Large-span prestress truss device and pipe belt machine
By setting up a system of arched large truss sleeves in the large span prestressed truss device, and using the cooperation of prestressed components and pole components, the stability problem of conveyor belt assembly under large span space is solved, and the structure is realized The strength increase and weight reduction meet the material conveying needs under complex terrain.
Patent Information
- Application Number
- CN202411179561.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-11-12
AI Technical Summary
The prior art is difficult to meet the needs of large-span prestressed truss devices for pipe belt conveyors used in large span spaces, and cannot effectively support the stable operation of conveyor belt assemblies under complex terrain.
A large span prestressed truss device is designed, including a first arch truss, a second arch truss, two sets of prestressed assemblies and two sets of strut assembly, by providing a second arch truss within the first arch truss , a system of arched large trusses with arched small trusses is formed. The prestressed component applies a tension force to the first arched truss, and the strut assembly cooperates with the prestressed component to provide a top tightening force to improve structural strength.
The stable operation of the large-span conveyor belt assembly is achieved, the overall weight and manufacturing cost is reduced, the necessity of increasing the cross-section of the truss chord material to improve strength is avoided, and the stable performance of the pipe belt machine in the large-span space is ensured.
Smart Images

Figure CN118929064A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of tubular belt conveyors, and in particular to a large-span prestressed truss device and a tubular belt conveyor. Background Art
[0002] With the rapid development of bulk material logistics industry, tubular belt conveyors (hereinafter referred to as "pipe belt conveyors") are widely used in coal mine storage and transportation, chemical steel plants and other production industries with their advantages of long distance, two-way transportation and space turning. As an important supporting structure in the pipe belt conveyor, the truss bears the longitudinal horizontal load, lateral wind load and earthquake effect transmitted by the material, providing a guarantee for the smooth operation of the pipe belt conveyor.
[0003] Large-span prestressed truss devices play an important role when crossing particularly complex terrains such as existing buildings, high-speed rail lines, original pipeline corridors, stream valleys, etc.
[0004] However, there is an urgent need for a large-span prestressed truss device for a pipe-belt machine that can meet the needs of larger span spaces. Summary of the invention
[0005] The embodiment of the present application provides a large-span prestressed truss device and a pipe-belt machine, which can solve the problem in the prior art that a large-span prestressed truss device of a pipe-belt machine that can meet the needs of a larger span space is urgently needed.
[0006] To achieve the above purpose, the present application provides the following technical solutions:
[0007] In one aspect, a long-span prestressed truss device is provided, the long-span prestressed truss device comprising:
[0008] A first arch truss, a second arch truss, two sets of prestressed assemblies, and two sets of brace assemblies;
[0009] The first arched truss has a receiving cavity, and the extending direction of the receiving cavity is the same as the extending direction of the first arched truss;
[0010] The second arched truss is fixed in the accommodating cavity, the extension direction of the second arched truss is the same as the extension direction of the first arched truss, and the second arched truss is used to carry the conveyor belt assembly;
[0011] The two groups of prestressed components are both located at the bottom of the first arched truss, and the two groups of prestressed components are arranged opposite to each other along the axial direction of the first arched truss, and the two ends of each group of prestressed components are respectively fastened to the two ends of the first arched truss, and each group of prestressed components is configured to: be able to apply tensioning force to the ends of the first arched truss;
[0012] The two groups of strut assemblies correspond to the two groups of prestressed assemblies respectively, each group of the strut assemblies is located between the bottom of the first arch truss and the corresponding prestressed assembly, each group of the strut assemblies includes a plurality of the strut assemblies, and both ends of the strut assemblies in each group of the strut assemblies are respectively connected to the bottom of the first arch truss and the corresponding prestressed assembly.
[0013] Optionally, the first arched truss comprises: a plurality of first square frames arranged in an array along an extension direction of the first arched truss, and a first connecting component located between every two adjacent first square frames, wherein two ends of the first connecting component are respectively fixedly connected to the corresponding two adjacent first square frames;
[0014] The plurality of first square frames and the plurality of first connecting assemblies are used to enclose the accommodating cavity, and one end of the strut assembly is connected to both the first square frame and the first connecting assembly.
[0015] Optionally, the first connecting assembly includes: a plurality of first connecting rods corresponding one-to-one to a plurality of corners of the first square frames, and at least one first auxiliary connecting rod located between every two adjacent first connecting rods, wherein both ends of the first connecting rod are respectively fixedly connected to the corners of two adjacent first square frames, and both ends of the first auxiliary connecting rod are respectively fixedly connected to the two adjacent first square frames.
[0016] Optionally, the strut assembly comprises: a connecting seat, a vertical strut and an anti-sway strut, the connecting seat is fastened to the prestressed assembly, one end of the vertical strut is fixedly connected to the connecting seat, and the other end of the vertical strut is hinged to the bottom of the first arched truss; one end of the anti-sway strut is fixedly connected to the connecting seat, and the other end of the anti-sway strut is hinged to the bottom of the first arched truss;
[0017] Wherein, the length direction of the anti-sway support rod intersects with the length direction of the vertical support rod.
[0018] Optionally, the connecting seat comprises: a first seat body and a second seat body which are arranged opposite to each other along the length direction of the vertical support rod, the first seat body has a first groove on a side facing the second seat body, and the second seat body has a second groove on a side facing the first seat body;
[0019] The first groove and the second groove form a hoop-shaped groove, the connecting seat is sleeved on the prestressed component through the hoop-shaped groove, and the first seat body is firmly connected to the second seat body.
