High-strength negative Poisson's ratio structure for ore removal roadway support, support facility and construction process

Through the high-strength negative Poisson ratio structure and support facilities, combined with the design of anchor rods, anchor nets and sandbags, the stability and cost problems of tunnel support construction in mining technology are solved, and efficient and safe tunnel support effect is achieved. .

CN118934015AActive Publication Date: 2024-11-12CENT SOUTH UNIV +2

Patent Information

Application Number
CN202411131971.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-12
Estimated Expiration
2044-08-16

AI Technical Summary

Technical Problem

In the existing mining technology, the support method of mine exit tunnels has problems such as long construction cycle, high cost, low degree of mechanization and poor stability of the filling body. Especially when tunnels are dug into the filling body, it is easy to collapse and fall, and the filling body is The body damage is large, affecting the stability of the tunnel.

Method used

Adopt a high-strength negative Poisson's ratio structure, including filler, negative Poisson's ratio protection module, anchor rod, anchor net and sandbag, connected through the bottom plate groove fixing and tenon self-locking structure, anchor rod and anchor net reinforce, and Fill sandbags in the gap to ensure the drainage of the filling slurry and the stability of the tunnel.

Benefits of technology

It realizes high-strength support, simplifies construction, reduces costs, ensures the stability of the filling body and tunnel, and avoids damage to the filling body by anchors. It is suitable for a variety of filling mining methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934015A_ABST
    Figure CN118934015A_ABST
Patent Text Reader

Abstract

The invention discloses a high-strength negative Poisson's ratio structure for ore removal roadway supporting, a supporting facility and a construction technology, and belongs to the technical field of mining. Comprising a filling body, a negative Poisson's ratio protection module, an anchor rod, an anchor net and a sandbag, the filling body and the negative Poisson's ratio protection module are tightly attached and fixed through a groove in a bottom plate, and filling slurry which is not completely bleeding in the deep portion of the filling body can be drained through the negative Poisson's ratio protection module; the adjacent negative poisson ratio protection modules are connected in an engaged mode through mortise and tenon self-locking structures. The anchor rods are arranged at the contact positions of the ore removal roadway roof and the top ends of the negative Poisson's ratio protection modules, and the anchor net is additionally laid between the anchor rods. And the sandbag is filled in a gap between the negative Poisson's ratio protection module and the top ore body. The device is wide in applicability, the size of the negative Poisson's ratio protection module can be adjusted according to site conditions, and the device can be widely applied to various filling mining methods.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of mining, and in particular to a high-strength negative Poisson's ratio structure, supporting facilities and a construction process for supporting a mine tunnel. Background Art

[0002] Most domestic mining companies use the upward horizontal layer filling method, the upward layer approach filling method and the subsequent filling mining method to ensure the stability of the filling body, but it inevitably reduces the recovery rate of ore and causes resource waste. When some mines recover the pillars, there are two main ways to arrange the tunnels in the goaf: re-excavation and reserved tunnels. The former first fills the goaf, and then re-excavates a tunnel in the filling body after the filling body reaches the designed strength. However, this method has a long cycle, huge labor and financial consumption, and may also cause damage to the filling body during the excavation process. The commonly used methods for reserving tunnels in the latter are: installing a closed rigid baffle in the goaf, and removing the baffle after the filling is completed. This method has a low degree of mechanization and low construction efficiency. When the pressure is large, the rigid baffle does not have a pressure-relieving effect, and there is a safety hazard of the rigid baffle collapsing as a whole. The filling slurry will leak, and the cost is high; when the method of re-excavating the tunnel is adopted, how to ensure the stability of the filling body and the tunnel while excavating the tunnel in the filling body has become an urgent problem to be solved; the current solution of the mine is to use shotcrete, anchor rods, and anchor nets for support according to the state of the filling body while excavating, but as the length of the excavated tunnel increases, when going deep into the filling body, the problem of insufficient filling body strength caused by untimely and insufficient drainage will be encountered, resulting in the filling body collapsing and falling during the tunnel excavation process. At present, the mine can only continue to increase the number of anchor rods on the basis of the previous support to achieve tunnel stability. The construction process is complex and the cost is high. At the same time, it causes great damage to the filling body and is not conducive to the stability of the tunnel.

