Whole cabin coating efficient operation platform and erecting method
Through the combination of flat iron connecting strips and hook-type scaffolding platforms, the problem of long construction cycle and environmental impact of welded eye plate brackets in the entire cabin coating of ships is solved, and efficient and simple installation and removal of the working platform is achieved, shortening the shortening of the The construction cycle was completed and the coating quality was improved.
Patent Information
- Application Number
- CN202410994976.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-11-12
AI Technical Summary
In the existing ship full cabin coating operations, the use of welded eye plate brackets leads to an extended construction cycle, affecting the ship's performance and environment, and the removal and repair process have a negative impact on the coating quality.
A flat-iron connecting strip work platform and a hook-type scaffolding platform are used to erect a multi-layer working platform through flat-iron connecting strips and bracket workpieces to reduce the number of rooted eye plates, and use bolts to fix and support mechanisms to provide high detachment efficiency and simplify the construction process.
It shortens the ship construction cycle, reduces the amount of subsequent cutting and repair operations, improves construction efficiency, simplifies the decomposition process, meets the fixed management needs of different areas, and can be reused.
Smart Images

Figure CN118928699A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of shipbuilding, and in particular relates to a whole-cabin painting high-efficiency operation platform and a setting method thereof. Background Art
[0002] During ship construction, the entire cabin needs to be painted according to the ship's performance and operating environment requirements, such as finished oil / chemical tankers, aquaculture vessels, etc. Limited by the ship's cabin structure and construction environment, the entire cabin painting height is usually more than 20m, and the existing operating platform mainly adopts the full-cabin eye plate bracket scaffolding.
[0003] When using eye plate bracket scaffolding, the eye plate bracket scaffolding generally adopts a combination of one eye plate and one bracket. When painting the entire cabin, it is usually necessary to weld a large number of scaffolding eye plates to form an overall working platform. However, retaining the welded eye plates will have a certain impact on the operating environment and ship performance of some special ships. For example, all welded eye plates in the cabin of aquaculture ships need to be removed in the later stage to avoid affecting the growth of fish in the cabin. When a large number of welded eye plates are removed, the cutting and repairing operations will prolong the construction period and cause greater damage to the surrounding completed painting areas. The more damaged areas, the greater the impact on the construction quality of the entire cabin painting. Summary of the invention
[0004] The purpose of the present invention is to overcome the deficiencies of the above-mentioned prior art and to provide an efficient whole-tank painting operation platform and a method for erecting the same.
[0005] To achieve the above object, the present invention adopts the following technical solution:
[0006] A whole-cabin painting efficient work platform comprises a flat iron connecting bar type tooling platform and a hook type scaffolding platform, wherein the flat iron connecting bar type tooling platform extends from low to high along the inner side wall of a ship cabin structure, the top end of the flat iron connecting bar type tooling platform is connected to the hook type scaffolding platform, and the hook type scaffolding platform is connected to the inner top wall of the ship cabin structure.
[0007] Preferably, the flat iron connecting strip type tooling platform comprises a plurality of flat iron connecting strip type scaffolds arranged along the height direction of the inner side wall of the ship cabin structure;
[0008] The flat iron connecting bar type scaffolding includes at least two flat iron connecting bars arranged in the front-to-back direction, a plurality of bracket toolings distributed in the height direction and fixedly connected to the flat iron connecting bars, and scaffolding boards laid on the bracket toolings; the top end of the flat iron connecting bar is fixed to the inner wall of the ship's cabin structure through a rooting eye plate, and the bottom end of the flat iron connecting bar is fixed to the inner wall of the ship's cabin structure through a supporting mechanism; an upwardly extending edge guardrail is provided on the side of the bracket tooling away from the flat iron connecting bar.
[0009] Preferably, the flat iron connecting strip comprises a plurality of connecting strip plates, a plurality of flat iron connecting holes are evenly arranged on the connecting strip plates, and adjacent connecting strip plates in the flat iron connecting strip are connected by two bolts, and each bolt is adapted to two nuts.
