PEM electrolyzed water purification regeneration gas circulation system and method
Through the design of the venturi pipe and flow control valve, the gas circulation and regeneration of the hydrogen purification system is achieved, which solves the problems of complex equipment and waste of raw materials in the prior art, and improves the utilization rate of hydrogen and the applicability of equipment.
Patent Information
- Application Number
- CN202411038301.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-12
Smart Images

Figure CN118929573A_ABST
Abstract
Description
Technical Field
[0002] The invention belongs to the field of electrolytic water purification, and in particular relates to a regeneration gas circulation method for a PEM electrolytic water purification system. Background Art
[0003] The hydrogen purification system is used to connect the water electrolysis hydrogen production equipment to deoxygenate and purify the hydrogen produced by the water electrolysis hydrogen production equipment. In the related art, the hydrogen purification system includes a hydrogen pre-drying tower, a hydrogen first drying tower and a hydrogen second drying tower. The hydrogen first drying tower and the hydrogen second drying tower can alternately perform drying and purification work. The hydrogen pre-drying tower can regenerate the molecular sieve in a drying tower that stops drying and purification, so that the hydrogen purification work can be carried out continuously. Because the pressure of the regenerated hydrogen is lower than the inlet end of the purification system after flowing through a certain device, it can only be discharged directly, causing waste.
[0004] In the prior art, after the electrolyzer generates hydrogen, it will first enter the first gas-water separator for rough separation to separate the liquid water and part of the gaseous water in the hydrogen, then enter the condenser for cooling to precipitate the gaseous water into liquid water, then enter the second gas-water separator for secondary separation to separate the precipitated liquid water, and then enter the heater to heat the gas to achieve the overall deoxygenation tower of the deoxygenation reaction. The oxygen in the hydrogen is converted into liquid water through a chemical reaction. The gas after passing through the deoxygenation tower enters the third gas-water separator to separate the liquid water produced by the reaction, thereby improving the purity of the hydrogen again, and then enters the filter, cooler and separator to pre-treat the hydrogen to be purified. The pretreated gas is divided into two parts, a small part of the gas is cooled in the first drying tower, then passed through the second drying tower for adsorption regeneration, and finally returned to the third drying tower for drying and purification. Most of the gas enters the third drying tower for drying and purification (the [cooling / regeneration / drying and purification] states of the above three drying towers are alternately performed, and only one case is given as an example), and the gas after drying and purification is pressurized by the compressor and output.
[0005] The disadvantage of the existing technology is that the overall principle is relatively complicated, and there are more equipment, which is not suitable for industrial application. The compression pump scheme hydrogen production equipment has high power consumption and larger overall equipment volume, which is not suitable for small hydrogen production equipment. The gas pressure after cooling and regeneration is low and cannot be returned to the purification route without pressurization, so it can only be discharged directly, but direct discharge will cause waste of raw gas and low hydrogen utilization rate. Summary of the invention
[0006] The present invention adopts a venturi tube to overcome the above-mentioned defects, provides a new recycling scheme and control scheme, and reduces the overall equipment volume and power consumption.
[0007] The technical solution of the present invention is as follows.
[0008] A PEM electrolytic water purification regeneration gas circulation system comprises an electrolytic cell, a gas-water separator, a deoxidation tower, a first flow control valve, a second flow control valve, an ejector and a drying tank; the electrolytic cell, the gas-water separator, the ejector and the deoxidation tower are connected in sequence; the deoxidation tower is connected to a cooling inlet and a purification inlet of the drying tank respectively through pipelines; the deoxidation tower is also connected to a centralized discharge port through a pipeline; the bottom of the drying tank is connected to a hydrogen production outlet; the pipeline between the electrolytic cell and the gas-water separator and the pipeline between the deoxidation tower and the drying tank are also connected to a replacement nitrogen inlet through pipelines; a second flow control valve is provided on the pipeline between the deoxidation tower and the cooling inlet of the drying tank; a first flow control valve is provided on the pipeline between the deoxidation tower and the purification inlet of the drying tank; the regeneration outlet of the drying tank is connected to the ejector.
[0009] Furthermore, the ejector is composed of an ejector front end structure, an ejector reflux end, an ejector body, a mixed gas outlet and a working gas inlet; one end of the ejector body is connected to the ejector front end structure, and the other end is provided with a mixed gas outlet; the ejector front end structure is provided with a working gas inlet, and the ejector body is provided with an ejector reflux end.
