Anti-floating anchor rod based on socket type segmented prefabricated grouting body
Through the plug-in sectioned prefabricated grout body and sealing structure, the problems of the construction complexity and insufficient side friction resistance of traditional floating anchors are solved, the resistance to pull-up bearing capacity and construction quality are improved, and the service life of the anchors is extended.
Patent Information
- Application Number
- CN202411131627.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-08-16
AI Technical Summary
The construction process of traditional prestressed floating anchors is complicated and it is difficult to ensure the construction quality. The side friction resistance between the grouting body and the holding layer is not fully utilized, resulting in insufficient pull-up bearing capacity, which can easily lead to early failure of the anchor.
Adopt the anti-floating anchor design based on the plug-in section prefabricated grouting body, and prefabricated multi-stage grouting body through the factory, and use bondless steel strands and sealing rings to form a sealing structure during the construction process, making full use of grouting body and holding force The lateral friction resistance of the layer improves the resistance to pull-up bearing capacity.
The controllability of construction quality and the strength of the grouting body have been improved, the pull-up bearing capacity has been significantly improved, the service life of the anchor rod has been extended, and the risk of anchor rod failure has been reduced.
Smart Images

Figure CN118932996A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an anti-floating anchor rod, in particular to an anti-floating anchor rod based on a socket-and-spigot type segmented prefabricated grouting body. Background Art
[0002] The application of prestressed anti-floating anchor rods in engineering is to solve the problem of buildings floating due to groundwater pressure. After the prestress is applied, the pressure-type prestressed anti-floating anchor rod becomes an active force-bearing rod, and the anchor rod is in a compressed state throughout its life cycle, without the concern of cracking of the grouting body and causing corrosion of the rod body. However, traditional prestressed anti-floating anchor rods have some problems and limitations during the construction process, which mainly include:
[0003] (1) Complexity of construction process: The traditional prestressed anti-floating anchor construction process involves multiple steps and requires precise operation and control, which increases the difficulty of construction and the requirements for technicians.
[0004] (2) Water seepage hazard: Since the anchor rod needs to pass through the foundation soil layer, if it is not properly sealed, water may penetrate through the holes of the anchor rod, thus affecting the waterproof performance of the structure. When using cast-in-place grouting, due to the complex environment in the hole, there are adverse conditions such as groundwater overflow, water gushing, and string holes, which can easily cause discontinuous and incomplete grouting of the grouting body and strength reduction. In the subsequent anchor cable working stage, the grouting body is prone to corrosion and water vapor intrusion. Under long-term action, the anchor rod will rust and fail.
[0005] (3) Defects in bearing capacity: The pull-out bearing capacity of the anti-floating anchor rod mainly comes from two parts. One is the prestress of the prestressed transfer device on the grouting body; the other is the lateral friction between the grouting body and the bearing layer. In the prior art, the grouting body of the anti-floating anchor rod is cast in place as a whole. During the anchor tensioning stage, the upper part of the grouting body is squeezed by the prestressed transfer device, and the lower part is squeezed by the extrusion anchor. The grouting body is in a self-balanced state as a whole, and no effective lateral friction is formed between the surrounding bearing layer. At the same time, in the actual construction process, the grouting body is often affected by many factors, and its strength is reduced. In addition, when the bottom plate is subjected to buoyancy, the extrusion anchor position at the lower end of the grouting body usually suffers local concrete crushing and damage first, which causes the anti-floating anchor rod to fail prematurely. Similarly, the lateral friction between the grouting body and the bearing layer is not fully utilized. Summary of the invention
[0006] In view of the above problems, the present invention provides an anti-floating anchor rod based on a socket-type segmented prefabricated grouting body to solve the problems that the existing anti-floating anchor rod has complex construction technology, it is difficult to ensure the construction quality of cast-in-place grouting, and the side friction resistance between the grouting body and the bearing layer cannot be effectively exerted after construction.
[0007] The present invention is achieved through the following technical solutions.
