Tunnel defect construction device

By combining advanced forecasting and detection agencies with intelligent construction platforms, efficient detection and repair of tunnel defects across the entire cross section are achieved. This solves the problems of low detection efficiency and limited repair capabilities in existing technologies, improves construction efficiency and safety, and enables proactive prevention of defects.

CN118934036APending Publication Date: 2024-11-12CHINA RAILWAY FIFTH SURVEY & DESIGN INST GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411090025.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

Existing methods for detecting tunnel defects are inefficient and inaccurate, making it difficult to achieve full-section coverage detection. Furthermore, they have limitations in the repair process and cannot effectively prevent defects, resulting in low construction efficiency and insufficient safety.

Method used

By employing an advanced forecasting and detection agency combined with multiple detection methods, data collection and defect prediction of the entire tunnel section are achieved. Full-section coverage repair is realized through an intelligent construction platform. Data mining and genetic algorithms are integrated for defect prediction. The collaborative operation of the drive base and construction platform ensures repair quality and efficiency.

Benefits of technology

It enables efficient, full-section detection and repair of tunnel defects, improves detection accuracy and predictive ability, enhances construction efficiency and safety, meets the requirements of different construction spaces, and avoids the risk of delayed detection and treatment of defects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934036A_ABST
    Figure CN118934036A_ABST
Patent Text Reader

Abstract

The invention discloses a tunnel defect construction device which comprises a railway flatcar detachably connected with an external locomotive. The advanced forecasting detection mechanism is arranged on the railway flatcar; the driving base is arranged on the railway flatcar, and the driving base is electrically connected with the advanced forecasting detection mechanism; the construction platform is arranged on the driving base, and the construction platform has an unfolded form and a contracted form; the first detection mechanism and the second detection mechanism are arranged on the construction platform, and the first detection mechanism, the second detection mechanism and the construction platform are respectively connected with the advanced forecasting detection mechanism. Therefore, detection of defects such as fine cracks and water seepage of tunnel surface diseases and efficient detection and prediction of potential hazards of deep water layers and cavities can be achieved, meanwhile, the equipment has the full-section multi-point simultaneous construction capacity, accurate construction and efficient operation of a construction platform are guaranteed, different construction space requirements are met, and the construction efficiency is improved. The whole operation process is more flexible, and the construction efficiency and safety are remarkably improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of tunnel maintenance equipment, and in particular to a tunnel disease construction device. Background Art

[0002] In the long-term operation and maintenance of tunnels, facing multiple challenges such as complex geological conditions, differences in construction quality, accumulated service life, dynamic vehicle loads and natural disasters, the tunnel structure is prone to potential defects such as crack expansion, increased water seepage and increased deformation, which seriously threaten its safety, stability and smooth passage. Therefore, regular implementation of comprehensive construction maintenance (covering disease detection and repair) has become an indispensable safeguard.

[0003] At present, one method of detecting defects on the tunnel surface is to use a catenary maintenance vehicle equipped with a mechanical arm, relying on manual visual judgment and hand hammer knocking echo analysis to determine tunnel cracks and water seepage problems. Although this method is intuitive, it has significant limitations: during the detection process, a single tunnel arch can only focus on 1 to 2 detection points at the same time, and point-to-point detection leads to low overall detection efficiency. At the same time, due to the uncertainty of human factors (such as fatigue, distraction, etc.) during the detection process, the risk of missed detection or false detection is also increased. Secondly, manual knocking detection mainly relies on the echo of the knocking sound to determine whether there are cavities or defects inside the tunnel lining. However, the accuracy of this method is highly dependent on the experience and judgment of the inspectors. For deeper cavities or water layers, since the sound will be affected by the medium (such as concrete, rock, water, etc.) during the propagation process, the echo may become blurred or difficult to identify. Therefore, it is impossible to achieve comprehensive coverage detection of the tunnel wall, especially for the deeper cavities and water layers in the tunnel, it is impossible to know, which increases the risk of concrete failure and the decrease of surface tension of the tunnel soil layer and even tunnel collapse.

[0004] As another conventional means of advance prediction, LiDAR can indeed make up for the shortcomings of manual inspection to a certain extent in tunnel surface quality inspection, but it still has certain limitations: the single detection form and relatively insufficient detection accuracy make it difficult to capture all subtle structural changes, especially for long cracks that are not obvious on the surface but are caused by the shear force of the tunnel. This can easily lead to the existence of water layers or water accumulation in cavities inside the tunnel. These water may quietly seep out along the tiny pores or fine cracks inside the concrete, making the tunnel potentially risky.

[0005] At the same time, after the surface defects of the tunnel are detected and identified, in order to ensure the implementation and comprehensive repair work of the problem area, it is often necessary to urgently build an additional scaffolding structure or use the support platform of the maintenance vehicle to open up the working area. However, the above two methods have their own limitations. Although the support platform of the maintenance vehicle provides operating space, it only provides a single free working surface and cannot exceed the free working surface for full-section coverage repair. It may cause side leakage of water seepage problems after repair, so that the disease problem is only transferred between locations instead of being truly solved. In contrast, although the scaffolding structure can break through this limitation and achieve a wider range of repair work surfaces, its installation and disassembly process is often limited by time constraints (generally six hours), and it is easy to cause irregular erection due to rush work, and safety is difficult to guarantee. It also increases the complexity of construction and affects the efficiency and flexibility of the overall operation.

