Strip mine dump material pushing and discharging and retaining wall building method
By adopting the upper and lower layered push and discharge method in open-pit mining, the problem of landslide and low construction efficiency of retaining walls when bulldozers push and discharge materials is solved, the push and discharge efficiency and retaining wall construction quality are improved, and the safety of mining heavy vehicles is ensured. Turn and unload.
Patent Information
- Application Number
- CN202411129609.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-12
AI Technical Summary
During open-pit mining, bulldozers are prone to landslides and overturning accidents when pushing and discharging materials, and the retaining wall construction efficiency and poor quality, which affects the safe overturning and unloading of heavy-duty mining vehicles.
Using the upper and lower layered push and row method, first push and row three-quarters of the material above the material pile from left to right horizontally to the bottom of the steps, repeatedly push and row 4-6 times to reduce the risk of landslide, and then return the remaining materials for the construction to reduce the The load and materials of the bulldozer slide down, improving the qualification rate of retaining wall construction.
The efficiency of pushing and discharge operation and the quality of retaining wall construction have been improved, the fuel consumption and accident risk of bulldozers have been reduced, and the qualification rate of retaining wall construction has been improved to more than 95%.
Smart Images

Figure CN118933788A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of open-pit mining, and in particular relates to a method for pushing and discharging materials in an open-pit mine dump and building a retaining wall. Background Art
[0002] Pushing and rowing operation is one of the important processes in open-pit mining. It is mainly responsible for the construction of the push and row retaining wall of the spoil dump material, and provides safety guarantee for the safe unloading of heavy-duty mining vehicles. With the continuous improvement of production tasks, the continuous improvement of safety management and the continuous refinement of cost control, each production link is facing tremendous pressure. In this regard, managers at all levels, professional and technical personnel and front-line operators are actively exploring "new measures to reduce costs and increase efficiency based on safety" to help the high-quality development of enterprises.
[0003] Conventional pushing and discharging operations are to use a bulldozer to push the materials piled on the spoil dump table directly to the bottom of the steps, and rebuild the retaining wall according to the "four standards". That is, when the materials are piled on the spoil dump retaining wall, a bulldozer is needed to carry out the pushing and discharging operation. Generally, the materials are pushed and discharged in sequence from left to right in a horizontal partitioning manner until the materials are pushed and discharged to the bottom of the spoil dump steps. However, there are the following problems: ① Due to the high material stacking height (about 3.5 meters), the material section is prone to collapse during the bulldozer pushing and discharging process, and the stones rolling down to the middle of the bulldozer crawler will cause damage to the drive accessories; at the same time, the bulldozer rolls over the collapsed materials during the reverse operation, which is very likely to cause rollover accidents. ② When the materials are pushed and discharged to the rear of the retaining wall, the bulldozer blade does not stay long enough, the materials are not scattered cleanly, and the bulldozer blade often reverses and carries goods, drops blocks, etc., not only does the finish of the spoil dump table fail to meet the standards, but also easily causes scratches and punctures on the tires of heavy mining vehicles. ③ Affected by the original retaining wall, the bulldozer has a large resistance to pushing and discharging in the lateral partitions, and the crawler track slips and easily rolls out deep grooves on the ground, or the bulldozer rolls out deep grooves or ridges when reversing with a sharp turn, resulting in the flatness of the dumping ground surface failing to meet the standard. In order to avoid rolling deep grooves due to the bulldozer's sharp turn when reversing, long-distance reversing (15 meters to 20 meters) is usually adopted, but this will cause a waste of fuel costs. Taking the Caterpillar D10T bulldozer pushing and discharging 200 tons of ore and rock materials as an example, the present invention requires 15-20 reciprocating pushes and discharges, and the push and discharge operation takes 12-16 minutes. This not only reduces the efficiency of the push and discharge operation, but also the quality of the retaining wall construction is uneven, and the qualified rate of the retaining wall construction is only about 60%, which seriously affects the safe operation of heavy-duty mining vehicles. Summary of the invention
[0004] The purpose of the present invention is to provide a method for pushing and discharging materials and building a retaining wall in an open-pit mine dump, which can not only improve the pushing and discharging efficiency of materials, but also ensure the building quality of the retaining wall.
[0005] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0006] The present invention discloses a method for pushing and discharging materials in an open-pit mine dump and building a retaining wall, comprising:
[0007] When the materials unloaded by heavy mining trucks are piled up above the retaining wall, the bulldozer pushes them in an upper and lower layered manner. First, three quarters of the materials above the pile are pushed horizontally from left to right directly to the bottom of the spoil dump steps, reducing the material stacking height and the risk of landslides in the material section; the pushing and discharging is repeated 4-6 times, and the pushing and discharging operation takes 6-8 minutes; after the pushing and discharging is completed, the bulldozer returns to the starting point, and then the retaining wall is built with the remaining one quarter of the materials, and this is repeated 4-6 times, and the pushing and discharging operation takes 2-4 minutes.