[0003] For example: [Application Number] 202210722533.5, [Application Date] 2022.06.24, [Name] A device for reserving a tunnel for filling a goaf and a construction process thereof. The process separates the goaf into a reserved tunnel through an inflatable air cushion. In the specific implementation, the inflatable air cushion is prone to leakage. The presence of the air cushion will affect the precipitation of water in the filling slurry, and the water filtration is incomplete and inefficient, which affects the safety of the tunnel and the stability of the filling body.

[0004] For example: [Application Number] 202123383631.0, [Application Date] 2021.12.29, [Name] A reserved tunnel device for underground cementing filling. The device adopts a detachable and linked retaining wall monomer, which is a rigid support and has no pressure-relieving effect. When the pressure is large, there is a risk of overall collapse. Summary of the invention

[0005] The technical problem to be solved by the present invention is to propose a high-strength negative Poisson's ratio structure, support facilities and construction process for supporting mine tunnels in view of the deficiencies of the above-mentioned prior art.

[0006] To achieve its purpose, the present invention adopts the following technical scheme: a high-strength negative Poisson's ratio structure for supporting mining tunnels, including a filling body, a negative Poisson's ratio protection module, an anchor rod, an anchor net and a sandbag. The filling body and the negative Poisson's ratio protection module are tightly fitted and fixed by a groove at the bottom plate, which is conducive to the drainage of the filling slurry that has not completely seeped water in the deep part of the filling body through the negative Poisson's ratio protection module. Adjacent negative Poisson's ratio protection modules are mutually engaged and connected by a mortise and tenon self-locking structure; the anchor rod is driven at the contact position between the top plate of the mining tunnel and the top of the negative Poisson's ratio protection module, and an anchor net is laid and installed between the anchor rods; the sandbag fills the gap between the negative Poisson's ratio protection module and the top ore body.

[0007] Furthermore, the negative Poisson's ratio protection module is a trapezoidal body with protrusion and groove structures on both sides.

[0008] Another technical solution of the present invention: a support facility on both sides of a mine exit tunnel, comprising the high-strength negative Poisson's ratio structure in the above technical solution.

[0009] A construction process for supporting facilities on both sides of a mine tunnel of the present invention comprises the following steps:

[0010] T1: After the backfilling of the stope is completed, it is necessary to dig a section of the exit tunnel in the stope that has been filled. The number of negative Poisson's ratio protection modules required is determined according to the length of each tunnel excavation.

[0011] T2: Leveling the tunnel, trimming the protruding filling body at the location where the negative Poisson's ratio protection module has been determined, trimming the mine tunnel into a regular cross section, and at the same time, digging grooves in the filling body on both sides of the bottom plate for fixing the negative Poisson's ratio protection module;

[0012] T3: After each excavation, fix the negative Poisson's ratio protection modules in the grooves of the bottom plates on both sides of the tunnel in sequence; the negative Poisson's ratio protection modules are trapezoidal, with protrusions and grooves on both sides, and two adjacent structural blocks are connected to each other through their own mortise and tenon structures to form a whole; when installing the structural blocks, they should be wedged in pairs according to the structural block design, and firmly wedged by relying on the special performance of the negative Poisson's ratio structure to expand laterally when subjected to axial tension;

[0013] T4: After the negative Poisson's ratio protection module of each section of the tunnel is installed, the tunnel roof is reinforced, and anchor rods are installed at the contact position between the top of the negative Poisson's ratio protection module and the roof on both sides of the tunnel, and a certain number of anchor rods are installed in sequence according to the spacing, and anchor nets are laid on the anchor rods to make it a supporting whole;

[0014] T5: After all the negative Poisson's ratio protection modules are stacked, fill the top of the negative Poisson's ratio protection modules with sandbags and perform grouting to fill the gaps around them to form a complete support structure;

[0015] T6: After the first section of the tunnel support is completed, repeat the above steps until the tunnel excavation and support are completed, and finally lay the concrete pavement on the bottom plate.