[0006] In addition, the previous operational methods for detecting and repairing defects such as water seepage and cracks had low correlation, and it was impossible to form an efficient and coordinated operating system, resulting in the overall inflexibility of the operating process, affecting construction efficiency and response speed. Regardless of whether it is radar detection or manual detection, only the surface defects that have occurred can be detected, and there is no ability to predict surface defects, and there is a lack of prevention of tunnel surface defects. Summary of the invention

[0007] In order to solve the above technical problems, the present application provides a tunnel disease construction device.

[0008] The present application provides a tunnel disease construction device, comprising: a railway flat car, which is detachably connected to an external locomotive; an advance prediction detection mechanism, which is arranged on the railway flat car, and is used to collect tunnel full-section data and perform tunnel surface disaster forecasts and tunnel water layer disaster forecasts; a driving base, which is arranged on the railway flat car and is electrically connected to the advance prediction detection mechanism; a construction platform, which is arranged on the driving base, and has an expanded form and a contracted form; a first detection mechanism and a second detection mechanism, which are arranged on the construction platform, and the first detection mechanism, the second detection mechanism and the construction platform are respectively connected to the advance prediction detection mechanism, and the first detection mechanism and the second detection mechanism are used to obtain the distance of the construction platform relative to the tunnel surface during the expanded form; the advance prediction detection mechanism is also used to control the driving base and the construction platform according to the tunnel full-section data and the feedback data of the first detection mechanism and the second detection mechanism.

[0009] In one embodiment of the present application, the advanced prediction detection mechanism includes an information processing cabinet, a sonar transceiver, a laser radar scanner and an infrared scanner, wherein the information processing cabinet is arranged on the railway flat car; the sonar transceiver, the laser radar scanner and the infrared scanner are respectively arranged on the information processing cabinet, and the sonar transceiver, the laser radar scanner and the infrared scanner are respectively electrically connected to the information processing cabinet.

[0010] In one embodiment of the present application, both the laser radar scanner and the infrared scanner can adjust the scanning angle.

[0011] In one embodiment of the present application, the driving base includes a bottom bracket, a mounting platform, two groups of hydraulic legs, a gear ring, a motor and a gear, wherein the bottom bracket is placed on the railway flat car, and a group of hydraulic legs are fixedly connected to both sides of the bottom bracket; the mounting platform is rotatably connected to the bottom bracket; the gear ring is fixed to the inner wall of the mounting platform; the motor is fixed to the bottom bracket, and the motor is arranged inside the mounting platform; the gear is fixed to the output shaft of the motor, and the gear is meshed with the gear ring.

[0012] In one embodiment of the present application, the hydraulic support leg includes two first hydraulic cylinders and two second hydraulic cylinders, wherein the two second hydraulic cylinders are arranged in a close fit on the railway flat car, and the two second hydraulic cylinders are fixedly arranged side by side and have opposite telescopic directions, and the bottom bracket is fixedly connected to an adjacent second hydraulic cylinder; the telescopic ends of the first hydraulic cylinder and the second hydraulic cylinder are rotatably connected.

[0013] In one embodiment of the present application, the construction platform includes a first platform, two second platforms, a third platform, two fourth platforms, two fifth platforms and a sixth platform, wherein the first platform is arranged on the mounting table; the two second platforms are symmetrically distributed on the first platform; the third platform is fixed on the first platform by means of columns; the two fourth platforms are fixed on the first platform, and the two fourth platforms are respectively distributed on both sides of the third platform; the two fifth platforms and the sixth platform are respectively lifted and lowered on the third platform by means of lifting frames, and the two fifth platforms are symmetrically distributed on both sides of the sixth platform.

[0014] In one embodiment of the present application, the sixth platform includes a main platform and two auxiliary platforms, wherein the main platform is liftable on the third platform through a lifting frame; the two auxiliary platforms are slidably connected to the inside of the main platform, and a driving mechanism for driving the two auxiliary platforms to move relative to each other or toward each other is connected between the two auxiliary platforms; the second platform, the fourth platform and the auxiliary platform are respectively electric telescopic platforms, and the second detection mechanism is arranged below the second platform, the fourth platform and the auxiliary platform; rotating side panels are respectively arranged on both sides of the fifth platform and the main platform, and hydraulic rods are installed between the fifth platform and the main platform and the corresponding side panels; the first detection mechanism is arranged on the fifth platform and the main platform.

[0015] In one embodiment of the present application, the first detection mechanism includes a first laser rangefinder and a second laser rangefinder, wherein the first laser rangefinder is respectively arranged on each of the side panels, and the second laser rangefinder is respectively arranged on the fifth platform and the main platform; the second detection mechanism includes a third laser rangefinder and a fourth laser rangefinder, wherein the fourth laser rangefinder is arranged on the lower surfaces of the second platform, the fourth platform and the auxiliary platform, and the third laser rangefinder is arranged on the lower surfaces of the telescopic platforms of the second platform, the fourth platform and the auxiliary platform.

[0016] In one embodiment of the present application, the present application also includes a power supply device, which is respectively connected to the advance prediction detection mechanism, the driving base, the construction platform, the first detection mechanism and the second detection mechanism; the power supply device is a diesel generator.

[0017] In one embodiment of the present application, the present application further comprises a plurality of suspension vertical beams, which are symmetrically distributed and fixed on the third platform, and the suspension vertical beams are used to suspend construction equipment.

