Method for efficiently removing phosphorus from phosphorus-containing sewage

Through efficient permeability coupling of iron-based permeability reaction wall system, using acid-modified sponge iron and steel slag and other materials, the high cost and complex operation problems of electroflocculation and magnetic coagulation methods are solved, and low-energy consumption and efficient phosphorus pollution control is achieved. , suitable for different water quality characteristics, especially in phosphorus-containing sewage treatment in phosphate mine areas.

CN118929865AActive Publication Date: 2024-11-12HARBIN INST OF TECH
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411012486.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-11-12
Estimated Expiration
2044-07-26

AI Technical Summary

Technical Problem

The existing electroflocculation and magnetic coagulation and phosphorus removal methods have problems such as high operating and maintenance costs, complex operation and by-product production, and their scope of application is limited by water quality characteristics, making it difficult to effectively treat water bodies with high turbidity and high organic content.

Method used

High-efficiency permeability coupled iron-based permeability reaction wall system is used to modify sponge iron and steel slag as permeability fillers, combining the synergistic effects of zero-valent iron and activated carbon to achieve phosphorus adsorption and removal, avoiding the use of electromagnetic equipment and The generation of by-products reduces the difficulty of system operation and maintenance.

Benefits of technology

It realizes low-energy consumption and efficient phosphorus pollution control, is suitable for different water quality characteristics, can maintain efficient phosphorus removal capacity for a long time, and the total phosphorus removal rate of the effluent treated within 42 days reaches 100%-75%, which is suitable for phosphorus-containing sewage in phosphate mine areas. deal with.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118929865A_ABST
    Figure CN118929865A_ABST
Patent Text Reader

Abstract

The invention discloses a method for efficiently removing phosphorus from phosphorus-containing sewage, and relates to a method for treating phosphorus-containing sewage. The invention aims to solve the technical problems of high operation and maintenance cost, complex operation and generation of byproducts in the conventional electric flocculation and magnetic coagulation dephosphorization method. According to the method, acid-modified sponge iron and steel slag are used as an upper layer of an infiltration bed, quartz sand is used as a lower layer of the infiltration bed to build a continuous flow phosphorus removal infiltration bed, and then a reduced iron powder and activated carbon mixed material and standard sand are uniformly mixed to serve as a filler to be filled into a PRB adsorption wall to build a dynamic PRB adsorption wall; the method comprises the following steps: conveying phosphorus-containing sewage to the top of a phosphorus removal percolation bed through a peristaltic pump, feeding water, pumping water discharged from the bottom of the percolation bed into a bottom water inlet of a dynamic PRB adsorption column in an up-flow form by using the peristaltic pump, and controlling hydraulic retention time HRT to be 1-1.5 h, thereby finishing the treatment of the phosphorus-containing sewage. According to the method, the total phosphorus removal rate of treated effluent within 42 days reaches 100%-75%, and the method can be used for phosphorus-containing sewage treatment in a phosphorite area.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a method for treating phosphorus-containing sewage. Background Art

[0002] In the areas of phosphate mines, phosphorus chemicals and phosphogypsum enterprises, phosphorus and other pollutants carried by rainwater runoff are particularly serious in polluting surface water and groundwater. Under the action of rainwater scouring, mine water gushing and leaching, large amounts of phosphorus, fluorine and other elements enter the nearby water system with untreated rainwater, sewage and leachate from phosphate mines and phosphogypsum storage depots, causing serious non-point source pollution. In order to address these problems, current pollution control measures for rainwater runoff in phosphorus areas mainly adopt strategies such as rainwater storage tanks combined with special phosphorus adsorption materials. However, the construction of storage tanks is limited by the size of urban plots and the centralized collection capacity is limited.

