Method for treating special geology through combination of vibration gravel pile and preloading

Through the combined loading and pre-pressure treatment method of vibrating gravel piles, the problems of uneven settlement and high costs in traditional foundation treatment methods are solved, the bearing capacity and stability of the backfill water foundation is improved, construction is simplified, and later maintenance costs are reduced .

CN118932977AActive Publication Date: 2024-11-12CHINA CONSTR EIGHT ENG DIV CORP LTD

Patent Information

Application Number
CN202411339564.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2024-11-12
Estimated Expiration
2044-09-25

AI Technical Summary

Technical Problem

Traditional foundation treatment methods tend to cause uneven settlement when dealing with backfill foundations with high moisture content, high compression properties and low strength, and are costly and have a great impact on the environment.

Method used

Using the combined loading and pre-pressure treatment method of vibrating gravel piles, vibrating and gravel piles are placed in special geology, using hole-forming equipment to vibrating into holes in the clay and silt layer, and filling materials are vibrating to form pile foundations and piles. gravel cushion layer and sand cushion layer are laid, and pre-pressure and graded loading are carried out to improve the bearing capacity of the foundation.

Benefits of technology

It effectively improves the bearing capacity of the backfill water foundation, reduces the amount of settlement in the later stage, ensures the uniform and stable stress of the building, reduces the project cost, and simplifies the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932977A_ABST
    Figure CN118932977A_ABST
Patent Text Reader

Abstract

The invention discloses a method for treating special geology by combining a vibration gravel pile with preloading. The method comprises the following steps: measuring and positioning on the special geology to release a hole site of the vibration gravel pile; a hole-forming device is provided, a vibratory hammer of the hole-forming device is clamped on an impact double-pipe through a clamp, the impact double-pipe comprises an inner pipe and an outer pipe, the outer pipe is movably arranged outside the inner pipe in a sleeving mode, and the impact double-pipe is aligned to the hole site; starting the vibratory hammer to insert the lower end of the impact double pipe into the clay layer; the inner pipe is pulled out of the outer pipe, so that the outer pipe is arranged in special geology; a vibroflot forms holes in the clay layer through the outer pipe in a vibroflot mode, and a pile foundation is formed through padding and vibroflot; the outer pipe is pulled out, and a pile body is formed in the silt layer and the block gravel filler from bottom to top through vibration and impact; a broken stone hardcore is laid on the special geology; laying a sand cushion layer on the broken stone cushion layer; and a drainage plate is arranged on the sand cushion layer in a driving mode, and pre-pressing graded stacking is conducted. The problem that differential settlement is easily caused by a traditional foundation treatment method is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a method for treating special geology by combining a vibrating gravel pile with a preloading load. Background Art

[0002] With the rapid economic development and the acceleration of urbanization, land resources are becoming increasingly scarce. In order to meet the needs of urban construction, industrial development and port construction, water filling and land reclamation has become an important way to expand land resources. However, the backfilled waters are often backfilled with stones. During the backfilling process, the bottom silt is squeezed to form protrusions or lenses of varying sizes in the plane and space. Therefore, the backfill foundation usually has the characteristics of high water content, high compressibility and low strength. Traditional single foundation treatment methods such as dynamic compaction method and replacement method have certain limitations in treating such foundations. Dynamic compaction method may cause uneven settlement and vibration of the foundation; replacement method requires a large amount of high-quality filler, which is costly and may have an impact on the environment. Summary of the invention

[0003] In order to overcome the defects of the prior art, a method of treating special geological conditions by combining vibrating gravel piles with preloading is provided to solve the problem of uneven settlement easily caused by traditional foundation treatment methods.

[0004] To achieve the above object, a method for treating special geological conditions by using vibrating gravel piles combined with preloading is provided, comprising the following steps:

[0005] Measure and locate the hole position for vibrating gravel piles in special geology, the special geology including clay layer, silt layer and block gravel fill layer from bottom to top;

[0006] A hole-forming device is provided, the hole-forming device comprises a pile frame, a vibrating hammer and an impact double tube, the vibrating hammer is installed on the pile frame, the vibrating hammer is clamped on the impact double tube by a clamp, the impact double tube comprises an inner tube and an outer tube, the outer tube is movably sleeved on the outside of the inner tube, and the impact double tube is aligned with the hole position;

[0007] Turning on the vibrating hammer to insert the lower end of the impact double tube into the clay layer;

[0008] Pulling the inner tube out of the outer tube so that the outer tube is placed in the special geology;

[0009] Vibrating holes in the clay layer through the outer tube using a vibrator and vibrating fillers to form a pile foundation;

[0010] The outer tube is removed, and fillers in the muddy layer and the gravel filling are vibrated from bottom to top to form a pile body;

[0011] Laying a crushed stone cushion layer on the special geology;

[0012] Laying a sand cushion layer on the gravel cushion layer;

[0013] A drainage board is installed on the sand cushion layer and pre-compression and graded loading is performed.

