High-energy-level dynamic compaction combined rammer and type parameter determination method

By designing a high-energy-level strong tamp combined tamp hammer with adjustable cross-section and weight and a model parameter determination method, the problem of increasing shearing effect of tamp hammer on soil and inconvenient transportation is solved, and efficient tamping construction is achieved.

CN118932974APending Publication Date: 2024-11-12SHAANXI ACAD OF ARCHITECTONICS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411410512.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-10
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the prior art, the small cross-sectional size of the tamp hammer leads to an increase in the shearing effect on the soil, and is inconvenient for transportation and energy level adjustment, affecting the optimization of the high-energy-level tamping process.

Method used

Design a high-energy-level strong tamp combined tamp hammer, stacking multi-stage tamp combined structural sheets to form a pagoda or inverted bolt structure, using bolt connections and rubber pads for assembly, and propose a method for model parameter determination. Ensure that the cross-sectional size and hammer weight of the tamper are adjustable, making it easier to transport and process adjustment.

Benefits of technology

Effectively reduce the shearing effect of the ramming hammer on the soil, simplify transportation and energy level adjustment, improve the construction efficiency of the ramming, and ensure that the process parameters are in the optimal state.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932974A_ABST
    Figure CN118932974A_ABST
Patent Text Reader

Abstract

The invention discloses a high-energy-level dynamic compaction combined rammer and a model parameter determination method, and relates to the technical field of rammers, the high-energy-level dynamic compaction combined rammer comprises a rammer combined structure piece, a rammer split structure piece, a groove type connecting hole, a connecting bolt, a rammer lifting hook structure and a rubber pad. According to the combined rammer provided by the invention, parameters such as the sectional area of the bottom of the rammer and the weight of the rammer can be freely adjusted, meanwhile, the split type structural sheets are relatively convenient to transport after being split, the problem that the diameter of the rammer is limited due to the fact that the conventional high-energy-level rammer is limited by transportation conditions is solved, and the shearing effect of the edge of the rammer on a soil body is effectively reduced. The method for determining the model parameters of the rammer is used in cooperation with the combined rammer, rationality of the size parameters of the rammer in high-energy-level dynamic compaction construction can be guaranteed, and the method has important guiding significance for dynamic compaction process optimization, technical development and application and popularization.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of rammers, and in particular relates to a high-energy-level strong rammer combined type rammer and a method for determining model parameters. Background Art

[0002] Dynamic compaction is an important technical means in the field of foundation treatment. The main reinforcement mechanism is to generate dynamic stress and shock waves in the soil through the powerful tamping energy generated by the free fall of the tamping hammer, compact the foundation soil, and then improve the strength of the soil and reduce its compression deformation under load. It is one of the most cost-saving and time-saving foundation treatment methods with outstanding economic and social benefits. With the continuous advancement of large-scale engineering projects such as high filling in mountainous areas, backfilling of block stones in mountain openings, and construction of large-thickness loess sites, the depth and requirements of foundation treatment have increased accordingly, and high-energy dynamic compaction technology has gradually emerged. Among the current national or industry standards, the highest dynamic compaction energy level standard of "Technical Specification for Building Foundation Treatment" (JGJ 79-2012) can reach 12000kN·m, and the highest dynamic compaction energy level of "Technical Specification for Steel Storage Tank Foundation Treatment" (GB / T 50756-2012) and "Technical Specification for Composite Foundation" (GB / T 50783-2012) can reach 18000kN·m. In actual engineering cases, the highest energy level of some strong compaction treatments of collapsible loess foundations has reached 20,000 kN·m, and the highest energy level of some strong compaction treatments of crushed stone backfill foundations has reached 25,000 kN·m.

[0003] The main way to increase the energy level of dynamic compaction is to increase the deadweight of the rammer. However, due to the size restrictions of large-scale highway transportation, the diameter of the rammer is usually limited to less than 2.5m. The weight of the rammer can only be increased vertically in high-energy dynamic compaction, which leads to the enhanced shearing effect of the edge of the rammer on the foundation soil in engineering applications. The depth of the ramming pit can sometimes be close to 10m, which is somewhat different from the dynamic compaction reinforcement mechanism and seriously affects the process optimization of high-energy dynamic compaction. Therefore, it is necessary to develop a high-energy combined rammer that is easy to transport and easy to adjust the cross-sectional area and weight, and form a set of rammer model parameter determination methods. Summary of the invention

