Bolt-mesh-shotcrete supporting method suitable for unfavorable geological section of underground roadway

By using high-strength threaded steel mesh and improved jet concrete ratio in downhole tunnels, the problem of insufficient strength of the existing anchor mesh spray support in poor geological sections is solved, and the tensile and impact resistance of the support structure is improved. Ensures the stability of the tunnel and the safety of blasting and mining.

CN118933846APending Publication Date: 2024-11-12YUXI DAHONGSHAN MINING
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411214396.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-31
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In underground mine underground tunnels, the existing anchor mesh spraying support method has low tensile strength of steel bars, low bond strength between steel mesh and jet concrete, and small resistance to explosion impact in poor geological sections, resulting in the overall reinforcement arch strength of the support. It is low and cannot effectively support the top plate and eyebrow line, resulting in difficulty in blasting and mining recovery and mine loss problems.

Method used

Using Φ14mm HRB400E threaded steel mesh, the spacing between anchors and spray concrete ratio are changed, the tensile strength of the steel bars and the bonding strength of the concrete are improved, the overall warp and lattice layout and reinforcement arches are formed, and the tensile and impact resistance of the support structure is enhanced. .

Benefits of technology

It significantly improves the overall strength of the anchor net spray support, effectively avoids tunnel deformation and post-blasting damage, enhances the reinforcement capacity of loose and broken rock layers, ensures the safety of blasting and mining, and avoids the phenomenon of mine loss.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933846A_ABST
    Figure CN118933846A_ABST
Patent Text Reader

Abstract

The invention discloses an anchor net shotcrete supporting method suitable for an unfavorable geological section of an underground roadway. According to the method, existing engineering materials and mechanical equipment are utilized, and main technical parameters such as materials, tensile strength and mesh degree of a reinforcing mesh, the row distance between anchor rods, the thickness of sprayed concrete and the bonding strength of reinforced concrete in traditional anchor, mesh and shotcrete combined supporting are changed, so that the overall supporting strength of the anchor, mesh and shotcrete combined supporting is improved; the common bearing capacity of the surrounding rock and the reinforcing arch is improved, meanwhile, the capability of resisting blasting impact damage is improved, roadways such as a transverse drift and a drift in an ore body, a brow line opening and a top plate are effectively supported, blasting stoping is effectively guaranteed, and ore throwing is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of underground mining, and in particular relates to an anchor-net spraying support method suitable for poor geological sections of underground tunnels. Background Art

[0002] The mining depth of Dahongshan underground mine exceeds 800m. High depth is accompanied by high stress. As mining progresses, the mining geological conditions become more complex, and the proportion of broken roofs above level II increases. High-segment collapse and open-pit mining methods are adopted. The charge volume of each row of medium-deep holes is large, the blasting disturbance is large, and the blasting-derived disasters are obvious. The underground safety production management faces severe challenges. The support level required in the unfavorable geological sections such as fault fracture zones, large exposed surfaces, high stress, and strong blasting disturbance is high. The previously used Φ6 round steel mesh-anchor mesh spraying support has problems such as low tensile strength of steel bars, low bonding strength between steel mesh and sprayed concrete, low resistance to blasting impact, and low strength of the overall reinforcement arch of the support. The tunnels such as veins and approaches in the ore body are prone to collapse of the roof and eyebrow due to the low original support strength. The impact damage caused by blasting can easily cause the roof and eyebrow line to collapse, and it is impossible to charge and blast normally, resulting in ore loss. Summary of the invention

[0003] In view of the above problems, the object of the present invention is to provide an anchor-net spraying support method suitable for poor geological sections of underground tunnels.

[0004] The purpose of the present invention is to provide an anchor-net spraying support method suitable for poor geological sections of underground tunnels, which is achieved by following the steps: 1) Carry out comprehensive prying of the tunnel to ensure the safety of on-site operations, clean the tunnel rock walls, clean the accumulated slag in the tunnel, and clean the side walls thoroughly; 2) Measurement of tunnels in poor geological sections: Use a 3D scanner to measure the tunnels and obtain tunnel cross-section and model data to facilitate support design; 3) Installation of threaded steel mesh: The full section and full support section of the steel mesh are laid horizontally and vertically to form an overall warp and weft grid arrangement. Φ14mm HRB400E threaded steel bars are used as horizontal and vertical bars. The mesh spacing of the threaded steel mesh is 300-350mm. The distance from the steel mesh to the side wall of the tunnel is 5-6cm, and the overlap length is 45-50cm, which is used as the reinforcement for shotcrete. Thin iron wires are tied at each intersection of the horizontal and vertical bars, and the vertical bars must be laid to the bottom when they are woven. Before installing the steel mesh, use an impact drill to construct anchor bars with a diameter of 6mm and a depth of 5cm on the rock wall every 1m to fix the steel mesh. 4) Anchor bolt pressing mesh: After the threaded steel mesh is installed, an anchor trolley is used to construct a pipe-seam anchor bolt pressing mesh with a row spacing of 1.5m~1.6m; 5) Spraying concrete: Prepare concrete according to the ratio of cement: gravel: river sand: cement = 1:1.93:2.17:0.4. Spray concrete in 4 times. The thickness of the 1st and 2nd spraying is 4 cm, and the thickness of the 3rd and 4th spraying is 4 cm and 3 cm respectively. There is a 20-minute interval between each spraying of concrete.