[0008] An anti-floating anchor rod based on a socket-type segmented prefabricated grouting body, comprising a prestressed transmission device and anchorage arranged in the basement floor, unbonded steel strands, upper threaded bars, a steel pad, lower threaded bars and prestressed bar extrusion anchors respectively connected to the upper and lower surfaces of the steel pad, characterized in that it also comprises a socket inner sealing ring, a socket outer sealing ring, and multiple sections of prefabricated grouting bodies arranged in the anchoring holes and connected in sequence from top to bottom; the upper and lower connecting ends of the prefabricated grouting bodies of adjacent sections are respectively provided with protruding plugs and recessed slots that fit in with each other; the multiple sections of the prefabricated grouting bodies are reserved with threading holes and grouting holes that connect with each other from top to bottom, a grouting diffusion cavity connected to the grouting holes, and a plurality of grouting guide holes; the plurality of grouting guide holes laterally pass through the prefabricated grouting bodies One end of the slurry is connected to the grouting diffusion chamber, and the other end is connected to the anchor hole; the inner side of the socket outer sealing ring is sealed and connected to the plug-in seam on the periphery of the raised plug and the recessed slot, and the outer side is in contact with the hole wall of the anchor hole; the socket inner sealing ring is reserved with a through hole matching the threading hole and the grouting hole, and the socket inner sealing ring is sealed and connected to the plug-in seam at the center position of the raised plug and the recessed slot; the steel pad, lower threaded ribs and prestressed rib extrusion anchor are reserved at the bottom of the lowest prefabricated grouting body, the upper threaded ribs are reserved at the top of the upper prefabricated grouting body, one end of the unbonded steel strand is reserved at the bottom of the lowest prefabricated grouting body and is connected to the prestressed rib extrusion anchor, and the other end passes through the threading holes of each prefabricated grouting body from bottom to top in sequence to be connected to the anchor.
[0009] Preferably, a grouting pipe is connected to the top of the grouting hole of the uppermost prefabricated grouting body, and the grouting pipe passes through the grouting holes of each section of the prefabricated grouting body and extends to the bottom of the anchor hole.
[0010] Preferably, the present invention further comprises an inverted cone-shaped frame, which is reserved at the bottom of the lowest prefabricated grouting body, and the upper end of the inverted cone-shaped frame is fixedly connected to the steel base plate, and the lower end extends to the outside of the lowest prefabricated grouting body.
[0011] Preferably, the bottom of the prefabricated grouting body in the lowest section is in a cone shape.
[0012] Preferably, a layer of glass fiber mesh is adhered to the surface of the prefabricated grouting body or a concave-convex pattern is provided.
[0013] Preferably, the diameter of the prefabricated grouting body is 4 to 5 cm smaller than the diameter of the anchor hole.
[0014] Preferably, the grouting holes and the grouting diffusion chamber are arranged at the axial center position of the prefabricated grouting body; the middle part of the cross-section of the grouting diffusion chamber is cylindrical, and the upper and lower ends are inverted cones; 3 to 4 grouting guide holes are evenly arranged along the circumferential direction in the cross-section of the prefabricated grouting body, and are connected to the middle part of the grouting diffusion chamber.
[0015] Preferably, the notch portion of the notch slot and the convex portion of the convex plug are both in the shape of an inverted conical column, and the circumferential sides of the notch slot and the convex plug are provided with socket convex edges that abut against each other.
[0016] Preferably, the prefabricated grouting body is arranged in 3 to 4 sections, and the length of the prefabricated grouting body in the lowest section is greater than that of the remaining sections.
[0017] Preferably, upper and lower edges of the through hole in the socket inner sealing ring that matches the threading hole are provided with sealing clamps that can just fit into the gap between the unbonded steel strand and the threading hole.
[0018] Preferably, the socket inner sealing ring, the socket outer sealing ring and the sealing clamp ring are all made of EPDM rubber.
[0019] Compared with the prior art, the beneficial effects of the present invention include at least:
[0020] (1) The present invention adopts factory-prefabricated grouting body, the casting and curing quality of which is controllable, and the grouting body has high strength and no cracking.