[0004] The purpose of the present invention is to solve the shortcomings of the prior art that the small cross-sectional size of the rammer increases the shearing effect on the soil, is inconvenient to transport, and is inconvenient to adjust the energy level, and a high-energy-level dynamic tamping combined rammer and a method for determining model parameters are proposed. The high-energy-level dynamic tamping combined rammer and a method for determining model parameters can reduce the shearing effect on the soil when the cross-sectional size of the rammer is small, facilitate rammer transportation, energy level adjustment, and dynamic tamping process optimization.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions: A high-energy level strong tamping combined rammer is designed, including a rammer combined structural piece, and several of the rammer combined structural pieces are stacked to form multi-level rammer bodies of different sizes, characterized in that each level of the rammer combined structural piece is composed of several rammer split structural pieces of the same size spliced ​​together to form a regular hexagonal structure; the rammer combined structural piece is respectively composed of the same blocks of the rammer split structural pieces to form a double-layer structure; the rammer split structural piece is located on the splicing side, and is symmetrically provided with a plurality of grooved connecting holes for splicing and fixing with the diagonal obtuse angle line as the axis, and the grooved connecting holes on the symmetrical side are grouped in two, and each group is equidistant from the edge line of the splicing side of the rammer split structural piece and the diagonal obtuse angle line, so that the positions of the grooved connecting holes on the rammer split structural pieces of each level correspond to each other, and after splicing, the grooved connecting holes are symmetrically distributed on both sides of each diagonal line of the rammer combined structural piece.

[0006] It also includes a rammer hook structure, which consists of a hook bent rod, a hook cross brace and a hook bolt vertical rod. The two hook bent rods are vertically arranged to each other, and the hook bolt vertical rod is connected to the grooved connecting holes of the rammer combination structure pieces at each level.

[0007] Furthermore, when assembling the rammer body, rammer combination structural pieces of adjacent sizes are combined into a pagoda-like structure in a graded continuous or discontinuous order from large at the bottom to small at the top, and the rammer combination structural pieces of each level are stacked with staggered seams and connected by bolts.

[0008] Furthermore, the size of two adjacent rammer combination structure pieces is determined according to the following formula:

[0009] Wherein, w1 is the side length of the regular hexagonal rammer combined structure piece of the previous level; w2 is the side length of the regular hexagonal rammer combined structure piece of the adjacent next level. The area of ​​the rammer combined structure piece of the next level is 25% smaller than that of the previous level.

[0010] Furthermore, when the rammer body is assembled, the bottom layer of rammer combination structural pieces has a large size, while the upper layers of rammer combination structural pieces have the same size, forming an inverted bolt structure. The rammer combination structural pieces at each layer are stacked with staggered seams and connected by bolts.

[0011] Furthermore, each level of the rammer combination structural sheet is composed of 6 rammer split structural sheets, and each layer is provided with 3 rammer split structural sheets. There are rubber pads between the rammer split structural sheets of two adjacent layers and between each level of the rammer combination structural sheets. The rubber pads are in an equilateral triangle structure and are located on the surfaces on both sides of the rammer split structural sheets.

[0012] Furthermore, the rammer split structural piece is a diamond shape, one of the diagonals of which is an acute angle of 60°. The rammer split structural pieces between the two layers of the rammer combined structural piece are staggered and the staggered rotation degree is 60°, so that the six rammer split structural pieces between the two layers of the rammer combined structural piece are interlocked with each other.

[0013] Furthermore, the number of the slot-type connecting holes on the rammer split structural piece is 8, which are symmetrically distributed on both sides of the diagonal obtuse angle connection line, in groups of two.

[0014] Furthermore, the groove-type connecting hole is composed of a connecting hole shallow groove and a connecting hole through groove. The connecting hole shallow groove is arranged on the upper and lower surfaces of the rammer split structure piece, and is in a rectangular shape. The depth is not less than the nut thickness of the connecting bolt, and the width is not less than the working size of the fastening bolt sleeve. The connecting hole through groove is rectangular in shape, and the width is between the screw diameter and the nut diameter.

[0015] Furthermore, the thickness of the rammer split structure piece is not less than 5 cm, and the maximum size of the rammer split structure piece is determined according to the road transport width limit. w The geometric relationship calculation when the side length of the split structure piece of the rammer is parallel to the length direction of the carriage is as follows:

[0016] In the formula, w max The side length of the theoretical maximum rammer combination structure piece; w Width limit for road transport; When the theoretically largest level rammer combination structure is placed flat for transportation, the minimum length requirement for the transport vehicle is calculated according to the following formula: Where a is the number of longitudinally placed blocks of the rammer split structure pieces when transported in a flat layout. l It is the longitudinal length after placement.