[0005] The method of the present invention is applicable to the support engineering of bad geological sections such as underground fault fracture zone, large exposed surface, high stress, strong disturbance of blasting, etc. The present invention utilizes existing engineering materials and mechanical equipment, and improves the overall support strength of anchor-net-spraying combined support by changing the material, tensile strength and mesh size of the main steel mesh in the traditional anchor-net-spraying support, the spacing between anchor rods, the thickness of shotcrete, the bonding strength of reinforced concrete, and other technical parameters: first, the tensile strength of the steel bars in the anchor-net-spraying combined support is improved, which effectively avoids the serious deformation of the tunnel due to the tensile stress concentration in the deep mining tunnel; second, the improvement of the bonding strength of reinforced concrete improves the large-scale damage of the support body after blasting; third, the overall support arch formed by the anchor-net-spraying effectively reinforces the loose and broken weak rock layer, improves the common bearing capacity of the surrounding rock and the reinforced arch, and is conducive to improving the ability to resist blasting impact damage. For the tunnels such as the vein and approach in the ore body, the eyebrow line and the top plate are effectively supported, so that the blasting recovery is effectively guaranteed and the loss of ore is avoided. BRIEF DESCRIPTION OF THE DRAWINGS

[0006] Figure 1 Secondary cataloging of the tunnel geology of Example 1; Figure 2 This is a schematic diagram of the steel mesh preparation of Example 1; Figure 3 Schematic diagram of anchor bars and No. 14 iron wire for fixing and tying the steel mesh in Example 1: Figure 4 This is a schematic diagram of anchor construction in Example 1; Figure 5 This is a schematic diagram of reinforced concrete bonding strength detection in Example 1; Figure 6 This is a schematic diagram of shotcrete in Example 1; Figure 7 This is a schematic diagram of the reinforced arch section of Example 1; Among them, 1-measured section of the tunnel, 2-HRB400E diameter Φ14 rebar, 3-rebar mesh, 4-integral rebar mesh, 5-anchor rod, 6-anchor rod spacing, 7-anchor rod spacing, 8-spacing between rebar mesh and wall, 9-thickness of rebar protective layer, 10-concrete filling of pits, 11-reinforcement arch, 12-anchor bar, 13-14# iron wire. DETAILED DESCRIPTION

[0007] The present invention is further described below in conjunction with the embodiments, but the present invention is not limited in any way. Any changes or substitutions made based on the teachings of the present invention belong to the protection scope of the present invention.

[0008] The present invention provides an anchor-net spraying support method applicable to the poor geological section of underground tunnels, which is implemented according to the following steps: 1) Carry out comprehensive prying of the tunnel to ensure the safety of on-site operations, clean the tunnel rock walls, clean the accumulated slag in the tunnel, and clean the side walls thoroughly; 2) Measurement of tunnels in poor geological sections: Use a 3D scanner to measure the tunnels and obtain tunnel cross-section and model data to facilitate support design; 3) Installation of threaded steel mesh: The full section and full support section of the steel mesh are laid horizontally and vertically to form an overall warp and weft grid arrangement. Φ14mm HRB400E threaded steel bars are used as horizontal and vertical bars. The mesh spacing of the threaded steel mesh is 300-350mm. The distance from the steel mesh to the side wall of the tunnel is 5-6cm, and the overlap length is 45-50cm, which is used as the reinforcement for shotcrete. Thin iron wires are tied at each intersection of the horizontal and vertical bars, and the vertical bars must be laid to the bottom when they are woven. Before installing the steel mesh, use an impact drill to construct anchor bars with a diameter of 6mm and a depth of 5cm on the rock wall every 1m to fix the steel mesh. 4) Anchor bolt pressing mesh: After the threaded steel mesh is installed, an anchor trolley is used to construct a pipe-seam anchor bolt pressing mesh with a row spacing of 1.5m~1.6m; 5) Spraying concrete: Prepare concrete according to the ratio of cement: gravel: river sand: cement = 1:1.93:2.17:0.4. Spray concrete in 4 times. The thickness of the 1st and 2nd spraying is 4 cm, and the thickness of the 3rd and 4th spraying is 4 cm and 3 cm respectively. There is a 20-minute interval between each spraying of concrete.