[0021] (2) The present invention makes full use of the lateral friction between the grouting body and the bearing layer, so that the pull-out bearing capacity of the anti-floating anchor is greatly improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 This is a schematic diagram of the main structure of the anti-floating anchor rod of the present invention;
[0023] Figure 2 This is a schematic diagram of the main structure of the anti-floating anchor rod after grouting of the present invention;
[0024] Figure 3 This is a schematic diagram of the main structure of the lowest prefabricated grouting body;
[0025] Figure 4 This is a schematic diagram of the main structure of the uppermost prefabricated grouting body;
[0026] Figure 5 This is a schematic diagram of the main structure of the prefabricated grouting body in the middle;
[0027] Figure 6 for Figure 5 Cross-section at AA in the middle;
[0028] Figure 7 It is a schematic diagram of the cross-sectional three-dimensional structure of the prefabricated grouting body;
[0029] Figure 8 Schematic diagram of the cable threading for the prefabricated grouting body;
[0030] Fig. 9 It is a schematic diagram of the sockets and spigots of the adjacent prefabricated grouting bodies;
[0031] Fig.10 This is a schematic diagram of the main structure of the socket inner sealing ring;
[0032] Fig.11 It is a top view of the inner sealing ring of the socket;
[0033] Fig.12 It is the force diagram of the uppermost grouting anchoring section;
[0034] Fig.13 It is the force diagram of the grouting anchor section in the middle;
[0035] Fig.14 It is the force diagram of the lowest grouting anchoring section;
[0036] Fig.15 is a schematic diagram of the structure of a cone-shaped skeleton;
[0037] Fig.16 This is a schematic diagram of grouting guided by a grouting pipe;
[0038] The meanings of the marks in the above figure are: prestressed transmission device 1, anchor 2, unbonded steel strand 3, prefabricated grouting body 4, raised plug 401, raised portion 4011, recessed slot 402, socket flange 4021, recessed portion 4022, grouting diffusion cavity 403, grouting guide hole 404, threading hole 405, grouting hole 406, steel pad 5, upper threaded rib 6, lower threaded rib 7, prestressed rib extrusion anchor 8, socket inner sealing ring 9, through hole 901, sealing clamp 9011, socket outer sealing ring 10, basement floor 11, anchor hole 12, grouting pipe 13, PVC protective pipe 14, annular cavity section 15, grouting anchor section 16, basement floor 17, concrete cushion layer 18, inverted cone skeleton 19. DETAILED DESCRIPTION
[0039] To facilitate understanding of the present invention, the present invention will be described more comprehensively below with reference to the relevant drawings. Several embodiments of the present invention are given in the drawings, but the present invention can be implemented in different forms and is not limited to the embodiments described in the text. On the contrary, these embodiments are provided to make the content disclosed in the present invention more thorough and comprehensive.
[0040] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by technicians in the technical field to which the present invention belongs. The terms used in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.
[0041] The present invention is further described in detail below in conjunction with the accompanying drawings.
[0042] Example 1
[0043] An anti-floating anchor based on a socket-type segmented prefabricated grouting body, see Figures 1 to 11 , including a prestressed transfer device 1 and an anchor 2 arranged in a basement floor 11, an unbonded steel strand 3, an upper threaded rib 6, a steel pad 5, a lower threaded rib 7 and a prestressed rib extrusion anchor 8 respectively connected to the upper and lower surfaces of the steel pad 5, a socket inner sealing ring 9, a socket outer sealing ring 10, and a plurality of sections of prefabricated grouting bodies 4 arranged in an anchor hole 12 and connected sequentially from top to bottom; wherein the upper and lower connecting ends of the prefabricated grouting bodies 4 of adjacent sections are respectively provided with a protruding plug 401 and a recessed slot 402 that are plugged in and matched with each other; the central position of the inner portion of the plurality of sections of the prefabricated grouting bodies 4 is reserved with threading holes 4 that are connected to each other from top to bottom. 05 and grouting hole 406, a grouting diffusion cavity 403 connected to the grouting hole 406, and a plurality of grouting guide holes 404; a plurality of the grouting guide holes 404 horizontally pass through the prefabricated grouting body 4, one end of which is connected to the grouting diffusion cavity 403, and the other end is connected to the anchor hole 12; the inner side of the socket outer sealing ring 10 is sealed and connected to the plug-in seam around the protruding plug 401 and the recessed slot 402, and the outer side is in contact with the hole wall of the anchor hole 12; the socket inner sealing ring 9 is reserved with a through hole 901 matching the threading hole 405 and the grouting hole 406, and the socket inner sealing ring 9 is sealed and connected to the protruding plug 401, ... sealed and connected to the protruding plug 401, the recessed slot 402, and the inner side is in contact with the inner side of the socket inner sealing ring 9. 