[0016] Preferably, in step T2, the size of the mining tunnel is 4.5m×2.5m. Mechanical rock breaking and masonry leveling methods are used to make the tunnel smoother during tunnel excavation. Sprayed concrete and manual finishing methods are used to make the tunnel smooth and easy to stack structural blocks.

[0017] Preferably, the grooves excavated on both sides of the mining tunnel have a width of 1-1.5 m and a depth of 0.2-0.3 m.

[0018] Preferably, in step T3, the size of the negative Poisson's ratio protection module is 1m×1m×2.5m, the size of the mortise and tenon structure of the module is 0.2m×0.1m, and the connection between adjacent negative Poisson's ratio protection modules is a structure that can be wedged together; the module material is a high-strength plastic with a tensile strength of 100-200Mpa, and the high-strength plastic is nylon or polyamide.

[0019] Preferably, in step T4, when the structural blocks are longitudinally laid at the preset positions of the support structure, two adjacent longitudinal negative Poisson's ratio protection modules need to be embedded in the grooves of the bottom plate to be fixed.

[0020] Further preferably, in step T5, when grouting is performed on the gaps around the stacked negative Poisson's ratio structure mine tunnel support facilities, the gaps need to be filled to make it a complete retaining wall structure and prevent it from cracking along the gaps. At the same time, when there is a gap between the negative Poisson's ratio protection module and the top ore body, sandbags should be filled in to make the overall structure more stable.

[0021] Further preferably, in step T6, the negative Poisson's ratio structure mine tunnel support facilities need to reach a stress strength that can support the first section of tunnel excavation before the next stage of tunnel excavation can be carried out.

[0022] Beneficial effects of the present invention:

[0023] Compared with the prior art, the high-strength negative Poisson's ratio structure, the mine tunnel support facility and the construction method of the present invention have more prominent advantages:

[0024] 1. The supporting facilities are high in strength, highly modularized, easy to install, and can play the role of supporting the tunnel in a short time.

[0025] 2. The construction is simple, the materials are easy to obtain, and the manufacturing cost is relatively low.

[0026] 3. The filling water filtration effect is good, which is beneficial to the drainage of the filling body, so that its strength is further increased. There is no need to worry about the damage to the filling body caused by anchor rods in the excavation tunnel. It can ensure the strength of the filling body on both sides of the mining tunnel and ensure the safety and stability of the mining tunnel.

[0027] 4. Wide applicability. The size of the negative Poisson's ratio protection module can be adjusted according to the on-site conditions and can be widely used in various filling mining methods. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] For ease of explanation, the present invention is described in detail with reference to the following specific embodiments and the accompanying drawings.

[0029] Figure 1 This is a schematic diagram of the support facilities for the mine tunnel with a negative Poisson's ratio structure in the stope;

[0030] Figure 2 This is the three-view diagram of the negative Poisson's ratio protection module;

[0031] Figure 3 This is a schematic diagram of the negative Poisson's ratio protection module;

[0032] Figure 4 This is a schematic diagram of the fixing groove of the negative Poisson's ratio protection module;

[0033] Figure 5 This is a schematic diagram of the negative Poisson's ratio protection module and the anchor bolt fixing point;

[0034] Figure 6 It is a schematic diagram of the mortise and tenon connection of adjacent negative Poisson's ratio protection modules;

[0035] Figure 7 This is a schematic diagram of the location of the mine tunnel;

[0036] Description of reference numerals:

[0037] 1-Negative Poisson's ratio protection module; 2-Sandbag; 3-Bottom plate; 4-Filling body; 5-Mine exit tunnel; 6-Mining column; 7-Anchor rod; 8-Anchor net. DETAILED DESCRIPTION

[0038] The following are specific embodiments of the present invention and are combined with the attached Figure 1-7, the technical solutions of the present invention are further described, but the present invention is not limited to these embodiments; in the following description, specific details such as specific configurations are provided only to help fully understand the embodiments of the present invention. Therefore, it should be clear to those skilled in the art that various changes and modifications can be made to the embodiments described herein without departing from the scope and spirit of the present invention.

