Shield receiving method for water-containing soft soil stratum below existing station
By setting up frozen reinforcement and welding and gap filling in shield construction, the problem of sand and water gushing in shield construction is solved, the safety and efficiency of construction is improved, and the smooth progress of construction is ensured.
Patent Information
- Application Number
- CN202411014703.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-11-12
AI Technical Summary
During shield construction, the water-containing soft soil strata below the existing building leads to sand and water swelling, which affects the construction safety and progress. Especially when the pressure-bearing water layer exists, it is difficult to effectively prevent groundwater from being removed from the shield pipe and holes. Speeping in the gap.
By setting up frozen reinforcement in the shield area, the frozen reinforcement is formed and welded to the pipe sheet at the shield tail of the shield machine, and welded to the connecting ring of the hole door in the shield machine shell, combining the foam concrete support and ring hoop Fill the gaps to avoid the occurrence of sand and water surges.
The gap between the pipe segment and the soil is effectively sealed, the probability of sand and water gushing is reduced, the safety and efficiency of construction is improved, and the smooth progress of construction is ensured.
Smart Images

Figure CN118933807A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of shield construction, and in particular to a shield receiving method for a water-containing soft soil layer under an existing station. Background Art
[0002] When a new tunnel passes under an existing building, such as a new subway line passing under an existing subway station, a terminal well will be set up next to the existing subway station to receive the tunnel shield machine. Therefore, during the tunnel shield construction, the shield machine will successively pass through the underground continuous wall under the existing station and on the side of the existing station near the terminal well, and finally reach the terminal well and complete the shield reception.
[0003] In addition, in order to ensure that the shield machine can pass through the underground continuous wall normally, before the shield machine passes through the underground continuous wall, it is necessary to manually chisel away the wall on the underground continuous wall and form a portal for the shield machine to pass through. As the shield machine excavates, shield segments will also be installed in the shield tunnel to complete the initial protection of the tunnel.
[0004] However, when the soil layer below the existing building is a soft soil aquifer, especially when there is a confined water layer, in order to ensure the normal progress of the shield construction and avoid the settlement of the existing building above, the shield area is generally frozen to form a frozen reinforcement. After the shield construction is completed, the tunnel gate lacks obstruction. After the frozen reinforcement is thawed, groundwater will gush out from the gap between the shield segment and the tunnel gate, bringing great difficulties and risks to the construction. Summary of the invention
[0005] This application provides a shield receiving method for the water-bearing soft soil layer under the existing station, which can effectively prevent the sand and water gushing phenomenon on the wall, ensure the smooth progress of the construction side, and improve the safety of the construction. The following technical solutions are adopted: A shield receiving method for a water-bearing soft soil layer under an existing station comprises the following steps: Chiseling out the underground continuous wall; chiseling out the part of the second underground continuous wall of the existing building in the shield area to form a tunnel; fixing the tunnel door connecting ring on the underground continuous wall and making the tunnel door connecting ring surround the tunnel door; Shield tunneling construction; the shield tail of the shield machine reaches the steel ring position and stops tunneling; The tunnel portal is sealed; after the shield reaches the end shaft, the ends of the segments are first sealed and connected with the shield tail of the shield machine inside the shield machine; the tunnel portal connecting ring is sealed and connected with the outer shell of the shield machine. After the overall connection is completed, the shield tail of the shield machine is cut off as a whole.
[0006] By adopting the above technical scheme, the underground continuous wall is chiseled out, the portal connecting ring is preset, the shield excavation construction is carried out, and the portal sealing step is carried out in sequence. In the portal sealing step, the pipe segment is welded to the shield tail of the shield machine, and then the portal connecting ring is welded to the shield tail of the shield machine, so that the gap between the pipe segment and the soil can be effectively sealed, thereby avoiding the phenomenon of sand and water gushing, ensuring the smooth progress of the construction side, and improving the safety of the construction.
[0007] Preferably, it also includes freezing reinforcement, which is set before the underground continuous wall is removed; a freezing pipeline is set in the end shaft at the shield receiving hole position to freeze the soil under the existing subway station to form a frozen reinforcement body; the shield area passes through the frozen reinforcement body.
[0008] By adopting the above technical solution, the setting of frozen reinforcement bodies can effectively increase the stability of the soft soil pressure water layer under the existing buildings, reduce the impact of the shield on the existing buildings, and at the same time reduce the probability of sand and water gushing, thereby facilitating the smooth construction of the shield.