[0010] Furthermore, a cooling inlet, a purification inlet and a regeneration outlet are respectively provided at the top of the drying tank; the cooling inlet, purification inlet and regeneration outlet pipelines are connected with a cooling inlet valve, a purification inlet valve and a regeneration outlet valve; a cooling outlet, a purification outlet and a regeneration inlet are provided at the bottom of the drying tank; the cooling outlet, purification outlet and regeneration inlet pipelines are connected with a cooling outlet valve, a purification outlet valve and a regeneration inlet valve.
[0011] Furthermore, the drying tank includes a first drying tank, a second drying tank and a third drying tank; the first drying tank, the second drying tank and the third drying tank 26 are arranged in parallel.
[0012] Furthermore, the cooling outlet valve, the purification outlet valve and the regeneration inlet valve are gathered at the hydrogen production outlet through a pipeline.
[0013] Furthermore, the regeneration outlet valve is connected to the reflux end of the ejector through a pipeline.
[0014] Furthermore, a back pressure valve, a flow meter, a switch valve and a flame arrester are provided on the pipeline of the hydrogen production outlet.
[0015] Furthermore, a gas detection battery valve and a discharge battery valve are provided on the pipeline between the deoxygenation tower and the centralized discharge port.
[0016] Furthermore, the pipeline between the detection gas battery valve and the discharge battery valve is also connected to the anti-backflow check valve and the oxygen in hydrogen sensor through pipelines; the oxygen in hydrogen sensor is connected to the centralized discharge port through pipelines; the anti-backflow check valve is connected to the centralized discharge port and the hydrogen production outlet respectively; The anti-backflow one-way valve and the centralized discharge port are also connected in sequence with a dew point meter and an anti-backflow one-way valve.
[0017] Furthermore, the pipeline between the electrolyzer and the gas-water separator and the pipeline between the deoxidation tower and the drying tank are respectively connected to the first purge cell valve and the second purge cell valve through pipelines and then connected to the replacement nitrogen inlet.
[0018] A regeneration gas circulation method for a PEM electrolysis water purification regeneration gas circulation system comprises the following steps: (1) When the oxygen in the deoxygenated gas hydrogen meets the requirements of the purification system inlet, the system works normally. The route is: the system working route is from the electrolyzer through the serial gas-water separator and the ejector to the deoxygenation tower, and then the first flow control valve and the second flow control valve are in the open state. Generally speaking, the volume flow rate of the purified gas and the volume flow rate of the regenerated gas are in the ratio of 7:3 to 9:1. Then the first drying tower is in the purification state, the second drying tower is in the cooling state, and the third drying tower is in the regeneration state. According to the working state of each drying tower, the purification inlet valve and the purification outlet valve of the first drying tower are in the open state, and the other four valves are in the closed state. After the raw gas passes through the first drying tower and completes the purification process, it will flow through the purification outlet valve and the oxygen in hydrogen sensor to continuously detect whether it meets the requirements. If the detected gas pressure is too small, it is not suitable to return to the main road, so it will be directly discharged; at the same time, it will flow through the back pressure valve to hold the pressure to the required pressure, and then output after passing through the flow meter, switch valve and flame arrester; (2) The regeneration inlet valve and regeneration outlet valve of the second drying tower are in the open state, and the other four valves are in the closed state. The cooling inlet valve and cooling outlet valve of the third drying tower are in the open state, and the other four valves are in the closed state. The small stream of raw gas flowing through the second flow control valve will first pass through the cooling inlet valve of the second drying tower to enter the second drying tower for cooling. Then, after this heat exchange process, the temperature of this stream of raw gas will be increased, and then it will flow out of the second drying tower through the cooling outlet valve, and flow to the regeneration inlet valve of the third drying tower through the pipeline to enter the third drying tower. After the small stream of raw gas completes the auxiliary regeneration in the third drying tower, it will flow out of the third drying tower through the regeneration outlet valve. The small stream of raw gas will return to the main path under the gravity of the high-speed gas in the main path of the ejector, and after mixing with the hydrogen to be deoxygenated, it will enter the deoxygenation tower again for circulation.
[0019] Compared with the prior art, the advantages of the present invention are: (1) The system structure of the present invention is simple, and the number of parts of the entire system is reduced, so the integration is higher and the cost is lower; (2) The present invention adopts an ejector to recover the raw gas that has been cooled and regenerated and circulate it again, thereby avoiding the waste of the cooled and regenerated gas and improving the utilization rate of the raw gas. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 A schematic diagram of the principle of a PEM electrolysis water purification regeneration gas circulation system; Figure 2 The gas flow direction when the PEM electrolysis water purification regeneration gas circulation system is working normally; Figure 3 This is a schematic diagram of the structure of the ejector.
