Chiseling-free reuse type grouting structure for underground structure and grouting construction method
By using a combination structure of steel fiber concrete and embedded steel cavity in the underground structure, drill-free grouting and slurry reflux prevention are achieved, safety risks and resource waste in the existing technology are solved, and construction efficiency is improved and component utilization.
Patent Information
- Application Number
- CN202411055206.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-11-12
AI Technical Summary
The existing underground structure grouting process requires drilling, which poses safety risks, water leakage, resource waste and leakage problems, and it is difficult to achieve convenient hole opening and component recycling.
The side walls and embedded steel cavity of the underground structure composed of steel fiber concrete are grouted through the removable connection and expansion of the bladder structure to avoid drilling and prevent mud from flowing back. The removable connection and retarder ensure construction safety and Resource utilization.
A safe and controllable grouting operation is achieved, reducing the risk of water pressure, avoiding slurry reflux and leakage, improving construction efficiency, and allowing multiple utilization of some components.
Smart Images

Figure CN118933865A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of underground structure construction, and in particular to a chiseling-free reusable grouting structure and a grouting construction method for underground structures. Background Art
[0002] In underground projects, pressure pumps are often used to inject the prepared slurry with solidification function into the target area, which mainly plays the role of anti-seepage, water blocking, and sedimentation control.
[0003] The main defects of the existing process are as follows:
[0004] 1. It is often necessary to drill holes in underground structures with drill rods before grouting operations can be carried out. When drilling holes, the drill rods are very likely to damage the grouting head, resulting in failure of the sealing plug in the later stage and easy leakage. Affected by factors such as uneven soil distribution and construction technology, the safety risk of grouting and drilling operations in underground structures is relatively high. To ensure smooth injection, the slurry needs to have a large impact force, which increases the workload of the grouting pump and is easy to cause damage to the rock and soil that needs to be reinforced.
[0005] 2. When the drill is pulled out after the grouting hole is drilled, especially when working in a high water pressure and water-rich sand layer environment, it is very easy for a large amount of water and sand to continue to flow out or spray out when the drill is pulled out, which poses a great risk to the safety of construction workers. At the same time, the sprayed slurry greatly affects the appearance quality of the underground structure, and requires a certain amount of manpower and material resources to deal with, thereby reducing construction efficiency.
[0006] 3. The traditional process is prone to slurry reflux, causing cement slurry to overflow, which not only affects the grouting effect, but also causes waste of resources. In particular, the slurry is pressed into the grouting pipe, causing it to be blocked, seriously affecting the construction progress.
[0007] 4. After the drilling and grouting is completed, the mud in the grouting hole will shrink, thus forming a water seepage channel. When the gaps in the grouting holes of the underground structure are not filled densely, the grouting holes will leak water under high water pressure, and even cause mud and water gushing accidents in the grouting holes.
[0008] Therefore, how to easily drill a hole without removing the drill rod, prevent mud from flowing back, avoid the formation of water seepage channels, and recover some components for next use has become a technical problem that technical personnel in this field urgently need to solve. Summary of the invention
[0009] In view of the above-mentioned defects of the prior art, the present invention provides a reusable grouting structure and a grouting construction method for underground structures that do not require chiseling. The purpose of the grouting reinforcement construction of underground structures is to conveniently open holes without chiseling with a drill rod, prevent mud backflow, avoid the formation of water seepage channels, and recover some components for next use.
[0010] To achieve the above-mentioned purpose, the present invention discloses a non-removal reusable grouting structure for underground structures, comprising an underground structure side wall cast by steel fiber concrete, and a pre-buried steel cavity reserved at a position to be grouted when casting the underground structure side wall;
[0011] The embedded steel cavity is tubular, penetrates the underground structure side wall along the thickness direction of the underground structure side wall, is provided with a detachably connected rod cap at one end corresponding to the back surface of the underground structure side wall, is provided with a petal-shaped steel sheet at the other end corresponding to the front surface of the underground structure side wall, and is provided with a grout stopper near the rod cap inside;
[0012] The rod cap is a round tube with a bulkhead that matches the corresponding end of the embedded steel cavity, and the inner cavity is provided with a support rod extending along the length direction of the embedded steel cavity to the other end of the embedded steel cavity;
[0013] One end of the support rod is fixed to the rod cap, and the other end is connected to the center position of the petal-shaped steel sheet;
[0014] During the grouting construction, the rod cap with the support rod is removed through the detachable connection, and a relay pipe is coaxially arranged in the embedded steel cavity;
[0015] The relay pipe is a grouting pipe section, and one or more grouting pipe sections are connected to the other end of the underground structure side wall facing the soil surface, and one or more grouting pipe sections are connected to the end of the underground structure side wall facing the soil surface;
[0016] The outer diameter of the relay pipe is smaller than the inner diameter of the embedded steel cavity and larger than the inner diameter of the stop grout plate. The outer wall is provided with a tubular sac that can expand due to slurry filling, and the side wall is provided with a plurality of grouting holes communicating with the sac.