[0009] Preferably, the portion of the frozen reinforcement body located in the shield area is an inner circle, and the portion located on the peripheral side of the shield area is an outer circle; During the shield tunneling construction steps, the freezing pipes in the outer circle area are retained and the freezing of the outer circle area is maintained; the freezing pipes in the inner circle area are cut, and the freezing pipe parts located outside the frozen reinforcement body are removed, and the freezing pipe parts located inside the frozen reinforcement body are retained, thereby maintaining the freezing of the inner circle area.
[0010] By adopting the above technical solution and cutting the inner circle freezing pipe, the inner circle area can be kept frozen, which can avoid the inner circle area from melting rapidly and thus causing adverse effects on the shield construction, thereby ensuring the smooth progress of the construction.
[0011] Preferably, the freezing pipes in the inner circle area are set as PVC pipes, and during shield tunneling construction, the freezing pipes and the soil are excavated simultaneously by the shield machine.
[0012] By adopting the above technical solution, the shield machine can remove the soil connected to the PVC pipe together during excavation, eliminating the need to pull out the frozen pipe and improving construction efficiency.
[0013] Preferably, during shield tunneling construction, after the shield machine advances into the interior of the frozen reinforcement body, polyurethane is injected between the shield body of the shield machine and the frozen reinforcement body, and the polyurethane reacts with groundwater to form a polymer that fills the gap between the shield body and the frozen reinforcement body.
[0014] By adopting the above technical solution, polyurethane is injected, and the polyurethane reacts with groundwater to form a polymer, thereby sealing the gap between the shield body and the frozen reinforcement body, and after the pipe segment is installed, a protective layer is formed around the pipe segment to effectively avoid sand and water leakage.
[0015] Preferably, it also includes support body construction, which is arranged after the underground continuous wall is removed and before the shield tunneling construction; The support body construction includes: filling a foam concrete support body in the removed area of the underground continuous wall to form a temporary support body, and burying the tunnel door connection ring in the foam concrete support body.
[0016] By adopting the above technical solution, the foam concrete support body can play a better supporting role in the chiseled area to ensure that the underground continuous wall is not easily damaged during shield excavation, thereby ensuring the stability of the existing building structure.
[0017] Preferably, after the excavated area of the underground continuous wall is filled, the foam concrete support body is poured and filled in the end well.
[0018] By adopting the above technical solution, the foam concrete support body can also play a supporting role for the end well, so as to ensure that the structure of the end well will not be damaged during shield excavation, thereby ensuring the reception of the shield.
[0019] Preferably, in the tunnel portal sealing step, the foam concrete supporting body in the end well is first chiseled out to expose the tunnel portal connecting ring; and the chiseling out of the foam concrete supporting body and the welding of the tunnel portal connecting ring are carried out simultaneously.
[0020] By adopting the above technical solution, the removal of the foam concrete support body and the welding of the portal connecting ring are carried out simultaneously. On the one hand, the construction efficiency can be improved, and on the other hand, the foam concrete support body can support the unwelded part, thereby ensuring the stability of the structure and facilitating the smooth progress of subsequent construction.
[0021] Preferably, grouting holes are added to the shield machine to inject grout between the shield body of the shield machine and the soil and to apply a hoop to block the water-sand channel and fill the gap between the pipe segment and the underground continuous wall.
[0022] By adopting the above technical solution, by setting a hoop so that the hoop surrounds the shield body and the soil and fills between the pipe segment and the underground continuous wall, the gap between the pipe segment and the underground continuous wall can be filled and sealed, thereby reducing the probability of sand and water gushing and ensuring the normal progress of shield construction.