[0018] Compared with the prior art, the technical solution provided by the embodiments of the present application has the following advantages:

[0019] (1) The advanced prediction detection agency adopts a non-contact, multi-detection combination to detect tunnel defects. It can not only achieve efficient detection of the entire tunnel arch surface, ensuring the comprehensiveness and meticulousness of the detection range, but also significantly improve the speed and efficiency of the detection operation. In addition, the advanced prediction detection agency integrates data mining and genetic algorithms in its algorithm, which can quickly detect tunnel seepage problems and accurately detect liquid seeping through concrete and liquid flowing out of cracks before the disease can be detected by the naked eye. It can further optimize the tunnel disease prediction ability and conduct disease prediction, thereby improving the accuracy and timeliness of tunnel disease prediction, and transforming from passive response to active prevention, effectively curbing the risks and losses caused by delayed discovery and treatment of diseases.

[0020] (2) In the repair phase, the advance prediction detection agency can control the driving base and construction platform based on the full-section data of the tunnel and the complex boundary conditions such as the tunnel arch curve and contact line, and cooperate with the first detection agency and the second detection agency as a feedback mechanism to promote the multi-working surface collaborative operation mode, so that the construction platform can be deformed to cope with different tunnel curves, and the full-section working platform compatible with single-line and double-line tunnels can be accurately built, and a full-coverage working surface can be constructed to meet the requirements of different construction spaces, eliminate the side leakage problems that may occur during the repair process, ensure the quality of the repair, and make the overall operation process more flexible, significantly improving the construction efficiency and safety.

[0021] (3) When the construction platform is in the retracted state, it can be placed within the limits of the railway locomotive and vehicle, thereby meeting the requirement of not exceeding the limit for transportation in the tunnel. This allows the tunnel disease construction device to be transported along the entire railway line, has strong passability, is not troubled by the first and second level over-limits of the tunnel, and can be transported to any railway bureau and freight station. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.

[0023] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.

[0024] Figure 1 It is a structural schematic diagram of a tunnel disease treatment device in an expanded state according to an embodiment of the present application;

[0025] Figure 2It is a schematic diagram of the structure of part of a tunnel disease treatment device according to one embodiment of the present application;

[0026] Figure 3 It is a structural schematic diagram of an advance prediction detection mechanism according to an embodiment of the present application;

[0027] Figure 4 According to one embodiment of the present application Figure 2 Schematic diagram of the enlarged structure of area A in the middle;

[0028] Figure 5 This is a structural diagram of the connection between the main platform and the auxiliary platform according to one embodiment of the present application;

[0029] Figure 6 This is a structural schematic diagram of the connection between the second detection mechanism and the third platform according to one embodiment of the present application;

[0030] Figure 7 It is a schematic diagram of the structure of a tunnel disease construction device in a contracted state according to an embodiment of the present application.

[0031] As shown in the figure: 1. Railway flat car; 2. Advanced forecast detection mechanism; 3. Driving base; 4. Construction platform; 5. First detection mechanism; 6. Second detection mechanism; 7. Power supply equipment; 8. Suspension vertical beam; 20. Information processing cabinet; 21. Sonar transceiver equipment; 22. LiDAR scanner; 23. Infrared scanner; 30. Bottom bracket; 31. Mounting table; 32. Hydraulic support leg; 33. Gear ring; 34. Motor; 35. Gear; 40. First platform; 41. Second platform; 42. Third platform; 43. Fourth platform; 44. Fifth platform; 45. Sixth platform; 50. First laser rangefinder; 51. Second laser rangefinder; 60. Third laser rangefinder; 61. Fourth laser rangefinder; 320. First hydraulic cylinder; 321. Second hydraulic cylinder; 450. Main platform; 451. Auxiliary platform. DETAILED DESCRIPTION

[0032] In order to more clearly understand the above-mentioned purposes, features and advantages of the present application, the scheme of the present application will be further described below. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.

[0033] In the following description, many specific details are set forth to facilitate a full understanding of the present application, but the present application may also be implemented in other ways different from those described herein; obviously, the embodiments in the specification are only part of the embodiments of the present application, rather than all of the embodiments.

[0034] The tunnel damage construction device according to an embodiment of the present application is described below with reference to the accompanying drawings.

[0035] like Figure 1 , Figure 2 , Figure 3 and Figure 7 As shown, the tunnel disease construction device of the embodiment of the present application may include a railway flat car 1, which is detachably connected to an external locomotive.

[0036] It should be noted that the railway flat car 1 and the external locomotive can be connected by a detachable connection mechanism achieved through a James-type coupler. The locking pin on the James-type coupler can be pulled and the hook tongue will automatically pop out, thereby realizing the separation of the railway flat car 1 from the external locomotive. The operation is simple and convenient, and the connection, installation or separation between the railway flat car 1 and the external locomotive can be quickly realized.

[0037] The advanced forecast detection mechanism 2 is arranged on the railway flat car 1. The advanced forecast detection mechanism 2 is used to collect the whole section data of the tunnel and to forecast the tunnel surface disaster and the tunnel water layer disaster.

[0038] It should be noted that the advanced prediction detection mechanism 2 adopts non-contact detection, which not only completely eliminates the problem of low efficiency of traditional robotic arm point-to-point detection, but also completely gets rid of the limitations and time-consuming nature of manual naked eye observation, and realizes the rapid and non-destructive collection of geometric parameters covering the entire cross-section of the tunnel (including but not limited to width, height, cross-sectional area and shape, etc.), which greatly accelerates the detection process and improves work efficiency.