02 The plug-in joint at the center position is sealed and connected; the steel pad 5, the lower threaded rib 7 and the prestressed rib extrusion anchor 8 are reserved at the bottom of the lowest prefabricated grouting body 4, and the upper threaded rib 6 is reserved at the top of the upper prefabricated grouting body 4. One end of the unbonded steel strand 3 is reserved at the bottom of the lowest prefabricated grouting body 4 and connected to the prestressed rib extrusion anchor 8, and the other end passes through the threading holes 405 of each prefabricated grouting body 4 from bottom to top in sequence and is connected to the anchor 2; in the above structure, the diameters of the multiple sections of the prefabricated grouting body 4 are the same and slightly smaller than the diameter of the anchor hole 12, so that the prefabricated grouting body 4 can be smoothly penetrated into the anchor hole 12; the socket inner sealing ring 9 is used to seal the plug-in seam at the center of the protruding plug 401 and the recessed slot 402 to prevent the grouting body from penetrating into the threading hole 405 when flowing through the grouting hole 406 of the adjacent section; the outer diameter of the socket outer sealing ring 10 is the same as or slightly larger than the diameter of the anchor hole 12, so as to isolate the cavity formed by the side wall of the prefabricated grouting body 4 and the hole wall of the anchor hole 12 into annular cavity sections 15 corresponding to each prefabricated grouting body 4 in the upper and lower sections, and also prevent the cement mortar flowing into the annular cavity section 15 from infiltrating back into the threading hole 405 from the outside;
[0044] The construction steps of the anti-floating anchor rod of the present invention are as follows:
[0045] S1. Pad construction and drilling: First, the concrete pad is constructed, and then the anchor holes 12 are drilled according to the design requirements;
[0046] S2. Prefabrication of socket-type prefabricated grouting bodies in factories: Prefabricate multiple sections of prefabricated grouting bodies 4 separately in factories; when prefabricating multiple sections of prefabricated grouting bodies 4, please refer to Figure 4 , prefabricate the upper threaded bar 6 on the top of the uppermost prefabricated grouting body 4, see Figure 3 , prefabricate the steel plate 5, the lower threaded bar 7 and the prestressed bar extrusion anchor 8 at the bottom of the lowest prefabricated grouting body 4, prefabricate one end of the unbonded steel strand 3 at the bottom of the lowest prefabricated grouting body 4 and connect it to the prestressed bar extrusion anchor 8, and reserve the other end outside the lowest prefabricated grouting body 4 to form a free end;
[0047] S3, Prefabricated grouting body through the cable: please refer to Fig. 9 When all the prefabricated grouting bodies 4 are prefabricated, the unbonded steel strands 3 are used as guides to thread the prefabricated grouting bodies 4 into a whole. The specific method is to thread the free ends of the unbonded steel strands 3 reserved in the lowest prefabricated grouting body 4 into the threading holes 405 of the remaining prefabricated grouting bodies 4 from bottom to top, and at the same time, the socket inner sealing ring 9 and the socket outer sealing ring 10 are installed between the upper and lower connecting ends of the adjacent prefabricated grouting bodies 4. At this time, the grouting holes 406 in the multiple prefabricated grouting bodies 4 are connected from top to bottom, and are threaded into a whole through the unbonded steel strands 3;
[0048] S4. Initial tensioning of anchors: please refer to Figure 1 , lower the multi-section prefabricated grouting body 4 formed as a whole by the cable threading to a suitable position in the anchor hole 12, then install the prestressed stress transfer device 1 and the anchor 2, and after the anchor is threaded, connect the unbonded steel strand 3 with the anchor 2 for preliminary tensioning, so that the multi-section prefabricated grouting body 4 is socket-fastened, and a seal is formed by the socket inner sealing ring 9 and the socket outer sealing ring 10 to prevent cement mortar from penetrating into the threading hole 405 from the connection seam of adjacent prefabricated grouting bodies 4 during grouting;