[0023] In summary, the present invention includes at least one of the following beneficial technical effects: 1. In this application, the underground continuous wall is removed, the tunnel door connection ring is preset, the shield tunneling construction is carried out, and the tunnel door is blocked. In the tunnel door blocking step, the pipe segment is welded to the shield tail of the shield machine, and then the tunnel door connection ring is welded to the shield tail of the shield machine, so that the gap between the pipe segment and the soil can be effectively blocked, thereby avoiding the phenomenon of sand and water gushing, ensuring the smooth progress of the construction side, and improving the safety of the construction; 2. Keep the frozen pipes in the outer ring area and maintain the freezing of the outer ring area; cut the frozen pipes in the inner ring area, remove the frozen pipe parts outside the frozen reinforcement body, and keep the frozen pipe parts inside the frozen reinforcement body, so as to maintain the freezing of the inner ring area. During the shield excavation construction, the frozen pipes and the soil are excavated at the same time by the shield machine, which can avoid the rapid melting of the inner ring area and thus have an adverse effect on the shield construction, thereby ensuring the smooth progress of the construction, realizing the elimination of the need to pull out the frozen pipes, and improving the construction efficiency; 3. By injecting polyurethane between the shield body and the frozen reinforcement of the shield machine, the polyurethane reacts with groundwater to form a polymer to fill the gap between the shield body and the frozen reinforcement, thereby sealing the gap between the shield body and the frozen reinforcement. In addition, by setting a hoop, the hoop surrounds the shield body and the soil and fills between the pipe segment and the underground continuous wall, the gap between the pipe segment and the underground continuous wall can be filled and sealed, thereby reducing the probability of sand and water gushing and ensuring the normal progress of the shield construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a schematic diagram of the relative position relationship between the existing buildings, the end well, the frozen joint and the shield tunnel; Figure 2 It is a schematic diagram of setting the freezing pipe; Figure 3 It is a schematic diagram of removing the underground continuous wall and forming a tunnel entrance; Figure 4 It is a schematic diagram of cutting the freezing pipe in the inner circle area; Figure 5 It is a structural diagram of the construction of the foam concrete support body and the tunnel portal connection ring; Figure 6 This is a schematic diagram of the tunneling of the shield machine before it enters the frozen reinforcement body; Figure 7 This is a schematic diagram of the shield machine entering the frozen reinforcement body for excavation; Figure 8 This is a schematic diagram of the shield machine entering the foam concrete support body in the ground-connected wall removal area for excavation; Fig. 9 This is a schematic diagram of the tunnel boring machine entering the foam concrete support body of the end well; Fig.10 This is a schematic diagram of the tunnel gate blocking; Fig.11 is a schematic diagram of step S6.
[0025] Markings in the attached drawings: 1. existing building; 11. underground continuous wall; 111. tunnel portal; 2. end well; 3. frozen reinforcement; 31. inner ring; 32. outer ring; 4. frozen pipe; 5. tunnel portal connecting ring; 6. foam concrete support body; 7. shield machine; 8. pipe segment; 9. polymer; 10. hoop. DETAILED DESCRIPTION
[0026] The following is combined with Figure 1-11 The present invention is described in further detail.
[0027] The embodiment of the present application discloses a shield receiving method for a water-containing soft soil layer under an existing station, which is mainly aimed at a newly built tunnel passing under an existing building 1, such as a newly built subway line passing under an existing subway station, etc., and the soil layer under the existing building 1 is a soft soil aquifer, especially there is a pressurized water layer.
[0028] Reference Figure 1 In this application, a specific construction example of a new subway line under an existing subway station is used. Since the new tunnel is located under the existing subway station and is close to the floor of the existing subway station, a terminal well 2 will be set up next to the existing subway station for receiving the tunnel shield machine 7. Therefore, during the shield construction of the tunnel, the shield machine 7 will successively pass through the underground continuous wall 11 under the existing station and on the side of the existing station near the terminal well 2, and finally reach the terminal well 2 and complete the shield reception.
[0029] Synchronously, along with the excavation of the shield machine 7, it is also necessary to install the shield segment 8 in the shield tunnel. Before the shield machine 7 passes through the underground continuous wall 11, it is necessary to manually chisel out the wall on the underground continuous wall 11 and form a tunnel door 111 for the shield machine 7 to pass through.
[0030] However, since the geology below the existing station is soft soil and there is a pressurized water layer, after the shield machine 7 reaches the end shaft 2, groundwater and sand are very likely to gush out from between the shield segment 8 and the underground continuous wall 11 tunnel door 111, which may at least affect the normal progress of the construction, or even cause a construction accident and cause the existing subway station to sink.
[0031] The present application provides a shield receiving method for a water-containing soft soil layer under an existing station, the purpose of which is to solve the above-mentioned technical problems.
