Water-rich joint soft rock tunnel excavation construction catastrophe evaluation and early warning system
Patent Information
- Application Number
- CN202411114224.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-12
Smart Images

Figure CN118934053A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of tunnel geological detection and relates to a tunnel excavation construction disaster assessment and early warning system. Background Art
[0002] Soft rock has the characteristics of low strength, easy softening when exposed to water, and poor properties. The problem of large deformation is particularly prominent under high ground stress. When the tunnel passes through a water-rich area, lining leakage and water gushing will occur, and in severe cases, collapse will occur. If the working condition is complex water-rich jointed soft rock, the previous disaster assessment and early warning system can only determine the deformation location, but cannot determine the amount of deformation and the situation of the water-rich area. It is difficult to meet new needs. Therefore, new materials, new processes, new technologies, and new concepts also need to be further proposed.
[0003] The existing disaster assessment and early warning system for tunnel excavation construction often only monitors and warns of single risks of deformation in water-rich areas or jointed soft rock, which is difficult to meet the warning needs of more complex geological conditions. At this time, it is particularly important to propose a disaster assessment and early warning system for tunnel excavation construction in water-rich jointed soft rock that can be used under complex working conditions. Summary of the invention
[0004] In order to overcome the limitation that the traditional disaster assessment and early warning system can only be used for a single geological condition, meet the needs of simultaneous monitoring and early warning of multiple parameters under complex conditions, and fully protect the safety of life and property, the present invention provides a comprehensive, safe, and efficient disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction. The system is easy to understand, has high data transmission efficiency, strong data integration and processing capabilities, fast computing speed, and high intelligence. It fully utilizes the advantages of large databases, can appropriately liberate manpower, conduct quantitative risk analysis of risk sources in a timely manner, transmit data in real time, and alarm at the first time, which not only provides decision makers with sufficient thinking time, but also warns on-site personnel and leaves them with sufficient escape time.
[0005] The objective of the present invention is achieved through the following technical solutions:
[0006] A disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction includes a user management module, a database, a field data acquisition module, a communication module, a data calculation module, a disaster early warning module, and an imaging module, wherein:
[0007] The user management module is used for the creation of new users and the input, modification and deletion of existing data of specific engineering projects, including the creation, login, management, maintenance and logout of new users, as well as the creation and editing of specific engineering folders matched with new users, the input and rewriting of existing data and the input of real-time parameters of projects;
[0008] The database is used to provide project engineering overview data, early warning information data, existing disaster avoidance measures data, risk data obtained by detection, and real-time engineering parameter data obtained by detection;
[0009] The field data acquisition module is used to record the water-rich area data obtained by transient electromagnetic method, ground penetrating radar method, advanced drilling and digital imaging method, as well as the joint surface information and jointed soft rock deformation data in real time and push them to the database, and then transmit them to the management center;
[0010] The communication module is used to realize real-time communication between the management center and the site, and information transmission between the disaster warning module and the site, so as to guide evacuation in the first time when encountering danger;
[0011] The data operation module is used for three-dimensional modeling and operation of the dangerous situation data collected in real time, and pushes the obtained results to the database and then to the management center;
[0012] The disaster warning module is used to automatically classify the risk data obtained by the data calculation module into risk levels and push them to the database, and then push them to the management center and construction personnel;
[0013] The imaging module is used to collect image data of the implementation of laser scanner, advance drilling and digital imaging method and soft rock deformation after excavation.