[0017] In order to solve the above technical problems, the present invention also proposes a method for determining model parameters of a high-energy level dynamic compaction combined rammer, which is used for the high-energy level dynamic compaction combined rammer, and specifically comprises the following steps: Step 1: Determine the theoretical rammer mass m according to the planned dynamic tamping energy level and the maximum effective lifting height of the on-site equipment, where the theoretical rammer mass m is:

[0018] M is the tamping energy level, g is the acceleration of gravity, m is the theoretical tamping hammer mass, and L is the maximum effective lifting height of the on-site equipment. When preliminarily determining the hammer weight, a 10% margin should be reserved; Step 2: According to the static pressure requirement of the rammer bottom, preliminarily determine the range of the dimension parameters of the rammer combined structure piece at the bottom level:

[0019] Wherein, wact is the side length of the rammer composite structure piece at the bottom level; wmax is the maximum static pressure at the bottom of the rammer; wmin is the minimum static pressure at the bottom of the rammer; Step 3: Combine the geological survey data and the depth of the foundation to be reinforced and the parameters of the foundation soil after reinforcement in the design documents to give the theoretical value of the tamping amount, where the theoretical value of the tamping amount is:

[0020] Where H1 is the estimated theoretical tamping settlement; n0i is the porosity of the i-th soil layer before dynamic tamping reinforcement; n1i is the porosity of the i-th soil layer under the expected dynamic tamping reinforcement quality; hi is the thickness of the i-th soil layer before dynamic tamping reinforcement; H0 is the total dynamic tamping foundation reinforcement depth; Step 4: Based on the theoretical rammer weight m and the side length wact interval of the bottom-level composite structure piece, combined with the corresponding relationship between the sizes of two adjacent groups of rammer composite structure pieces, preliminarily determine the model and quantity of the rammer composite structure pieces to be assembled; Step 5: Calculate the actual rammer mass m1 based on the preliminarily determined rammer assembly structure piece model and quantity; Step 6: Connect the rammer combination structure pieces into a whole by bolts, and install the rammer hook structure; Step 7: Carry out preparatory work before the test ramming. According to the actual mass of the ramming hammer, determine the ramming hammer drop distance during the test ramming. The ramming hammer drop distance is:

[0021] Where, L1 is the drop distance of the rammer during the test ramming, M is the ramming energy level, g is the gravitational acceleration, and m1 is the actual rammer mass; Step 8: Conduct on-site tamping test to determine the actual tamping amount H2; Step 9: According to the comparison result between the estimated theoretical tamping amount H1 and the actual tamping amount H2, determine and analyze whether the tamping hammer model parameters are appropriate; (1) The error between the actual tamping amount H2 and the estimated theoretical tamping amount H1 is within 20%, indicating that the tamping hammer parameters initially determined are reasonable; (2) The actual tamping amount H2 is less than the estimated theoretical tamping amount H1 by more than 20%, indicating that the tamping hammer size is too large and the size of the lowest level tamping hammer combined structure piece needs to be reduced; (3) The actual tamping amount H2 is more than 20% greater than the estimated theoretical tamping amount H1, indicating that the tamping hammer is too small and the shearing effect on the soil is too large. The size of the lowest level tamping hammer combined structure piece needs to be reduced; Step 10: If the rammer model is not suitable, follow the adjustment principles of step 9, retry tamping from step 4, and simultaneously fine-tune the number of tamping times and tamping energy parameters until reasonable rammer model parameters are determined.

[0022] Compared with the prior art, the high-energy-level dynamic tamping combined rammer and the method for determining the model parameters proposed by the present invention have the following beneficial effects: (1) The combined rammer designed by the present invention has the characteristics of adjustable cross-sectional size and hammer weight and convenient transportation. Under the condition of 2.5m road width limit, an ordinary truck with a box length of 7.21m can meet the transportation requirements of the rammer split structure components. The theoretical maximum cross-sectional area of ​​the assembled rammer can reach 21.65m 2 , which is 4.41 times that of a conventional 2.5m diameter cylindrical rammer.

[0023] (2) The high-energy combined rammer designed in the present invention has a clear structure and is easy to assemble. The overall structure consists of a rammer split structure sheet, connecting bolts, a rammer hook structure, a rubber pad, etc. The combined rammer components can be reused and freely combined, and the strong tamping process under different types of strata conditions can be adjusted multiple times and conveniently.