[0010] Preferably, the support fixture is arranged at an angle, and the end of the support fixture connected to the edge guardrail is higher than the end connected to the flat iron connecting strip.
[0011] Preferably, round steel stops are provided at the upper and lower ends of the support mechanism to prevent the flat iron connecting bar from rotating.
[0012] Preferably, a special rooting point opening for the safety belt is provided on the support tooling.
[0013] Preferably, the hook-type scaffolding platform comprises a plurality of vertically arranged round steel tie rods, and the vertical projections of the round steel tie rods are distributed in a grid shape;
[0014] The upper end of the round steel tie rod is provided with a first bent portion bent downward, and the round steel tie rod is connected to a hook-type eye plate through the first bent portion, and the hook-type eye plate is fixedly arranged on the wall surface of the ship cabin;
[0015] The lower end of the round steel tie rod is provided with two opposite second bending parts bending upward, and horizontal steel pipes are arranged on the corresponding second bending parts on the adjacent round steel tie rods at the same height, and the horizontal steel pipes at the same height are arranged in parallel, and the horizontal steel pipes are fixed to the corresponding second bending parts by iron wire binding;
[0016] Several steel pedals are laid on the horizontal steel pipes at the same height;
[0017] A vertical steel pipe is vertically fixed between the horizontal steel pipes aligned up and down, and the vertical steel pipe is fixed to the horizontal steel pipe by binding with wires.
[0018] Preferably, the top end of the flat iron connecting bar type tooling platform is connected to the corresponding horizontal steel pipe in the hook type scaffolding platform;
[0019] The end of the horizontal steel pipe connected to the top of the flat iron connecting bar type tooling platform is plugged into the supporting device;
[0020] The support device is a right-angled bending structure, one right-angle side of the support device is provided with a plug hole for the corresponding horizontal steel pipe to pass through, and the other right-angle side of the support device is provided with two support connection holes for corresponding to the flat iron connection holes on the flat iron connection strip;
[0021] Fastening bolts are arranged in the corresponding flat iron connection holes and support connection holes.
[0022] Preferably, safety nets are provided around the flat iron connecting bar type tooling platform and the hook type scaffolding platform.
[0023] The present invention also provides a method for erecting a high-efficiency operation platform for whole-cabin painting.
[0024] A method for setting up an efficient operation platform for whole-tank painting comprises the following steps:
[0025] Step 1, set up a flat iron connecting bar type tooling platform;
[0026] In the stage of block production, the rooting eye plate is welded to the inner wall of the ship cabin structure in advance, and then the flat iron connecting strip, supporting mechanism, bracket tooling, and edge guardrail are set up in sequence, and then the scaffolding board is laid on the bracket tooling;
[0027] Step 2, hook-type scaffolding platform;
[0028] In the stage of block production, the hook-type eye plate is welded to the inner wall of the ship cabin structure in advance, and then the round steel tie rods are installed on the hook-type eye plate, followed by the horizontal steel pipes and vertical steel pipes, and then the steel pedals are laid on the horizontal steel pipes;
[0029] Step 3: Improve the operation platform;
[0030] Install a support device at the position where the flat iron connecting bar type tooling platform is connected to the hook type scaffolding platform, and plug the end of the horizontal steel pipe connected to the top of the flat iron connecting bar type tooling platform into the support device to form a complete working platform that meets the requirements of the whole cabin painting operation;
[0031] Step 4: Set up a safety net around the working platform.
[0032] The beneficial effects of the present invention are:
[0033] In the flat iron connecting bar type tooling platform of the present invention, a single rooting eye plate can be used to build a multi-layer working platform using the flat iron connecting bar. The flat iron connecting bar and the bracket tooling are fixed by means of bolts, and a supporting mechanism is arranged at the bottom. The number of rooting eye plates is greatly reduced, thereby reducing the subsequent eye plate cutting and painting repair work and shortening the ship construction period. At the same time, the assembly and disassembly form of the working platform of the present application is relatively simple, the assembly and disassembly efficiency is high, and the construction period is short. The modular structure of the working platform is simple, and the layer height setting standard is adjustable, which can meet the fixed management of different areas and can be reused. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] The drawings in the specification, which constitute a part of the present application, are used to provide further understanding of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute improper limitations on the present application.