[0014] Furthermore, when implementing the step of vibrating holes in the clay layer, it includes:

[0015] a. sinking the vibrator into the clay layer at a speed of 1 to 2 m / min to 30 to 50 cm below the designed reinforcement depth of the vibrating gravel pile;

[0016] b. Lifting the vibrator to the top of the clay layer at a lifting rate of 5 to 6 m / min;

[0017] c. Repeat steps a and b once or twice, and leave the vibrator at the bottom of the hole;

[0018] d. Clean the hole with circulating water.

[0019] Furthermore, the filler of the vibrating gravel pile material is any one of crushed stone, pebbles and slag.

[0020] Furthermore, the maximum particle size of the filler is less than or equal to 150 mm, the strength of the filler is not less than 30 MPa, and the mud content of the filler is not more than 5%.

[0021] Furthermore, the thickness of the crushed stone cushion layer is 0.3 mm.

[0022] Furthermore, the thickness of the sand cushion layer is 30 to 50 cm.

[0023] The beneficial effect of the present invention lies in that the method of treating special geological conditions by combining vibrating gravel piles with preloading can effectively improve the bearing capacity of the backfill water foundation through the compaction effect of the vibrating gravel piles and the combined effect of pile-soil and preloading to promote soil consolidation, thereby greatly reducing the settlement of the backfill foundation during later use, ensuring that all parts of the building are evenly stressed, and ensuring the stability and safety of the building.

[0024] The method of treating special geological conditions with vibrating gravel piles combined with preloading for preloading of the present invention can penetrate the upper stone layer and penetrate into the lower soil layer to form a composite foundation, thereby improving the overall performance of the foundation, such as special geological conditions with stones on top and mud on the bottom. Preloading for preloading can adjust the loading height and loading rate according to different geological conditions and engineering requirements to adapt to foundation treatment under special geological conditions. The method of treating special geological conditions with vibrating gravel piles combined with preloading for preloading is simple and quick to construct, does not require a large amount of mechanical equipment and manpower input, and reduces engineering costs. The method of treating special geological conditions with vibrating gravel piles combined with preloading for preloading of the present invention effectively improves the bearing capacity and stability of the foundation, reduces the cost of later maintenance and reinforcement, and saves engineering costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

[0026] Figure 1 A cross-sectional view of a special geology according to an embodiment of the present invention.

[0027] Figure 2 It is a cross-sectional view of the pre-compression loading according to an embodiment of the present invention.

[0028] Figure 3 The figure is a schematic diagram of the arrangement of the vibrating gravel piles according to an embodiment of the present invention.

[0029] Figure 4 The present invention is a schematic flow chart of the steps of a method for treating special geological conditions by using vibrating gravel piles combined with preloading. DETAILED DESCRIPTION

[0030] The present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant invention, rather than to limit the invention. It is also necessary to explain that, for ease of description, only the parts related to the invention are shown in the accompanying drawings.

[0031] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0032] Reference Figures 1 to 4 As shown, the present invention provides a method for treating special geological conditions by combining vibrating gravel piles with preloading, comprising the following steps:

[0033] S1. Measure and locate the hole position for placing the vibrating gravel pile 1 on the special geology, the special geology including a clay layer a, a silt layer b and a block gravel fill layer c from bottom to top.

[0034] In this embodiment, the special geology is an artificial island formed by land reclamation, and the marine sedimentary layer is directly backfilled without treatment. The backfill material is mainly blocks and crushed stones with clear edges and corners, a particle size of 20mm to 400mm, a small part of which has a particle size greater than 400mm, and a loose to slightly dense structure. This area is more than 1km away from the reclamation boundary and far away from the sea. It has the characteristics of high water content, large porosity, high compressibility and low bearing capacity.

[0035] See also Figure 3 As shown, vibrating gravel piles combined with preloading are used to treat the reclamation foundation. The vibrating gravel piles are arranged in a plum blossom shape, with a pile spacing of 2.5m, a pile diameter of 1.2m and a length of 25m.