[0024] (3) The method for determining the model parameters of the rammer proposed in the present invention is used together with the combined rammer to ensure that the tamping process parameters under different energy levels and formation conditions are in the optimal state range, effectively reducing the shearing effect of the rammer edge on the soil.

[0025] (4) The present invention adopts a regular triangle arrangement of tamping points. The bottom cross-section of the tamping hammer designed by the present invention is a regular hexagon. The soil at the centroid position of the three tamping points is easier to be reinforced.

[0026] (5) The combined rammer of the present invention has a large maximum cross-sectional area, which can reduce the number of lifting times and effectively improve the construction efficiency during full ramming construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings: Figure 1 It is a schematic diagram of an assembled combined rammer structure in the present invention; Figure 2 It is a schematic diagram of the assembled combined rammer structure 2 in the present invention; Figure 3 It is a schematic diagram of assembling the rammer combined structural piece in the present invention; Figure 4 It is a schematic diagram of the size parameters of the combined structural pieces of two adjacent layers of rammers in the present invention; Figure 5 It is a schematic diagram of the maximum size and transportation and stacking method of the split structural piece of the rammer in the present invention; Figure 6 It is a schematic diagram of the rammer hook structure in the present invention; Marked in the figure: 1. Rammer combined structural piece; 2. Rammer split structural piece; 3. Groove-type connecting hole; 301. Connecting hole shallow groove; 302. Connecting hole through groove; 4. Connecting bolt; 5. Rammer hook structure; 501. Hook bent rod; 502. Hook cross brace rod; 503. Hook bolt vertical rod; 6. Rubber pad. DETAILED DESCRIPTION

[0028] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention; it is obvious that the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments, and all other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making creative work are within the scope of protection of the present invention.

[0029] In the description of the present invention, it should be noted that the terms "upper", "lower", "inside", "outside", "top / bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0030] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "mounted / connected", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0031] The structural features of the present invention are now described in detail with reference to the accompanying drawings.

[0032] See also Figure 1-Figure 6A high-energy level strong tamping combined rammer includes a rammer combined structure piece 1, a rammer split structure piece 2, a groove-type connecting hole 3, a connecting hole shallow groove 301, a connecting hole through groove 302, a connecting bolt 4, a rammer hook structure 5, a hook bent rod 501, a hook cross brace rod 502, a hook bolt vertical rod 503, and a rubber pad 6. Among them, a plurality of rammer combined structure pieces 1 are stacked to form a multi-level rammer body with different sizes. When the combined rammer is assembled, the rammer combined structure pieces 1 of adjacent sizes can be combined into a pagoda-type structure in a hierarchical continuous or discontinuous order of "large at the bottom and small at the top"; or an inverted bolt-type structure can be formed in which the rammer combined structure piece 1 of the bottom layer is large in size and the rammer combined structure pieces 1 of each layer on the upper layer are of the same size. When the rammer combined structure pieces 1 of each layer are assembled, they are stacked with staggered seams and then connected by bolts to provide the structural integrity of the combined rammer. Each level of rammer composite structural piece 1 is composed of 6 pieces of rammer split structural pieces 2 of the same size, forming a regular hexagonal structure. Each layer is provided with 3 rammer split structural pieces 2. There are rubber pads 6 between two adjacent layers of rammer split structural pieces 2 and between each level of rammer composite structural pieces 1. The rubber pads 6 are in a regular triangle structure and are located on the surfaces on both sides of the rammer split structural piece 2 to play a buffering and protective role. The rammer composite structural piece 1 is respectively composed of the same pieces of rammer split structural pieces 2 to form a double-layer structure for splicing. The rammer split structural piece 2 is a rhombus, with 4 equal sides, one of which is an acute angle of 60°. The rammer split structural pieces 2 between the two layers of the rammer composite structural piece 1 are staggered and spliced, and the staggered rotation degree is 60°, so that the 6 rammer split structural pieces 2 between the two layers of the rammer composite structural piece 1 are interlocked.