[0039] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features of the embodiments may be combined with each other.

[0040] Example 1

[0041] A high-strength negative Poisson's ratio structure for supporting a mine tunnel includes a filling body 4, a negative Poisson's ratio protection module 1, an anchor rod 7, an anchor net 8 and a sandbag 2. The filling body 4 and the negative Poisson's ratio protection module 1 fit tightly together and are fixed by a groove at a bottom plate 3. Adjacent negative Poisson's ratio protection modules 1 are interlocked and connected with each other by a mortise and tenon self-locking structure. The anchor rod 7 is set at the contact position between the top plate of the mine tunnel 5 and the top of the negative Poisson's ratio protection module 1, and an anchor net 8 is laid and installed between the anchor rods 7. The sandbag 2 is filled in the gap between the negative Poisson's ratio protection module 1 and the top ore body. The negative Poisson's ratio protection module 1 is a trapezoidal body with protrusions and groove structures on both sides.

[0042] Example 2

[0043] A support facility on both sides of a mine tunnel, comprising the high-strength negative Poisson's ratio structure in the above technical solution. The size of the mine tunnel 5 is 4.5m×2.5m; the size of the grooves excavated on both sides of the mine tunnel 5 is 1-1.5m wide and 0.2-0.3m deep; the size of the negative Poisson's ratio protection module 1 is 1m×1m×2.5m, and the size of the mortise and tenon structure of the module is 0.2m×0.1m.

[0044] Example 3

[0045] A construction process for support facilities on both sides of a mine tunnel comprises the following steps:

[0046] T1: After the backfilling of the stope is completed, it is necessary to dig a section of the exit tunnel 5 in the stope that has been filled. The number of negative Poisson's ratio protection modules 1 required is determined according to the length of each tunnel excavation.

[0047] T2: Leveling the tunnel, trimming the protruding filling body at the determined location of the negative Poisson's ratio protection module 1, trimming the mine tunnel into a regular cross section, and at the same time, digging grooves in the filling body on both sides of the bottom plate 3 to fix the negative Poisson's ratio protection module 1; the size of the mine tunnel 5 is 4.5m×2.5m. Mechanical rock breaking and masonry leveling methods are used to make the tunnel more flat during tunnel excavation. When leveling the tunnel, spraying concrete and manual finishing methods are used to make the tunnel flat and smooth to facilitate the stacking of structural blocks; the grooves on both sides of the mine tunnel 5 are 1-1.5m wide and 0.2-0.3m deep;

[0048] T3: After each excavation, the negative Poisson's ratio protection module 1 is fixed in the grooves of the bottom plate 3 on both sides of the tunnel in sequence; wherein, the negative Poisson's ratio protection module 1 is a trapezoidal body with protrusions and groove structures on both sides, and two adjacent structural blocks are interlocked and connected to form a whole through their own mortise and tenon structures; when installing the structural blocks, they should be wedged in pairs according to the structural block design, and firmly wedged by relying on the special performance of the lateral expansion of the negative Poisson's ratio structure when axially tensile; the size of the negative Poisson's ratio protection module 1 is 1m×1m×2.5m, and the size of the module at the mortise and tenon structure is 0.2m×0.1m, and the module material is a high-strength plastic with a tensile strength of 100-200Mpa, and the high-strength plastic is nylon or polyamide;

[0049] T4: After the negative Poisson's ratio protection module 1 of each section of the tunnel is installed, the tunnel roof is reinforced, anchor rods are installed at the contact position between the top of the negative Poisson's ratio protection module 1 and the roof on both sides of the tunnel, and a certain number of anchor rods 7 are installed in sequence according to the spacing, and anchor nets 8 are laid on the anchor rods to form a supporting whole;