[0022] The components in the figure are as follows: electrolytic cell 1, gas-water separator 2, deoxidation tower 3, purification gas flow control valve (first flow control valve) 4, regeneration gas flow control valve (second flow control valve) 5, cooling inlet valve 6, cooling outlet valve 7, purification inlet valve 8, purification outlet valve 9, regeneration outlet valve 10, regeneration inlet valve 11, anti-backflow check valve 12, hydrogen oxygen sensor 13, dew point meter 14, back pressure valve 15, flow meter 16, switch valve 17, flame arrester 18, detection gas battery valve 19, discharge battery valve 20, first purge battery valve 21, second purge battery valve 22, ejector 23, ejector front end 23.1; ejector reflux end 23.2; ejector body 23.3; mixed gas outlet 23.4; working gas inlet 23.5. DETAILED DESCRIPTION
[0023] The present invention will be further described in detail below in conjunction with specific embodiments, but the embodiments of the present invention are not limited thereto. For process parameters not particularly noted, conventional techniques may be used.
[0024] Example 1 like Figure 1 As shown, the present embodiment is a PEM electrolysis water purification regeneration gas circulation system, comprising an electrolytic cell 1, a gas-water separator 2, a deoxidation tower 3, a first flow control valve 4, a second flow control valve 5, an ejector 23 and a drying tank; the electrolytic cell 1, the gas-water separator 2, the ejector 23 and the deoxidation tower 3 are connected in sequence; the deoxidation tower 3 is connected to the cooling inlet and the purification inlet of the drying tank respectively through pipelines; the deoxidation tower 3 is also connected to the centralized discharge port through a pipeline; the bottom of the drying tank is connected to the hydrogen production outlet; the pipeline between the electrolytic cell 1 and the gas-water separator 2 and the pipeline between the deoxidation tower 3 and the drying tank are also connected to the replacement nitrogen inlet through pipelines; the second flow control valve 5 is provided on the pipeline between the deoxidation tower 3 and the cooling inlet of the drying tank; the first flow control valve 4 is provided on the pipeline between the deoxidation tower 3 and the purification inlet of the drying tank; the regeneration outlet of the drying tank is connected to the ejector.
[0025] The drying tank includes a first drying tank 24, a second drying tank 25 and a third drying tank 26; the first drying tank 24, the second drying tank 25 and the third drying tank 26 are arranged in parallel. The top of the drying tank is respectively provided with a cooling inlet, a purification inlet and a regeneration outlet; the cooling inlet, the purification inlet and the regeneration outlet pipelines are connected with a cooling inlet valve 6, a purification inlet valve 8 and a regeneration outlet valve 10; the bottom of the drying tank is provided with a cooling outlet, a purification outlet and a regeneration inlet; the cooling outlet, the purification outlet and the regeneration inlet pipelines are connected with a cooling outlet valve 7, a purification outlet valve 9 and a regeneration inlet valve 11. The cooling outlet valve 7, the purification outlet valve 9 and the regeneration inlet valve 11 are collected at the hydrogen production outlet through a pipeline. The regeneration outlet valve 10 is connected to the ejector reflux end through a pipeline. The pipeline of the hydrogen production outlet is provided with a back pressure valve 15, a flow meter 16, a switch valve 17 and a flame arrester 18. The pipeline between the deoxidation tower 3 and the centralized discharge port is provided with a detection gas battery valve 19 and a discharge battery valve 20. The pipeline between the detection gas battery valve 19 and the discharge battery valve 20 is also connected to the anti-backflow check valve 12 and the oxygen sensor in hydrogen 13 through pipelines; the oxygen sensor in hydrogen 13 is connected to the centralized discharge port through pipelines; the anti-backflow check valve 12 is connected to the centralized discharge port and the hydrogen production outlet respectively; the anti-backflow check valve 12 and the centralized discharge port are also connected in sequence with a dew point meter 14 and an anti-backflow check valve 12. The pipeline between the electrolyzer 1 and the gas-water separator 2 and the pipeline between the deoxidation tower 3 and the drying tank are also connected to the first purge battery valve 21 and the second purge battery valve 22 through pipelines, and then connected to the replacement nitrogen inlet.