[0036] Before drilling, the detection holes are laid out in a 10×10m grid. After the survey is completed, the results are recorded and a columnar diagram of the detection holes is drawn, indicating the thickness of the cover layer and the thickness of the silt in each area.

[0037] Before construction, clean and level the construction site to ensure that the site meets the construction requirements. Arrange the pile positions according to the designed pile layout, spacing and maintenance structure range, draw a plan layout, and number each pile. At the same time, inspect and maintain the construction machinery and equipment to ensure that they meet the use requirements. Calculate the required materials based on the design parameters of the vibrating gravel pile and preloading to determine the filler specifications and usage quantity, and purchase and store them as required.

[0038] S2. Provide a hole-forming device, which includes a pile frame, a vibrating hammer 2 and an impact double tube 3. The vibrating hammer 2 is installed on the pile frame. The vibrating hammer 2 is clamped on the impact double tube 3 by a clamp. The impact double tube 3 includes an inner tube and an outer tube. The outer tube can be movably sleeved on the outside of the inner tube to align the impact double tube 3 with the hole position.

[0039] After measuring and positioning, according to the control pile and design drawing, the vibrating gravel pile hole is placed, and the vibrating hammer is installed on the pile frame. The impact double pipe is aligned with the pile position.

[0040] S3, turn on the vibrating hammer 2 to insert the lower end of the impact double tube 3 into the clay layer a.

[0041] Specifically, the position and verticality of the pile frame are adjusted to ensure that the plane error of the pile position is no more than 50mm and the verticality error is no more than 1%. The vibrating hammer is turned on to make the impact double tube pass through the block gravel layer and the silt layer through the vibration impact effect to reach the underlying clay layer.

[0042] S4. Pull the inner tube out of the outer tube so that the outer tube can be placed in special geology.

[0043] The vibrating hammer stops vibrating, the clamp is loosened, and the position of the clamp is adjusted so that the clamp clamps the inner tube. The vibrating hammer is lifted up to pull the inner tube out of the outer tube, and the outer tube is left in the hole to protect the wall, block the gravel layer and the silt layer to complete the hole. After pulling out the inner tube, keep the inner tube on the pile frame, move the pile frame away from the construction hole, and wait for the next step of construction.

[0044] S5. Vibrate holes in the clay layer a through the outer tube using the vibrator 4 and vibrate the filler to form a pile foundation.

[0045] As a preferred embodiment, when implementing the step of vibrating holes in the clay layer a, it includes:

[0046] a. Sink the vibrator 4 into the clay layer a at a speed of 1 to 2 m / min to a depth of 30 to 50 cm below the designed reinforcement depth of the vibrating gravel pile 1;

[0047] b. Lift the vibrator 4 to the top of the clay layer at a lifting rate of 5 to 6 m / min;

[0048] c. Repeat steps a and b once or twice, and leave the vibrator 4 at the bottom of the hole;

[0049] d. Clean the hole with circulating water.

[0050] Specifically, a hole is vibrated in the clay layer, and a 180kW vibrator is hoisted to the top of the clay layer with a crawler crane. The position of the vibrator is adjusted to ensure that the plane error of the pile position is no more than 50mm. Start the crane winch to slowly sink the vibrator in the clay layer at a speed of 1 to 2m / min until it reaches 30 to 50cm below the designed reinforcement depth. At this time, the vibrator is lifted to the top of the clay layer, and the lifting rate can be increased to 5 to 6m / min. Repeat the above steps one or two times, and finally stop the vibrator 30 to 50cm above the designed reinforcement depth, use circulating water to thin the mud in the hole, and complete the hole cleaning.

[0051] The diameter of the impact hole is 500-800mm, and the verticality deviation of the hole is not more than 1%.

[0052] After the vibrator is installed, length marks should be made on the equipment, with 0.5m as a section, so that the operator can control the depth of the vibrator into the soil accordingly.

[0053] When vibrating piles in clay layers, fillers are poured into the hole, and the vibrator is sunk into the fillers for compaction. At this time, the current value of the vibrator increases rapidly. When the compaction current reaches the specified value, the pile body at this depth is considered to have been compacted. If the compaction current does not reach the specified value, the vibrator needs to be lifted to continue to fill the hole, and then the vibrator is sunk to continue compaction. Repeat this operation until the compaction current at this depth reaches the specified value. After one section of gravel pile is completed, the vibrator is lifted to construct the next section of gravel pile, and the density is increased in sections upwards in sequence until the top surface of the clay layer, completing the construction of gravel piles in the clay layer.