[0014] A method for implementing the above-mentioned disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction includes the following steps:
[0015] S1: Start the user management module, create administrators, set the names of administrators at all levels and their management permissions; create a new project folder, enter the tunnel design parameters, data obtained from on-site exploration, and existing disaster avoidance measures data;
[0016] S2: Start the field data acquisition module and imaging module to conduct advanced geological prediction for the water-rich area in the tunnel construction direction, including the following steps:
[0017] S21: Implement geological survey method: collect the original geological data and previous geological survey data of the construction site, manually input relevant geological information and save it into the database, combine the on-site observations, analyze the locations where hidden dangers may occur, and conduct key inspections;
[0018] S22: Implementation of transient electromagnetic method: Implementation of transient electromagnetic method along the entire length of the tunnel. If risk factors are found, data will be transmitted to the management center and database and ground penetrating radar method will be implemented. Otherwise, forecasting will be stopped;
[0019] S23: Implementation of ground penetrating radar method: Based on the results obtained by transient electromagnetic method and the actual engineering conditions in the tunnel, ground penetrating radar method is implemented in important areas. If risk factors appear, the data will be transmitted to the management center and database and advance drilling and digital imaging methods will be implemented. Otherwise, the forecast will be stopped;
[0020] S24: Implement advance drilling and digital imaging: Combined with the results obtained by the ground penetrating radar method, according to the actual engineering conditions in the tunnel, advance drilling and digital imaging are implemented in the area where disasters are most likely to occur, so as to obtain specific water-rich hazards in the construction direction. The obtained data is automatically transmitted to the database and saved. At the same time, the image information in the drilling probe is transmitted back to the management center in real time through the imaging module;
[0021] S3: Real-time monitoring of deformation of jointed soft rock, including the following steps:
[0022] S31: Acquisition of joint surface information of jointed soft rock in key areas: Use laser scanner to scan the joint surface information of jointed soft rock in the tunnel, obtain data and transmit it back to the database, and the obtained real-time image data is synchronously transmitted to the management center;
[0023] S32: 3D construction of site model: The position parameters obtained by the laser scanner are transmitted to the data calculation module for calculation and processing to construct a 3D model containing position coordinate information;
[0024] S33: Kinematic analysis of risky locations: Calculate the self-stabilization coefficient of key blocks around the tunnel chamber and the safety factor after reinforcement;
[0025] S34: Deformation monitoring at risky locations: Paste strain gauges at risky locations, start the on-site data acquisition module and imaging module, and monitor the displacement changes of the block to be tested in real time; if the risk at the location is high, a camera can be added on top of the strain gauge to obtain data and image information in real time, transmit the strain gauge monitoring data back to the database in real time and enter the data calculation module for calculation, and transmit the on-site real-time images collected by the camera back to the management center;
[0026] S4: After the advanced geological prediction and real-time monitoring data of jointed soft rock deformation are obtained, they are transmitted to the disaster warning module through the data calculation module. The disaster warning module sets three risk levels: high risk, medium risk, and low risk. When the data exceeds the threshold, the disaster warning module automatically determines the risk level and transmits it back to the database and management center;
[0027] S5: After the disaster warning module determines the risk level, the management center and construction personnel will receive information on the risk level, risk location, estimated time of risk occurrence after calculation, and recommended risk avoidance measures. At the same time, if the management center personnel have any objections to the automatic assessment results after receiving the data, they will change the risk level through the management center and manually send it to the construction personnel through the communication module.
[0028] Compared with the prior art, the present invention has the following advantages:
[0029] The disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction of the present invention can detect the condition of the water-rich area in the construction direction through advanced geological forecasts during construction, and at the same time monitor the deformation of the jointed soft rock, and transmit and analyze the risks under the two conditions at the same time, so that the system early warning is more comprehensive and fully protects the safety of people's property; when the system calculates the risk level, on the one hand, it is automatically transmitted to the construction personnel and guides the evacuation plan, and at the same time it is transmitted back to the management center for secondary analysis by the monitoring personnel, giving full play to the subjective initiative of people, combining the calculated data with manual experience, and if there is a deviation in the analysis result, the management center can issue a second instruction to guide the next step of production work on site. In summary, the present invention comprehensively warns of the risks of water-rich areas and jointed soft rock deformation, can implement risk monitoring, automatic calculation of risk levels, automatic early warning, and machine learning of existing risk information, and can better use existing data to guide tunnel construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of the framework of the disaster assessment and early warning system for excavation construction of water-rich jointed soft rock tunnels of the present invention;
[0031] Figure 2 This is a flow chart of advanced geological prediction of the present invention;
[0032] Figure 3 This is a schematic diagram of the deformation monitoring process of jointed soft rock according to the present invention;
[0033] Figure 4 This is a working flow chart of the disaster assessment and early warning system for excavation construction of water-rich jointed soft rock tunnels of the present invention. DETAILED DESCRIPTION
[0034] The technical solution of the present invention is further described below in conjunction with the accompanying drawings, but is not limited thereto. Any modification or equivalent replacement of the technical solution of the present invention without departing from the spirit and scope of the technical solution of the present invention should be included in the protection scope of the present invention.