[0003] At present, the phosphorus removal effect of sewage in phosphate mines is mainly achieved through electrocoagulation and magnetic coagulation technology. Although this technology has significant effects, it has the following disadvantages and shortcomings:

[0004] The first is the high operating cost. The equipment and operating costs of electrocoagulation and magnetic coagulation are relatively high, and special equipment is required, such as electrolytic cells, electrodes and power supplies, or magnetic field generators and magnetic poles, etc., which have significant costs for equipment purchase, daily maintenance and energy consumption.

[0005] Secondly, electrical energy and electrode contamination. In electrocoagulation, the electrodes may be contaminated by the deposition of substances in the water, resulting in reduced efficiency and difficult maintenance. Hydrogen may also be produced during the electrolysis process, which needs to be treated to prevent safety issues.

[0006] Third, the operation and control of electrocoagulation and magnetic coagulation are relatively complex and require precise parameter control and monitoring. For example, electrocoagulation requires adjustment of parameters such as current density, electrode spacing, and electrolysis time, while magnetic coagulation requires control of the intensity and direction of the magnetic field to achieve the best effect.

[0007] Fourth, the application scope of electroflocculation and magnetic coagulation is limited by the characteristics of water quality. The salt content, particulate matter and organic matter content in water may affect the effect of electroflocculation and magnetic coagulation. In particular, for water bodies with high turbidity and high organic matter content, the efficiency of these technologies is low.

[0008] Fifth, some by-products, such as sediment or gas, are generated during the electro-flocculation and magnetic coagulation processes. These by-products need to be properly handled to reduce environmental impact and resource waste. Summary of the invention

[0009] The present invention aims to solve the technical problems of high operation and maintenance costs, complex operation and generation of by-products in the existing electro-flocculation and magnetic coagulation phosphorus removal methods, and provide a method for efficient phosphorus removal of phosphorus-containing wastewater. The method uses a high-efficiency percolation coupled iron-based permeable reaction wall system to replace the electro-flocculation and magnetic coagulation technologies, thereby avoiding the purchase of electromagnetic equipment, the pollution and by-products generated by the electric energy electrodes, reducing the difficulty of system operation and maintenance, saving costs, solving the problem of limited water quality characteristics, enhancing the ecological benefits of the system, realizing the combination of phosphorus pollution control and ecological restoration, and improving the recycling of water resources.

[0010] The method for efficient phosphorus removal from phosphorus-containing wastewater of the present invention is carried out according to the following steps:

[0011] 1. Preparation of percolation bed filler: soak the dried sponge iron in a diluted H2SO4 solution with a mass percentage concentration of 5% to 6% and stir to remove the surface oxides, then take out the sponge iron and rinse it with deionized water until the pH of the cleaning solution is neutral, and then dry it to obtain acid-modified sponge iron;

[0012] 2. Build a continuous flow phosphorus removal percolation bed: Use 15-20 cm thick quartz sand as the lower layer of the percolation bed, and then use a mixture of acid-modified sponge iron and steel slag in a volume ratio of 1: (1-1.2) as the upper layer of the percolation bed to obtain a continuous flow phosphorus removal percolation bed;

[0013] 3. Preparation of PRB adsorption wall filler: Reduced iron powder with an average particle size of 40-50 μm and activated carbon are mixed in a mass ratio of (1.7-2.3):1 and placed in a planetary ball mill. High-purity argon gas is introduced into the tank to avoid oxidation of the reduced iron powder. The ball mill is milled for 8-10 hours at a speed of 300-500 r / min. After the ball mill is completed, a mixed powder is obtained; the mixed powder is washed with ethanol to improve the hydrophilicity of the material, and then immersed in a dilute HNO3 solution and stirred to expose the active sites and oxidize part of the zero-valent iron; after acid treatment, the material is washed with pure water to neutrality, and then vacuum dried to obtain a mixed material of reduced iron powder and activated carbon;

[0014] 4. Building a dynamic PRB adsorption wall: Mix the reduced iron powder and activated carbon mixed material with standard sand in a mass ratio of 1: (5-6) and fill it into the PRB adsorption wall as a filler to obtain a dynamic PRB adsorption wall;

[0015] 5. System operation for phosphorus removal: The phosphorus-containing sewage is transported to the top inlet of the phosphorus removal infiltration bed through a peristaltic pump, and then the effluent from the bottom of the infiltration bed is pumped into the bottom inlet of the dynamic PRB adsorption wall in the form of upflow by a peristaltic pump. The hydraulic retention time HRT is controlled to be 1 to 1.5 hours to complete the treatment of the phosphorus-containing sewage.