[0050] T5: After all negative Poisson's ratio protection modules 1 are stacked, sandbags 2 are stuffed into the top of the negative Poisson's ratio protection modules 1, and grouting is performed around the gaps to make it a complete support structure; when grouting is performed around the gaps of the stacked negative Poisson's ratio structure mine tunnel support facilities, the gaps need to be filled to make it a complete retaining wall structure and prevent it from cracking along the gaps. At the same time, when there is a gap between the negative Poisson's ratio protection module 1 and the top ore body, the sandbags 2 should be stuffed in to make the overall structure more stable;

[0051] T6: After the first section of the tunnel support is completed, the above steps are repeated until the tunnel excavation support is completed, and finally the concrete pavement is laid on the bottom plate. The negative Poisson's ratio structure exit tunnel support facilities must reach the stress strength that can support the first section of the tunnel excavation before the next stage of tunnel excavation can be carried out.

[0052] In this embodiment, when the tunnel is uneven, shotcrete, manual finishing, mechanical rock breaking and masonry leveling can be used during tunnel excavation to make the tunnel as smooth as possible to facilitate the stacking of structural blocks; the required number of negative Poisson's ratio protection modules and the shape of the structural blocks need to be determined according to the size of the tunnel where the support facilities are located and the filling body pressure that needs to be borne; grooves of appropriate size are excavated on both sides of the bottom plate of the mine tunnel so that the bottom of the negative Poisson's ratio protection module can be embedded in the groove to meet the needs of subsequent fixing operations; the negative Poisson's ratio protection modules are stacked and fixed by the interlocking connection of the negative Poisson's ratio protection modules themselves; after the negative Poisson's ratio protection modules are stacked, the gaps on the negative Poisson's ratio support facilities are grouting filled, and sandbags are filled into the gaps between the negative Poisson's ratio protection modules and the upper ore body to make them a complete support structure; after each section of the negative Poisson's ratio protection module is installed, in order to ensure the stability of the tunnel roof, anchor rods and anchor nets are laid at appropriate intervals on the roof. The construction process of this embodiment is simple, the materials are easily available, and the manufacturing cost is relatively low.

[0053] Those skilled in the art to which the present application belongs may make various modifications or additions to the specific embodiments described or replace them in a similar manner, but they will not deviate from the inventive concept of the present application or exceed the scope defined by the attached claims.

Claims

1. A high-strength negative Poisson's ratio structure for supporting a mine tunnel, characterized in that: The invention comprises a filling body (4), a negative Poisson's ratio protection module (1), an anchor rod (7), an anchor net (8) and a sandbag (2); the filling body (4) and the negative Poisson's ratio protection module (1) are tightly fitted and fixed by a groove at a bottom plate (3); adjacent negative Poisson's ratio protection modules (1) are mutually engaged and connected by a mortise and tenon self-locking structure; the anchor rod (7) is driven at a contact position between a top plate of a mine exit tunnel (5) and the top of the negative Poisson's ratio protection module (1); an anchor net (8) is laid and installed between the anchor rods (7); and the sandbag (2) is filled in a gap between the negative Poisson's ratio protection module (1) and the top ore body.

2. The high-strength negative Poisson's ratio structure for supporting a mine tunnel according to claim 1, characterized in that: The negative Poisson's ratio protection module (1) is a trapezoidal body with convex and concave structures on both sides.

3. A support facility on both sides of a mine tunnel, characterized in that: The invention comprises the high-strength negative Poisson's ratio structure as described in claim 1 or 2.