[0017] The volume of the bladder after expansion corresponds to the dimension of the embedded steel cavity in the length direction and does not exceed the range from the grouting plate to the soil surface of the side wall of the underground structure.
[0018] Preferably, the rod cap has an inner cavity provided with a coaxially arranged external thread;
[0019] The embedded steel cavity is close to the rod cap and has an internal thread matching the external thread;
[0020] The rod cap realizes the detachable connection by fastening the internal external thread with the internal thread at the corresponding end of the embedded steel cavity.
[0021] Preferably, a tube structure matching the support rod is provided at the center position of one side of the petal-shaped steel sheet facing the support rod, and the tube structure is sleeved and fixed to the other end of the support rod.
[0022] Preferably, the petal-shaped steel sheet is a circular sheet structure formed by welding a plurality of fan-shaped steel sheets to one end of the pipe structure located on the soil surface of the side wall of the underground structure.
[0023] Preferably, the relay tube and the bladder are both provided with a retarder.
[0024] Preferably, each of the grouting holes is a tapered hole, and the hole diameter close to the inner side of the relay pipe is larger than the hole diameter close to the outer side of the relay pipe.
[0025] Preferably, the side walls of the underground structure are cast using steel fiber concrete.
[0026] The present invention also provides a grouting construction method, which uses the above-mentioned chiseling-free reusable grouting structure for underground structures to perform grouting construction, and the specific steps are as follows:
[0027] Step 1: Remove the pole cap with the support pole through the detachable connection;
[0028] Step 2: Select the relay pipe and one or more pipe sections located outside the embedded steel cavity and connect them to the grouting pipe section first;
[0029] Step 3, insert each of the first grouting pipe sections sequentially from one end of the pre-buried steel cavity corresponding to the back soil surface of the underground structure side wall, and after connecting the next first grouting pipe section, pass through the pre-buried steel cavity until the relay pipe is inserted into the pre-buried steel cavity;
[0030] Step 4, sequentially connect all the subsequent grouting pipe sections at one end of the relay pipe corresponding to the back soil surface of the underground structure side wall;
[0031] Step 5, performing grouting to form a reinforcement body outside the side wall of the underground structure, and the slurry flows into the bladder from the grouting hole of the relay pipe to expand the bladder;
[0032] Step 6: After the grouting is completed, all the subsequent grouting pipe sections, the relay pipes and all the first grouting pipe sections are withdrawn in sequence while grouting to ensure that the cavity is filled densely.
[0033] Beneficial effects of the present invention:
[0034] The present invention can fundamentally avoid the high-risk drill rod drilling operation on underground structures in the prior art, and avoid the risk of high water pressure breakdown caused by pulling out the drill after the prior drilling operation, so that each operation is safe and controllable, which not only improves the grouting efficiency and ensures the safety of the operators, but also effectively prevents mud backflow, effectively solves the problem of slurry condensation, shrinkage and water seepage, and can recycle some components multiple times.
[0035] The concept, specific structure and technical effects of the present invention will be further described below in conjunction with the accompanying drawings to fully understand the purpose, characteristics and effects of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 A schematic structural diagram of an embodiment of the present invention is shown.
[0037] Figure 2 Showing the present invention Figure 1 Schematic diagram of the cross-section structure along the A axis.
[0038] Figure 3 Showing the present invention Figure 2 Schematic diagram of the cross-sectional structure along the BB axis.
[0039] Figure 4 An exploded schematic diagram showing a connection structure of a pre-buried steel cavity, a rod cap and a petal-shaped steel sheet in one embodiment of the present invention.