[0033] The rammer split structure piece 2 is located on the splicing side, and 8 slot-type connection holes 3 for splicing and fixing are symmetrically arranged on the diagonal obtuse angle connecting line as the axis, and are symmetrically distributed on both sides of the diagonal obtuse angle connecting line. The slot-type connection holes 3 on the symmetrical side are grouped in two, and the angle between the two groups of slot-type connection holes 3 is α It is 60°, and the distance between each group of edge lines and diagonal obtuse angles of the rammer split structural pieces 2 on one side of the splicing is equal, so that the positions of the grooved connecting holes 3 on each level of the rammer split structural pieces 2 correspond to each other. After splicing, the grooved connecting holes 3 are symmetrically distributed on both sides of the diagonals of the rammer combination structural pieces 1, and the positions of the grooved connecting holes 3 on the rammer split structural pieces 2 of different sizes are the same. According to the control of the smallest level of size, it is ensured that the rammer split structural pieces 2 and the rammer combination structural pieces 1 of different sizes are convenient for assembly. The rammer split structural pieces 2 are made of steel. The groove-type connecting hole 3 is composed of a connecting hole shallow groove 301 and a connecting hole through groove 302. The connecting hole shallow groove 301 is arranged on the upper and lower surfaces of the rammer split structure piece 2, and is in a circular rectangular shape. The depth is not less than the nut thickness of the connecting bolt, and the width is not less than the working size of the fastening bolt sleeve. The connecting hole through groove 302 is in a rectangular shape, and the width is between the screw diameter and the nut diameter. The groove-type connecting hole 3 not only plays the role of fixed connection, but also simultaneously plays the role of exhausting and reducing the suction at the bottom of the pit.

[0034] It also includes a rammer hook structure 5, which consists of a hook bent rod 501, a hook cross brace rod 502 and a hook bolt vertical rod 503. The two hook bent rods 501 are vertically arranged to prevent the hook structure from deforming during lifting. The hook bolt vertical rod 503 is connected to the grooved connecting holes 3 of the rammer combination structure pieces 1 at each level. The rammer hook structure 5 is first installed on the topmost rammer combination structure piece 1 and then connected to other combination structure pieces.

[0035] As a preferred solution of this embodiment, the maximum size of the rammer split structure piece 2 is based on the road transportation width limit. w The geometric relationship calculation when the side length of the split structural piece is parallel to the length direction of the carriage is as follows: (1) In the formula, w max is the side length of the theoretically largest rammer combination structure piece 1; w Width limit for road transport.

[0036] Specifically, according to the road transport width limit of 2.5m, it can be known from formula (1) that the side length of the maximum first-level rammer combination structure piece 1 is 2.88m. Considering a certain margin, the side length of the rammer combination (split) structure piece is taken as 2.8m.

[0037] Specifically, when the rammer combination (split) structural piece with a side length of 2.8m is placed flat for transportation, the minimum length requirement for the transport vehicle is calculated according to the following formula: (2) Where a is the number of longitudinally placed pieces of the rammer split structure piece 2 when transported in a flat layout. l It is the longitudinal length after placement.

[0038] Specifically, two rammer split structure pieces 2 are placed on a plane for transportation. From formula (2), it can be seen that the minimum length of the carriage is 7 m.

[0039] Specifically, the size of the two adjacent rammer combination structure pieces 1 is determined according to the following formula: (3) Wherein, w1 is the side length of the regular hexagonal rammer combined structure piece 1 of the previous level; w2 is the side length of the regular hexagonal rammer combined structure piece 1 of the adjacent next level.

[0040] Specifically, the size parameters of the combined structural pieces of each level of rammers are calculated according to formula (3), and the thickness of each level of rammer split structural piece 2 is 5 cm, and the steel density is 7.85 t / m 3Without considering the reduced cross-section and weight of the bolt holes, the size, area and weight parameters of the combined (split) structural pieces of each level of rammer are summarized in the following table: Rammer combination structure sheet parameter table

[0041] As a preferred example of the present invention, it is planned to reinforce the foundation of collapsible loess site by high-energy level dynamic compaction. The dynamic compaction energy level to be selected is 12000 kN·m, the planned reinforcement depth is 12m, and the maximum effective lifting height of the on-site equipment is 20m. The porosity parameters of the original soil layer and the soil after reinforcement are as follows: Summary table of formation parameters

[0042] The present invention also proposes a method for determining the model parameters of a combined rammer, and the process is as follows: Step 1: According to the proposed dynamic compaction energy level and the maximum effective lifting height of the on-site equipment, determine the theoretical rammer mass according to the following formula: m .

[0043] (4) In the formula, M To strengthen the energy level, g is the acceleration due to gravity, m is the theoretical rammer mass, L In order to maximize the effective lifting height of the on-site equipment, a 10% margin should be reserved when preliminarily determining the hammer weight.