[0009] In step 3), the length of the anchor bar is 280~300mm. The intersection of the horizontal and vertical bars and the lap joints of the steel bars are all firmly tied with No. 14 iron wire; the horizontal and vertical bars should be pressed, knocked, and pulled against the rock wall, and the gap with the rock wall should be controlled at 50mm.

[0010] In step 4), the anchor rod length is 2000 mm, the outer diameter is 43 mm, the rod body tensile strength is 120 MPa, the anchor rod hole depth is 205 cm, and the anchoring force of the anchor rod is 35 KN. In step 4), the anchor holes are constructed at the intersection of the horizontal and vertical reinforcements of the steel mesh and on the lower side of the horizontal reinforcements. The size of the anchor tray is 20cm×20cm. The anchor is constructed perpendicular to the rock surface to ensure a construction angle of 85°-90°. The tray presses the intersection of the horizontal and vertical reinforcements.

[0011] In step 5), the strength of the concrete is 20-25MPa.

[0012] Example 1 1. After the tunnel excavation is completed and accepted, the tunnel is geologically catalogued again to determine the development of fissure water, lithology, fault properties, etc. According to the roof classification management specifications, combined with the actual conditions such as lithology, layer joints, fault fracture zones, service life, mining blasting disturbance, etc., the roof grade is comprehensively determined. Figure 1 As shown, the width of the fault fracture zone is 5m, the fault is a non-water-conducting fault and does not contain fissure water. The medium and deep hole mining blasting causes large disturbances. The service life is 2 years. It is a Class II roof and threaded steel coarse reinforcement-anchor mesh spraying support is determined.

[0013] 2. Support design: Carry out support design after actual measurement of tunnel cross section.

[0014] 3. Construction 1) Carry out comprehensive roughing of the tunnel to ensure the safety of on-site operations, clean the tunnel rock walls, clean up the accumulated slag in the tunnel, and clean up the side walls thoroughly.

[0015] 2) Measurement of tunnels in poor geological sections: Use a 3D scanner to measure the tunnels and obtain tunnel cross-section and model data ( Figure 2 ).

[0016] 3) On-site inspection of threaded steel bars: Use HRB400E diameter Φ14 threaded steel bars, check relevant quality certification documents, and have the tensile strength tested by a testing agency. The steel bars can only be used after they meet the requirements.

[0017] 4) Coarse steel mesh preparation: The vertical reinforcement is laid on the ground during construction, and the mesh size is 30cm×30cm (such as Figure 3 , overlap length 50cm, vertically and horizontally form an overall longitude and latitude network ( Figure 2 ), tie No. 14 thin wire at each node, use impact drill to construct 6mm diameter and 5cm depth anchor bars every 1m, fix the steel mesh, and ensure that the steel mesh is 5cm away from the top plate edge ( Figure 6 ).

[0018] 5) Anchor construction: The length of the anchor used is 2000mm, the outer diameter is 43mm, the tensile strength of the rod is 120MPa, the anchor hole depth is 205cm, and the anchor force is 35KN. The spacing between the anchors is 1.5m×1.5m, and the size of the anchor tray is 20cm×20cm( Figure 4 ), the anchor rod should be perpendicular to the rock surface during construction, ensuring the construction angle is 85°-90°, and the anchor rod tray should press the cross position of the steel mesh.

[0019] 6) Steel bar concrete bond strength test ( Figure 5): After anchor construction and before spraying concrete, a reinforced concrete test block (150mm×150mm) is made, and the steel bar passes through the test block and exceeds by at least 10cm so that the puller can clamp the steel bar. At least 3 groups are used to test the bonding strength of Φ6 round steel bar and Φ14 threaded steel bar when the thickness of the spraying is 15cm. Reinforced concrete bonding strength pull-out test, τ=N / πdι (N- is the maximum bond damage value, KN; d-the diameter of the steel bar; ι- is the bonding length). The next step of construction can be carried out only after the strength is qualified.

[0020] Results: Through pull-out test comparison, the bond strength of Φ14 threaded steel concrete in this embodiment is 4.47MPa. Compared with 1.41MPa of Φ6 plain round steel concrete, the bond strength of steel concrete is significantly improved, which can improve the large-scale damage of the support body after blasting.