[0040] Figure 5 A schematic diagram showing that a relay pipe is arranged in a pre-buried steel cavity in one embodiment of the present invention, and two ends of the relay pipe are respectively connected to a first grouting pipe section and a second grouting pipe section.
[0041] Figure 6 Showing the present invention Figure 5 The schematic diagram of the partial enlarged structure at C in the middle.
[0042] Figure 7 A schematic structural diagram of a relay tube and a capsule according to an embodiment of the present invention is shown.
[0043] Figure 8 A schematic diagram showing the state of a relay pipe and a bladder during grouting according to an embodiment of the present invention is shown. DETAILED DESCRIPTION
[0044] Example
[0045] like Figures 1 to 7 As shown, the excavation-free reusable grouting structure for underground structures includes an underground structure side wall 1 cast by steel fiber concrete, and a pre-buried steel cavity 2 reserved at a position to be grouted when casting the underground structure side wall 1;
[0046] The embedded steel cavity 2 is tubular, and penetrates the underground structure side wall 1 along the thickness direction of the underground structure side wall 1. A detachably connected rod cap 3 is provided at one end corresponding to the back surface of the underground structure side wall 1, and a petal-shaped steel sheet 7 is provided at the other end corresponding to the front surface of the underground structure side wall 1. A grout stopper 13 is provided inside near the rod cap 3.
[0047] The rod cap 3 is a round tube with a bulkhead that matches the corresponding end of the embedded steel cavity 2, and the inner cavity is provided with a support rod 6 that extends along the length direction of the embedded steel cavity 2 to the other end of the embedded steel cavity 2;
[0048] One end of the support rod 6 is fixed to the rod cap 3, and the other end is connected to the center position of the petal-shaped steel sheet 7;
[0049] During the grouting construction, the rod cap 3 with the support rod 6 is removed through the detachable connection, and the relay pipe 8 is coaxially arranged in the embedded steel cavity 2;
[0050] The relay pipe 8 is a grouting pipe segment, which is connected to one or more grouting pipe segments 11 at the other end of the underground structure side wall 1 facing the soil surface, and connected to one or more grouting pipe segments 12 at the end of the underground structure side wall 1 facing the soil surface;
[0051] The outer diameter of the relay pipe 8 is smaller than the inner diameter of the embedded steel cavity 2 and larger than the inner diameter of the stop grout plate 13. The outer wall is provided with a tubular bladder 9 that can expand due to the filling of grout, and the side wall is provided with a plurality of grouting holes 10 connected to the bladder 9.
[0052] The volume of the bladder 9 after expansion corresponds to the dimension of the embedded steel cavity 2 in the length direction and does not exceed the range from the stop grouting plate 13 to the soil surface of the side wall 1 of the underground structure.
[0053] In practical applications, the underground structure side wall 1 cast with steel fiber concrete can ensure that the surroundings of the embedded steel cavity 2 are densely filled and ensure that the corresponding underground structure has the ability to resist lateral water and soil pressure;
[0054] The embedded steel cavity 2 is in a hollow state, and a rod cap 3 with a support rod 6 inside is provided at one end corresponding to the back surface of the underground structure side wall 1, and a petal-shaped steel sheet 7 is provided at the other end corresponding to the back surface of the underground structure side wall 1;
[0055] The pole cap 3 is connected to the embedded steel cavity 2 by a detachable connection, and the petal-shaped steel sheet 7 is supported by the support rod 6. After the construction is completed, the pole cap 3 with the support rod 6 can be recycled and reused.
[0056] During the grouting construction, a grouting pipe section is coaxially arranged in the embedded steel cavity 2 as a relay pipe 8, and a tubular bladder 9 that can expand due to filling with slurry is arranged in the gap between the relay pipe 8 and the embedded steel cavity 2.
[0057] The two ends of the relay pipe 8 can be flexibly connected to other grouting pipe sections according to the positions where grouting is required and the actual distance requirements on site.
[0058] The hollow structure of the embedded steel cavity 2 of the present invention avoids the need for conventional drill rods to chisel away the side walls of the underground structure. Ordinary grouting pipe sections can easily penetrate the petal-shaped steel sheets 7 without requiring a large impact force, thereby reducing the workload of the grouting pump and greatly reducing the safety risks of grouting operations in underground structures.
[0059] The grout-stopping sheet 13, the bladder 9 and the petal-shaped steel sheet 7 of the present invention can effectively prevent the slurry from flowing back, prevent the slurry from being pressed into the grouting pipe and causing the grouting pipe to be blocked, and avoid wasting resources.