[0044] In this embodiment, the tamping energy level is 12000 kN·m, the maximum effective lifting height of the on-site equipment is 20m, and the gravity acceleration is 9.8N / kg. From formula (4), it can be known that the theoretical tamping hammer mass is 68t.

[0045] Step 2: Based on the static pressure requirements at the bottom of the rammer, preliminarily determine the size parameter range value of the bottom-level rammer composite structure piece 1.

[0046] (5) In the formula, w act is the side length of the lowest level rammer combined structure piece 1; w max is the maximum static pressure at the bottom of the rammer; w min It is the minimum static pressure at the bottom of the rammer.

[0047] In this embodiment, according to the Technical Specification for Treatment of Collapsible Loess Foundation by Dynamic Compaction (DBJ 61-9-2008), the static pressure of the hammer bottom is 20kPa~50kPa. wmax 50kPa, w min is 20 kPa. From formula (5), we can know that the dimension parameter range of the bottom ramming hammer composite structure piece 1 is w max is [2.26, 3.58] (unit: m).

[0048] Step 3: Based on the geological survey data and the depth of the foundation to be reinforced and the parameters of the foundation soil after reinforcement in the design documents, the theoretical value of the tamping amount is given according to the following formula.

[0049] (6) Where H1 is the estimated theoretical tamping amount; n 0i is the porosity of the i-th soil layer before dynamic compaction; n 1i is the porosity of the i-th soil layer under the expected dynamic compaction reinforcement quality; h i is the thickness of the i-th soil layer before dynamic compaction reinforcement; H0 is the total dynamic compaction foundation reinforcement depth.

[0050] In this embodiment, the depth of the foundation reinforced by dynamic compaction is 12m, and the number of strata n is 4. According to the strata parameter summary table and formula (6), the estimated theoretical compaction settlement of the first three layers of soil is 2.71m, the third layer is 0.18m, and the theoretical value of compaction settlement is 2.89m.

[0051] Step 4: Based on the theoretical rammer weight of 68t and the side length of the bottom-level composite structure piece w act In the interval [2.26, 3.58], combined with the parameter table of the rammer combination structural piece, it is preliminarily determined to use 1 two-level rammer combination structural piece, 5 three-level rammer combination structural pieces, 1 four-level rammer combination structural piece, and 1 six-level rammer combination structural piece.

[0052] Step 5: Based on the model and quantity of the rammer combination structural piece 1 preliminarily determined in step 4 and the parameter table of the rammer combination structural piece 1, calculate the actual rammer mass m1 to be 67.5t.

[0053] Step 6: Connect the selected 8 rammer combination structure pieces 1 into a whole by means of bolts, and install the rammer hook structure 3.

[0054] Step 7: Carry out preparatory work before trial tamping. According to the actual mass of the tamping hammer, determine the drop distance of the tamping hammer during trial tamping according to the following formula.

[0055] (7) In the formula, L 1 is the drop distance of the rammer during the test ramming, M To strengthen the energy level, g is the acceleration due to gravity, m 1 is the actual rammer mass.

[0056] In this embodiment, the tamping energy level is 12000 kN·m, the gravity acceleration is 9.8N / kg, the actual tamping hammer mass is 67.5t, and the tamping hammer drop distance during the test tamping can be calculated as 18.15m by formula (7).

[0057] Step 8: On-site trial tamping, assuming that the actual tamping settlement amounts are 2.0m, 2.9m and 3.8m respectively.

[0058] Step nine: Based on the comparison results of the estimated theoretical tamping sinking of 2.89m in step three and the actual trial tamping sinking in step eight, determine and analyze whether the tamping hammer model parameters are appropriate.

[0059] (1) If the actual tamping amount is 2.9 m, the estimated theoretical tamping amount error is 3.5%, indicating that the tamping hammer parameters preliminarily determined in step 4 are reasonable; (2) If the actual tamping amount is 2.0m, which is less than the estimated theoretical tamping amount of 30.8%, it means that the size of the lowest level tamping hammer combined structure piece in step 4 is too large. It is necessary to reduce the size of the lowest level tamping hammer combined structure piece and use the level 3 structure piece in the parameter table of tamping hammer combined structure piece 1 as the lowest layer; (3) If the actual tamping amount is 3.8 m, which is greater than the estimated theoretical tamping amount of 31.5%, it indicates that the size of the lowest level tamping hammer combined structure piece in step 4 is too small and the shearing effect of the tamping hammer edge on the soil is too large. It is necessary to increase the size of the lowest level tamping hammer combined structure piece and use the level 1 structure piece in the parameter table of the tamping hammer combined structure piece 1 as the lowest layer.