[0016] Furthermore, the stirring time in step 1 is 20 to 30 minutes.

[0017] Furthermore, the thickness of the upper layer in the continuous flow phosphorus removal percolation bed described in step 2 is 65 to 70 cm.

[0018] Furthermore, in step 3, the mass percentage concentration of the diluted HNO3 solution used to immerse the mixed powder is 4% to 5%, and the stirring time is 30 to 40 minutes.

[0019] Furthermore, the average diameter of the standard sand described in step 4 is 2 to 3 mm.

[0020] Furthermore, the filling height of the filler in the PRB adsorption column described in step 4 is 80 to 100 cm.

[0021] Furthermore, in order to prevent the loss of filler as described in step 4, standard sand is filled above and below the filler of the PRB adsorption wall, and the filling thickness of the standard sand is 5 to 10 cm.

[0022] Furthermore, the temperature of the phosphorus-containing wastewater in step five is 20-30°C.

[0023] The phosphorus removal principle of the present invention: Sponge iron is called direct reduction iron oxide, which has a loose and porous surface. Its main component is elemental iron, and it also contains substances such as Fe3C, Fe3O4, Fe2O3, and Fe2CO3. The iron ions or ferrous ions precipitated by the corrosion of elemental iron react with phosphate to form insoluble iron salts, ferric phosphate or ferrous phosphate. At the same time, when the sponge iron is oxidized in the air, iron oxides and hydroxy oxides will be formed on the surface, which will react with phosphate radicals through ion exchange, complex precipitation, electrostatic adsorption, etc. to remove phosphorus from the water. Acid modification can remove the aged passivation layer on the surface of the sponge iron, forming Fe ions with stronger phosphate adsorption activity, iron oxides and iron hydroxides with lower crystallinity. Steel slag is an industrial waste with low cost. Because it contains a certain amount of elements such as Ca, Mg, and Fe, it also has good phosphorus adsorption performance. By using acid-modified sponge iron and steel slag as percolation bed fillers, the surface of the steel slag is very rough, the adsorption pore size is small, and the specific surface area and pore volume are large. It not only has a high phosphorus adsorption efficiency, but also helps to improve the air permeability of the filler and the permeability of water flow due to its large specific surface area and pore volume. When steel slag is mixed with acid-modified sponge iron, these characteristics of steel slag can effectively reduce the adhesion and aggregation between sponge iron particles, and can effectively alleviate the problem of compaction during the operation of sponge iron percolation bed.

[0024] Zero-valent iron has excellent reduction performance and efficient adsorption capacity, and can reduce phosphate ions in water into insoluble phosphate salt precipitation or adsorption on its surface; activated carbon provides a large surface area and rich pore structure, enhancing the adsorption capacity of phosphorus and the stability of the filler. This composite material uses the synergistic effect of zero-valent iron and activated carbon to effectively remove phosphorus pollutants in water while maintaining the long-term stability and high efficiency of the filler.

[0025] After treatment by the ecological infiltration phosphorus removal unit with adsorption and interception as the core, the phosphorus content in the sewage is greatly reduced, but a small amount of phosphorus still remains. The effluent from the infiltration bed is then pumped into the PRB adsorption column for secondary treatment, achieving efficient, stable and continuous removal of low-concentration phosphorus at the end of the system.

[0026] The method of the present invention has the following advantages:

[0027] First, the high-efficiency infiltration system uses mixed fillers to absorb or degrade organic matter and remove phosphorus, with lower energy consumption and chemical use, less impact on the environment, low cost, and meets the requirements of sustainable development.