[0020] Optionally, the first base body has a first connecting hole, and the second base body has a second connecting hole communicating with the first connecting hole;
[0021] The connection seat further includes a fastener, and the fastener is configured to pass through the first connection hole and the second connection hole in sequence to be fastened to the first seat body and the second seat body.
[0022] Optionally, the bottom of the first arched truss has two support beams distributed at both ends of each group of prestressed components, the support beams have a limiting cavity, one end of the support beam close to the prestressed component has a first connection port, and one end of the support beam away from the prestressed component has a second connection port, and the first connection port and the second connection port are both connected to the limiting cavity;
[0023] The prestressed component comprises: a prestressed sleeve, a plurality of steel strands and two anchors, the two ends of the prestressed sleeve are respectively fixedly connected to the first connection ports of the two support beams, the two anchors are respectively fixedly connected to the second connection ports of the two support beams, a portion of the steel strands is distributed in the limiting cavity and the prestressed sleeve, and the two ends of the steel strands are respectively fastened to the two anchors;
[0024] Wherein, the connecting seat is tightly connected to the outer side surface of the prestressed sleeve.
[0025] Optionally, the second arched truss has an installation cavity, the extension direction of the installation cavity is the same as the extension direction of the second arched truss, and the conveyor belt assembly is installed in the installation cavity.
[0026] Optionally, the second arched truss comprises: a plurality of second square frames arranged in an array along the extension direction of the second arched truss, and a second connecting assembly located between every two adjacent second square frames, wherein both ends of the second connecting assembly are respectively fixedly connected to the corresponding two adjacent second square frames; the plurality of second square frames and the plurality of second connecting assemblies are used to enclose the installation cavity;
[0027] Wherein, a distance between two adjacent first square frames along the circumferential direction of the first arched truss is greater than a distance between two adjacent second square frames along the circumferential direction of the second arched truss.
[0028] Optionally, at least some of the multiple second connecting assemblies include: two groups of reinforcements that are arranged opposite to each other along the axial direction of the second arch truss and located on two side surfaces of the second square frame, and both ends of each group of reinforcements are respectively fixedly connected to two adjacent second square frames.
[0029] Optionally, the large-span prestressed truss device also includes: two brackets, which are respectively distributed at both ends of the first arch truss, and one end of the first arch truss is fastened to one of the brackets, and the other end of the first arch truss is movably connected to the other bracket.
[0030] In another aspect, a belt conveyor is provided, the belt conveyor comprising:
[0031] A long-span prestressed truss device and a conveyor belt assembly, wherein the conveyor belt assembly is installed on a second arched truss in the long-span prestressed truss device, and the long-span prestressed truss device is any of the long-span prestressed truss devices given above.
[0032] The beneficial effects brought by the technical solution provided by the embodiment of the present application include at least:
[0033] A long-span prestressed truss device may include: a first arched truss, a second arched truss, two groups of prestressed components and two groups of strut components. By arranging the first arched truss in the long-span prestressed truss device and arranging the second arched truss in the first arched truss, a large truss system of an arched large truss and an arched small truss is formed, the second arched truss plays a role in supporting the operation of the conveyor belt assembly, and the first arched truss with a relatively large volume can rely on the second arched truss to achieve long-distance spanning. In addition, the first arched truss has to bear the load from the second arched truss, as well as the load applied by subsequent operators during maintenance, etc. By arranging the prestressed component at the bottom of the first arched truss, the prestressed component can apply a tensioning force to the two ends of the first arched truss, and the tensioning force can offset the horizontal thrust borne by the first arched truss, thereby reducing the force on the bottom structure of the first arched truss. Furthermore, by providing a strut assembly between the prestressed component and the first arched truss, the strut assembly can cooperate with the prestressed component to generate an upward tightening force on the first arched truss, so that the structural strength of the first arched truss is relatively improved, effectively ensuring the stable performance of the belt conveyor truss in transporting materials across a larger space, and there is no need to further increase the strength of the truss by increasing the cross-section of the truss chord material, thereby effectively reducing the overall weight of the large-span prestressed truss device and reducing manufacturing costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0035] Figure 1It is a structural schematic diagram of a large-span prestressed truss device provided in an embodiment of the present application;
[0036] Figure 2 yes Figure 1 A partial structural schematic diagram of a large-span prestressed truss device is shown;
[0037] Figure 3 It is a partial structural exploded schematic diagram of a large-span prestressed truss device provided in an embodiment of the present application;
[0038] Figure 4 It is a partial structural schematic diagram of another large-span prestressed truss device provided in an embodiment of the present application;
[0039] Figure 5 is a schematic diagram of a perspective of the connection of the brace assembly provided in an embodiment of the present application with the first arch truss and the prestressed assembly respectively;
[0040] Figure 6 is a schematic diagram of another perspective of the connection between the brace assembly provided by an embodiment of the present application and the first arch truss and the prestressed assembly respectively;
[0041] Figure 7 This is a schematic diagram of the connection between a prestressed component and a support beam provided in an embodiment of the present application;
[0042] Figure 8 It is a structural schematic diagram of a prestressed casing provided in an embodiment of the present application;
[0043] Fig. 9 yes Figure 8 A cross-sectional view of a prestressed casing is shown;
[0044] Fig.10 is a schematic diagram of the installation of a second arched truss and a conveyor belt assembly provided in an embodiment of the present application;
[0045] Fig.11 It is a partial structural side view of a large-span prestressed truss device provided in an embodiment of the present application;
[0046] Fig.12 is a structural schematic diagram of a large-span prestressed truss device provided in another embodiment of the present application;
[0047] Fig.13 It is a displacement deformation diagram of a truss body in a large-span prestressed truss device provided in an embodiment of the present application under the support of a prestressed component and a brace component;
[0048] Fig.14 This is the displacement deformation diagram of the current conventional heightened truss body under the same span and load conditions provided by this application.