[0060] Step 10: If the rammer model parameters are appropriate, select this standard; otherwise, adjust the model parameters according to the test ramming results in step 9, retry ramming from step 4, and simultaneously fine-tune the ramming number, ramming energy and other strong ramming construction parameters until reasonable rammer model parameters are determined.

[0061] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention is described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A high-energy level strong tamping combined rammer, comprising a rammer combined structural piece (1), wherein a plurality of said rammer combined structural pieces (1) are stacked to form a rammer body of multiple levels with different sizes, characterized in that: The rammer combined structure piece (1) of each level is composed of a plurality of rammer separate structure pieces (2) of the same size, which are spliced ​​together to form a regular hexagonal structure; The rammer combined structure piece (1) is composed of the same pieces of rammer split structure pieces (2) at the top and bottom to form a double-layer structure; The rammer split structural piece (2) is located on the splicing side, and is symmetrically provided with a plurality of slot-type connection holes (3) for splicing and fixing, with the diagonal obtuse angle connecting line as the axis. The slot-type connection holes (3) on the symmetrical side are arranged in groups of two, and each group is at an equal distance from the edge line and the diagonal obtuse angle connecting line of the rammer split structural piece (2) on the splicing side, so that the positions of the slot-type connection holes (3) on each level of the rammer split structural piece (2) correspond to each other. After splicing, the slot-type connection holes (3) are symmetrically distributed on both sides of each diagonal line of the rammer combined structural piece (1); It also comprises a rammer hook structure (5), the rammer hook structure (5) comprising a hook bent rod (501), a hook cross brace rod (502) and a hook bolt vertical rod (503), the two hook bent rods (501) being arranged perpendicular to each other, and the hook bolt vertical rod (503) penetrating and connected to the grooved connection holes (3) of the rammer combined structure pieces (1) at each level.

2. A high-energy combined rammer according to claim 1, characterized in that: When assembling the rammer body, rammer combination structure pieces (1) of adjacent sizes are combined into a pagoda-like structure in a hierarchical continuous or discontinuous order of large at the bottom and small at the top. The rammer combination structure pieces (1) of each level are stacked with staggered seams and connected by bolts.

3. A high-energy combined rammer according to claim 2, characterized in that: The size of two adjacent rammer assembly structure pieces (1) is determined according to the following formula: ; In the formula, w1 is the side length of the regular hexagonal rammer combined structure piece (1) of the previous level; w2 is the side length of the regular hexagonal rammer combined structure piece (1) of the next level, and the area of ​​the next level rammer combined structure piece (1) is reduced by 25% compared with the previous level.

4. A high-energy combined rammer according to claim 1, characterized in that: When the rammer body is assembled, the bottom rammer combined structure piece (1) has a large size, and the upper rammer combined structure pieces (1) of each level have the same size, forming an inverted bolt-type structure, and the rammer combined structure pieces (1) of each level are stacked with staggered seams and connected by bolts.

5. A high-energy combined rammer according to claim 1, characterized in that: Each level of the rammer combined structural sheet (1) is composed of six rammer split structural sheets (2), and each layer is provided with three rammer split structural sheets (2). Rubber pads (6) are provided between two adjacent layers of the rammer split structural sheets (2) and between each level of the rammer combined structural sheets (1). The rubber pads (6) are in an equilateral triangle structure and are located on the surfaces of both sides of the rammer split structural sheets (2).

6. A high-energy combined rammer according to claim 1, characterized in that: The rammer split structural piece (2) is rhombus-shaped, one of the diagonals of which is an acute angle of 60°. The rammer split structural pieces (2) between two layers of the rammer combined structural piece (1) are staggered and spliced, and the staggered rotation degree is 60°, so that the six rammer split structural pieces (2) between the two layers of the rammer combined structural piece (1) are interlocked.

7. A high-energy combined rammer according to claim 1, characterized in that: The number of the groove-type connection holes (3) on the rammer split structural piece (2) is 8, which are symmetrically distributed on both sides of the diagonal obtuse angle connection line, in groups of two.