[0060] In the present invention, the rod cap 3 with the support rod 6 and all the first grouting pipe sections 11 and the second grouting pipe sections 12 are detachable and can be recycled.
[0061] In some embodiments, the rod cap 3 is provided with a coaxially arranged external thread 4 for the inner cavity;
[0062] The embedded steel cavity 2 is close to the rod cap 3 and has an internal thread 5 matching the external thread 4;
[0063] The rod cap 3 is detachably connected by fastening the internal external thread 4 with the internal thread 5 at the corresponding end of the embedded steel cavity 2 .
[0064] In some embodiments, a tube structure matching with the support rod 6 is provided at the center of the side of the petal-shaped steel sheet 7 facing the support rod 6, and the tube structure is sleeved and fixed to the other end of the support rod 6.
[0065] In some embodiments, the petal-shaped steel sheet 7 is a circular sheet structure formed by welding a plurality of fan-shaped steel sheets to one end of the pipe structure facing the soil surface of the side wall 1 of the underground structure.
[0066] In some embodiments, both the relay tube 8 and the balloon 9 are provided with a retarder.
[0067] In practical applications, the provision of the retarder can prevent the shrinkage of the slurry in the relay pipe 8 and the bladder 9 during grouting.
[0068] In some embodiments, each grouting hole 10 is a tapered hole, and the hole diameter close to the inner side of the relay pipe 8 is larger than the hole diameter close to the outer side of the relay pipe 8 .
[0069] In practical applications, the grouting holes 10 in the form of tapered holes with larger inner holes and smaller outer holes can enable the mud to expand the bladder 9 more quickly, thereby further preventing the mud from flowing back.
[0070] In some embodiments, the underground structure side wall 1 is cast by steel fiber concrete.
[0071] like Figures 1 to 8 As shown, the present invention also provides a grouting construction method, using the above-mentioned chiseling-free reusable grouting structure for underground structures to perform grouting construction, and the specific steps are as follows:
[0072] Step 1, removing the rod cap 3 with the support rod 6 through a detachable connection;
[0073] Step 2, select the relay pipe 8 and one or more pipe sections 11 located outside the embedded steel cavity 2 and connect them first;
[0074] Step 3, insert each first grouting pipe section 11 sequentially from the end of the pre-buried steel cavity 2 corresponding to the back soil surface of the underground structure side wall 1, and after connecting the subsequent first grouting pipe section 11, pass through the pre-buried steel cavity 2 until the relay pipe 8 is inserted into the pre-buried steel cavity 2;
[0075] Step 4, sequentially connect all the subsequent grouting pipe sections 12 at one end of the relay pipe 8 corresponding to the back soil surface of the underground structure side wall 1;
[0076] Step 5: Perform grouting to form a reinforcement body outside the side wall 1 of the underground structure, and the slurry flows into the bladder 9 from the grouting hole 10 of the relay pipe 8 to expand the bladder 9;
[0077] Step 6: After the grouting is completed, all the subsequent grouting pipe sections 12, the relay pipes 8 and all the previous grouting pipe sections 11 are withdrawn in sequence while grouting to ensure that the cavity is filled densely.
[0078] During construction, after grouting is completed, the grouting is withdrawn while it is being poured, and a reinforcement body has been formed on the outside of the side wall 1 of the underground structure. The safety of construction workers can be guaranteed during the pipe pulling process, and there is no risk of grouting affecting the appearance quality of the underground structure, thereby improving construction efficiency.
[0079] The preferred specific embodiments of the present invention are described in detail above. It should be understood that a person skilled in the art can make many modifications and changes based on the concept of the present invention without creative work. Therefore, any technical solution that can be obtained by a person skilled in the art through logical analysis, reasoning or limited experiments based on the concept of the present invention on the basis of the prior art should be within the scope of protection determined by the claims.