[0035] In order to fully protect the safety of people and property, the present invention provides a disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction. During tunnel excavation, the system can not only detect the risk of the water-rich area ahead, but also monitor and warn the deformation of the jointed soft rock in real time. It is an extremely comprehensive real-time monitoring and early warning system. Figure 1 As shown, the system includes a user management module, a database, a field data acquisition module, a communication module, a data calculation module, a disaster warning module, and an imaging module, wherein:
[0036] The user management module is mainly used for the creation of new users and the input, modification and deletion of existing data of specific engineering projects, including the creation, login, management, maintenance and logout of new users, as well as the creation and editing of specific engineering folders matched with new users, the input and rewriting of existing data and the input of real-time parameters of projects;
[0037] The database is used to provide project engineering overview data, early warning information data, existing disaster avoidance measures data, risk data obtained by detection, and real-time engineering parameter data obtained by detection;
[0038] The field data acquisition module is used to record the water-rich area data obtained by transient electromagnetic method, ground penetrating radar method, advanced drilling and digital imaging method, as well as the joint surface information and jointed soft rock deformation data in real time and push them to the database, and then transmit them to the management center;
[0039] The communication module is used to realize real-time communication between the management center and the site, and information transmission between the disaster warning module and the site, so as to guide evacuation in the first time when encountering danger;
[0040] The data operation module is used for three-dimensional modeling and operation of the dangerous situation data collected in real time, and pushes the obtained results to the database and then to the management center;
[0041] The disaster warning module is used to automatically classify the risk data obtained by the data calculation module into risk levels and push them to the database, and then push them to the management center and construction personnel;
[0042] The imaging module is used to collect on-site images captured by the "Feng Yi" laser scanner, real-time images obtained from advance drilling, and deformation of soft rocks after excavation.
[0043] A method for implementing a disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction, such as Figure 4 As shown, the following steps are included:
[0044] S1: Start the user management module, create an administrator, set the names of administrators at all levels and their management permissions; create a new project folder, and enter the tunnel design parameters, data obtained from on-site exploration, and existing disaster avoidance measures data.
[0045] S2: Carry out advanced geological prediction for the water-rich area in the tunnel construction direction, and start the on-site data acquisition module and imaging module, such as Figure 2 As shown, the following steps are included:
[0046] S21: Implement geological survey method: This method focuses on geological survey inside the tunnel, collects original geological data and previous geological survey data of the construction site, manually inputs relevant geological information and saves it into the database, combines it with on-site observations, analyzes possible locations of hidden dangers, and conducts key inspections. In fact, this step has been completed when creating a new user.
[0047] S22: Implementation of transient electromagnetic method: Implementation of transient electromagnetic method along the entire length of the tunnel, with a forecast distance of 75 meters. If risk factors occur, data will be transmitted to the management center and database and ground penetrating radar method will be implemented. Otherwise, forecasting will be stopped;
[0048] S23: Implementation of ground penetrating radar method: In combination with the results obtained by transient electromagnetic method, according to the actual engineering conditions in the tunnel, the ground penetrating radar method is implemented in important areas, with a forecast distance of 5 to 15 meters. If risk factors appear, the data will be transmitted to the management center and database, and advanced drilling and digital imaging methods will be implemented. Otherwise, the forecast will be stopped.