8. A high-energy combined rammer according to claim 1, characterized in that: The groove-type connecting hole (3) is composed of a connecting hole shallow groove (301) and a connecting hole through groove (302); the connecting hole shallow groove (301) is provided on the upper and lower surfaces of the rammer split structural piece (2), is in the shape of a round rectangle, has a depth not less than the thickness of the nut of the connecting bolt, and has a width not less than the working size of the fastening bolt sleeve; the connecting hole through groove (302) is in the shape of a rectangle, and has a width between the diameter of the screw rod and the diameter of the nut.

9. A high-energy combined rammer according to claim 1, characterized in that: The thickness of the rammer split structure piece (2) is not less than 5 cm, and the maximum size of the rammer split structure piece (2) is determined according to the road transport width limit. w The geometric relationship calculation when the side length of the rammer split structure piece (2) is parallel to the length direction of the carriage is as follows: ; In the formula, w max is the side length of the theoretical maximum-level rammer combination structure piece (1); w Width limit for road transport; When the theoretically largest level rammer combination structure piece (1) is placed flat for transportation, the minimum length requirement for the transport vehicle is calculated according to the following formula: ; Where a is the number of longitudinally placed blocks of the rammer split structure pieces when transported in a flat layout. l It is the longitudinal length after placement.

10. A method for determining model parameters of a high-energy level dynamic compaction combined rammer, used for the high-energy level dynamic compaction combined rammer as claimed in any one of claims 1 to 9, characterized in that: The specific steps include: Step 1: Determine the theoretical rammer mass m according to the planned dynamic tamping energy level and the maximum effective lifting height of the on-site equipment, where the theoretical rammer mass m is: ; M is the tamping energy level, g is the acceleration of gravity, m is the theoretical tamping hammer mass, and L is the maximum effective lifting height of the on-site equipment. When preliminarily determining the hammer weight, a 10% margin should be reserved; Step 2: According to the static pressure requirement of the rammer bottom, preliminarily determine the size parameter range of the rammer combination structure piece (1) at the bottom level: ; Wherein, wact is the side length of the bottom-level rammer composite structure piece (1); wmax is the maximum static pressure at the bottom of the rammer; wmin is the minimum static pressure at the bottom of the rammer; Step 3: Combine the geological survey data and the depth of the foundation to be reinforced and the parameters of the foundation soil after reinforcement in the design documents to give the theoretical value of the tamping amount, where the theoretical value of the tamping amount is: ; Where H1 is the estimated theoretical tamping settlement; n0i is the porosity of the i-th soil layer before dynamic tamping reinforcement; n1i is the porosity of the i-th soil layer under the expected dynamic tamping reinforcement quality; hi is the thickness of the i-th soil layer before dynamic tamping reinforcement; H0 is the total dynamic tamping foundation reinforcement depth; Step 4: preliminarily determine the model and quantity of the rammer combined structure pieces (1) to be assembled based on the theoretical rammer weight m and the side length wact interval of the bottom-level combined structure piece, combined with the corresponding relationship between the sizes of two adjacent groups of rammer combined structure pieces (1); Step 5: Calculate the actual rammer mass m1 based on the preliminarily determined rammer assembly structure piece (1) model and quantity; Step 6: Connect the rammer assembly structure pieces (1) into a whole by means of bolts, and install the rammer hook structure (5); Step 7: Carry out preparatory work before the test ramming. According to the actual mass of the ramming hammer, determine the ramming hammer drop distance during the test ramming. The ramming hammer drop distance is: ; Where, L1 is the drop distance of the rammer during the test, M is the ramming energy level, g is the gravitational acceleration, and m1 is the actual rammer mass; Step 8: Conduct on-site tamping test to determine the actual tamping amount H2; Step 9: According to the comparison result between the estimated theoretical tamping amount H1 and the actual tamping amount H2, determine and analyze whether the tamping hammer model parameters are appropriate; (1) The error between the actual tamping amount H2 and the estimated theoretical tamping amount H1 is within 20%, indicating that the tamping hammer parameters initially determined are reasonable; (2) The actual tamping amount H2 is less than the estimated theoretical tamping amount H1 by more than 20%, indicating that the tamping hammer is too large and the size of the lowest level tamping hammer combination structure piece (1) needs to be reduced; (3) The actual tamping amount H2 is more than 20% greater than the estimated theoretical tamping amount H1, indicating that the tamping hammer is too small and the shearing effect on the soil is too large. The size of the lowest level tamping hammer combination structure piece (1) needs to be reduced; Step 10: If the rammer model is not suitable, follow the adjustment principles of step 9, retry tamping from step 4, and simultaneously fine-tune the number of tamping times and tamping energy parameters until reasonable rammer model parameters are determined.