[0039] At the same time, the advanced prediction detection agency 2 combines multiple detection forms to build a comprehensive and multi-level tunnel data collection system. Through the deep processing of massive data, an accurate tunnel sonar model is generated, and on this basis, potential problem areas are pre-marked, and judgment and analysis of the problem areas are performed. The algorithm of the advanced prediction detection agency 2 integrates data mining and genetic algorithms to predict defects (cracks, water seepage, deformation). Among them, data mining technology deeply analyzes the acquired full-section data to explore hidden laws and patterns; while genetic algorithms use their powerful optimization search capabilities to simulate the natural evolution process and make efficient and accurate predictions of possible tunnel defects (such as cracks, water seepage, deformation, etc.), thereby improving the accuracy and timeliness of tunnel defect prediction, and the transformation from passive response to active prevention effectively curbs the risks and losses caused by delayed discovery and treatment of defects.

[0040] The driving base 3 is arranged on the railway flat car 1 , and the driving base 3 is electrically connected to the advance prediction detection mechanism 2 .

[0041] It can be understood that the driving base 3 is used to drive the construction platform 4 to rotate 90°, and can lift the construction platform 4 off the railway flat car 1.

[0042] The construction platform 4 is arranged on the driving base 3, and the construction platform 4 has an expanded state and a retracted state.

[0043] Among them, it can be understood that the construction platform 4 can be within the freight limit in the retracted state, thereby meeting the requirement of not exceeding the limit for transportation in the tunnel, and the construction platform 4 can be quickly provided with a construction work space for construction personnel in the expanded state to meet the requirements of the tunnel construction plane height, reduce the time for setting up and dismantling scaffolding, increase construction time, and the strength and rigidity of the construction platform 4 are more controllable than temporary structures such as scaffolding, ensuring the safety and reliability of the construction process.

[0044] The first detection mechanism 5 and the second detection mechanism 6 are arranged on the construction platform 4, and the first detection mechanism 5, the second detection mechanism 6 and the construction platform 4 are respectively connected to the advanced prediction detection mechanism 2, and the first detection mechanism 5 and the second detection mechanism 6 are used to obtain the distance of the construction platform 4 relative to the tunnel surface during the unfolding process.

[0045] The advanced prediction detection mechanism 2 is also used to control the driving base 3 and the construction platform 4 according to the full-section data of the tunnel and the feedback data of the first detection mechanism 5 and the second detection mechanism 6.

[0046] Specifically, please refer to Figure 7 The tunnel disease construction device is highly flexible and intelligent in design. In the retracted state, it can be towed by a locomotive and move along the railway line in the tunnel, realizing convenient and efficient transportation. During the journey, the full-section data of the tunnel can be collected in a non-contact manner through the advanced prediction detection mechanism 2, covering the data collection of the surface quality and water seepage of the full section of the tunnel, as well as the surface interlayer and other problems, and a three-dimensional sonar model of the tunnel can be constructed. After data processing, the location of the expected surface quality problem is delineated, and then the marked problem is accurately scanned and analyzed again, and finally the problem of tunnel surface disease is determined.

[0047] Once the surface disease of the tunnel is discovered or predicted, the data collected by the advance prediction detection mechanism 2 on the tunnel can be used to quickly obtain the internal curve of the tunnel at the construction location, intelligently plan the deformation path of the construction platform 4, and guide the deformation control of the driving base 3 based on the above data. First, the driving base 3 is controlled to safely lift the construction platform 4 and separate it from the railway flat car 1, so as to avoid the influence of the tunnel slope on the construction surface of the construction platform 4. After the jacking up, the construction platform 4 is no longer subjected to force on the tunnel platform, reducing the damage caused by uneven force on the railway flat car 1 and the rails. Subsequently, the construction platform 4 rotates 90 degrees under the precise control of the driving base 3 and overlaps with the tunnel horizontally, realizing the seamless construction of the full-section construction platform 4 and ensuring the precise implementation of the full-feedback internal closed-loop deformation control.

[0048] In view of the complex and changeable curve shape inside the tunnel, in order to ensure the full-section construction capacity and to cope with the problem that the platform distance from the tunnel surface is different under different working conditions, the first detection mechanism 5 and the second detection mechanism 6 monitor and feedback the relative distance between the construction platform 4 and the tunnel surface in real time during the whole process of deformation and expansion of the construction platform 4, providing double protection for the safe deformation of the construction platform 4. After the advance prediction detection mechanism 2 obtains the boundary conditions such as the tunnel arch curve and the contact line, the first detection mechanism 5 and the second detection mechanism 6 are used as feedback to obtain the distance of the construction platform 4 relative to the tunnel surface during the expansion process, and timely feedback to the advance prediction detection mechanism 2, so that the advance prediction detection mechanism 2 can know the deformation degree of the construction platform 4. The advance prediction detection mechanism 2 comprehensively processes the received feedback data and dynamically optimizes the deformation strategy to ensure that the construction platform 4 can flexibly avoid obstacles such as traction lines and contact lines during the expansion process, perfectly adapt to the single-track and double-track tunnel environment, and realize the flexible construction of the full-section construction platform 4.

[0049] In summary, the tunnel disease construction device is not only convenient to transport, but also realizes efficient detection and prediction of tunnel surface diseases (detection of defects such as fine cracks and water seepage, and potential hazards of deep water layers and cavities) through the integrated advanced prediction detection mechanism 2, driving base 3, construction platform 4, first detection mechanism 5 and second detection mechanism 6 collaborative operation mode. At the same time, it ensures the accurate construction and efficient operation of the construction platform 4, meets the requirements of different construction spaces, makes the overall operation process more flexible, and significantly improves construction efficiency and safety.

[0050] As a possible situation, in order to facilitate the repair and treatment of defects at the construction location, multiple lighting devices can be installed on the construction platform 4 and the railway flat car 1. The installation position of the lighting equipment can be selected according to actual conditions to ensure that it can be flexibly adjusted according to actual work needs to maximize the lighting effect. Among them, the lighting equipment can be a searchlight, LED (Light Emitting Diode) lamp, etc.