[0035] Figure 1This is a schematic diagram of the structure of the efficient operation platform for whole-tank painting of the present invention;
[0036] Figure 2 It is a structural schematic diagram of the flat iron connecting strip type scaffold in the present invention;
[0037] Figure 3 It is a schematic diagram of the connection of adjacent connecting strips in the present invention;
[0038] Figure 4 It is a structural schematic diagram of the hook-type scaffolding platform of the present invention;
[0039] Figure 5 It is a top view of the arrangement of the round steel tie rod and the horizontal steel pipe in the present invention;
[0040] Figure 6 It is a structural schematic diagram of the support mechanism in the present invention;
[0041] Figure 7 It is a schematic front view of the structure of the support device in the present invention;
[0042] Figure 8 is a schematic side view of the structure of the support device in the present invention;
[0043] Fig. 9 is a schematic side view of the structure of the support device in the present invention;
[0044] in:
[0045] 1- flat iron connecting strip, 101- flat iron connecting hole, 102- bolt, 103- nut, 2- rooting eye plate, 3- supporting mechanism, 301- round steel stopper, 4- bracket tooling, 401- special rooting point opening for safety belt, 5- edge guardrail, 6- scaffolding board, 7- safety net, 8- round steel pull rod, 801- first bending part, 802- second bending part, 9- hook type eye plate, 10- horizontal steel pipe, 11- steel pedal, 12- vertical steel pipe, 13- supporting device, 1301- socket, 1302- supporting connecting hole. DETAILED DESCRIPTION
[0046] It should be noted that the following detailed descriptions are illustrative and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.
[0047] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0048] In the present invention, the directions or positional relationships indicated by terms such as "upper", "lower", "bottom", "top", etc. are based on the directions or positional relationships shown in the accompanying drawings. They are relational words determined only for the convenience of describing the structural relationships of the various parts or elements of the present invention. They do not specifically refer to any part or element in the present invention and cannot be understood as limitations on the present invention.
[0049] In the present invention, terms such as "connected" and "connection" should be understood in a broad sense, indicating that the connection can be fixed, integral or detachable; it can be directly connected or indirectly connected through an intermediate medium. Relevant scientific research or technical personnel in this field can determine the specific meaning of the above terms in the present invention according to specific circumstances, and they should not be understood as limiting the present invention.
[0050] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0051] Embodiment 1:
[0052] like Figure 1 As shown, an efficient work platform for whole-cabin painting includes a flat iron connecting bar type tooling platform and a hook type scaffolding platform. The flat iron connecting bar type tooling platform extends from low to high along the inner wall of the ship's cabin structure, and the top of the flat iron connecting bar type tooling platform is connected to the hook type scaffolding platform, and the hook type scaffolding platform is connected to the inner top wall of the ship's cabin structure.
[0053] Preferably, the flat iron connecting strip type tooling platform comprises a plurality of flat iron connecting strip type scaffolds arranged along the height direction of the inner side wall of the ship cabin structure;
[0054] like Figure 2 As shown, the flat iron connecting bar type scaffolding includes at least two flat iron connecting bars 1 arranged along the front-to-back direction, a plurality of bracket fixtures 4 distributed along the height direction and fixedly connected to the flat iron connecting bars 1, and a scaffolding board 6 laid on the bracket fixtures 4; the top end of the flat iron connecting bar 1 is fixed to the inner wall of the ship's cabin structure through a rooting eye plate 2, and the bottom end of the flat iron connecting bar 1 is fixed to the inner wall of the ship's cabin structure through a supporting mechanism 3; the side of the bracket fixture 4 away from the flat iron connecting bar 1 is provided with an upwardly extending edge guardrail 5.