[0049] S5. Grouting: Please refer to Figure 2 , cement mortar is injected into the top of the grouting hole 406 in the uppermost prefabricated grouting body 4, and the cement mortar is transported to each prefabricated grouting body 4 along the grouting holes 406 that penetrate up and down in the multiple sections of prefabricated grouting bodies 4, and is injected into the corresponding annular cavity section 15 formed by the side wall of the corresponding section of the prefabricated grouting body 4, the socket outer sealing ring 10 at the upper and lower ends of the prefabricated grouting body 4 and the hole wall of the anchor hole 12 through the grouting diffusion cavity 403 and the plurality of grouting guide holes 404; after the annular cavity section 15 is filled with cement mortar and solidified, the cement mortar in the annular cavity section 15 will bond with the prefabricated grouting body 4 at the corresponding position to form a corresponding grouting anchoring section 16;
[0050] S5, tensioning and locking: continue tensioning the steel strands, lock the unbonded steel strands 3 on the anchor 2, and cut the excess steel strands; since the socket inner seal ring 9 and the socket outer seal ring 10 are arranged between the adjacent sections of the prefabricated grouting body 4, during the tensioning process of the steel strands, the elastic deformation of the seal ring can provide displacement space for the slight movement of each grouting anchoring section 16, so as to form the anchor rod side friction resistance in advance during the tensioning and anchoring stage of the steel strands;
[0051] The force model of the prestressed anti-floating anchor in the prior art:
[0052] 1. Steel strand tensioning and anchoring stage
[0053] For traditional prestressed anti-floating anchors, when the unbonded steel strands 3 are tensioned, the prestressed transfer device 1 generates a downward pressure, and the prestressed tendon extrusion anchor 8 at the lower part of the steel strands generates an upward pressure on the grouting body. The grouting body as a whole is in a self-balanced state, and the friction between the grouting body and the bearing layer is 0.
[0054] 2. Anti-floating anchor in working condition
[0055] For traditional prestressed anti-floating anchor rods, when the basement floor is affected by the buoyancy of groundwater, the floor deforms upward, and the prestressed transmission device is lifted upward together, the prestressed pressure of the prestressed transmission device on the grouting body is reduced, and the stress of the steel strand continues to increase, driving the prestressed tendon extrusion anchor 8 to squeeze the lower grouting body until the grouting body is partially crushed and damaged, and the extrusion anchor fails. At this time, there are:
[0056] F 浮 =F f +F N
[0057] In the formula, F 浮 is the groundwater buoyancy, F N F is the partial preload of the anti-floating anchor. f It is the friction force between the grouting body and the bearing layer.
[0058] However, since the friction between the grouting body and the bearing layer is only generated during the working stage of the anti-floating anchor, under the condition of high prestress, the concrete at the anchor position will be crushed and damaged, which will lead to the failure of the anti-floating anchor in advance, and the side friction resistance of the anchor will not be fully exerted.
[0059] The force model of the anti-floating anchor rod of the present invention is:
[0060] 1. Steel strand tensioning and anchoring stage
[0061] In this embodiment, the number of prefabricated grouting bodies 4 is three sections. When the present invention is prefabricated in sections in the factory according to the cushion construction and drilling, the socket-type prefabricated grouting body is prefabricated in sections, the prefabricated grouting body is threaded, anchored and tensioned, and grouting steps are completed, because the grouting body is prefabricated in sections in advance, and after grouting, the grouting body is solidified in each separated annular cavity section 15, and is bonded with the prefabricated grouting body 4 corresponding to the position to form a corresponding grouting anchor section 16; when the prestress is just applied, please refer to Figures 11 to 13 The lowest grouting anchor section 16, i.e., the grouting anchor section corresponding to the lowest prefabricated grouting body after grouting, is subjected to the pretension of the steel strand, and the pretension is transmitted to the lowest grouting anchor section 16 by the extrusion anchor, and the lowest grouting anchor section 16 produces a small displacement upwards. Since the inner socket seal ring 9 and the outer socket seal ring 10 are arranged between the adjacent prefabricated grouting bodies, the seal ring will be compressed, so that the lowest grouting anchor section and the rock formation in the area will produce a vertical downward lateral friction resistance, which will hinder the upward sliding trend of the lowest grouting anchor section; and the uppermost grouting anchor section is subjected to the pressure of the prestressed transmission device, so that the rock formation in the area and the uppermost grouting anchor section will produce a vertical upward lateral friction resistance, which will offset part of the pressure. At this time, for the uppermost grouting anchor section:
[0062]
[0063] For the lowest grouting anchor section:
[0064]
[0065] At this time, the grouting anchor section in the middle position is not subjected to stress.