[0008] Furthermore, using surplus materials to build retaining walls can not only reduce the operating load of the bulldozer, but also prevent deep grooves or ridges caused by the rolling of the bulldozer tracks from affecting the safe unloading of heavy mining trucks.
[0009] Furthermore, the longitudinal stratification reduces the cargo stacking height, and the material cross-section is not easy to collapse during the bulldozer pushing process, thereby avoiding damage to the bulldozer drive accessories or the bulldozer running over collapsed materials during reverse operation, causing rollover accidents.
[0010] Furthermore, the amount of material pushed by the bulldozer for the second time is reduced, the number of repeated pushing and discharging is reduced, and the time waiting for the material at the front end of the blade to slide down is shortened, thereby avoiding the probability of the bulldozer blade carrying large pieces of material and spilling them, which in turn affects the quality of the retaining wall construction.
[0011] Furthermore, after the improvement, the qualified rate of retaining wall construction was increased to more than 95%.
[0012] Further, the specific steps include:
[0013] Step 1: When the materials dumped by the mining truck are piled up on the retaining wall, the bulldozer pushes the three-quarters of the materials on the top of the pile to the bottom of the steps in a longitudinal layered manner from left to right. This step is generally repeated 4-6 times and takes 6-8 minutes. The problems of reversing distance, sharp turns, track slippage, and bulk cargo retention can be ignored, which effectively improves the efficiency of pushing and discharging operations;
[0014] Step 2: After the upper material is pushed, return the bulldozer to the starting point, and use the horizontal layering method from left to right to build a retaining wall with a quarter of the material under the cargo pile, and push the excess material to the bottom of the steps. This step is usually repeated 4-6 times, 2-4 minutes;
[0015] Step 3: After the materials are pushed out, check them according to the "four standards" of the retaining wall. If there are any defects, rebuild the retaining wall again to ensure the quality of the retaining wall.
[0016] Furthermore, in the step 2: ① After each pushing and discharging operation is completed, the bulldozer blade needs to stay above the retaining wall for 8-10 seconds, and then repeat the pushing and discharging operation after the materials on the blade are scattered cleanly; ② Each time the bulldozer reverses, the steering angle should not exceed 30° as much as possible to avoid rolling out deep grooves or ridges on the ground, which will affect the flatness of the table surface.
[0017] Furthermore, the "four standards" of retaining walls are: retaining wall height, retaining wall width, reverse slope at the base of the retaining wall, and the smoothness and flatness of the spoil dump table.
[0018] Compared with the prior art, the beneficial technical effects of the present invention are:
[0019] The present invention improves the bulldozer's pushing and discharging efficiency and effectively avoids various risks in the pushing and discharging operation, which is of great significance to the low-consumption and high-efficiency development of enterprises. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The present invention will be further described below in conjunction with the accompanying drawings.
[0021] Figure 1 The present invention is a flow chart of the method for pushing and discharging materials in an open-pit mine dump and building a retaining wall. DETAILED DESCRIPTION
[0022] The invention provides a method for pushing and discharging materials and building a retaining wall in an open-pit mine dump, which can improve the pushing and discharging efficiency of materials and ensure the building quality of the retaining wall.
[0023] The method adopted by the present invention is that after the materials unloaded by the mining heavy truck are piled up above the retaining wall, the bulldozer is pushed and discharged in an upper and lower layered manner, and first three quarters of the materials above the cargo pile are directly pushed and discharged from left to right in a horizontal partition manner to the bottom of the dumping field step, thereby reducing the material stacking height and the risk of material cross-section collapse. Generally, the pushing and discharging is repeated 4-6 times, and the pushing and discharging operation takes 6-8 minutes; after the pushing and discharging is completed, the bulldozer returns to the initial point, and then the remaining one quarter of the materials are used to build the retaining wall, which is generally repeated 4-6 times, and the pushing and discharging operation takes 2-4 minutes. Using the remaining materials to build the retaining wall can not only reduce the operating load of the bulldozer, but also avoid the deep grooves caused by the rolling of the bulldozer crawler that affect the safe unloading of the mining heavy truck; at the same time, the amount of materials pushed and discharged by the bulldozer for the second time is reduced, and the time for waiting for the materials at the front end of the blade to slide down is shortened, which can avoid the probability of the bulldozer blade carrying goods and spilling large pieces, thereby affecting the quality of the retaining wall construction, and the qualified rate of the improved retaining wall construction is increased to more than 95%.