[0026] like Figure 3 As shown, in this embodiment, the ejector 23 is composed of an ejector front end structure 23.1, an ejector return end 23.2, an ejector body 23.3, a mixed gas outlet 23.4 and a working gas inlet 23.5; one end of the ejector body 23.3 is connected to the ejector front end structure 23.1, and the other end is provided with a mixed gas outlet 23.4; the ejector front end structure 23.1 is provided with a working gas inlet 23.5, and the ejector body 23.3 is provided with an ejector return end 23.2. The ejector No. 23 in the present invention uses the Venturi effect for gas pressurization.
[0027] Example 2 The working principle of the boosting method schematic diagram of the present invention is: When the oxygen in the deoxygenated gas hydrogen meets the requirements of the purification system inlet, the system works normally. The route is [only one of the conditions is given as an example here, and the other two conditions are as follows: Condition 1, the purification inlet valve 8 and the purification outlet valve 9 of the third drying tower 26 are opened, and the cooling inlet valve 6 and the cooling outlet valve 7 of the first drying tower 24 are opened; the regeneration inlet valve 11 and the regeneration outlet valve 10 of the second drying tower 25 are opened, the third drying tower 26 is in the purification operation state, the first drying tower 24 is in the cooling operation state, and the second drying tower 25 is in the regeneration operation state, the purified gas only flows through the third drying tower 26, and the regeneration gas first flows through the first drying tower 24 and then flows to the second drying tower 25. Condition 2: the purification inlet 8 and purification outlet valve 9 of the second drying tower 25 are open, and the cooling inlet valve 6 and cooling outlet valve 7 of the third drying tower 26 are open; the regeneration inlet valve 11 and regeneration outlet valve 10 of the first drying tower 24 are open, the second drying tower 25 is in the purification operation state, the third drying tower 26 is in the cooling operation state, and the first drying tower 24 is in the regeneration operation state. The purified gas only flows through the second drying tower 25, and the regeneration gas first flows through the third drying tower 26 and then flows to the first drying tower 24. The operating sequence of the drying tower is cooling → regeneration → purification: the system working route is from the electrolytic cell 1 through the sequence number gas-water separator 2, the ejector 23 to the deoxidation tower 3, and then the purification gas flow control valve (first flow control valve) 4 and the regeneration gas flow control valve (second flow control valve) 5 are in the open state. Generally speaking, the ratio of the purified gas volume flow to the regeneration gas volume flow is in the range of 7:3~9:1, and this range is determined according to the regeneration time of the drying tower. Then the first drying tower 24 is in the purification state, the second drying tower 25 is in the cooling state, and the third drying tower 26 is in the cooling state. Tower 26 is in a regeneration state. According to the working state of each drying tower, it can be known that the purification inlet valve 8 and the purification outlet valve 9 of the first drying tower 24 are in an open state, and the other four valves are in a closed state. After the raw gas passes through the first drying tower 24 and completes the purification process, it will flow through the purification outlet valve 14 and the oxygen sensor 13 in hydrogen to continuously detect whether it meets the requirements. The detected gas pressure is too small and is not suitable for returning to the main road, so it will be directly discharged; at the same time, it will flow through the back pressure valve 15 to hold the pressure to the required pressure, and then output after passing through the flow meter 16, the switch valve 17 and the flame arrester 18; The regeneration inlet valve 11 and the regeneration outlet valve 10 of the second drying tower 25 are in an open state, and the other four valves are in a closed state. The cooling inlet valve 6 and the cooling outlet valve 7 of the third drying tower 26 are in an open state, and the other four valves are in a closed state. The small stream of raw gas flowing through the regeneration gas flow control valve (second flow control valve) 5 will first pass through the cooling inlet valve 6 of the second drying tower 25 to enter the second drying tower 25 for cooling. Then, after this heat exchange process, the temperature of this stream of raw gas will be increased to a certain extent, and then it will flow out of the second drying tower 25 through the cooling outlet valve 7, and flow to the regeneration inlet valve 11 of the third drying tower 26 through the pipeline to enter the third drying tower 26. After the small stream of raw gas is assisted in completing regeneration in the third drying tower, it will flow out of the third drying tower 26 through the regeneration outlet valve 10. The small stream of raw gas will return to the main road under the gravity of the high-speed gas in the main road of the ejector 23, and will enter