[0066] When the prestress is applied to a certain extent, for the uppermost grouting anchor section:
[0067] F N1 =F f1 +F N2
[0068] For the grouting anchoring section in the middle part, there are:
[0069]
[0070] For the lowest grouting anchor section:
[0071] F=F f3 +F N3
[0072] In the above formulas, F is the preload pressure of the lowest grouting anchor section, F N1 is the preload of the uppermost grouting anchoring section, F N2 is the preload between the middle grouting anchor section and the uppermost grouting anchor section, F N3is the preload between the middle grouting anchor section and the lowest grouting anchor section, F f1 is the friction force between the uppermost grouting anchor section and the bearing layer, F f2 is the friction force between the grouting anchor section and the bearing layer in the middle part, F f3 is the friction force between the lowest grouting anchor section and the bearing layer;
[0073] From the above, it can be seen that the present invention can make the lateral friction resistance between the grouting anchoring section and the bearing layer effective during the steel strand tensioning and anchoring stage, so that the pull-out bearing capacity of the anti-floating anchor rod is greatly improved.
[0074] 2. Anti-floating anchor in working condition
[0075] The overall stress analysis of the anti-floating anchor in working state includes:
[0076] F 浮 =F N+ F f3
[0077] In the formula, F 浮 is the groundwater buoyancy, F N is the partial preload of the anti-floating anchor, F f3 It is the lateral friction resistance generated in advance between the lowest grouting anchor section and the bearing layer during the steel strand tensioning stage.
[0078] From the above, it can be seen that due to the lateral friction resistance generated in advance between the lowest grouting anchor section and the bearing layer during the tensioning stage of the steel strand, the pull-out bearing capacity of the anchor rod is greatly improved, the reliability of the anchor rod is enhanced, and the risk of anchor rod failure is reduced.
[0079] Further, in a preferred embodiment, see Fig.16 The top of the grouting hole 406 of the uppermost prefabricated grouting body 4 is connected with a grouting pipe 13, and the grouting pipe 13 passes through the grouting holes 406 of each section of the prefabricated grouting body 4 and extends to the bottom of the anchor hole 12; during the threading process of the prefabricated grouting body, the grouting pipe 13 can be simultaneously inserted into the grouting holes of each section of the prefabricated grouting body 4 until it protrudes from the bottom of the lowermost prefabricated grouting body 4; and during grouting, grouting can be started from the bottom of the anchor hole 12 under the guidance of the grouting pipe 13 to squeeze out the accumulated water or mud at the bottom of the hole. When the cement slurry rises to the guide hole 404 of the lowermost prefabricated grouting body 4, the grouting and slow pipe pulling operation can be started, so that all the accumulated water or mud is gradually squeezed out from the annular cavity section 15 to ensure the density of the grouting body.
[0080] To facilitate grouting, further, in a preferred embodiment, refer to Fig.15The anti-floating anchor rod of the present invention also includes an inverted cone-shaped skeleton 19, which is reserved at the bottom of the lowest prefabricated grouting body 4, and the upper end of the inverted cone-shaped skeleton 19 is fixedly connected to the steel pad 5, and the lower end extends to the outside of the lowest prefabricated grouting body 4; the inverted cone-shaped skeleton 19 is made of steel bars; based on the above structural setting, after grouting is completed, the lowest prefabricated grouting body 4 can be better connected with the cast-in-place grouting body to form an integral structure.