[0049] The above drawings have shown clear embodiments of the present application, which will be described in more detail later. These drawings and text descriptions are not intended to limit the scope of the present application in any way, but to illustrate the concept of the present application to those skilled in the art by referring to specific embodiments. DETAILED DESCRIPTION
[0050] In order to make the objectives, technical solutions and advantages of the present application clearer, the implementation methods of the present application will be further described in detail below in conjunction with the accompanying drawings.
[0051] Please refer to Figure 1 and Figure 2 , Figure 1 is a structural schematic diagram of a large-span prestressed truss device provided in an embodiment of the present application, Figure 2 yes Figure 1 A partial structural schematic diagram of a large-span prestressed truss device is shown. The large-span prestressed truss device is used as a supporting structure for a pipe conveyor to transport materials across a large space. The large-span prestressed truss device 000 may include: a first arched truss 100, a second arched truss 200, two groups of prestressed assemblies 300, and two groups of brace rod assemblies 400.
[0052] The first arched truss 100 in the large-span prestressed truss device 000 may have a receiving cavity a1 , and the extending direction of the receiving cavity a1 of the first arched truss 100 may be the same as the extending direction of the first arched truss 100 .
[0053] The second arched truss 200 in the large-span prestressed truss device 000 can be fixed in the accommodating cavity a1 of the first arched truss 100, the extension direction of the second arched truss 200 can be the same as the extension direction of the first arched truss 100, and the second arched truss 200 can be used to carry the conveyor belt assembly A. Here, the first arched truss 100 and the second arched truss can be concentrically arranged, and the turning radius of the truss body composed of the first arched truss 100 and the second arched truss 200 can range from 50m to 100m.
[0054] The two groups of prestressed components 300 in the large-span prestressed truss device 000 can be both located at the bottom of the first arched truss 100, and the two groups of prestressed components 300 can be relatively arranged along the axial direction of the first arched truss 100, and the two ends of each group of prestressed components 300 can be respectively fastened to the two ends of the first arched truss 100, and each group of prestressed components 300 can be configured to apply tensioning force to the end of the first arched truss 100.
[0055] The two groups of strut assemblies 400 in the long-span prestressed truss device 000 may correspond to the two groups of prestressed assemblies 300, respectively. Each group of strut assemblies 400 may be located between the bottom of the first arched truss 100 and the corresponding prestressed assembly 300. Each group of strut assemblies 400 may include a plurality of strut assemblies 400, and the two ends of the strut assemblies 400 in each group of strut assemblies may be connected to the bottom of the first arched truss 100 and the corresponding prestressed assembly 300, respectively. Here, the two groups of strut assemblies 400 may also be arranged relatively along the axial direction of the first arched truss 100.
[0056] In the embodiment of the present application, by setting the first arched truss 100 in the long-span prestressed truss device 000, and setting the second arched truss 200 in the first arched truss 100, a large truss system of an arched large truss enclosed in an arched small truss is formed, and the second arched truss 200 plays a role in supporting the operation of the conveyor belt assembly A, and the first arched truss 100 with a relatively large volume can rely on the second arched truss 200 to achieve long-distance span. In addition, the first arched truss 100 has to bear the load from the second arched truss 200, as well as the load applied by the subsequent operator during maintenance, etc., and by setting the prestressed component 300 at the bottom of the first arched truss 100, the prestressed component 300 can apply tension to both ends of the first arched truss 100, and the tension can offset the horizontal thrust borne by the first arched truss 100, thereby reducing the force on the bottom structure of the first arched truss 100. Furthermore, by setting the strut assembly 400 between the prestressed component 300 and the first arched truss 100, the strut assembly 400 can cooperate with the prestressed component 300 to generate an upward tightening force on the first arched truss 100, so that the structural strength of the first arched truss 100 is relatively improved. In this way, the overall structure is simple, the force form is clear, and the large-span prestressed truss device 000 can form a prestressed self-balancing structural system under the dual protection of the prestressed component 300 and the strut assembly 400, which effectively guarantees the stable performance of the belt conveyor truss in conveying materials across a large space, and there is no need to further increase the strength of the truss by increasing the cross-section of the truss chord material, which effectively reduces the overall weight of the large-span prestressed truss device and reduces the manufacturing cost.
[0057] In summary, the embodiment of the present application provides a long-span prestressed truss device, which may include: a first arched truss, a second arched truss, two groups of prestressed components and two groups of strut components. By setting the first arched truss in the long-span prestressed truss device and setting the second arched truss in the first arched truss, a large truss system of an arched large truss and an arched small truss is formed, and the second arched truss plays a role in supporting the operation of the conveyor belt assembly, and the first arched truss with a relatively large volume can rely on the second arched truss to achieve long-distance span. In addition, the first arched truss must bear the load from the second arched truss, as well as the load applied by the subsequent operator during maintenance, etc. By setting the prestressed component at the bottom of the first arched truss, the prestressed component can apply a tensioning force to the two ends of the first arched truss, and the tensioning force can offset the horizontal thrust borne by the first arched truss, thereby reducing the force on the bottom structure of the first arched truss. Furthermore, by providing a strut assembly between the prestressed component and the first arched truss, the strut assembly can cooperate with the prestressed component to generate an upward tightening force on the first arched truss, so that the structural strength of the first arched truss is relatively improved, effectively ensuring the stable performance of the belt conveyor truss in transporting materials across a larger space, and there is no need to further increase the strength of the truss by increasing the cross-section of the truss chord material, thereby effectively reducing the overall weight of the large-span prestressed truss device and reducing manufacturing costs.