[0051] In order to further clarify the above embodiment, in one embodiment of the present application, Figure 3 As shown, the advance prediction detection mechanism 2 includes an information processing cabinet 20, a sonar transceiver 21, a laser radar scanner 22 and an infrared scanner 23.

[0052] Among them, the information processing cabinet 20 is set on the railway flat car 1, the sonar transceiver equipment 21, the laser radar scanner 22 and the infrared scanner 23 are respectively set on the information processing cabinet 20, and the sonar transceiver equipment 21, the laser radar scanner 22 and the infrared scanner 23 are respectively electrically connected to the information processing cabinet 20.

[0053] Specifically, the information processing cabinet 20 is used to summarize, process and analyze the data collected by three different detection devices, namely the sonar transceiver 21, the lidar scanner 22 and the infrared scanner 23, and a strategy of logical complementarity and multi-means coupling is adopted to ensure the comprehensiveness and accuracy of the detection results.

[0054] First, during the whole detection process, the sonar transceiver 21 is used to bombard the tunnel surface and conduct a comprehensive scan of the tunnel to collect data on the entire cross-section of the tunnel. The data on surface quality, water seepage, surface interlayers and other issues are collected and fed back to the information processing cabinet 20. The information processing cabinet 20 constructs a three-dimensional sonar model of the tunnel based on the collected data, and after processing the data, it determines the locations where surface quality problems are expected to exist.

[0055] Subsequently, the information processing cabinet 20 controls the laser radar scanner 22 to perform laser scanning on the problem area, determine the expected surface defects, record and modify the data, obtain a high-precision tunnel surface point cloud, and obtain information on cracks on the entire tunnel surface. As the vehicle drives, a high-precision tunnel surface cloud map can be gradually completed to obtain reliable tunnel surface quality information.

[0056] When the sonar transceiver 21 captures the problem of water seepage in the tunnel, the information processing cabinet 20 controls the infrared scanner 23 to start immediately and quickly locate the water seepage area. The infrared scanner 23 can effectively detect the surface and shallow water content of the tunnel, and start the patrol mode to perform deep and repeated scanning of the water seepage point and its surrounding areas. This step not only confirms the water seepage situation, but also further reveals the distribution law of the shallow water content state of the tunnel. As the vehicle continues to travel, the infrared scanner 23 gradually completes the comprehensive detection of the water seepage and shallow water content state of the entire tunnel, and the data is transmitted back to the information processing cabinet 20 in real time for comprehensive analysis. The information processing cabinet 20 adopts a disaster prediction system coupled with multiple means, and integrates data mining and genetic algorithms. It can obtain highly reliable advance disaster predictions of tunnel concrete surface quality and problems such as air inclusion and water inclusion under the coupled data collection and correction of multiple means.

[0057] Throughout the entire inspection process, the advantages of different inspection methods are fully utilized while avoiding their own limitations. The initial screening by sonar points the way for the precise inspection by the lidar scanner 22 and the infrared scanner 23, while the complementary application of the lidar scanner 22 and the infrared scanner 23 ensures the comprehensiveness and accuracy of the inspection results.

[0058] In one embodiment of the present application, Figure 3 As shown, both the laser radar scanner 22 and the infrared scanner 23 can adjust the scanning angle.

[0059] Among them, it can be understood that the information processing cabinet 20 can predict the location of the surface quality problem, accurately control the flexible adjustment of the angle of the scanning probes of the laser radar scanner 22 and the infrared scanner 23, and ensure accurate and targeted scanning coverage of the predicted problem area. Among them, the laser radar scanner 22 and the infrared scanner 23 may complete the angle adjustment of the scanning probe by means of a built-in motor. Since the method of adjusting the angle of the built-in motor is a prior art, it will not be elaborated here.

[0060] In one embodiment of the present application, Figure 2 and Figure 4 As shown, the driving base 3 includes a bottom bracket 30 , a mounting platform 31 , two sets of hydraulic legs 32 , a gear ring 33 , a motor 34 and a gear 35 .

[0061] The bottom bracket 30 is placed on the railway flat car 1 , and a group of hydraulic legs 32 are fixedly connected to both sides of the bottom bracket 30 .

[0062] As a possible situation, in order to improve the stability of the bottom bracket 30 on the railway flat car 1 during transportation, the F-TR lock can be used to reinforce the bottom bracket 30 and the railway flat car 1 to effectively resist vibration during transportation, thereby ensuring the stability of the bottom bracket 30 and the construction platform 4 when the locomotive tows the tunnel disease construction device.

[0063] The mounting platform 31 is rotatably connected to the bottom bracket 30, the ring gear 33 is fixed to the inner wall of the mounting platform 31, the motor 34 is fixed to the bottom bracket 30, and the motor 34 is arranged inside the mounting platform 31, the gear 35 is fixed to the output shaft of the motor 34, and the gear 35 is meshed with the ring gear 33.

[0064] Specifically, the information processing cabinet 20 controls the deployment of each group of hydraulic legs 32 according to the full-section data, and controls the lifting height of each group of hydraulic legs 32, so as to drive the construction platform 4 to separate from the railway flat car 1 through the bottom bracket 30. After the lifting is completed, the information processing cabinet 20 controls the motor 34 to cooperate with the gear 35 to drive the ring gear 33 according to a preset rotation angle (for example, 90°) to drive the mounting platform 31 to rotate. The rotation of the mounting platform 31 drives the construction platform 4 to rotate, thereby completing the rotation of the construction platform 4.