[0081] In order to facilitate the penetration of the prefabricated grouting bodies 4 that are threaded into a whole into the anchoring hole 12, further, in a preferred embodiment, the bottom of the lowermost prefabricated grouting body 4 is in a cone shape.
[0082] In order to make the grouting body in the annular cavity section 15 bond better with the prefabricated grouting body 4 to form an integral structure after solidification, further, in a preferred embodiment, a layer of glass fiber mesh is adhered to the surface of the prefabricated grouting body 4 or a concave-convex pattern is provided.
[0083] Furthermore, in a preferred embodiment, the diameter of the prefabricated grouting body 4 is 4 to 5 cm smaller than the diameter of the anchor hole 12 .
[0084] Furthermore, in a preferred embodiment, the grouting hole 406 and the grouting diffusion cavity 403 are arranged at the axial center position of the prefabricated grouting body 4; the grouting diffusion cavity 403 is a cavity with a cylindrical middle section and inverted conical ends; the grouting guide holes 404 are evenly arranged 3 to 4 in the circumferential direction in the cross section of the prefabricated grouting body 4, and are connected to the middle of the grouting diffusion cavity 403.
[0085] Furthermore, in a preferred embodiment, the recessed portion 4022 of the recessed slot 402 and the raised portion 4011 of the raised plug 401 are both in the shape of an inverted cone, and the recessed slot 402 and the raised plug 401 have socket convex edges 4021 abutting against each other on their circumferential sides.
[0086] Furthermore, in a preferred embodiment, the number of the prefabricated grouting bodies 4 is 3 to 4 sections, and the length of the prefabricated grouting bodies 4 in the lowest section is greater than that of the other sections; in the present invention, the length of the grouting body in the lowest section is relatively large, and a relatively large side friction resistance can be provided between the grouting body in the lowest section and the bearing layer; when the anti-floating anchor is tensioned and locked, the upper end of the prefabricated grouting body in the uppermost section abuts against the prestressed stress transmission device 1, and the prefabricated grouting body in the lowest section is integrally cast and embedded with the extrusion anchor. Since the force is transmitted along the shortest path, the upper end of the grouting body in the uppermost section and the lower end of the grouting body in the lowest section are The slurry will be stressed first; since an inner socket sealing ring 9 and an outer socket sealing ring 10 are arranged between the grouting bodies, after being squeezed by the prestressed transfer device 1, a slight slip occurs between the uppermost grouting body and the bearing layer, so that the sealing rings between each section of the grouting body are compressed; the steel strand is continued to be tensioned, and the lowermost grouting body will undergo a slight deformation upward, the sealing ring is compressed, and a large lateral friction resistance is generated in advance between the lowermost grouting body and the rock formation; at this time, the entire grouting body is under pressure, and lateral friction resistance is generated in advance between it and the bearing layer.
[0087] Furthermore, in a preferred embodiment, the upper and lower edges of the through hole 901 in the socket inner sealing ring 9 that matches the threading hole 405 are provided with a sealing clamp 9011 that can just fit into the gap between the unbonded steel strand 3 and the threading hole 405; based on this setting, the sealing clamp 9011 can further seal the threading hole 405 at the upper and lower connecting ends of the adjacent prefabricated grouting body 4 to prevent the grouting body from penetrating into the threading hole 405.
[0088] Furthermore, in a preferred embodiment, the inner socket seal ring 9, the outer socket seal ring 10 and the sealing clamp ring 9011 are all made of EPDM rubber, so that they have strong corrosion resistance and mildew resistance, so that the designed service life can reach 100 years.