the deoxidation tower 3 again for circulation after mixing with the hydrogen to be deoxygenated. (For details, see Figure 2 ) 1. Intermediate parameters involved: Parameters of hydrogen production in the electrolyzer: the volume fraction of hydrogen gas is between 98% and 99%, and the rest is gaseous water, liquid water and oxygen; after separation in the first-stage separator: the volume fraction of hydrogen gas is ≥99.9%, the volume fraction of oxygen is ≤0.06%, and the volume fraction of gaseous water is ≤0.03%; the flow rate controlled by flow control valve 1 is 90% to 70% of the hydrogen produced; the flow rate controlled by flow control valve 2 is 30% to 10% of the hydrogen produced; the overall temperature of the drying tower is between 200 and 260°C; when the flow rate controlled by flow control valve 2 is between 10% and 13%, only the small nozzle is used at the front end of the ejector; and when the flow rate controlled by flow control valve 2 is between 13% and 30%, both the small nozzle and the large nozzle at the front end of the ejector are used; 2. Test data: Pressure sensors are installed at the electrolyzer outlet P1, the middle position of the pressurized system P2, and the hydrogen outlet P3. By detecting the pressure at the three positions, the system operation status and safety as well as the hydrogen output pressure are ensured; the back pressure valve is adjusted according to the P3 requirement so that the pressure of P1P2 reaches the specified value. Under normal operation, P1>P2>P3=target. If any one of them increases abnormally (1.2-1.5 times), the electric exhaust valve should be opened to reduce the pressure to the target value range; 3. Partial Control Logic 1) The raw material device will enter the subsequent drying step only when the oxygen content after deoxygenation is ≤1ppm, otherwise it will be deemed as unqualified raw material gas and discharged directly; 2) When the back-end dew point meter detects that the product gas dew point is less than -70℃, the product gas is supplied normally. Otherwise, the drying tower is deemed abnormal and the back pressure valve is directly closed, the discharge valve is opened, and the dryer temperature is increased to improve the purity of the product gas.
Claims
1. A PEM electrolysis water purification regeneration gas circulation system, characterized in that: The invention comprises an electrolytic cell (1), a gas-water separator (2), a deoxidation tower (3), a first flow control valve (4), a second flow control valve (5), an ejector (23) and a drying tank; the electrolytic cell (1), the gas-water separator (2), the ejector (23) and the deoxidation tower (3) are connected in sequence; the deoxidation tower (3) is connected to a cooling inlet and a purification inlet of the drying tank respectively through pipelines; the deoxidation tower (3) is also connected to a centralized discharge port through a pipeline; the bottom of the drying tank is connected to a hydrogen production outlet; the pipeline between the electrolytic cell (1) and the gas-water separator (2) and the pipeline between the deoxidation tower (3) and the drying tank are also connected to a replacement nitrogen inlet through pipelines; a second flow control valve (5) is provided on the pipeline between the deoxidation tower (3) and the cooling inlet of the drying tank; a first flow control valve (4) is provided on the pipeline between the deoxidation tower (3) and the purification inlet of the drying tank; and the regeneration outlet of the drying tank is connected to the ejector.
2. A PEM electrolysis water purification regeneration gas circulation system according to claim 1, characterized in that: The ejector (23) is composed of an ejector front end structure (23.1), an ejector return end (23.2), an ejector body (23.3), a mixed gas outlet (23.4) and a working gas inlet (23.5); one end of the ejector body (23.3) is connected to the ejector front end structure (23.1), and the other end is provided with a mixed gas outlet (23.4); the ejector front end structure (23.1) is provided with a working gas inlet (23.5), and the ejector body (23.3) is provided with an ejector return end (23.2).
3. A PEM electrolysis water purification regeneration gas circulation system according to claim 1, characterized in that: The top of the drying tank is respectively provided with a cooling inlet, a purification inlet and a regeneration outlet; the cooling inlet, purification inlet and regeneration outlet pipelines are connected to a cooling inlet valve (6), a purification inlet valve (8) and a regeneration outlet valve (10); the bottom of the drying tank is provided with a cooling outlet, a purification outlet and a regeneration inlet; the cooling outlet, purification outlet and regeneration inlet pipelines are connected to a cooling outlet valve (7), a purification outlet valve (9) and a regeneration inlet valve (11).
4. A PEM electrolysis water purification regeneration gas circulation system according to claim 3, characterized in that: The drying tank comprises a first drying tank (24), a second drying tank (25) and a third drying tank (26); the first drying tank (24), the second drying tank (25) and the third drying tank (26) are arranged in parallel.