[0055] Preferably, the flat iron connecting strip 1 comprises a plurality of connecting strip plates, and a plurality of flat iron connecting holes 101 are evenly arranged on the connecting strip plates. Figure 3 As shown, the adjacent connecting strips in the flat iron connecting strip 1 are connected by two bolts 102, and each bolt 102 is adapted to two nuts 103, so as to protect the bolts 102 and prevent them from slipping. The two bolts 102 between the adjacent connecting strips in the flat iron connecting strip 1 are arranged in different directions.
[0056] Preferably, the support fixture 4 is arranged at an angle, and the end of the support fixture 4 connected to the edge guardrail 5 is higher than the end connected to the flat iron connecting bar 1, so as to ensure that the overall working platform 6 will not collapse and ensure the safety of the workers.
[0057] Preferably, the support mechanism 3 is bolted to the flat iron connecting bar 1 .
[0058] Preferably, Figure 6 As shown, round steel stops 301 are provided at the upper and lower ends of the support mechanism 3 to prevent the flat iron connecting bar 1 from rotating.
[0059] Preferably, the support fixture 4 is bolted to the flat iron connecting strip 1 .
[0060] Preferably, the support tooling 4 is provided with a special rooting point opening 401 for the safety belt to ensure the safety of personnel during operation.
[0061] Preferably, Figure 4-Figure 5 As shown, the hook-type scaffolding platform includes a plurality of vertically arranged round steel tie rods 8, and the vertical projections of the round steel tie rods 8 are distributed in a grid shape;
[0062] The upper end of the round steel tie rod 8 is provided with a first bending portion 801 bent downward, and the round steel tie rod 8 is connected to the hook-type eye plate 9 through the first bending portion 801, and the hook-type eye plate 9 is fixedly arranged on the wall of the ship cabin;
[0063] The lower end of the round steel tie rod 8 is provided with two opposite second bending parts 802 bending upward, and the corresponding second bending parts 802 on the adjacent round steel tie rods 8 at the same height are provided with horizontal steel pipes 10, and the horizontal steel pipes 10 at the same height are arranged in parallel, and the horizontal steel pipes 10 and the corresponding second bending parts 802 are tied and fixed by wire;
[0064] A plurality of steel pedals 11 are laid on the horizontal steel pipes 10 at the same height;
[0065] A vertical steel pipe 12 is vertically fixed between the horizontal steel pipes 10 aligned up and down, and the vertical steel pipe 12 is fixed to the horizontal steel pipe 10 by binding with wires.
[0066] Preferably, the top of the flat iron connecting bar type tooling platform is connected to the corresponding horizontal steel pipe 10 in the hook type scaffolding platform;
[0067] The end of the horizontal steel pipe 10 connected to the top of the flat iron connecting bar type tooling platform is plugged into the supporting device 13;
[0068] like Figure 7-Figure 9 As shown, the support device 13 is a right-angled structure, and a plug hole 1301 is provided on one right-angle side of the support device 13 for the corresponding horizontal steel pipe 10 to pass through, and two support connection holes 1302 are provided on the other right-angle side of the support device 13 for corresponding to the flat iron connection holes 101 on the flat iron connection strip 1;
[0069] Fastening bolts are arranged in the corresponding flat iron connection holes 101 and support connection holes 1302 .
[0070] Preferably, safety nets 7 are provided around the flat iron connecting bar type tooling platform and the hook type scaffolding platform.
[0071] Embodiment 2:
[0072] The method for setting up the whole cabin painting high-efficiency operation platform in Example 1 comprises the following steps:
[0073] Step 1, set up a flat iron connecting bar type tooling platform;
[0074] In the stage of segmented production, the rooting eye plate 2 is welded to the inner wall of the ship cabin structure in advance, and then the flat iron connecting strip 1, the supporting mechanism 3, the bracket tooling 4, the edge guardrail 5 are set up in sequence, and then the scaffolding board 6 is laid on the bracket tooling 4;
[0075] A safety net is installed at the back 6.