[0065] In one embodiment of the present application, Figure 2 As shown, the hydraulic support leg 32 includes two first hydraulic cylinders 320 and two second hydraulic cylinders 321 .

[0066] Among them, the two second hydraulic cylinders 321 are arranged closely on the railway flat car 1, and the two second hydraulic cylinders 321 are fixedly arranged side by side and have opposite telescopic directions. The bottom bracket 30 is fixedly connected to an adjacent second hydraulic cylinder 321, and the telescopic ends of the first hydraulic cylinder 320 and the second hydraulic cylinder 321 are rotatably connected.

[0067] It should be noted that the first hydraulic cylinder 320 is rotatable relative to the second hydraulic cylinder 321, and the direction of the first hydraulic cylinder 320 can be flexibly adjusted, which can significantly reduce the space occupied by the first hydraulic cylinder 320 in the non-working state, thereby improving the compactness of the tunnel disease construction device and meeting the requirement of not exceeding the limit for transportation in the tunnel. Among them, the first hydraulic cylinder 320 can be rotatably connected with the telescopic end of the second hydraulic cylinder 321 by adding a driving member (a motor or an electric telescopic rod with a connecting rod) to the first hydraulic cylinder 320 and the second hydraulic cylinder 321. Since it is a prior art, it is not described in detail here. Before deformation, the telescopic end of the first hydraulic cylinder 320 can be rotated toward the bottom surface by controlling the driving member.

[0068] Specifically, the information processing cabinet 20 first controls the telescopic end of the second hydraulic cylinder 321 to unfold according to the full-section data, and then controls the telescopic end of the first hydraulic cylinder 320 to extend, and lifts it according to a preset height (which can be set according to actual conditions), so that the construction platform 4 after lifting is no longer subjected to force on the tunnel platform, reducing the damage to the railway flat car 1 and the rails due to uneven force, thereby increasing the service life of the rails and the railway flat car 1.

[0069] As a possible situation, in order to further improve the stability of the first hydraulic cylinder 320 during jacking, a circular base can be installed on the telescopic end of the first hydraulic cylinder 320 to increase the contact area of ​​the telescopic end of the first hydraulic cylinder 320 relative to the bottom surface, which not only improves the overall stability during the jacking process, but also enhances the anti-overturning ability, providing a more solid guarantee for the safe and efficient progress of tunnel construction.

[0070] In one embodiment of the present application, Figure 1 As shown, the construction platform 4 includes a first platform 40 , two second platforms 41 , a third platform 42 , two fourth platforms 43 , two fifth platforms 44 and a sixth platform 45 .

[0071] Among them, the first platform 40 is set on the mounting table 31, the two second platforms 41 are symmetrically distributed on the first platform 40, the third platform 42 is fixed on the first platform 40 by means of columns, the two fourth platforms 43 are both fixed on the first platform 40, and the two fourth platforms 43 are respectively distributed on both sides of the third platform 42, the two fifth platforms 44 and the sixth platform 45 are respectively lifted and lowered on the third platform 42 by means of lifting frames, and the two fifth platforms 44 are symmetrically distributed on both sides of the sixth platform 45.

[0072] It should be noted that the lifting frame described in this embodiment may be an electric lifting frame or a hydraulic lifting frame. For example, taking a hydraulic lifting frame as an example, the height of the lifting frame may be changed by controlling a hydraulic cylinder in the hydraulic lifting frame.

[0073] Specifically, in the process of controlling the intelligent deployment of the construction platform 4, the information processing cabinet 20 firstly monitors the distance relative to the tunnel surface in real time based on the tunnel full-section data and the complex boundary conditions such as the tunnel arch curve and the contact line obtained, and then the first detection mechanism 5 and the second detection mechanism 6 act as a feedback mechanism to evaluate the deformation degree of the construction platform 4, thereby dynamically optimizing the deformation strategy. In this process, the information processing cabinet 20 controls the lifting height and sequence of the fifth platform 44 and the sixth platform 45 lifting frames to ensure that they work together and seamlessly connect, and finally realize the precise construction of a full-section working platform compatible with single-track and double-track tunnels. The information processing cabinet 20 can automatically calibrate the distance between the tunnel surface, control the range within the preset range, and autonomously adjust the telescopic amount to achieve true unmanned operation, flexibly respond to various height requirements in the tunnel, and easily transport workers and materials to any designated location.

[0074] In one embodiment of the present application, Figure 1 and Figure 5 As shown, the sixth platform 45 includes a main platform 450 and two auxiliary platforms 451 .

[0075] Among them, the main platform 450 can be lifted and lowered on the third platform 42 through a lifting frame, the two auxiliary platforms 451 can be slidably connected inside the main platform 450, and a driving mechanism (not shown in the figure) is connected between the two auxiliary platforms 451 to drive the two auxiliary platforms 451 to move relative to each other or move toward each other.

[0076] It should be noted that the driving mechanism described in this embodiment may be two hydraulic cylinders or electric telescopic rods, and the hydraulic cylinders are used to push the auxiliary platform 451 to change its position, thereby changing the state (expanded or retracted state) of the sixth platform 45.

[0077] The second platform 41 , the fourth platform 43 and the auxiliary platform 451 are respectively electric telescopic platforms, and a second detection mechanism 6 is disposed below the second platform 41 , the fourth platform 43 and the auxiliary platform 451 .

[0078] It should be noted that the electric telescopic platform described in this embodiment means that telescopic platforms are provided on both sides of the second platform 41, the fourth platform 43 and the auxiliary platform 451, and the control of the telescopic platform is improved to increase the construction area.