4. A construction process for the support facility according to claim 3, characterized in that: The steps include: T1: After the backfilling of the stope is completed, it is necessary to dig a mine exit tunnel in the stope that has been filled. First, a section of the mine exit tunnel (5) is excavated by mechanical means. The number of negative Poisson's ratio protection modules (1) required is determined according to the length of the tunnel excavated each time. T2: leveling the tunnel, trimming the protruding filling body at the determined location of the negative Poisson's ratio protection module (1), trimming the mine tunnel into a regular cross section, and at the same time, drilling grooves in the filling body on both sides of the bottom plate (3) for fixing the negative Poisson's ratio protection module (1); T3: After each excavation, the negative Poisson's ratio protection module (1) is fixed in sequence in the grooves of the bottom plate (3) on both sides of the tunnel; wherein the negative Poisson's ratio protection module (1) is a trapezoidal body with protrusions and grooves on both sides, and two adjacent structural blocks are interlocked and connected to each other through their own mortise and tenon structures to form a whole; T4: After the negative Poisson's ratio protection module (1) of each section of the tunnel is installed, the tunnel roof is reinforced, anchor rods are installed at the contact position between the top of the negative Poisson's ratio protection module (1) and the roof on both sides of the tunnel, and a certain number of anchor rods (7) are installed in sequence according to the spacing, and anchor nets (8) are laid on the anchor rods to form a supporting whole; T5: After all the negative Poisson's ratio protection modules (1) are stacked, sandbags (2) are stuffed on top of the negative Poisson's ratio protection modules (1), and grouting is performed on the gaps around the negative Poisson's ratio protection modules (1) to form a complete support structure; T6: After the first section of the tunnel support is completed, repeat the above steps until the tunnel excavation and support are completed, and finally lay the concrete pavement on the bottom plate.

5. The construction process according to claim 4, characterized in that: In step T2, the size of the mining tunnel (5) is 4.5m×2.5m. Mechanical rock breaking and masonry leveling methods are used to make the tunnel more flat during tunnel excavation. Sprayed concrete and manual finishing methods are used to make the tunnel smooth and flat to facilitate the stacking of structural blocks.

6. The construction process according to claim 4, characterized in that: In step T2, grooves with a width of 1-1.5 m and a depth of 0.2-0.3 m are excavated on both sides of the mine tunnel (5).

7. The construction process according to claim 4, characterized in that: In step T3, the size of the negative Poisson's ratio protection module (1) is 1m×1m×2.5m, the size of the mortise and tenon structure of the module is 0.2m×0.1m, and the connection between adjacent negative Poisson's ratio protection modules (1) is a structure that can be wedged together; the module material is a high-strength plastic with a tensile strength of 100-200Mpa, and the high-strength plastic is nylon or polyamide.

8. The construction process according to claim 4, characterized in that: In step T4, when the structural blocks are longitudinally laid at the preset positions of the support structure, two adjacent longitudinal negative Poisson's ratio protection modules (1) need to be embedded in the grooves of the bottom plate to be fixed.

9. The construction process according to claim 4, characterized in that: In step T5, when grouting is performed on the gaps around the stacked negative Poisson's ratio structure mine tunnel support facilities, the gaps need to be filled to make it a complete retaining wall structure and prevent it from cracking along the gaps. At the same time, when there is a gap between the negative Poisson's ratio protection module (1) and the top ore body, it should be filled with sandbags (2) to make the overall structure more stable.

10. The construction process according to claim 4, characterized in that: In step T6, the negative Poisson's ratio structure of the mine tunnel support facilities must reach a stress strength that can support the first section of the tunnel excavation before the next stage of tunnel excavation can be carried out.

Citation Information

Patent Citations

  • Method of withdrawal passage combined with paste prefabricated blocks to assist working face withdrawal

    CN109209484A

  • Work face withdrawal method in end-mining stage with waste rocks helpful for filling

    CN109209490A

  • Underground abandoned roadway full tailings consolidation disposal system and method

    CN110056390A

  • Collaborative design and construction method of gob-side entry retaining anchor protection structure without roadside filling

    CN114704273A

  • Filling body drainage system and construction method thereof

    CN116181409A

Cited By

  • Roadway negative Poisson's ratio gradient energy absorption supporting device

    CN119801603A

  • A roadway negative Poisson's ratio gradient energy absorption support device

    CN119801603B

  • Advanced support combined with negative Poisson's ratio structural slab filling and construction method thereof

    CN119982061A

  • Advanced support combined with negative Poisson's ratio structural plate filling and its construction method

    CN119982061B