[0058] Optional, please refer to Figure 3 , Figure 3 It is a partial structural exploded schematic diagram of a large-span prestressed truss device provided in an embodiment of the present application. The first arched truss 100 in the large-span prestressed truss device 000 may include: a plurality of first square frames 101 arranged in an array along the extension direction of the first arched truss 100, and a first connecting assembly 102 located between every two adjacent first square frames 101, and the two ends of the first connecting assembly 102 can be respectively fixedly connected to the corresponding two adjacent first square frames 101. Among them, the plurality of first square frames 101 and the plurality of first connecting assemblies 102 can be used to enclose the accommodating cavity a1 of the first arched truss 100, and one end of the brace assembly 400 can be connected to both the first square frame 101 and the first connecting assembly 102. In this case, by arranging a plurality of first square frames 101 in the first arched truss 100, and fixing the two adjacent first square frames 101 with the first connecting assembly 102, in this way, effective support for the second arched truss 200 can be achieved while ensuring the structural strength of the first arched truss 100. It should be noted that the second arched truss 200 can be fixedly connected to the bottom frames of the plurality of first square frames 100 by welding.
[0059] In the embodiments of the present application, Figure 3As shown, the first connection assembly 102 may include: a plurality of first connection rods 1021 corresponding to the plurality of corners of the first square frame 101, and at least one first auxiliary connection rod 1022 located between every two adjacent first connection rods 1021. The corners of every two adjacent first square frames 101 correspond to each other, the two ends of the first connection rod 1021 may be fixedly connected to the corners of the two adjacent first square frames 101, and the two ends of the first auxiliary connection rod 1022 may be fixedly connected to the two adjacent first square frames 101. As an example, two adjacent first square frames 101, and the first connecting rod 1021 and the first auxiliary connecting rod 1022 between the two first square frames 101 are used as examples for schematic description: the two ends of each first connecting rod 1021 can be fixedly connected to a set of corresponding corners in the two adjacent first square frames 101, and the two ends of the first auxiliary connecting rod 1022 can be fixedly connected to the two adjacent first square frames 101, thereby effectively ensuring the structural strength of the first arched truss 100, thereby ensuring stable support for the second arched truss 200 under large-span spatial conditions.
[0060] For example, Figure 3 As shown, the first square frame 101 includes: two first frames 1011 arranged along the radial direction of the first arched truss 100, and two second frames 1012 arranged along the axial direction of the first arched truss 100. Two cross-arranged first auxiliary connecting rods 1022 may be arranged between the two first frames 1011 on the same side of two adjacent first square frames 101; one first auxiliary connecting rod 1022 may be arranged between the two second frames 1012 on the same side of two adjacent first square frames 101. For example, the first frame 1011, the second frame 1012 and the first connecting rod 1021 may all be rod structures made of H-shaped steel, and the first auxiliary connecting rod 1022 may be a rod structure made of round tube steel. Here, the first frame 1011, the second frame 1012, the first connecting rod 1021 and the first auxiliary connecting rod 1022 may also be structures made of other forms of steel, and the embodiment of the present application does not specifically limit this.
[0061] Optional, please refer to Figure 1 and Figure 4 , Figure 4It is a partial structural schematic diagram of another large-span prestressed truss device provided in an embodiment of the present application. The strut assembly 400 in the large-span prestressed truss device 000 may include: a connecting seat 401, a vertical strut 402 and an anti-sway strut 403. The connecting seat 401 can be fastened to the prestressed assembly 300, one end of the vertical strut 402 can be fixedly connected to the connecting seat 401, and the other end of the vertical strut 402 can be hinged to the bottom of the first arch truss 100. One end of the anti-sway strut 403 can be fixedly connected to the connecting seat 401, and the other end of the anti-sway strut 403 can be hinged to the bottom of the first arch truss 100. Among them, the length direction of the anti-sway strut 403 can intersect with the length direction of the vertical strut 402. In this case, the vertical struts 402 in the strut assembly 400 can generate an upward tightening force on the first arch truss 100, and the anti-sway struts 403 arranged to intersect with the vertical struts 402 can effectively enhance the lateral stiffness of the prestressed assembly 300, reduce the frequency of the prestressed assembly 300 swinging left and right when subjected to wind loads, and achieve an anti-sway effect. Here, the angle between the length direction of the anti-sway struts 403 and the length direction of the vertical struts 402 can be an acute angle.
[0062] In the present application, the plurality of strut assemblies 400 in each group of strut assemblies may correspond to the plurality of first square frames 101 one by one, one end of the vertical strut 402 may be fixedly connected to the connection seat 401, and the other end of the vertical strut 402 may be hinged to the first connection assembly 102; one end of the anti-sway strut 403 may be fixedly connected to the connection seat 401, and the other end of the anti-sway strut 403 may be hinged to the first square frame 101. For examples, please refer to Figure 5 and Figure 6 , Figure 5 is a schematic diagram of a perspective of the connection between the brace assembly provided in an embodiment of the present application and the first arch truss and the prestressed assembly, respectively. Figure 6 Schematic diagram of another perspective of the connection between the brace assembly provided in the embodiment of the present application and the first arch truss and the prestressed assembly respectively. The first connection assembly 102 may have a first node plate 102a and a first reinforcement plate 102b fixed to the side of the first node plate on the side facing the vertical brace 402, and the other end of the vertical brace 402 may be hinged to the first node plate 102a. The first square frame 101 may have a second node plate 101a and a second reinforcement plate 101b fixed to the side of the second node plate on the side facing the anti-sway brace 403, and the other end of the anti-sway brace 403 may be hinged to the second node plate 101a.