[0054] The depth of vibration drilling in clay layers should be 0.3 to 0.5 m higher than the designed treatment depth to prevent high-pressure water from disturbing the foundation soil below the designed treatment depth.

[0055] S6. Remove the outer pipe and vibrate the fillers in the silty layer b and the gravel filling from bottom to top to form the pile body.

[0056] Specifically, when pulling out the outer tube, the pile frame and vibrating hammer used to pull out the inner tube are moved to the construction hole position, and the inner tube is hoisted on the top of the pile frame by the auxiliary winch and kept still. The vibrating hammer is lowered to the hole mouth, and the clamp on the vibrating hammer clamps the outer tube, and then the vibrating hammer is lifted up to vibrate and pull out the outer tube. As the outer tube is gradually pulled up, the inner and outer tubes are reassembled together. The position of the vibrating hammer pile clamp is adjusted so that the pile clamp clamps the inner and outer tubes at the same time, and the pile frame is moved to the next construction point for impact hole construction.

[0057] When vibrating piles in the mud layer, after removing the vibrating hammer, use a crawler crane to lift the 180kW vibrator to the top of the gravel backfilled in the hole, adjust the position of the vibrator to ensure that the pile position plane error is no more than 50mm. Start the crane winch to slowly sink the vibrator in the soil at a speed of 1 to 2m / min until it reaches the bottom of the mud layer;

[0058] When vibrating piles in the gravel layer, the vibrator is continuously lifted to the bottom of the gravel layer. Filling material is poured into the hole, and the vibrator is sunk into the filling material for compaction. After one section of gravel pile is completed, the vibrator is lifted up to construct the next section of gravel pile, and the piles are compacted in sections upwards until the designed elevation of the pile top is reached, completing the construction of gravel piles in the gravel layer.

[0059] As a preferred embodiment, the filler material of the vibrating gravel pile 1 is any one of crushed stone, pebbles and slag.

[0060] The maximum particle size of the filler is less than or equal to 150mm, the strength of the filler is not less than 30MPa, and the mud content of the filler is not more than 5%.

[0061] The filler should be well graded, with a maximum particle size of ≤20cm, natural compressive strength ≥30MPa, softening coefficient ≥0.75, and mud content ≤10%. Silt, cultivated soil, frozen soil, expansive soil, and soil with an organic matter content greater than 5% shall not be used.

[0062] As a preferred implementation method, gravel is filled and compacted at a depth of about 1 m from the ground surface to ensure the density of the pile top.

[0063] S7. Lay a crushed stone cushion layer 5 on special geology.

[0064] A gravel cushion layer with a thickness of 0.3m is set on the top of the pile, and well-graded gravel is used for paving. After paving, the cushion layer is vibrated and rolled to make it level.

[0065] S8. Lay a sand cushion layer on the gravel cushion layer 5.

[0066] Before laying the sand cushion layer, quality inspection procedures such as foundation strength or foundation bearing capacity inspection are carried out.

[0067] A sand cushion layer is laid on the foundation surface, with a thickness of generally 30 to 50 cm.

[0068] After laying the sand cushion layer, the drainage board is installed. The width of the drainage board is between 100 and 400 mm, and the thickness is between 3 and 8 mm.

[0069] Monitoring points are set up in the preloading area, including settlement observation points, pore water pressure observation points, horizontal displacement observation points, etc., to ensure that the deformation and consolidation of the foundation can be accurately monitored.

[0070] Carry out graded loading according to design requirements and strictly control the height and loading rate of each level of loading.

[0071] During the preloading process, the monitoring points are regularly observed to record the data of foundation settlement, pore water pressure, horizontal displacement, etc. Based on the monitoring results, the preloading height and loading rate are adjusted in time to ensure the stability and safety of the foundation.

[0072] The thickness of each layer shall not exceed 500mm, and the height difference between adjacent surfaces shall not exceed 200mm.

[0073] When the settlement rate of the foundation is lower than the design settlement rate for several consecutive days, or when the consolidation degree of the foundation reaches the design requirements, graded unloading is carried out.

[0074] Use a bulldozer to remove debris and obstacles on the surface of the site and perform preliminary site leveling; use a roller to compact the site; the rolling operation follows the principle of from the edge to the center and from low to high to ensure that the site is compacted evenly and densely.

[0075] After the reinforcement is completed, the static load test method is used to detect the bearing capacity of the foundation in the reinforced area.