Claims
1. An anti-floating anchor rod based on a socket-type segmented prefabricated grouting body, comprising a prestressed transfer device and anchor set in the basement floor, unbonded steel strands, upper threaded bars, steel pads, lower threaded bars and prestressed bar extrusion anchors respectively connected to the upper and lower surfaces of the steel pads, It is characterized in that It also includes a socket inner sealing ring, a socket outer sealing ring, and multiple sections of prefabricated grouting bodies that are arranged in the anchor hole and plugged in and connected in sequence from top to bottom; the upper and lower connecting ends of the prefabricated grouting bodies of adjacent sections are respectively provided with protruding plugs and recessed slots that plug in and match with each other; the multiple sections of the prefabricated grouting bodies are reserved with threading holes and grouting holes that connect with each other up and down, a grouting diffusion cavity connected to the grouting holes, and a plurality of grouting guide holes; a plurality of the grouting guide holes horizontally pass through the prefabricated grouting body at one end and are connected to the grouting diffusion cavity, and the other end is connected to the anchor hole; the inner side of the socket outer sealing ring is connected to the protruding plug and the peripheral side of the recessed slot The plug-in joint is sealed and connected, and the outer side abuts against the hole wall of the anchor hole; the inner sealing ring of the socket is reserved with a through hole matching the threading hole and the grouting hole, and the inner sealing ring of the socket is sealed and connected to the plug-in joint at the center of the raised plug and the recessed slot; the steel pad, lower threaded ribs and prestressed rib extrusion anchor are reserved at the bottom of the lowermost prefabricated grouting body, the upper threaded ribs are reserved at the top of the uppermost prefabricated grouting body, one end of the unbonded steel strand is reserved at the bottom of the lowermost prefabricated grouting body and is connected to the prestressed rib extrusion anchor, and the other end passes through the threading holes of each prefabricated grouting body from bottom to top in turn to be connected to the anchor.
2. An anti-floating anchor rod based on a socket-type segmented prefabricated grouting body as claimed in claim 1, It is characterized in that The top of the grouting hole of the uppermost prefabricated grouting body is connected with a grouting pipe, and the grouting pipe runs through the grouting holes of each prefabricated grouting body and extends to the bottom of the anchor hole.
3. The anti-floating anchor rod based on the socket-type segmented prefabricated grouting body as claimed in claim 1, It is characterized in that It also includes an inverted cone frame, which is reserved at the bottom of the lowest prefabricated grouting body, and the upper end of the inverted cone frame is fixedly connected to the steel base plate, and the lower end extends to the outside of the lowest prefabricated grouting body.
4. The anti-floating anchor rod based on the socket-type segmented prefabricated grouting body as claimed in claim 1, It is characterized in that The bottom of the prefabricated grouting body in the lowest section is in a cone shape.
5. The anti-floating anchor rod based on the socket-type segmented prefabricated grouting body as claimed in claim 1, It is characterized in that A layer of glass fiber mesh is adhered to the surface of the prefabricated grouting body or concave-convex patterns are provided.
6. The anti-floating anchor rod based on the socket-type segmented prefabricated grouting body as claimed in claim 1, It is characterized in that The grouting holes and the grouting diffusion chamber are arranged at the axial center of the prefabricated grouting body; the middle part of the longitudinal section of the grouting diffusion chamber is cylindrical, and the upper and lower ends are inverted cones; 3 to 4 grouting guide holes are evenly arranged along the circumferential direction in the cross section of the prefabricated grouting body, and are connected to the middle part of the grouting diffusion chamber.
7. The anti-floating anchor rod based on the socket-type segmented prefabricated grouting body as claimed in claim 1, It is characterized in that The notch portion of the notch slot and the convex portion of the convex plug are both in the shape of an inverted cone column, and the circumferential sides of the notch slot and the convex plug are provided with socket convex edges that abut against each other.
8. The anti-floating anchor rod based on the socket-type segmented prefabricated grouting body as claimed in claim 1, It is characterized in that The number of the prefabricated grouting bodies is 3 to 4 sections, and the length of the prefabricated grouting body at the bottom section is greater than that of the other sections.
9. The anti-floating anchor rod based on the socket-type segmented prefabricated grouting body as claimed in claim 1, It is characterized in that The upper and lower edges of the through hole in the socket inner sealing ring that matches the threading hole are provided with a sealing clamp ring that can just fit into the gap between the unbonded steel strand and the threading hole.
10. The anti-floating anchor rod based on the socket-type segmented prefabricated grouting body as claimed in claim 1, It is characterized in that The inner socket sealing ring, the outer socket sealing ring and the plugging clamp ring are all made of EPDM rubber.
Citation Information
Patent Citations
Compound-type prestressed anchor cable structure and construction method thereof
CN104775428A
Fabricated static pressure concrete anchor rod
CN114108622A
Single slurry molding process for tendon