[0049] S24: Implement advance drilling and digital imaging methods: Combined with the results obtained by the ground penetrating radar method, according to the actual engineering conditions in the tunnel, advance drilling and digital imaging methods are implemented in the range where disasters are most likely to occur, so as to obtain specific water-rich hazards in the construction direction. The obtained data is automatically transmitted to the database and saved. At the same time, the image information in the drilling probe is transmitted back to the management center in real time via the imaging module.
[0050] S3: Real-time monitoring of deformation of jointed soft rock, such as Figure 3 As shown, the following steps are included:
[0051] S31: Acquisition of joint surface information of jointed soft rock in key areas: The laser scanner carried by the "Feng Yi" independently developed by the Chongqing Research Institute of Harbin Institute of Technology is used to scan the joint surface information of jointed soft rock in the tunnel, and the data is transmitted back to the database. The real-time image data obtained is synchronously transmitted to the management center.
[0052] S32: Three-dimensional construction of site model: The position parameters obtained by the laser scanner are transmitted to the data calculation module for calculation and processing to construct a three-dimensional model containing position coordinate information.
[0053] S33: Kinematic analysis of risky locations: Calculate the self-stabilization coefficient of key blocks around the tunnel chamber and the safety factor after reinforcement. The calculation formula is as follows:
[0054]
[0055] When F>1.5, the block is intact and will not be destroyed in any form, and can be regarded as a stable block;
[0056] When F is less than 1.5, the block is considered to be a dangerous block and deformation monitoring of the risky position is required.
[0057] S34: Deformation monitoring at risky locations: Paste strain gauges at risky locations, start the on-site data acquisition module and imaging module, and monitor the displacement changes of the block to be tested in real time; if the risk at this location is high, a camera can be attached on the basis of the strain gauge to obtain data information and image information in real time, transmit the strain gauge monitoring data back to the database in real time and enter the data calculation module for calculation, and transmit the real-time on-site images collected by the camera back to the management center.
[0058] S4: After the advanced geological forecast and real-time monitoring data of jointed soft rock deformation are obtained, they are transmitted to the disaster warning module through the data calculation module. The disaster warning module sets three risk levels: high risk, medium risk and low risk. When the data exceeds the threshold (the threshold can be set according to the specific project conditions), the disaster warning module automatically judges the risk level and transmits it back to the database and management center.
[0059] S5: After the disaster warning module determines the risk level, the management center and construction personnel will receive information on the risk level, risk location, estimated time of risk occurrence after calculation, and recommended risk avoidance measures. At the same time, if the management center personnel have any objections to the automatic assessment results after receiving the data, they can change the risk level through the management center and manually send it to the construction personnel through the communication module.
[0060] Example:
[0061] S1: Start the user management module, create an administrator, set the names of administrators at all levels and their management permissions; create a new project folder, and enter the tunnel design parameters, data obtained from on-site exploration, and existing disaster avoidance measures data.
[0062] S2: Start the on-site data acquisition module and imaging module to conduct advanced geological prediction for the water-rich area in the tunnel construction direction:
[0063] S21: Implement geological survey methods: identify, separate and collect geological entities such as rocks, strata, structures, landforms, hydrogeology and their attributes, and determine key monitoring sections based on existing engineering data.
[0064] S22: Implementation of transient electromagnetic method: Implementation of transient electromagnetic method along the entire length of the tunnel, with a forecast distance of 75 meters. Using PROTEMEM-47 transient electromagnetic instrument, a large coil in front of the tunnel generates electromagnetic waves, which induce eddy currents in the aquifer, and the eddy currents generate induced electromagnetic fields. The receiving probe on the tunnel face can receive this electromagnetic field, and the low-resistance body farther away will be induced by this electromagnetic field to generate an induced electromagnetic field. The aquifer will show low resistance reflection on the transient electromagnetic method apparent resistivity profile.
[0065] S23: Implementation of ground penetrating radar method: Combined with the results obtained by transient electromagnetic method, according to the actual engineering conditions in the tunnel, if there is a risk area, the ground penetrating radar method is implemented, with a forecast distance of 5-15 meters. The GSSI company's SIR-20 ground penetrating radar is used to detect the target body by using high-frequency pulse electromagnetic wave reflection echoes. It has good anti-interference ability and can reach meter-level or even centimeter-level accuracy.