5. A PEM electrolysis water purification regeneration gas circulation system according to claim 3, characterized in that: The cooling outlet valve (7), the purification outlet valve (9) and the regeneration inlet valve (11) are connected to the hydrogen production outlet through a pipeline.
6. A PEM electrolysis water purification regeneration gas circulation system according to claim 3, characterized in that: The regeneration outlet valve (10) is connected to the reflux end of the ejector via a pipeline.
7. A PEM electrolysis water purification regeneration gas circulation system according to claim 1, characterized in that: A back pressure valve (15), a flow meter (16), a switch valve (17) and a flame arrester (18) are arranged on the pipeline of the hydrogen production outlet.
8. A PEM electrolysis water purification regeneration gas circulation system according to claim 1, characterized in that: A gas detection battery valve (19) and a discharge battery valve (20) are provided on the pipeline between the deoxidation tower (3) and the centralized discharge port; The pipeline between the gas detection battery valve (19) and the discharge battery valve (20) is also connected to the anti-backflow check valve (12) and the hydrogen-oxygen sensor (13) through pipelines; the hydrogen-oxygen sensor (13) is connected to the centralized discharge port through a pipeline; the anti-backflow check valve (12) is connected to the centralized discharge port and the hydrogen production outlet respectively; The anti-backflow one-way valve (12) and the centralized discharge port are also connected in sequence to a dew point meter (14) and the anti-backflow one-way valve (12).
9. A PEM electrolysis water purification regeneration gas circulation system according to claim 1, characterized in that: The pipeline between the electrolytic cell (1) and the gas-water separator (2) and the pipeline between the deoxidation tower (3) and the drying tank are also connected to a first purge cell valve (21) and a second purge cell valve (22) through pipelines, and then connected to a replacement nitrogen inlet.
10. The regeneration gas circulation method of the PEM electrolysis water purification regeneration gas circulation system according to any one of claims 1 to 9, characterized in that: The steps include: (1) When the oxygen in the deoxygenated gas hydrogen meets the requirements of the purification system inlet, the system works normally as follows: the system working route is from the electrolytic cell (1) through the sequence gas-water separator (2), the ejector (23) to the deoxygenation tower (3), and then the first flow control valve (4) and the second flow control valve (5) are in the open state. Generally speaking, the ratio of the purified gas volume flow to the regeneration gas volume flow is 7:3~9:1, and then the first drying tower (24) is in the purification state, the second drying tower (25) is in the cooling state, and the third drying tower (26) is in the regeneration state. The working state of the drying tower is that the purification inlet valve (8) and the purification outlet valve (9) of the first drying tower (24) are in an open state, and the other four valves are in a closed state. After the raw gas passes through the first drying tower (24) and completes the purification process, it will flow through the purification outlet valve (14) and the hydrogen oxygen sensor (13) to continuously detect whether it meets the requirements. If the detected gas pressure is too low, it is not suitable to return to the main road, so it will be directly discharged; at the same time, it will flow through the back pressure valve (15) to hold the pressure to the required pressure, and then pass through the flow meter (16), the switch valve (17) and the flame arrester (18) before being output; (2) The regeneration inlet valve (11) and the regeneration outlet valve (10) of the second drying tower (25) are in an open state, and the other four valves are in a closed state. The cooling inlet valve (6) and the cooling outlet valve (7) of the third drying tower (26) are in an open state, and the other four valves are in a closed state. The small stream of raw gas flowing through the second flow control valve (5) will first pass through the cooling inlet valve (6) of the second drying tower (25) and enter the second drying tower (25) for cooling. Then, this stream of raw gas will pass through this heat exchanger. After the process, the temperature will be raised, and then the gas will flow out of the second drying tower (25) through the cooling outlet valve (7), and then flow to the regeneration inlet valve (11) of the third drying tower (26) through the pipeline to enter the third drying tower (26). After the small amount of raw gas is assisted in regeneration in the third drying tower, it will flow out of the third drying tower (26) through the regeneration outlet valve (10). The small amount of raw gas will return to the main path under the gravity of the high-speed gas in the main path of the ejector (23), mix with the hydrogen to be deoxygenated, and then enter the deoxygenation tower (3) for circulation again.
Citation Information
Patent Citations
Preparation system and preparation method of high-purity food-grade liquid carbon dioxide
CN107934963A
Hydrogen fuel cell ejector and hydrogen circulation system
CN116936869A
Water electrolysis purification device
CN218741105U
Cited By
Molecular sieve-catalytic heating rod coupling water removal device and method for high-pressure PEM hydrogen production system
CN122214971A