[0063] In the embodiments of the present application, Figure 5 and Figure 6As shown, the connection seat 401 in the strut assembly 400 may include: a first seat body 4011 and a second seat body 4012 arranged opposite to each other along the length direction of the vertical strut, the first seat body 4011 may have a first groove b1 on the side facing the second seat body 4012, and the second seat body 4012 may have a second groove b2 on the side facing the first seat body 4011. The first groove b1 in the first seat body 4011 and the second groove b2 in the second seat body 4012 may form a hoop-shaped groove, the connection seat 401 may be sleeved on the prestressed assembly 300 through the hoop-shaped groove, and the first seat body 4011 and the second seat body 4012 may be tightly connected. In this case, by arranging the first seat body 4011 and the second seat body 4012 in the connection seat 401, the hoop-shaped groove formed by the first groove b1 of the first seat body 4011 and the second groove b2 of the second seat body 4012 can generate a large clamping force on the prestressed assembly 300, and can withstand a certain unbalanced force.
[0064] Optional, such as Figure 5 and Figure 6 As shown, the first seat body 4011 in the connection seat 401 may have a first connection hole c1, and the second seat body 4012 may have a second connection hole c2 connected to the first connection hole c1. The connection seat 401 may also include: a fastener 4013, and the fastener 4013 may be configured to: pass through the first connection hole c1 of the first seat body 4011 and the second connection hole c2 of the second seat body 4012 in sequence and be fastened and connected to the first seat body 4011 and the second seat body 4012. For example, the fastener 4013 may be a high-strength bolt. It should be noted that the first seat body 4011 and the second seat body 4012 in the connection seat 401 may also be fastened and connected by welding, clamping, etc., and the embodiment of the present application does not make specific limitations on this.
[0065] In the examples of this application, please refer to Figure 1 , Figure 4 and Figure 7 As shown, Figure 7This is a schematic diagram of the connection between a prestressed component and a support beam provided in an embodiment of the present application. The bottom of the first arched truss 100 may have two support beams 103 distributed at both ends of each group of prestressed components 300, and the support beams 103 may have a limiting cavity (not shown in the figure), and the end of the support beam 103 close to the prestressed component 300 may have a first connection port d1, and the end of the support beam 103 away from the prestressed component 300 may have a second connection port d2, and the first connection port d1 and the second connection port d2 of the support beam 103 may both be connected to the limiting cavity of the support beam 103. The prestressed component 300 may include: a prestressed sleeve 301, a plurality of steel strands 302 and two anchors 303. The two ends of the prestressed sleeve 301 may be fixedly connected to the first connection ports d1 of the two support beams 103, respectively. The two anchors 303 may be fixedly connected to the second connection ports d2 of the two support beams 103, respectively. Parts of the plurality of steel strands 302 are distributed in the limiting cavity of the support beam 103 and the prestressed sleeve 301, and the two ends of the steel strands 302 may be fastened to the two anchors 303, respectively. Among them, the connection seat 401 may be fastened to the outer side of the prestressed sleeve 301. In this way, prestress is applied to the steel strands 302 at the two ends of the support beam 103, and the ends of the steel strands 302 and the support beam 103 are fastened by the anchors 303, so that the steel strands 302 are always kept at the center of the prestressed sleeve 301 to maintain the overall stability of the prestressed component 300. It should be noted that the shape of the hoop-shaped groove formed by the first groove b1 of the first seat body 4011 and the second groove b2 of the second seat body 4012 in the connecting seat 401 can match the shape of the cross section of the prestressed sleeve 301 .
[0066] In order to ensure a stable connection between the steel strand 302 and the support beam 103 in the first arch truss 100, a grouting port (not shown in the figure) can be opened on the support beam 103. After the prestressed component 300 is assembled, cement slurry can be poured into the limiting cavity of the support beam 103 through the grouting port. The solidified cement slurry can offset the friction loss and variable angle tension loss at the anchor port of the steel strand 302.
[0067] Here, the bottom ends of the first arched truss 100 may have two groups of support beams 103 corresponding to the two groups of prestressed components 300, and the two groups of support beams 103 may be arranged opposite to each other along the axial direction of the first arched truss 100. In addition, the structures and working principles of the two groups of prestressed components 300 are the same, and a group of prestressed components is used as an example for schematic description. Figure 7As shown, the first connection port d1 of the support beam 103 may be a square port, and the prestressed sleeve 301 may include: a sleeve body 301a and a transition connection pipe 301b in a cylindrical shape, wherein the transition connection pipe 301b is located between the first connection port d1 of the support beam 103 and the sleeve body 301a, and the transition connection pipe 301b may have a circular connection port e1 at one end close to the sleeve body 301a, and a square connection port e2 at one end close to the support beam 103, and the transition connection pipe 301b may be fixedly connected to the sleeve body 301a and the support beam 103 through the circular connection port e1 and the square connection port e2, respectively. It should be noted that the sleeve body 301a and the transition connection pipe 301b in the prestressed sleeve 301 may also have the same form, and the sleeve body 301a and the transition connection pipe 301b may be an integral structure.