[0066] S24: Implementation of advance drilling and digital imaging: Combined with the results obtained by the ground penetrating radar method, according to the actual engineering conditions in the tunnel, if there are risk areas, the advance drilling and digital imaging method is implemented to provide drilling images in the form of photos and videos.
[0067] S3: Real-time monitoring of deformation of jointed soft rock:
[0068] S31: Acquisition of joint surface information of jointed soft rock in key areas: The laser scanner carried by the "Feng Yi" independently developed by the Chongqing Research Institute of Harbin Institute of Technology is used to scan the joint surface information of jointed soft rock in the tunnel, and the data is transmitted back to the database. The real-time image data obtained is synchronously transmitted to the management center.
[0069] S32: Three-dimensional construction of site model: The position parameters obtained by the laser scanner are transmitted to the data calculation module for calculation and processing to construct a three-dimensional model containing position coordinate information.
[0070] S33: Kinematic analysis of risky locations: Calculate the self-stabilization coefficient of key blocks around the tunnel chamber and the safety factor after reinforcement. The calculation formula is as follows:
[0071]
[0072] When F>1.5, the block is intact and will not be destroyed in any form, and can be regarded as a stable block;
[0073] When F is less than 1.5, the block is considered to be a dangerous block and deformation monitoring of the risky position is required.
[0074] S34: Deformation monitoring at risky locations: Paste strain gauges at risky locations, start the on-site data acquisition module and imaging module, and monitor the displacement changes of the block to be tested in real time; if the risk at this location is high, a camera can be attached on the basis of the strain gauge to obtain data information and image information in real time, transmit the strain gauge monitoring data back to the database in real time and enter the data calculation module for calculation, and transmit the real-time on-site images collected by the camera back to the management center.
[0075] S4: After the advanced geological forecast and real-time monitoring data of jointed soft rock deformation are obtained, they are transmitted to the disaster warning module through the data calculation module. The disaster warning module sets three risk levels: high risk, medium risk and low risk. When the data exceeds the threshold (the threshold can be set according to the specific project conditions), the disaster warning module automatically judges the risk level and transmits it back to the database and management center.
[0076] S5: After the disaster warning module determines the risk level, the management center and construction personnel will receive information on the risk level, risk location, estimated time of risk occurrence after calculation, and recommended risk avoidance measures. At the same time, if the management center personnel have any objections to the automatic assessment results after receiving the data, they can change the risk level through the management center and manually send it to the construction personnel through the communication module.
Claims
1. A disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction, characterized in that The system includes a user management module, a database, a field data acquisition module, a communication module, a data calculation module, a disaster warning module, and an imaging module, wherein: The user management module is used for the creation of new users and the input, modification and deletion of existing data of specific engineering projects, including the creation, login, management, maintenance and logout of new users, as well as the creation and editing of specific engineering folders matched with new users, the input and rewriting of existing data and the input of real-time parameters of projects; The database is used to provide project engineering overview data, early warning information data, existing disaster avoidance measures data, risk data obtained by detection, and real-time engineering parameter data obtained by detection; The field data acquisition module is used to record in real time the water-rich area data obtained by transient electromagnetic method, ground penetrating radar method, advanced drilling and digital imaging method, as well as the joint surface information and jointed soft rock deformation data, and push them to the database, and then transmit them to the management center; The communication module is used to realize real-time communication between the management center and the site, and information transmission between the disaster warning module and the site, so as to guide evacuation in the first time when encountering danger; The data operation module is used for three-dimensional modeling and operation of the dangerous situation data collected in real time, and pushes the obtained results to the database and then to the management center; The disaster warning module is used to automatically classify the risk data obtained by the data calculation module into risk levels and push them to the database, and then push them to the management center and construction personnel; The imaging module is used to collect image data of the implementation of laser scanner, advance drilling and digital imaging method and soft rock deformation after excavation.