[0032] Specifically, the shield receiving method for the water-bearing soft soil layer under the existing station includes the following steps: S1, cryo-consolidation; ref. Figure 2, a freezing pipeline is set up in the end well 2 at the shield receiving hole position to freeze and reinforce the soil under the existing subway station, thereby forming a frozen reinforcement body 3. The shield machine 7 will pass through this frozen reinforcement body 3 during the subsequent excavation process. Due to the presence of the frozen reinforcement body 3, the stability of the soil layer is significantly improved, and the fluidity of the water-containing soft soil layer is effectively suppressed, thereby greatly reducing the construction risk.
[0033] For the setting of the freezing pipeline, it is necessary to drill a freezing hole in the end well 2, pass the freezing hole through the wall of the end well 2, the ground wall and enter the freezing area, and place the freezing pipe 4 in the freezing hole.
[0034] The part of the frozen reinforcement body 3 located in the shield area is defined as the inner circle 31, and the part located on the peripheral side of the shield area is defined as the outer circle 32. The freezing pipe 4 in the outer circle 32 area can be a metal pipe, while the freezing pipe 4 in the inner circle 31 is a PVC pipe.
[0035] S2, underground continuous wall 11 is removed; refer to Figure 3 and Figure 4 Within the scope of freezing reinforcement, the underground continuous wall 11 of the existing subway station and the side wall of the end shaft 2 are chiseled out to form a tunnel portal 111 for the shield machine 7 to pass through; the tunnel portal connecting ring 5 is fixed on the ground connecting wall, and the tunnel portal 111 is located inside the tunnel portal connecting ring 5.
[0036] The material of the tunnel door connecting ring 5 can be steel.
[0037] Reference Figure 4 , the outer circle 32 area is kept frozen, the frozen pipe 4 in the inner circle 31 is cut, and the frozen pipe 4 part outside the frozen reinforcement body 3 is removed, and the frozen pipe 4 part inside the frozen reinforcement body 3 is retained, so as to maintain the freezing of the inner circle 31 area. When the shield machine 7 is excavating, the soil and the frozen pipe 4 of the inner circle 31 are excavated together.
[0038] S3, support construction; see Figure 5 A disposable foam concrete support body 6 is filled in the removed area of the underground continuous wall 11 to form a temporary support body, and at the same time, the foam concrete support body 6 is filled in the end well 2; the tunnel door connecting ring 5 is also buried in the foam concrete support body 6.
[0039] S4, shield tunneling construction. Specifically, the shield tunneling construction steps include the following four sub-steps: (1) Excavation of the shield machine 7 before entering the frozen reinforcement body 3, refer to Figure 6 At this time, the shield machine 7 is entirely located below the existing station.
[0040] (2) The shield machine 7 enters the frozen reinforcement body 3 to excavate.
[0041] Reference Figure 7 After the shield machine 7 enters the reinforcement body, polyurethane is injected into the shield body of the shield machine 7. The polyurethane reacts with the groundwater outside the shield body to form a polymer 9 to fill the gap between the shield body and the reinforcement body to prevent the formation of a water seepage channel.
[0042] (3) The shield machine 7 enters the foam concrete support body 6 in the ground-connected wall removal area and excavates. Figure 8 .
[0043] (4) The shield machine 7 enters the foam concrete support body 6 of the end shaft 2 for excavation.
[0044] Reference Fig. 9 When the shield tail of the shield machine 7 reaches the outer edge of the steel ring, the excavation is stopped and the shield tail is prepared to be cut to seal the tunnel door 111.
[0045] Since the frozen reinforcement body 3 is easy to break and produce cracks to form water-sand channels during the shield excavation process, it is necessary to add grouting holes on the shield machine 7 to be used for grouting between the shield body of the shield machine 7 and the soil body and to apply the hoop 10 to block the water-sand channels and fill the gaps between the pipe segments 8 and the underground continuous wall 11.
[0046] S5, tunnel gate 111 is blocked; Reference Fig.10 First, the end of the segment 8 is welded to the shield tail of the shield machine 7 in the tunnel, and a circle is welded. Then the foam concrete support body 6 in the end well 2 is chiseled out to expose the tunnel portal connection ring 5, and the tunnel portal connection ring 5 is welded to the outer shell of the shield machine 7. In order to improve the welding efficiency, the construction method of chiseling out the foam concrete support body 6 and welding the tunnel portal connection ring 5 and the outer shell of the shield machine 7 is adopted.
[0047] After the tunnel portal connecting ring 5 is welded to the outer shell of the shield machine 7, a steel plate is arranged inside the tunnel portal 111 and the edge of the steel plate is welded to the inner wall of the shield tail of the shield machine 7, and finally the shield tail of the shield machine 7 is cut along the welding point.