[0068] For example, see Figure 8 and Fig. 9 , Figure 8 is a schematic structural diagram of a prestressed casing provided in an embodiment of the present application, Fig. 9 yes Figure 8 The cross-sectional view of the prestressed casing is shown. The casing body 301a in the prestressed casing 301 may include: an inner casing B1, an outer casing B2 and a plurality of annular baffles B3, wherein the plurality of annular baffles B3 may be distributed in an array in the area between the outer wall of the inner casing B1 and the inner wall of the outer casing B2, and the inner side surface of the annular baffle B3 is fixedly connected to the outer wall of the inner casing B1, and the outer side surface of the annular baffle B3 is fixedly connected to the inner wall of the outer casing B2. Among them, a plurality of steel strands 302 may be distributed in the inner casing B1, and may form a clearance fit with the inner wall of the inner casing B1. In this way, a concentric double-tube combined structure formed by the inner casing B1, the outer casing B2 and the annular baffle B3 not only has high strength and rigidity, but also avoids the steel strands 302 from directly contacting the inner wall of the outer casing B2 during tensioning to cause damage. For example, the distance between two adjacent annular baffles B3 may be 3m.
[0069] Optional, please refer to Fig.10 , Fig.10It is a schematic diagram of the installation of a second arch truss and a conveyor belt assembly provided in an embodiment of the present application. The second arch truss 200 in the large-span prestressed truss device 000 may have an installation cavity f1, and the extension direction of the installation cavity f1 of the second arch truss 200 may be the same as the extension direction of the second arch truss 200, and the conveyor belt assembly A may be installed in the installation cavity f1 of the second arch truss 200. In this way, by installing the conveyor belt assembly A in the installation cavity f1 of the second arch truss 200, the second arch truss 200 can support and protect the conveyor belt assembly A. For example, the number of second arch trusses 200 in the large-span prestressed truss device 000 may be at least one, and correspondingly, the number of conveyor belt assemblies A may also be at least one, and the number of conveyor belt assemblies A may be the same as the number of second arch trusses 200. For example, please refer to Fig.11 , Fig.11 It is a partial structural side view of a large-span prestressed truss device provided in an embodiment of the present application. When the number of the second arched trusses 200 is two, the two second arched trusses 200 can be arranged side by side in the accommodation cavity a1 of the first arched truss 100. And there can be a first inspection channel J1 between the two second arched trusses 200, and there can be a second inspection channel J2 between the second arched truss 200 and the inner side surface of the first arched truss 100, so that the operator can subsequently inspect the large-span prestressed truss device through the two inspection channels.
[0070] In the embodiments of the present application, Figure 3 and Fig.10As shown, the second arched truss 200 in the large-span prestressed truss device 000 may include: a plurality of second square frames 201 arranged in an array along the extension direction of the second arched truss 200, and a second connecting assembly 202 located between every two adjacent second square frames 201, and the two ends of the second connecting assembly 202 may be fixedly connected to the corresponding two adjacent second square frames 201 respectively. And the plurality of second square frames 201 and the plurality of second connecting assemblies 202 may be used to enclose the installation cavity f1 of the second arched truss 200. Among them, in the circumferential direction along the first arched truss 100, the distance between the two adjacent first square frames 101 may be greater than the distance between the two adjacent second square frames 201 in the circumferential direction along the second arched truss 200. In this case, by setting the distance between the two adjacent first square frames 101 to be greater than the distance between the two adjacent second square frames 201, the overall weight inside the large-span prestressed truss device 000 can be effectively reduced, and the structural stability of the large-span prestressed truss device can be improved. Here, each second connection assembly 202 may include: a plurality of second connection rods 2021 corresponding one-to-one to the plurality of corners of the second square frame 201 , and both ends of each second connection rod 2021 may be fixedly connected to a group of corners of two adjacent second square frames 201 .
[0071] For example, Fig.10 and Fig.11 As shown, the conveyor belt assembly A may include: an annular forming roller A1 and a conveyor belt A2, the forming roller A1 may be fixedly connected to the second square frame 201, and the conveyor belt A2 may be located in the area surrounded by the forming roller A1 and slidably connected to the forming roller A1. In this way, the conveyor belt A2 may move under the drive of the forming roller A1, thereby realizing the conveyance of materials.
[0072] Optional, such as Fig.10As shown, at least part of the second connecting components 202 of the second arched truss 200 may have: two groups of reinforcing members 2022 arranged opposite to each other along the axial direction of the second arched truss 200 and located at two sides of the second square frame 201, and the two ends of each group of reinforcing members 202 may be fixedly connected to two adjacent second square frames 201 respectively. For example, part of the second connecting components 202 of the plurality of second connecting components 202 may have reinforcing members 2022 located on both sides of the facade of the second arched truss 200, and another part of the second connecting components 202 of the plurality of second connecting components 202 may no longer be provided with reinforcing members 2022. In this way, the weight of the second arched truss 200 can be reduced as much as possible while ensuring the structural strength of the second arched truss 200; or, all of the plurality of second connecting components 202 may have reinforcing members. For example, the reinforcing member 2022 may be a cross brace, and the distance between two adjacent reinforcing members 2022 may be 15m.