2. A method for implementing the disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction as described in claim 1, characterized in that The method comprises the following steps: S1: Start the user management module, create an administrator, set the names of administrators at all levels and their management permissions; create a new project folder, enter the tunnel design parameters, data obtained from on-site exploration, and existing disaster avoidance measures data; S2: Start the on-site data acquisition module and imaging module to conduct advanced geological prediction for the water-rich area in the tunnel construction direction; S3: Real-time monitoring of deformation of jointed soft rock; S4: After the advanced geological prediction and real-time monitoring data of jointed soft rock deformation are obtained, they are transmitted to the disaster warning module through the data calculation module. The disaster warning module sets three risk levels: high risk, medium risk, and low risk. When the data exceeds the threshold, the disaster warning module automatically determines the risk level and transmits it back to the database and management center; S5: After the disaster warning module determines the risk level, the management center and construction personnel will receive information on the risk level, risk location, estimated time of risk occurrence after calculation, and recommended risk avoidance measures. At the same time, if the management center personnel have any objections to the automatic assessment results after receiving the data, they will change the risk level through the management center and manually send it to the construction personnel through the communication module.
3. The method for implementing the disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction according to claim 2 is characterized in that The S2 comprises the following steps: S21: Implement geological survey method: collect the original geological data and previous geological survey data of the construction site, manually input relevant geological information and save it into the database, combine the on-site observations, analyze the locations where hidden dangers may occur, and conduct key inspections; S22: Implementation of transient electromagnetic method: Implementation of transient electromagnetic method along the entire length of the tunnel. If risk factors are found, data will be transmitted to the management center and database and ground penetrating radar method will be implemented. Otherwise, forecasting will be stopped; S23: Implementation of ground penetrating radar method: Based on the results obtained by transient electromagnetic method and the actual engineering conditions in the tunnel, ground penetrating radar method is implemented in important areas. If risk factors appear, the data will be transmitted to the management center and database and advance drilling and digital imaging methods will be implemented. Otherwise, the forecast will be stopped; S24: Implement advance drilling and digital imaging methods: Combined with the results obtained by the ground penetrating radar method, according to the actual engineering conditions in the tunnel, advance drilling and digital imaging methods are implemented in the range where disasters are most likely to occur, so as to obtain specific water-rich hazards in the construction direction. The obtained data is automatically transmitted to the database and saved. At the same time, the image information in the drilling probe is transmitted back to the management center in real time via the imaging module.
4. The method for implementing the disaster assessment and early warning system for water-rich jointed soft rock tunnel excavation construction according to claim 2 is characterized in that The S3 comprises the following steps: S31: Acquisition of joint surface information of jointed soft rock in key areas: Use laser scanner to scan the joint surface information of jointed soft rock in the tunnel, obtain data and transmit it back to the database, and the obtained real-time image data is synchronously transmitted to the management center; S32: 3D construction of site model: The position parameters obtained by the laser scanner are transmitted to the data calculation module for calculation and processing to construct a 3D model containing position coordinate information; S33: Kinematic analysis of risky locations: Calculate the self-stabilization coefficient of key blocks around the tunnel chamber and the safety factor after reinforcement; S34: Deformation monitoring at risky locations: Paste strain gauges at risky locations, start the on-site data acquisition module and imaging module, and monitor the displacement changes of the block to be tested in real time; if the risk at this location is high, a camera can be attached on the basis of the strain gauge to obtain data information and image information in real time, transmit the strain gauge monitoring data back to the database in real time and enter the data calculation module for calculation, and transmit the real-time on-site images collected by the camera back to the management center.
5. The method for implementing the disaster assessment and early warning system for excavation construction of water-rich jointed soft rock tunnel according to claim 4 is characterized in that The safety factor is calculated as follows: When F>1.5, the block is intact and will not be destroyed in any form, and can be regarded as a stable block; When F is less than 1.5, the block is considered to be a dangerous block and deformation monitoring of the risky position is required.
Citation Information
Cited By
Tunnel under-excavation rock mass excavation method
CN121047597A