[0028] Secondly, it avoids frequent parameter adjustment and monitoring in electroflocculation and magnetic coagulation. The high-efficiency infiltration coupled iron-based permeable reaction wall system can maintain high-efficiency phosphorus removal capacity for a long time after stable operation. The total phosphorus removal rate of the treated water reaches 100% to 75% within 42 days. The system operation and maintenance requirements are relatively low, and it is suitable for long-term operation and large-scale application. In addition, unlike electroflocculation and magnetic coagulation, which are limited by water quality characteristics, the high-efficiency infiltration coupled iron-based permeable reaction wall system can be adjusted and optimized according to different water quality characteristics, adapt to different sewage sources and treatment requirements, and has high applicability.

[0029] The high-efficiency percolation coupled iron-based permeation reaction wall system of the present invention combines the two mechanisms of mixed filler adsorption and iron-based permeation reaction, and can effectively remove phosphorus in water, especially for the hard-to-degrade organic phosphorus forms, and achieve multi-stage high-efficiency phosphorus removal. The method of the present invention can be used in the field of treatment of phosphorus-containing wastewater in phosphate mining areas. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 This is the relationship curve between the total phosphorus removal rate and the reaction time in Example 1.

[0031] Figure 2 This is a curve showing the relationship between the total phosphorus removal rate and the reaction time in comparative example 1.

[0032] Figure 3 This is the curve showing the relationship between the total phosphorus removal rate and the amount of magnetic seed added in Example 2.

[0033] Figure 4It is a comparison chart of the total phosphorus removal rates of Example 1 and Comparative Example 3 when the reaction time lasts from 0 day to 42 days.

[0034] Figure 5 It is a comparison chart of the total phosphorus removal rates of Example 1 and Comparative Example 4 when the reaction time lasts from 0 day to 42 days.

[0035] Figure 6 It is a comparison chart of the total phosphorus removal rates of Example 1 and Comparative Example 5 when the reaction time lasts from 0 day to 42 days.

[0036] Figure 7 It is a comparison chart of the total phosphorus removal rates of Example 1 and Comparative Example 6 when the reaction time lasts from 0 day to 42 days.

[0037] Figure 8 It is a comparison chart of the total phosphorus removal rates of Example 1 and Comparative Example 7 when the reaction time lasts from 0 day to 42 days. DETAILED DESCRIPTION

[0038] The beneficial effects of the present invention are verified by the following examples.

[0039] Embodiment 1: The method for efficient phosphorus removal from phosphorus-containing wastewater in a phosphate mine area of ​​this embodiment is carried out according to the following steps:

[0040] 1. Preparation of percolation bed filler: soak the dried sponge iron in a diluted H2SO4 solution with a mass percentage concentration of 6% and stir for 30 minutes to remove the surface oxides, then take out the sponge iron and rinse it with deionized water until the pH of the cleaning solution is neutral, and then put it in a 105°C oven to dry for 10 hours to obtain acid-modified sponge iron;

[0041] 2. Build a continuous flow phosphorus removal percolation bed: Use organic glass columns to build a phosphorus removal percolation bed with an inner diameter of 10 cm and a height of 100 cm. Use 15 cm thick quartz sand as the lower layer of the percolation bed, and then use a mixture of acid-modified sponge iron and steel slag in a volume ratio of 1:1 as the upper filler of the percolation bed. The thickness of the upper filler is 65 cm, and a continuous flow phosphorus removal percolation bed is obtained with an effective volume of 4.0 L.