[0073] In the examples of this application, please refer to Fig.12 , Fig.12 It is a structural schematic diagram of a large-span prestressed truss device provided by another embodiment of the present application. The large-span prestressed truss device 000 may also include: two brackets 500, which may be respectively distributed at the two ends of the first arched truss 100, and one end of the first arched truss 100 may be fastened to one bracket 500, and the other end of the first arched truss 100 may be movably connected to another bracket 500. In this way, the main body of the large-span prestressed truss device 000 can be effectively supported by the two brackets 500, ensuring the stable operation of the large-span prestressed truss device after it is integrated into the belt conveyor. In the present application, if Fig.12 As shown, the large-span prestressed truss device 000 may further include: a fixed support 600 and a rolling support 700. The fixed support 600 may be fixedly connected to one end of the first arched truss 100 and a bracket 500, respectively. The rolling support 700 may be fixedly connected to the other end of the first arched truss 100 and movably connected to another bracket 500. In this way, by providing the fixed support 600 and the rolling support 700, the temperature stress of the large-span prestressed truss device 000 can be released, and at the same time, the vibration generated during the operation of the pipe belt machine integrated with the span prestressed truss device can be reduced.
[0074] Please refer to Fig.13 and Fig.14 , Fig.13 It is a displacement deformation diagram of a truss body in a large-span prestressed truss device provided in an embodiment of the present application under the support of a prestressed component and a strut component. Fig.14This is the displacement deformation diagram of the current conventional heightened truss body under the same span and load conditions. Finite element software was used to simulate the performance of the truss body supported by prestressed components and strut components and the conventional heightened truss body structure under the same span and load conditions. The overall truss structure reduced the vertical disturbance value at the mid-span by 30% (153-105.6 / 153) and the horizontal displacement value at the sliding end by 55% (75-32.4 / 75) under the constant-active combination condition. Fig.13 The truss body in Fig.14 The most unfavorable internal force value of the lower chord material in the middle of the truss main body is reduced by 50% (234.3-103.5 / 234.3). In this way, the large-span prestressed truss device of the pipe-belt machine in this application has good feasibility.
[0075] In summary, the embodiment of the present application provides a long-span prestressed truss device, which may include: a first arched truss, a second arched truss, two groups of prestressed components and two groups of strut components. By setting the first arched truss in the long-span prestressed truss device and setting the second arched truss in the first arched truss, a large truss system of an arched large truss and an arched small truss is formed, and the second arched truss plays a role in supporting the operation of the conveyor belt assembly, and the first arched truss with a relatively large volume can rely on the second arched truss to achieve long-distance span. In addition, the first arched truss must bear the load from the second arched truss, as well as the load applied by the subsequent operator during maintenance, etc. By setting the prestressed component at the bottom of the first arched truss, the prestressed component can apply a tensioning force to the two ends of the first arched truss, and the tensioning force can offset the horizontal thrust borne by the first arched truss, thereby reducing the force on the bottom structure of the first arched truss. Furthermore, by providing a strut assembly between the prestressed component and the first arched truss, the strut assembly can cooperate with the prestressed component to generate an upward tightening force on the first arched truss, so that the structural strength of the first arched truss is relatively improved, effectively ensuring the stable performance of the belt conveyor truss in transporting materials across a larger space, and there is no need to further increase the strength of the truss by increasing the cross-section of the truss chord material, thereby effectively reducing the overall weight of the large-span prestressed truss device and reducing manufacturing costs.
[0076] The embodiment of the present application also provides a pipe belt conveyor, which may include: a truss device and a conveyor belt assembly, the conveyor belt assembly may be installed on a second arched truss in the truss device, and the truss device may be any of the truss devices given above. In this way, the pipe belt conveyor integrated with the truss device can realize material transmission under a large spatial span.
[0077] In addition, the present application also discloses a construction method of a large-span prestressed truss device for a pipe belt machine, using the large-span prestressed truss device disclosed in the above embodiment, comprising the following steps:
[0078] First, the installation personnel are given safety technical explanations and operation process training; then, the first arch truss and the second arch truss are assembled; then, the prestressed components are installed; then, the brace components are installed;
[0079] Afterwards, the prestressed components are adjusted according to the number of tensioning times and tensioning sequence verified by the design; then, the steel hinge cables of the prestressed components are fixed by grouting; finally, quality inspection is carried out.
[0080] It should be noted that in the accompanying drawings, the sizes of layers and regions may be exaggerated for clarity of illustration. It is also understood that when an element or layer is referred to as being "on" another element or layer, it may be directly on the other element, or there may be an intermediate layer. In addition, it is understood that when an element or layer is referred to as being "under" another element or layer, it may be directly under the other element, or there may be more than one intermediate layer or element. In addition, it is also understood that when a layer or element is referred to as being "between" two layers or two elements, it may be the only layer between the two layers or two elements, or there may also be more than one intermediate layer or element. Similar reference numerals throughout the text indicate similar elements.
[0081] In the present application, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance. The term "plurality" refers to two or more than two, unless otherwise clearly defined.
[0082] The above description is only an optional embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application shall be included in the protection scope of the present application.
Claims
1. A long-span prestressed truss device, characterized in that: include: A first arch truss, a second arch truss, two sets of prestressed assemblies, and two sets of brace assemblies; The first arched truss has a receiving cavity, and the extending direction of the receiving cavity is the same as the extending direction of the first arched truss; The second arched truss is fixed in the accommodating cavity, the extension direction of the second arched truss is the same as the extension direction of the first arched truss, and the second arched truss is used to carry the conveyor belt assembly; The two groups of prestressed components are both located at the bottom of the first arched truss, and the two groups of prestressed components are arranged opposite to each other along the axial direction of the first arched truss, and the two ends of each group of prestressed components are respectively fastened to the two ends of the first arched truss, and each group of prestressed components is configured to: be able to apply tensioning force to the ends of the first arched truss; The two groups of strut assemblies correspond to the two groups of prestressed assemblies respectively, each group of the strut assemblies is located between the bottom of the first arch truss and the corresponding prestressed assembly, each group of the strut assemblies includes a plurality of the strut assemblies, and both ends of the strut assemblies in each group of the strut assemblies are respectively connected to the bottom of the first arch truss and the corresponding prestressed assembly.