[0076] The method of treating special geological conditions by combining vibrating gravel piles with preloading can effectively improve the bearing capacity of the backfilled water foundation through the compaction effect of the vibrating gravel piles and the combined effect of pile-soil and preloading to promote soil consolidation, greatly reduce the settlement of the backfilled foundation during later use, ensure that all parts of the building are evenly stressed, and ensure the stability and safety of the building.

[0077] The method of treating special geological conditions with vibrating gravel piles combined with preloading for preloading of the present invention can penetrate the upper stone layer and penetrate into the lower soil layer to form a composite foundation, thereby improving the overall performance of the foundation, such as special geological conditions with stones on top and mud on the bottom. Preloading for preloading can adjust the loading height and loading rate according to different geological conditions and engineering requirements to adapt to foundation treatment under special geological conditions. The method of treating special geological conditions with vibrating gravel piles combined with preloading for preloading is simple and quick to construct, does not require a large amount of mechanical equipment and manpower input, and reduces engineering costs. The method of treating special geological conditions with vibrating gravel piles combined with preloading for preloading of the present invention effectively improves the bearing capacity and stability of the foundation, reduces the cost of later maintenance and reinforcement, and saves engineering costs.

[0078] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, the above features are replaced with (but not limited to) technical features with similar functions disclosed in the present application.

Claims

1. A method for treating special geological conditions by using vibrating gravel piles combined with preloading, characterized in that: The following steps are involved: Measure and locate the hole position for vibrating gravel piles in special geology, the special geology including clay layer, silt layer and block gravel fill layer from bottom to top; A hole-forming device is provided, the hole-forming device comprises a pile frame, a vibrating hammer and an impact double tube, the vibrating hammer is installed on the pile frame, the vibrating hammer is clamped on the impact double tube by a clamp, the impact double tube comprises an inner tube and an outer tube, the outer tube is movably sleeved on the outside of the inner tube, and the impact double tube is aligned with the hole position; Turning on the vibrating hammer to insert the lower end of the impact double tube into the clay layer; Pulling the inner tube out of the outer tube so that the outer tube is placed in the special geology; Vibrating holes in the clay layer through the outer tube using a vibrator and vibrating fillers to form a pile foundation; The outer tube is removed, and fillers in the muddy layer and the gravel filling are vibrated from bottom to top to form a pile body; Laying a crushed stone cushion layer on the special geology; Laying a sand cushion layer on the gravel cushion layer; A drainage board is installed on the sand cushion layer and pre-compression and graded loading is performed.

2. The method for treating special geological conditions by using vibrating gravel piles combined with preloading according to claim 1 is characterized in that: When implementing the step of vibrating and forming holes in the clay layer, it includes: a. sinking the vibrator into the clay layer at a speed of 1 to 2 m / min to 30 to 50 cm below the designed reinforcement depth of the vibrating gravel pile; b. Lifting the vibrator to the top of the clay layer at a lifting rate of 5 to 6 m / min; c. Repeat steps a and b one or two times, and leave the vibrator at the bottom of the hole; d. Clean the hole with circulating water.

3. The method for treating special geological conditions by using vibrating gravel piles combined with preloading according to claim 2 is characterized in that: The filler of the vibrating gravel pile material is any one of crushed stone, pebbles and slag.

4. The method for treating special geological conditions by using vibrating gravel piles combined with preloading according to claim 3 is characterized in that: The maximum particle size of the filler is less than or equal to 150 mm, the strength of the filler is not less than 30 MPa, and the mud content of the filler is not more than 5%.

5. The method for treating special geological conditions by using vibrating gravel piles combined with preloading according to claim 1 is characterized in that: The thickness of the crushed stone cushion layer is 0.3 mm.

6. The method of treating special geological conditions by using vibrating gravel piles and preloading as claimed in claim 1 is characterized in that: The thickness of the sand cushion layer is 30 to 50 cm.

Citation Information

Patent Citations

  • Method for vibration impact holing and pile forming

    CN106337414A

  • Construction method for composite foundation covered with hillstone layer and underlying soft soil vibro-replacement gravel pile

    CN116289862A

  • Method for rapidly constructing composite foundation through gravel expanding piles

    CN118257244A

  • Method for constructing composite foundation through gravel piles and ballast drainage mode

    CN118309042A

  • Method for reinforcing soft ground by post-grouting combined with air-boosted vacuum preloading

    US20240133144A1

Cited By

  • Method for constructing gravel pile composite foundation through silt extrusion and water flushing replacement combined technology

    CN122428635A

  • A method for constructing a gravel pile composite foundation by using a combined dredging and water replacement technology

    CN122428635B