Claims
1. A non-removal reusable grouting structure for underground structures; characterized in that: It comprises a pre-buried steel cavity (2) reserved at a position to be grouting when pouring the underground structure side wall (1); The embedded steel cavity (2) is tubular and penetrates the underground structure side wall (1) along the thickness direction of the underground structure side wall (1). A detachably connected rod cap (3) is provided at one end corresponding to the back surface of the underground structure side wall (1), and a petal-shaped steel sheet (7) is provided at the other end corresponding to the front surface of the underground structure side wall (1). A grout stopper (13) is provided inside the cavity near the rod cap (3). The rod cap (3) is a round tube with a blanking end matched with a corresponding end of the embedded steel cavity (2), and the inner cavity is provided with a support rod (6) extending along the length direction of the embedded steel cavity (2) to the other end of the embedded steel cavity (2); One end of the support rod (6) is fixed to the rod cap (3), and the other end is connected to the center position of the petal-shaped steel sheet (7); During grouting construction, the rod cap (3) with the support rod (6) is removed through the detachable connection, and a relay pipe (8) is coaxially arranged in the embedded steel cavity (2); The relay pipe (8) is a grouting pipe segment, and the other end corresponding to the soil surface of the underground structure side wall (1) is connected to one or more grouting pipe segments (11) first, and the end corresponding to the soil surface of the underground structure side wall (1) is connected to one or more grouting pipe segments (12) later; The outer diameter of the relay pipe (8) is smaller than the inner diameter of the embedded steel cavity (2) and larger than the inner diameter of the stop grout plate (13); the outer wall is provided with a tubular sac (9) that can expand due to slurry filling, and the side wall is provided with a plurality of grouting holes (10) communicating with the sac (9); The volume of the bladder (9) after expansion corresponds to the dimension of the embedded steel cavity (2) in the length direction and does not exceed the range from the stop plate (13) to the soil surface of the underground structure side wall (1).
2. The chiseling-free reusable grouting structure for underground structures according to claim 1, characterized in that: The rod cap (3) has an inner cavity provided with a coaxially arranged external thread (4); The embedded steel cavity (2) is provided with an internal thread (5) matching the external thread (4) close to the rod cap (3); The rod cap (3) realizes the detachable connection by fastening the internal external thread (4) with the internal thread (5) at the corresponding end of the embedded steel cavity (2).
3. The chiseling-free reusable grouting structure for underground structures according to claim 1, characterized in that: A tube structure matching the support rod (6) is provided at the center of the petal-shaped steel sheet (7) facing the support rod (6), and the tube structure is sleeved and fixed to the other end of the support rod (6).
4. The non-excavation reusable grouting structure for underground structures according to claim 1, characterized in that: The petal-shaped steel sheet (7) is a circular sheet structure formed by welding a plurality of fan-shaped steel sheets to one end of the pipe structure located on the soil surface of the side wall (1) of the underground structure.
5. The chiseling-free reusable grouting structure for underground structures according to claim 1, characterized in that: The relay pipe (8) and the capsule (9) are both provided with a retarder.
6. The non-excavation reusable grouting structure for underground structures according to claim 1, characterized in that: Each of the grouting holes (10) is a tapered hole, and the hole diameter close to the inner side of the relay pipe (8) is larger than the hole diameter close to the outer side of the relay pipe (8).
7. The chiseling-free reusable grouting structure for underground structures according to claim 1, characterized in that: The underground structure side wall (1) is cast using steel fiber concrete.
8. A grouting construction method, characterized in that: The grouting construction is carried out by using the non-removal reusable grouting structure for underground structures as claimed in any one of claims 1 to 6, and the specific steps are as follows: Step 1, removing the rod cap (3) with the support rod (6) through a detachable connection; Step 2, select the relay pipe (8) and one or more pipe sections (11) located outside the embedded steel cavity (2); Step 3, inserting each of the first grouting pipe sections (11) sequentially from one end of the pre-buried steel cavity (2) corresponding to the back side of the underground structure side wall (1), and passing through the pre-buried steel cavity (2) after connecting the next first grouting pipe section (11) until the relay pipe (8) is inserted into the pre-buried steel cavity (2); Step 4, sequentially connecting all the subsequent grouting pipe sections (12) at one end of the relay pipe (8) corresponding to the back soil surface of the underground structure side wall (1); Step 5: performing grouting to form a reinforcement body outside the side wall (1) of the underground structure, wherein the grout flows into the bladder (9) from the grouting hole (10) of the relay pipe (8) to expand the bladder (9); Step 6: After the grouting is completed, all the subsequent grouting pipe sections (12), the relay pipe (8) and all the first grouting pipe sections (11) are withdrawn in sequence while grouting to ensure that the cavity is filled densely.