[0042] 3. Preparation of PRB adsorption column filler: Reduced iron powder with an average particle size of 45 μm and activated carbon are mixed in a mass ratio of 2:1 and placed in a planetary ball mill. High-purity argon gas is introduced into the tank to avoid oxidation of the reduced iron powder. The ball mill is milled for 8 hours at a speed of 375 r / min. After the ball milling is completed, a mixed powder is obtained; the mixed powder is washed with ethanol to improve the hydrophilicity of the material, and then immersed in a 5% HNO3 solution and stirred for 40 minutes to expose the active sites and oxidize part of the zero-valent iron; after acid treatment, the material is washed with pure water to neutrality, and then placed in a vacuum drying oven at a temperature of 60°C and vacuum dried for 2 hours to obtain a mixed material of reduced iron powder and activated carbon, which is recorded as ZVI-AC;

[0043] 4. Build a dynamic PRB adsorption column: Use an organic glass column to simulate the PRB reaction wall. The height of the organic glass column is 100 cm and the inner diameter is 10 cm. Mix 680 g of reduced iron powder and activated carbon mixed material with 3400 g of standard sand with an average material diameter of 2 mm and fill them into the PRB adsorption column as filler. The filling height of the filler is 80 cm. The top and bottom of the filler are filled with standard sand with a thickness of 5 cm to prevent filler loss, and a dynamic PRB adsorption column is obtained. The PRB adsorption column can maintain good hydraulic conditions of the system and effectively prevent the occurrence of system blockage.

[0044] 5. System operation Phosphorus removal: Use KH2PO4 to prepare simulated phosphorus-containing sewage with a phosphorus content of 10 mg / L; transport the simulated phosphorus-containing sewage to the top inlet of the phosphorus removal filter bed through a peristaltic pump, and then use a peristaltic pump to pump the effluent from the bottom of the filter bed into the bottom inlet of the dynamic PRB adsorption column in the form of upflow. Operate at a temperature of 25°C and control the hydraulic retention time HRT to 1h to complete the treatment of phosphorus-containing sewage; regularly collect effluent from the upper sampling port of the PRB adsorption column, filter through a 0.45μm filter membrane, and immediately analyze the water quality indicators. The change in total phosphorus removal rate from 0d to 42d is shown in the following figure. Figure 1 shown.

[0045] Comparative Example 1: This comparative example uses the electrocoagulation method to treat simulated phosphorus-containing wastewater, and the steps are as follows:

[0046] The plates were fixed with a plate rack and placed on a 1L beaker, the contact area between each plate and the solution was 10cm×8cm, and the plate spacing was set to 1.0cm; in order to simulate the phosphorus removal performance of the percolation bed under high phosphorus concentration in nature, this comparative example adopted a higher influent phosphorus load, and a simulated phosphorus-containing sewage with a phosphorus content of 10mg / L was prepared by adding KH2PO4 to tap water, 500mL of the simulated phosphorus-containing sewage was added to the beaker at one time, and the solution was fully mixed with a magnetic stirrer at a temperature of 25°C, a plate spacing of 1.0cm, a pH value of 6.70, and a current density of 4.01mA / cm2 Under the condition of , the phosphorus removal was carried out by power on; the change of total phosphorus removal rate when the reaction time was extended from 5min to 40min is as follows Figure 2 shown.

[0047] Comparative Example 2: This comparative example uses magnetic coagulation to treat simulated phosphorus-containing wastewater, and the steps are as follows:

[0048] In order to simulate the phosphorus removal performance of the percolation bed under high phosphorus concentration in nature, this experiment adopted a higher influent phosphorus load. By adding KH2PO4 to tap water to prepare simulated phosphorus-containing sewage with a phosphorus content of 10 mg / L, the temperature was 25°C, 500 ml of the prepared simulated phosphorus-containing sewage was added to a 1L beaker, and the mixer was placed on the mixer and powered on to wait for operation; the aluminum oxide content of polyaluminium chloride (PAC) was 30%, and a 2g / L solution was prepared for use; the relative molecular mass of anionic polyacrylamide (PAM) was 300×10 4 , prepare a 0.1g / L solution for standby use; prepare Fe3O4 magnetic seeds, which are industrial grade and have a particle size of 48μm;

[0049] The six-joint mixer was used at room temperature. First, magnetic seed and PAC (60 mg / L) were added, and the mixture was stirred rapidly at 300 r / min for 1 min. Then PAM (1 mg / L) was added, and the mixture was stirred at 120 r / min for 3 min. Then, the mixture was stirred slowly at 60 r / min for 5 min. After the coagulation was completed, the mixture was allowed to settle for 5 min, and the supernatant was taken 2 cm below the liquid surface to measure the water quality index. The change in total phosphorus removal rate when the magnetic seed dosage increased from 0 g / L to 5 g / L is shown in the figure. Figure 3 shown.