[0079] Rotating side plates are respectively provided on both sides of the fifth platform 44 and the main platform 450 , and hydraulic rods (not shown in the figure) are installed between the fifth platform 44 and the main platform 450 and the corresponding side plates. The first detection mechanism 5 is provided on the fifth platform 44 and the main platform 450 .

[0080] Specifically, by designing the second platform 41, the fourth platform 43, the fifth platform 44 and the sixth platform 45 as deformable structural platforms, not only the working space of the workers is greatly expanded during the construction phase, enabling them to perform fine construction on the tunnel surface more flexibly and efficiently, but also in the non-operating state, the compactness of the construction platform 4 is significantly improved through the retraction mechanism, greatly facilitating the transportation and transfer of the platform.

[0081] In the process of controlling the further intelligent deployment of the second platform 41, the fourth platform 43, the fifth platform 44 and the sixth platform 45, the information processing cabinet 20 is also used to monitor the distance relative to the tunnel surface in real time based on the full-section data of the tunnel and the complex boundary conditions such as the acquired tunnel arch curve and contact line, and cooperate with the first detection mechanism 5 and the second detection mechanism 6 as a feedback mechanism. Based on these real-time data, the information processing cabinet 20 responds quickly, precisely controls the driving distance of the driving mechanism and the telescopic distance of the telescopic platform in the electric telescopic platform, and at the same time carefully adjusts the lifting length and sequence of the hydraulic rods between the fifth platform 44, the sixth platform 45 and the main platform 450 and the corresponding side panels, so that the second platform 41, the fourth platform 43, the fifth platform 44 and the sixth platform 45 are deformed and deployed one by one under the command of the information processing cabinet 20.

[0082] During this process, the information processing cabinet 20 can continuously evaluate the deformation state of the construction platform 4, dynamically adjust the deformation strategy, and adjust the distance between the second platform 41, the fourth platform 43, the fifth platform 44 and the sixth platform 45 and the tunnel surface to a preset range in real time, and finally achieve the following Figure 1 The development operation status shown in the figure. Driven by this fully automated process, the construction team was able to complete the full-section construction deployment efficiently and safely without direct human intervention.

[0083] As a possible situation, when the construction platform 4 is unfolded, in order to facilitate the transfer of workers between the two key working areas of the fifth platform 44 and the sixth platform 45, a ladder can be fixed on the auxiliary platform 451.

[0084] In one embodiment of the present application, Figure 1 and Figure 6 As shown, the first detection mechanism 5 includes a first laser rangefinder 50 and a second laser rangefinder 51 .

[0085] Wherein, a first laser rangefinder 50 is respectively arranged on each side plate, and a second laser rangefinder 51 is respectively arranged on the fifth platform 44 and the main platform 450 .

[0086] The second detection mechanism 6 includes a third laser rangefinder 60 and a fourth laser rangefinder 61, wherein the fourth laser rangefinder 61 is arranged on the lower surface of the second platform 41, the fourth platform 43 and the auxiliary platform 451, and the third laser rangefinder 60 is arranged on the lower surface of the telescopic platform of the second platform 41, the fourth platform 43 and the auxiliary platform 451.

[0087] Specifically, the first laser rangefinder 50 is used to detect the distance of the side panel relative to the tunnel surface during rotation to ensure the safety boundary of the operation. The second laser rangefinder 51 is used to detect the distance of the fifth platform 44 and the main platform 450 relative to the tunnel surface during the jacking process to ensure precise control of the lifting operation.

[0088] The third laser rangefinder 60 is used to detect the dynamic distance of the telescopic platform in the second platform 41, the fourth platform 43 and the auxiliary platform 451 relative to the tunnel surface during the adjustment process to avoid collision. The fourth laser rangefinder 61 is used as a supplement to detect the distance of the second platform 41, the fourth platform 43 and the auxiliary platform 451 relative to the bottom surface of the tunnel, comprehensively detect the positional relationship between the whole and the tunnel space, and provide comprehensive data support for comprehensive evaluation.

[0089] Through the coordinated work among the first laser rangefinder 50, the second laser rangefinder 51, the third laser rangefinder 60 and the fourth laser rangefinder 61, the spatial position data of the second platform 41, the fourth platform 43, the fifth platform 44 and the sixth platform 45 during the deployment process can be collected in real time and accurately, and immediately fed back to the information processing cabinet 20. This mechanism not only improves the safety and efficiency of the operation, but also greatly enhances the ability of the information processing cabinet 20 to evaluate the degree of platform deformation, providing a solid data foundation for subsequent adjustment and optimization.

[0090] Furthermore, if Figure 1 As shown, the above-mentioned tunnel disease construction device also includes a power supply device 7, which is respectively connected to the advanced prediction detection mechanism 2, the driving base 3, the construction platform 4, the first detection mechanism 5 and the second detection mechanism 6, and the power supply device 7 is a diesel generator.

[0091] It can be understood that the power supply device 7 can be used to power all power-consuming components or equipment in the advance prediction detection mechanism 2, the driving base 3, the construction platform 4, the first detection mechanism 5 and the second detection mechanism 6, realizing a one-stop power supply solution for all power demand components. This design not only greatly simplifies the cumbersome process of traditional wire pulling or pulling, improves the cleanliness and safety of the construction site, but also ensures the stability and reliability of the power supply of each device during the operation.

[0092] Furthermore, if Figure 4 As shown, the above-mentioned tunnel disease construction device also includes a plurality of suspension vertical beams 8, and the plurality of suspension vertical beams 8 are symmetrically distributed and fixed on the third platform 42, and the suspension vertical beams 8 are used to suspend the construction equipment.