[0076] In this application, the components of the flat iron connecting strip tooling platform are flexibly combined to form an easy-to-assemble and disassemble work platform; all normally constructed sections can be erected before the sections are painted, and the flat iron connecting strip tooling platform is not dismantled after the sections are painted, and is transferred to the overall assembly stage for continued use;
[0077] Step 2, hook-type scaffolding platform;
[0078] In the stage of segmented production, the hook-type eye plate 9 is welded to the inner wall of the ship cabin structure in advance, and then each round steel tie rod 8 is installed on the hook-type eye plate 9, and then each horizontal steel pipe 10 and vertical steel pipe 12 are set up, and then the steel pedal 11 is laid on the horizontal steel pipe 10;
[0079] Step 3: Improve the operation platform;
[0080] Install a support device 13 at the position where the flat iron connecting bar type tooling platform is connected to the hook type scaffolding platform, and plug the end of the horizontal steel pipe 10 connected to the top of the flat iron connecting bar type tooling platform into the support device 13 to form a complete working platform that meets the requirements of the whole cabin painting operation;
[0081] Step 4, set up a safety net 7 around the working platform.
[0082] After the work platform is set up, the whole tank will be painted. After the whole tank is painted, the work platform will be dismantled, and the construction platform will be dismantled according to the construction standards, and the materials will be sorted and organized. After that, the remaining work from painting will be handled. After all the tooling platforms are dismantled, the reserved areas for painting of all eye plates and support mechanisms will be handled to complete the painting of the whole tank.
[0083] In the flat iron connecting bar tooling platform of the present application, a single rooting eye plate 2 can be used to build a multi-layer work platform using the flat iron connecting bar 1. The flat iron connecting bar 1 and the bracket tooling are fixed with bolts, and a supporting mechanism 3 is set at the bottom. The number of rooting eye plates 2 is greatly reduced, which reduces the amount of subsequent cutting eye plates and painting repair work, shortening the ship construction period. At the same time, the assembly and disassembly form of the work platform of the present application is relatively simple, with high assembly and disassembly efficiency and short construction period; the modular structure of the work platform is simple, the layer height setting standard is adjustable, which can meet the fixed management of different areas and can be reused.
[0084] Although the above describes the specific implementation mode of the present invention in conjunction with the accompanying drawings, it is not a limitation of the present invention. Those skilled in the art should understand that various modifications or variations that can be made by those skilled in the art on the basis of the technical solution of the present invention without creative work are still within the protection scope of the present invention.
Claims
1. An efficient operation platform for whole-tank painting. It is characterized in that It comprises a flat iron connecting bar type tooling platform and a hook type scaffolding platform. The flat iron connecting bar type tooling platform extends from low to high along the inner side wall of the ship cabin structure. The top of the flat iron connecting bar type tooling platform is connected to the hook type scaffolding platform, and the hook type scaffolding platform is connected to the inner top wall of the ship cabin structure.
2. The efficient operation platform for whole-tank painting as claimed in claim 1, It is characterized in that The flat iron connecting strip type tooling platform comprises a plurality of flat iron connecting strip type scaffolds arranged along the height direction of the inner side wall of the ship cabin structure; The flat iron connecting bar type scaffolding includes at least two flat iron connecting bars arranged in the front-to-back direction, a plurality of bracket toolings distributed in the height direction and fixedly connected to the flat iron connecting bars, and scaffolding boards laid on the bracket toolings; the top end of the flat iron connecting bar is fixed to the inner wall of the ship's cabin structure through a rooting eye plate, and the bottom end of the flat iron connecting bar is fixed to the inner wall of the ship's cabin structure through a supporting mechanism; an upwardly extending edge guardrail is provided on the side of the bracket tooling away from the flat iron connecting bar.