[0050] Compared with Comparative Examples 1 and 2, Example 1 is less dependent on electric energy. Electric flocculation and magnetic coagulation require a large amount of electric energy to maintain system operation, while the high-efficiency infiltration coupled iron-based permeable reaction wall system only needs to increase the electric energy consumption of the pump; at the same time, it also avoids the large-scale use of chemical agents such as PAM and PAC in magnetic coagulation, reducing the impact on the environment and operating costs.

[0051] In comparative example 1, it is necessary to monitor the current density, electrode spacing, and electrolysis time at any time, and strictly control the plate spacing and loss; while in comparative example 2, it is necessary to monitor the stirring rate and drug consumption at any time, and frequently adjust the stirring time and rate. However, in embodiment 1, only the filler ratio needs to be adjusted, and there is no need for too much complicated operation. After stable operation, it can maintain efficient phosphorus removal capacity for a long time, solving the problems of complex system operation and high maintenance difficulty.

[0052] Comparative Examples 1 and 2 are limited by a large number of parameter controls and are only suitable for the treatment of phosphorus-containing wastewater with a single water quality characteristic. However, Example 1 has low requirements on the source of wastewater and water quality characteristics, and can be adjusted and optimized according to different water quality characteristics, and has higher adaptability.

[0053] Comparative Examples 1 and 2 are both single-stage treatments, and the total phosphorus removal rate of the treated effluent is about 70%, and it is impossible to ensure that the effluent is stable and up to the standard. However, Example 1 uses two mechanisms, namely, biodegradation absorption and iron-based permeation reaction, to achieve multi-stage efficient phosphorus removal, and the total phosphorus removal rate of the treated effluent reaches 100% to 75% within 42 days. At the same time, multiple treatments ensure that the effluent is stable and up to the standard.

[0054] Comparative Example 3: This comparative example is different from Example 1 in that the operation in step 2 is replaced by the following operation:

[0055] Second, a phosphorus removal filtration bed was constructed using organic glass columns with an inner diameter of 10 cm and a height of 100 cm. A 15 cm thick quartz sand was used as the lower layer of the filtration bed, and a mixture of acid-modified sponge iron and steel slag in a volume ratio of 1:2 was used as the upper filler of the filtration bed. The thickness of the upper filler was 65 cm, and a continuous flow phosphorus removal filtration bed was obtained with an effective volume of 4.0 L.

[0056] The other steps and parameters are the same as those in Example 1.

[0057] The total phosphorus removal rate of the treated effluent in this comparative example 3 within 42 days was worse than that of the treatment effect of Example 1. The total phosphorus removal rate on the first day was 83.12%. As the operation time increased, the total phosphorus removal rate of the treated effluent dropped to 63.49% on the 42nd day. The content of the acid-modified sponge iron, which plays a major adsorption role, decreased, and the total phosphorus removal rate of the effluent was significantly reduced. The total phosphorus removal rate of Example 1 and Comparative Example 3 from 0 days to 42 days is compared. Figure 4 shown.

[0058] Comparative Example 4: This comparative example is different from Example 1 in that the operation in step 2 is replaced by the following operation:

[0059] Second, a phosphorus removal percolation bed was constructed using organic glass columns with an inner diameter of 10 cm and a height of 100 cm. A 15 cm thick quartz sand was used as the lower layer of the percolation bed, and a mixture of acid-modified sponge iron and steel slag in a volume ratio of 1:0.5 was used as the upper filler of the percolation bed. The thickness of the upper filler was 65 cm, and a continuous flow phosphorus removal percolation bed was obtained with an effective volume of 4.0 L.