2. The long-span prestressed truss device according to claim 1, characterized in that: The first arched truss comprises: a plurality of first square frames arranged in an array along an extension direction of the first arched truss, and a first connecting assembly located between every two adjacent first square frames, wherein two ends of the first connecting assembly are respectively fixedly connected to the corresponding two adjacent first square frames; The plurality of first square frames and the plurality of first connecting assemblies are used to enclose the accommodating cavity, and one end of the strut assembly is connected to both the first square frame and the first connecting assembly.
3. The long-span prestressed truss device according to claim 2, characterized in that: The first connecting assembly includes: a plurality of first connecting rods corresponding one by one to the plurality of corners of the first square frame, and at least one first auxiliary connecting rod located between every two adjacent first connecting rods, the two ends of the first connecting rod being fixedly connected to the corners of two adjacent first square frames, and the two ends of the first auxiliary connecting rod being fixedly connected to the two adjacent first square frames.
4. The large-span prestressed truss device according to claim 2, characterized in that: The strut assembly comprises: a connecting seat, a vertical strut and an anti-sway strut, the connecting seat is fastened to the prestressed assembly, one end of the vertical strut is fixedly connected to the connecting seat, and the other end of the vertical strut is hinged to the bottom of the first arched truss; one end of the anti-sway strut is fixedly connected to the connecting seat, and the other end of the anti-sway strut is hinged to the bottom of the first arched truss; Wherein, the length direction of the anti-sway support rod intersects with the length direction of the vertical support rod.
5. The large-span prestressed truss device according to claim 4, characterized in that: The connecting seat comprises: a first seat body and a second seat body which are arranged opposite to each other along the length direction of the vertical support rod, the first seat body has a first groove on one side facing the second seat body, and the second seat body has a second groove on one side facing the first seat body; The first groove and the second groove form a hoop-shaped groove, the connecting seat is sleeved on the prestressed component through the hoop-shaped groove, and the first seat body is firmly connected to the second seat body.
6. The large-span prestressed truss device according to claim 5, characterized in that: The first base body has a first connecting hole, and the second base body has a second connecting hole communicating with the first connecting hole; The connection seat further includes a fastener, and the fastener is configured to pass through the first connection hole and the second connection hole in sequence to be fastened to the first seat body and the second seat body.
7. The large-span prestressed truss device according to claim 5, characterized in that: The bottom of the first arched truss has two support beams distributed at both ends of each group of prestressed components, the support beam has a limiting cavity, one end of the support beam close to the prestressed component has a first connection port, and one end of the support beam away from the prestressed component has a second connection port, and the first connection port and the second connection port are both connected to the limiting cavity; The prestressed component comprises: a prestressed sleeve, a plurality of steel strands and two anchors, the two ends of the prestressed sleeve are respectively fixedly connected to the first connection ports of the two support beams, the two anchors are respectively fixedly connected to the second connection ports of the two support beams, a portion of the steel strands is distributed in the limiting cavity and the prestressed sleeve, and the two ends of the steel strands are respectively fastened to the two anchors; Wherein, the connecting seat is tightly connected to the outer side surface of the prestressed sleeve.
8. The long-span prestressed truss device according to any one of claims 2 to 7, characterized in that: The second arched truss has an installation cavity, the extension direction of the installation cavity is the same as the extension direction of the second arched truss, and the conveyor belt assembly is installed in the installation cavity.
9. The large-span prestressed truss device according to claim 8, characterized in that: The second arched truss comprises: a plurality of second square frames arranged in an array along the extension direction of the second arched truss, and a second connecting assembly located between every two adjacent second square frames, wherein two ends of the second connecting assembly are respectively fixedly connected to the corresponding two adjacent second square frames; the plurality of second square frames and the plurality of second connecting assemblies are used to enclose the installation cavity; Wherein, in the circumferential direction along the first arched truss, the distance between two adjacent first square frames is greater than the distance between two adjacent second square frames in the circumferential direction along the second arched truss.
10. The large-span prestressed truss device according to claim 9, characterized in that: At least some of the multiple second connecting assemblies have: two groups of reinforcements arranged opposite to each other along the axial direction of the second arch truss and located on the two side surfaces of the second square frame, and the two ends of each group of reinforcements are respectively fixedly connected to two adjacent second square frames.
11. The long-span prestressed truss device according to any one of claims 1-7, 9-10, characterized in that: The large-span prestressed truss device also includes: two brackets, which are respectively distributed at both ends of the first arched truss, and one end of the first arched truss is fastened to one of the brackets, and the other end of the first arched truss is movably connected to the other bracket.
12. A belt conveyor, characterized in that: include: A large-span prestressed truss device and a conveyor belt assembly, wherein the conveyor belt assembly is installed on a second arched truss in the large-span prestressed truss device, and the large-span prestressed truss device is the large-span prestressed truss device described in any one of claims 1-11.
Citation Information
Patent Citations
Novel prestress industrial stockyard canopy structure and method for constructing same
CN104847017A
Long-span beam string truss beam off-site construction method
CN108894496A
Conveyor trestle
CN114655720A
Pipe belt conveyor conveying system
CN116853733A
Truss of pipe belt conveyor
CN214933510U