[0024] Example 1
[0025] This embodiment takes the Caterpillar D10T bulldozer pushing 200 tons of waste rock materials as an example, and specifically includes the following steps:
[0026] Step 1: When the materials dumped by the mining truck are piled up on the retaining wall, the bulldozer pushes the three-quarters of the materials on the top of the pile to the bottom of the steps in a longitudinal layered manner from left to right. This step is generally repeated 4-6 times and takes 6-8 minutes. The problems of reversing distance, sharp turns (steering angle greater than 30°), track slippage, and stationary bulk cargo can be ignored, which can effectively improve the efficiency of pushing and discharging.
[0027] Step 2: After the upper material is pushed and discharged, return the bulldozer to the starting point, and use the horizontal layered pushing method from left to right to build a retaining wall with one-fourth of the material under the cargo pile, and push the excess material to the bottom of the steps. This step is generally repeated 4-6 times for 2-4 minutes. Focus on several key points: ① After each pushing and discharging operation, the bulldozer blade needs to stay above the retaining wall for 8-10 seconds, and repeat the pushing and discharging operation after the material on the blade is scattered cleanly. ② Each time the bulldozer is reversed, try not to turn the angle more than 30° to avoid rolling out deep grooves on the ground and affecting the flatness of the table surface.
[0028] Step 3: After the materials are pushed out, check them according to the "four standards" of the retaining wall (retaining wall height, retaining wall width, reverse slope at the root of the retaining wall, and smoothness and flatness of the spoil dump table). If there are defects, rebuild the retaining wall again to ensure the construction quality of the retaining wall.
[0029] The embodiments described above are only descriptions of the preferred modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.
Claims
1. A method for pushing and discharging materials and building retaining walls in an open-pit mine dump, characterized in that: include: When the materials dumped by the mining trucks are piled up above the retaining wall, the bulldozer pushes them in layers, first pushing the three-quarters of the materials on the top of the pile from left to right horizontally to the bottom of the dumping yard steps, reducing the material stacking height and the risk of collapse of the material section; repeat the pushing and discharging 4-6 times, and the pushing and discharging operation takes 6-8 minutes; After the pushing and discharging is completed, the bulldozer returns to the starting point and uses the remaining quarter of the material to build a retaining wall. This is repeated 4-6 times and the pushing and discharging operation takes 2-4 minutes.
2. The method for pushing and discharging materials and building retaining walls in an open-pit mine dump according to claim 1, characterized in that: Using surplus materials to build retaining walls can not only reduce the operating load of the bulldozer, but also avoid the deep trenches caused by the bulldozer tracks that affect the safe unloading of heavy mining trucks.
3. The method for pushing and discharging materials and building retaining walls in an open-pit mine dump according to claim 1, characterized in that: The amount of material pushed and discharged by the bulldozer for the second time is reduced, the number of repeated operations is reduced, and the time waiting for the material at the front end of the blade to slide down is shortened, thereby avoiding the probability of the bulldozer blade carrying large pieces of material and spilling them, which in turn affects the quality of the retaining wall construction.
4. The method for pushing and discharging materials and building retaining walls in an open-pit mine dump according to claim 1, characterized in that: After the improvement, the pass rate of retaining wall construction increased to more than 95%.
5. The method for pushing and discharging materials and building retaining walls in an open-pit mine dump according to claim 1, characterized in that: The specific steps include: Step 1: When the materials dumped by the mining truck are piled up above the retaining wall, the bulldozer pushes three quarters of the materials above the pile to the bottom of the steps in a longitudinal layered manner from left to right. This step is generally repeated 4-6 times and takes 6-8 minutes. The problems of reversing distance, sharp turns, track slippage, and bulk cargo retention can be ignored, which effectively improves the efficiency of pushing and discharging operations; Step 2: After the upper material is pushed, return the bulldozer to the starting point, and use the horizontal layering method from left to right to build a retaining wall with a quarter of the material under the cargo pile, and push the excess material to the bottom of the steps. This step is usually repeated 4-6 times, 2-4 minutes; Step 3: After the materials are pushed out, check them according to the "four standards" of the retaining wall. If there are any defects, rebuild the retaining wall again to ensure the construction quality of the retaining wall.
6. The method for pushing and discharging materials and building retaining walls in an open-pit mine dump according to claim 5, characterized in that: In the step 2: ① After each pushing and discharging operation is completed, the bulldozer blade needs to stay above the retaining wall for 8-10 seconds, and the pushing and discharging operation can be repeated after the materials on the blade are scattered cleanly; ② Each time the bulldozer is reversed, the steering angle should not exceed 30° as much as possible to avoid rolling out deep grooves or ridges on the ground, which will affect the flatness of the table surface.
7. The method for pushing and discharging materials and building retaining walls in an open-pit mine dump according to claim 5, characterized in that: The "four standards" of retaining walls are: retaining wall height, retaining wall width, reverse slope at the base of the retaining wall, and the smoothness and flatness of the spoil dump table.