[0060] The other steps and parameters are the same as those in Example 1.

[0061] The total phosphorus removal rate of the treated effluent in this comparative example 4 within 42 days was inferior to that of the treatment effect of Example 1. The total phosphorus removal rate on the first day was 85.33%. As the operation time increased, the total phosphorus removal rate of the treated effluent decreased to 65.87% on the 42nd day. The slag content decreased, and the acid-modified sponge iron had a hardening problem, which affected the phosphorus removal effect, and the total phosphorus removal rate of the effluent was significantly reduced.

[0062] Comparison of total phosphorus removal rates between Example 1 and Comparative Example 4 from 0 days to 42 days Figure 5 shown.

[0063] Comparative Example 5: This comparative example is different from Example 1 in that the operation in step 2 is replaced by the following operation:

[0064] Second, a phosphorus removal filtration bed was constructed using organic glass columns with an inner diameter of 10 cm and a height of 100 cm. A 15 cm thick quartz sand was used as the lower layer of the filtration bed, and a mixture of sponge iron and steel slag in a volume ratio of 1:1 was used as the upper filler of the filtration bed. The thickness of the upper filler was 65 cm, and a continuous flow phosphorus removal filtration bed was obtained with an effective volume of 4.0 L.

[0065] The other steps and parameters are the same as those in Example 1.

[0066] The total phosphorus removal rate of the treated effluent in this comparative example 5 within 42 days was worse than that of the treatment effect of Example 1. The total phosphorus removal rate on the first day was 82.12%. As the operation time increased, the total phosphorus removal rate of the treated effluent dropped to 59.25% on the 42nd day. An aged passivation layer will form on the surface of the unmodified sponge iron, which will reduce the content of Fe ions with lower phosphate adsorption activity, iron oxides and iron hydroxides with lower crystallinity, affecting the phosphorus removal effect, and significantly reducing the total phosphorus removal rate of the effluent. A comparison of the total phosphorus removal rates of Example 1 and Comparative Example 5 when the reaction time lasted from 0d to 42d is as follows: Figure 6 shown.

[0067] Comparative Example 6: This comparative example is different from Example 1 in that the mass ratio of the reduced iron powder with an average particle size of 40 to 50 μm and the activated carbon in step 3 is 3:1, and the other steps and parameters are the same as those in Example 1.

[0068] In this comparative example 6, the excessive content of reduced iron powder will reduce the pore structure of the composite material and reduce the adsorption capacity of the activated carbon. A high proportion of reduced iron powder will also cause iron ions to dissolve, forming iron phosphate precipitation, blocking the pores and reducing the permeability of the material. A large amount of precipitate accumulation will block the percolation filler, resulting in poor water flow, affecting the normal operation and long-term stability of the system, thereby reducing the overall treatment efficiency. Comparison of the total phosphorus removal rate of Example 1 and Comparative Example 6 from 0 days to 42 days of reaction time Figure 7 shown.

[0069] Comparative Example 7: This comparative example is different from Example 1 in that the mass ratio of the reduced iron powder with an average particle size of 40 to 50 μm and the activated carbon in step 3 is 1:1, and the other steps and parameters are the same as those in Example 1.

[0070] In this comparative example 7, the reduced iron powder content in the composite material is insufficient, which will lead to a decrease in its reduction performance and affect the effective reduction of phosphate ions. At the same time, it will also reduce the adsorption capacity of the composite material for phosphate ions and reduce the phosphorus removal efficiency. In addition, a high content of activated carbon may change the mechanical strength of the material and affect the structural stability and service life of the filler. Comparison of the total phosphorus removal rate of Example 1 and Comparative Example 7 from 0d to 42d of reaction time Figure 8 shown.