3. The efficient whole-tank painting operation platform as claimed in claim 2, It is characterized in that The flat iron connecting strip comprises a plurality of connecting strip plates, on which a plurality of flat iron connecting holes are evenly arranged, and adjacent connecting strip plates in the flat iron connecting strip are connected by two bolts, and each bolt is adapted to two nuts.
4. The efficient whole-tank painting operation platform as claimed in claim 3, It is characterized in that The support fixture is arranged in an inclined manner, and the end of the support fixture connected to the edge guardrail is higher than the end connected to the flat iron connecting strip.
5. The efficient operation platform for whole-tank painting as claimed in claim 4, It is characterized in that Round steel stops are provided at the upper and lower ends of the support mechanism to prevent the flat iron connecting strip from rotating.
6. The efficient operation platform for whole-tank painting as claimed in claim 5, It is characterized in that The support tooling is provided with a special rooting point opening for the safety belt.
7. The efficient operation platform for whole-tank painting as claimed in claim 6, It is characterized in that The hook-type scaffolding platform comprises a plurality of vertically arranged round steel tie rods, and the vertical projections of the round steel tie rods are distributed in a grid shape; The upper end of the round steel tie rod is provided with a first bent portion bent downward, and the round steel tie rod is connected to a hook-type eye plate through the first bent portion, and the hook-type eye plate is fixedly arranged on the wall surface of the ship cabin; The lower end of the round steel tie rod is provided with two opposite second bending parts bending upward, and horizontal steel pipes are arranged on the corresponding second bending parts on the adjacent round steel tie rods at the same height, and the horizontal steel pipes at the same height are arranged in parallel, and the horizontal steel pipes are fixed to the corresponding second bending parts by iron wire binding; Several steel pedals are laid on the horizontal steel pipes at the same height; A vertical steel pipe is vertically fixed between the horizontal steel pipes aligned up and down, and the vertical steel pipe is fixed to the horizontal steel pipe by binding with iron wire.
8. The efficient operation platform for whole-tank painting as claimed in claim 7, It is characterized in that The top end of the flat iron connecting bar type tooling platform is connected to the corresponding horizontal steel pipe in the hook type scaffolding platform; The end of the horizontal steel pipe connected to the top of the flat iron connecting bar type tooling platform is plugged into the supporting device; The support device is a right-angled bending structure, one right-angle side of the support device is provided with a plug hole for the corresponding horizontal steel pipe to pass through, and the other right-angle side of the support device is provided with two support connection holes for corresponding to the flat iron connection holes on the flat iron connection strip; Fastening bolts are arranged in the corresponding flat iron connection holes and support connection holes.
9. The efficient whole-tank painting operation platform as claimed in claim 8, It is characterized in that Safety nets are provided around the flat iron connecting bar type tooling platform and the hook type scaffolding platform.
10. The method for setting up the efficient operation platform for whole-tank painting according to claim 9, It is characterized in that The following steps are involved: Step 1, set up a flat iron connecting bar type tooling platform; In the stage of block production, the rooting eye plate is welded to the inner wall of the ship cabin structure in advance, and then the flat iron connecting strip, supporting mechanism, bracket tooling, and edge guardrail are set up in sequence, and then the scaffolding board is laid on the bracket tooling; Step 2, hook-type scaffolding platform; In the stage of block production, the hook-type eye plate is welded to the inner wall of the ship cabin structure in advance, and then the round steel tie rods are installed on the hook-type eye plate, followed by the horizontal steel pipes and vertical steel pipes, and then the steel pedals are laid on the horizontal steel pipes; Step 3: Improve the operation platform; Install a support device at the position where the flat iron connecting bar type tooling platform is connected to the hook type scaffolding platform, and plug the end of the horizontal steel pipe connected to the top of the flat iron connecting bar type tooling platform into the support device to form a complete working platform that meets the requirements of the whole cabin painting operation; Step 4: Set up a safety net around the working platform.
Citation Information
Cited By
Non-welding type rooting fixing method for segmented outer plate scaffold
CN120817218A
Non-welding fixing method for segmental outer plate scaffold
CN120817218B