[0093] Among them, it can be understood that the setting of the suspension vertical beam 8 can be used to suspend the construction equipment, which can reduce the difficulty of workers carrying it, reduce the construction difficulty and reduce the number of construction personnel groups compared to the prior art.

[0094] It should be noted that, in this article, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0095] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments described herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A tunnel disease construction device, characterized in that: include: A railway flat car, wherein the railway flat car is detachably connected to an external locomotive; An advance prediction detection mechanism, which is arranged on the railway flat car and is used to collect tunnel full-section data and to predict tunnel surface disasters and tunnel water layer disasters; A driving base, the driving base is arranged on the railway flat car, and the driving base is electrically connected to the advanced prediction detection mechanism; A construction platform, the construction platform is arranged on the driving base, and the construction platform has an expanded state and a retracted state; a first detection mechanism and a second detection mechanism, wherein the first detection mechanism and the second detection mechanism are arranged on the construction platform, and the first detection mechanism, the second detection mechanism and the construction platform are respectively connected to the advance prediction detection mechanism, and the first detection mechanism and the second detection mechanism are used to obtain the distance of the construction platform relative to the tunnel surface during the unfolding process; The advanced prediction detection mechanism is also used to control the driving base and the construction platform according to the full-section data of the tunnel and the feedback data of the first detection mechanism and the second detection mechanism.

2. The tunnel damage treatment device according to claim 1, characterized in that: The advanced forecast detection mechanism includes an information processing cabinet, a sonar transceiver, a laser radar scanner and an infrared scanner, wherein: The information processing cabinet is arranged on the railway flat car; The sonar transceiver device, the laser radar scanner and the infrared scanner are respectively arranged on the information processing cabinet, and the sonar transceiver device, the laser radar scanner and the infrared scanner are respectively electrically connected to the information processing cabinet.

3. The tunnel damage treatment device according to claim 2 is characterized in that: Both the laser radar scanner and the infrared scanner can adjust the scanning angle.

4. The tunnel disease construction device according to claim 1 is characterized in that: The driving base includes a bottom bracket, a mounting platform, two sets of hydraulic legs, a gear ring, a motor and a gear, wherein: The bottom bracket is placed on the railway flat car, and a group of hydraulic legs are fixedly connected to both sides of the bottom bracket; The mounting platform is rotatably connected to the bottom bracket; The gear ring is fixed on the inner wall of the mounting platform; The motor is fixed on the bottom bracket, and the motor is arranged inside the mounting platform; The gear is fixed on the output shaft of the motor, and is meshedly connected with the gear ring.

5. The tunnel damage treatment device according to claim 4 is characterized in that: The hydraulic support leg comprises two first hydraulic cylinders and two second hydraulic cylinders, wherein: The two second hydraulic cylinders are arranged closely on the railway flat car, and the two second hydraulic cylinders are fixedly arranged side by side and extend and retract in opposite directions, and the bottom bracket is fixedly connected to an adjacent second hydraulic cylinder; The telescopic ends of the first hydraulic cylinder and the second hydraulic cylinder are rotatably connected.

6. The tunnel damage treatment device according to claim 4, characterized in that: The construction platform includes a first platform, two second platforms, a third platform, two fourth platforms, two fifth platforms and a sixth platform, wherein: The first platform is arranged on the mounting platform; The two second platforms are symmetrically distributed on the first platform; The third platform is fixedly arranged on the first platform through columns; The two fourth platforms are both fixed on the first platform, and the two fourth platforms are respectively distributed on both sides of the third platform; The two fifth platforms and the six platforms are respectively liftably arranged on the third platform through lifting frames, and the two fifth platforms are symmetrically distributed on both sides of the sixth platform.

7. The tunnel damage treatment device according to claim 6, characterized in that: The sixth platform includes a main platform and two auxiliary platforms, wherein: The main platform can be lifted and lowered on the third platform by a lifting frame; The two auxiliary platforms are respectively slidably connected inside the main platform, and a driving mechanism for driving the two auxiliary platforms to move relative to each other or toward each other is connected between the two auxiliary platforms; The second platform, the fourth platform and the auxiliary platform are respectively electric telescopic platforms, and the second detection mechanism is arranged below the second platform, the fourth platform and the auxiliary platform; Rotatable side plates are respectively arranged on both sides of the fifth platform and the main platform, and hydraulic rods are installed between the fifth platform and the main platform and the corresponding side plates; The first detection mechanism is arranged on the fifth platform and the main platform.

8. The tunnel damage treatment device according to claim 7, characterized in that: The first detection mechanism includes a first laser rangefinder and a second laser rangefinder, wherein: A first laser rangefinder is respectively arranged on each of the side plates, and a second laser rangefinder is respectively arranged on the fifth platform and the main platform; The second detection mechanism includes a third laser rangefinder and a fourth laser rangefinder, wherein: The lower surfaces of the second platform, the fourth platform and the auxiliary platform are provided with a fourth laser rangefinder, and the lower surfaces of the telescopic platforms of the second platform, the fourth platform and the auxiliary platform are provided with the third laser rangefinder.

9. The tunnel damage treatment device according to claim 1, characterized in that: It also includes a power supply device, which is respectively connected to the advanced prediction detection mechanism, the driving base, the construction platform, the first detection mechanism and the second detection mechanism; The power supply equipment is a diesel generator.

10. The tunnel damage treatment device according to any one of claims 6 to 7, characterized in that: It also includes a plurality of suspension vertical beams, which are symmetrically distributed and fixed on the third platform, and are used to suspend construction equipment.