Claims

1. A method for efficient phosphorus removal from phosphorus-containing wastewater, characterized in that The method proceeds as follows:

1. Preparation of percolation bed filler: soak the dried sponge iron in a diluted H2SO4 solution with a mass percentage concentration of 5% to 6% and stir to remove the surface oxides, then take out the sponge iron and rinse it with deionized water until the pH of the cleaning solution is neutral, and then dry it to obtain acid-modified sponge iron; 2. Build a continuous flow phosphorus removal percolation bed: Use 15-20 cm thick quartz sand as the lower layer of the percolation bed, and then use a mixture of acid-modified sponge iron and steel slag in a volume ratio of 1: (1-1.2) as the upper layer of the percolation bed to obtain a continuous flow phosphorus removal percolation bed; 3. Preparation of PRB adsorption wall filler: Reduced iron powder with an average particle size of 40-50 μm and activated carbon are mixed in a mass ratio of (1.7-2.3):1 and placed in a planetary ball mill. High-purity argon gas is introduced into the tank to avoid oxidation of the reduced iron powder. The ball mill is milled for 8-10 hours at a speed of 300-500 r / min. After the ball mill is completed, a mixed powder is obtained; the mixed powder is washed with ethanol to improve the hydrophilicity of the material, and then immersed in a dilute HNO3 solution and stirred to expose the active sites and oxidize part of the zero-valent iron; after acid treatment, the material is washed with pure water to neutrality, and then vacuum dried to obtain a mixed material of reduced iron powder and activated carbon; 4. Building a dynamic PRB adsorption wall: Mix the reduced iron powder and activated carbon mixed material with standard sand in a mass ratio of 1: (5-6) and fill it into the PRB adsorption wall as a filler to obtain a dynamic PRB adsorption wall; 5. System operation for phosphorus removal: The phosphorus-containing wastewater is transported to the top inlet of the phosphorus removal infiltration bed through a peristaltic pump, and then the effluent from the bottom of the infiltration bed is pumped into the bottom inlet of the dynamic PRB adsorption wall in the form of upflow by a peristaltic pump. The hydraulic retention time HRT is controlled to be 1 to 1.5 hours to complete the treatment of the phosphorus-containing wastewater.

2. The method for efficient phosphorus removal from phosphorus-containing wastewater according to claim 1, characterized in that: The stirring time in step 1 is 20 to 30 minutes.

3. The method for efficient phosphorus removal from phosphorus-containing wastewater according to claim 1 or 2, characterized in that: The thickness of the upper layer in the continuous flow phosphorus removal percolation bed described in step 2 is 65 to 70 cm.

4. The method for efficient phosphorus removal from phosphorus-containing wastewater according to claim 1 or 2, characterized in that: In step 3, the mass percentage concentration of the dilute HNO3 solution used to immerse the mixed powder is 4% to 5%, and the stirring time is 30 to 40 minutes.

5. The method for efficient phosphorus removal from phosphorus-containing wastewater according to claim 1 or 2, characterized in that: The average diameter of the standard sand described in step 4 is 2 to 3 mm.

6. The method for efficient phosphorus removal from phosphorus-containing wastewater according to claim 1 or 2, characterized in that: The filling height of the filler in the PRB adsorption wall described in step 4 is 80 to 100 cm.

7. The method for efficient phosphorus removal from phosphorus-containing wastewater according to claim 1 or 2, characterized in that: The temperature of the phosphorus-containing wastewater described in step 5 is 20-30°C.

Citation Information

Patent Citations

  • Permeable reactive barrier device for underground water treatment

    CN104671438A

  • Method of applying engineering wastes as PRB packing to treatment of flow-out water of farmland

    CN110872138A

  • Composite permeable reactive barrier system based on Fe < 0 >-bentonite modified biochar filler and application of composite permeable reactive barrier system

    CN114249507A

  • Permeable reactive barrier system

    CN214218476U

  • Ds-mprbs

    KR100597886B1