolley, the utilization rate of the trolley is increased by 40%, and the lining of the trailer assembly hole 1, the large-piece assembly hole 2, and the starting hole 3 are all constructed after the start.

[0022] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A TBM assembly hole lining construction method, characterized in that: The construction process includes the following steps: preparatory hole lining, trailer assembly hole lining, large-component assembly hole lining, starting hole lining, small hole lining, and sand blowing backfill area construction; first, a formwork is erected in the TBM large-component assembly hole to form a small hole lining, and then the small hole lining and the middle part of the large-component assembly hole are sand blown backfilled.

2. The TBM assembly hole lining construction method according to claim 1, characterized in that: The method of forming a small hole lining by erecting formwork includes: firstly, dividing the large assembly hole section into 8 lining sections, of which the first seven lining sections of the small hole can be constructed by open hole method, that is, using a formwork trolley as the inner formwork and a combined steel formwork as the outer formwork to pour the arch wall lining concrete at one time; the eighth section is constructed by concealed method.

3. The TBM assembly hole lining construction method according to claim 2, characterized in that: The concrete is produced by an automatic metering mixing station, transported by a tank truck, pumped into a mold, and vibrated by an inserted vibrator.

4. The TBM assembly hole lining construction method according to claim 2, characterized in that: The construction sequence of the concealed section includes: backfilling concrete on both sides of the arch foot, mortaring stone slabs on both sides of the side wall, crushed stone filter layer, concrete arch protection, pouring arch wall lining, backfilling soil and stone or blowing sand backfill.

5. The TBM assembly hole lining construction method according to claim 2, characterized in that: When backfilling and sand blowing, in order to ensure the backfill is dense, after the first seven linings are completed, two shotcrete trucks are set up at the eighth lining position for sand blowing. After the first seven linings are completed, the eighth lining is cast using a dark method, and sand blowing holes are reserved on the arch for backfilling.

6. The TBM assembly hole lining construction method according to claim 1, characterized in that: The large assembly hole lining is constructed after the TBM starts. Before starting, the invert precast blocks are laid on the floor of the large assembly hole, and C30 fine stone concrete is backfilled in the 50 cm area on both sides of the invert precast blocks to meet the TBM stepping conditions. After starting, C25 concrete is used for backfilling to make the floor of the large assembly hole have a uniform elevation.