[0021] 7) Shotcrete: The weight ratio of finished concrete is cement: crushed stone: river sand: cement = 1:1.93:2.17:0.4. The design strength of concrete is 20MPa, the thickness is 15cm, and the concrete is shotcrete in 4 times: the thickness of the first and second shots is 4cm, subtotal 8cm, the main function is to ensure that the concrete can cover the steel bars, the thickness of the third and fourth shots is 4cm and 3cm respectively, subtotal 7cm, the main function is to ensure a 10cm steel bar protection layer, and at the same time fill the pits and uneven places on the surface of the surrounding rock ( Figure 6 ).

[0022] 8) Calculate the thickness of the reinforced arch: Figure 7 It can be seen that in this embodiment, the anchor mesh spraying forms an integral reinforcement arch, and the thickness of the reinforcement arch is d=1.8m ( Figure 7 ). The thickness of the reinforcement arch d = (Ltanα-a) / tanα (L-effective length of the anchor, 2m; d-thickness of the reinforcement arch; α-the average control angle of the anchor construction is 85°; a-the spacing between the anchors).

Claims

1. An anchor-net spraying support method suitable for poor geological sections of underground tunnels, characterized in that: Follow these steps to achieve this: 1) Carry out comprehensive prying of the tunnel to ensure the safety of on-site operations, clean the tunnel rock walls, clean the accumulated slag in the tunnel, and clean the side walls thoroughly; 2) Measurement of tunnels in poor geological sections: Use a 3D scanner to measure the tunnels and obtain tunnel cross-section and model data; 3) Installation of threaded steel mesh: The full section and full support section of the steel mesh are laid horizontally and vertically to form an overall warp and weft grid arrangement. Φ14mm HRB400E threaded steel bars are used as horizontal and vertical bars. The mesh spacing of the threaded steel mesh is 300-350mm. The distance from the steel mesh to the side wall of the tunnel is 5-6cm, and the overlap length is 45-50cm, which is used as the reinforcement for shotcrete. Thin iron wires are tied at each intersection of the horizontal and vertical bars, and the vertical bars must be laid to the bottom when they are woven. Before installing the steel mesh, use an impact drill to construct anchor bars with a diameter of 6mm and a depth of 5cm on the rock wall every 1m to fix the steel mesh. 4) Anchor bolt pressing mesh: After the threaded steel mesh is installed, an anchor trolley is used to construct a pipe-seam anchor bolt pressing mesh with a row spacing of 1.5m~1.6m; 5) Spraying concrete: Prepare concrete according to the ratio of cement: gravel: river sand: cement = 1:1.93:2.17:0.

4. Spray concrete in 4 times. The thickness of the 1st and 2nd spraying is 4 cm, and the thickness of the 3rd and 4th spraying is 4 cm and 3 cm respectively. There is a 20-minute interval between each spraying of concrete.

2. The anchor-net spraying support method applicable to the poor geological section of underground tunnel according to claim 1 is characterized in that: In step 3), the length of the anchor bar is 280~300mm.

3. The anchor-net spraying support method applicable to the poor geological section of underground tunnel according to claim 1 is characterized in that: In step 3), the intersection of the horizontal and vertical reinforcements and the lap joints of the reinforcements are fully tied with No. 14 iron wire.

4. The anchor-net spraying support method applicable to the poor geological section of underground tunnel according to claim 1 is characterized in that: In step 3), the horizontal and vertical reinforcements should be pressed, knocked, and pulled against the rock wall, and the gap between them and the rock wall should be controlled at 50 mm.

5. The anchor-net spraying support method applicable to the poor geological section of underground tunnel according to claim 1 is characterized in that: In step 4), the anchor rod length is 2000 mm, the outer diameter is 43 mm, the rod body tensile strength is 120 MPa, the anchor rod hole depth is 205 cm, and the anchor rod anchoring force is 35 KN.

6. The anchor-net spraying support method applicable to the poor geological section of underground tunnel according to claim 1 is characterized in that: In step 4), the anchor holes are constructed at the intersection of the horizontal and vertical reinforcements of the steel mesh and on the lower side of the horizontal reinforcements. The size of the anchor tray is 20cm×20cm. The anchor is constructed perpendicular to the rock surface to ensure a construction angle of 85°-90°. The tray presses the intersection of the horizontal and vertical reinforcements.

7. The anchor-net spraying support method applicable to the poor geological section of underground tunnel according to claim 1 is characterized in that: In step 5), the strength of the concrete is 20-25MPa.