[0048] S6, ref. Fig.11 , remove the remaining foam concrete support body 6 in the end well 2, hoist the shield machine 7, leave the site after stopping freezing and thawing, and carry out settlement grouting reinforcement treatment.
[0049] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, all equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A shield receiving method for a water-bearing soft soil layer under an existing station, characterized in that: The following steps are involved: The underground continuous wall (11) is chiseled out; the portion of the second underground continuous wall (11) of the existing building (1) in the shield area is chiseled out to form a tunnel portal (111); a tunnel portal connecting ring (5) is fixed to the underground continuous wall (11), and the tunnel portal connecting ring (5) is surrounded by the circumference of the tunnel portal (111); Shield tunneling construction; the shield tail of the shield machine (7) reaches the position of the tunnel portal connection ring (5), and the tunneling stops; The tunnel door (111) is sealed; after the shield machine reaches the end shaft (2), the end of the segment (8) is first sealed and connected with the shield tail of the shield machine (7) inside the shield machine (7); the tunnel door connecting ring (5) is sealed and connected with the outer shell of the shield machine (7); after the overall connection is completed, the shield tail of the shield machine (7) is cut off as a whole.
2. The shield receiving method for the water-bearing soft soil layer under the existing station according to claim 1 is characterized in that: It also includes freezing reinforcement, which is set before the underground continuous wall (11) is removed; a freezing pipeline is set in the end well (2) at the shield receiving hole position to freeze the soil under the existing subway station to form a freezing reinforcement body (3); the shield area passes through the freezing reinforcement body (3).
3. The shield receiving method for the water-bearing soft soil layer under the existing station according to claim 2 is characterized in that: The portion of the frozen reinforcement body (3) located in the shield area is an inner circle (31), and the portion located on the peripheral side of the shield area is an outer circle (32); During the shield tunneling construction step, the freezing pipe (4) in the outer ring (32) area is retained and the freezing of the outer ring (32) area is maintained; the freezing pipe (4) in the inner ring (31) area is cut, and the part of the freezing pipe (4) located outside the freezing reinforcement body (3) is removed, and the part of the freezing pipe (4) located inside the freezing reinforcement body (3) is retained, thereby maintaining the freezing of the inner ring (31) area.
4. The shield receiving method for the water-bearing soft soil layer under the existing station according to claim 3 is characterized in that: The freezing pipe (4) in the inner circle (31) area is set as a PVC pipe, and during shield tunneling construction, the freezing pipe (4) and the soil are excavated simultaneously by the shield machine (7).
5. The shield receiving method for the water-bearing soft soil layer under the existing station according to claim 1 is characterized in that: During shield tunneling construction, after the shield machine (7) has tunneled into the interior of the frozen reinforcement body (3), polyurethane is injected between the shield body of the shield machine (7) and the frozen reinforcement body (3), and the polyurethane reacts with groundwater to form a polymer (9) that fills the gap between the shield body and the frozen reinforcement body (3).
6. The shield receiving method for the water-bearing soft soil layer under the existing station according to claim 1 is characterized in that: It also includes support body construction, which is arranged after the underground continuous wall (11) is removed and before the shield tunneling construction; The support body construction comprises: filling a foam concrete support body (6) in the removed area of the underground continuous wall (11) to form a temporary support body, and burying the tunnel door connection ring (5) inside the foam concrete support body (6).
7. The shield receiving method for the water-bearing soft soil layer under the existing station according to claim 6 is characterized in that: After the filling of the removed area of the underground continuous wall (11) is completed, the foam concrete support body (6) is poured and filled into the end well (2).
8. The shield receiving method for the water-bearing soft soil layer under the existing station according to claim 6 is characterized in that: In the tunnel portal (111) blocking step, the foam concrete support body (6) in the end well (2) is first chiseled out to expose the tunnel portal connection ring (5); and the chiseling out of the foam concrete support body (6) and the welding of the tunnel portal connection ring (5) are performed simultaneously.
9. The shield receiving method for the water-bearing soft soil layer under the existing station according to claim 1, characterized in that: Grouting holes are added to the shield machine (7) to inject grout between the shield body of the shield machine (7) and the soil body and to apply a hoop (10) to block the water-sand passage and fill the gap between the pipe segment (8) and the underground continuous wall (11).