Plant-level coal-electricity hybrid thermoelectric production system and method using stored heat and waste heat

By combining equipment such as boilers, back pressure machines, generators, thermal storage units, and compressor units, flexible thermal energy management and storage of the thermal power production system are realized, solving the problems of low energy utilization efficiency and unutilized waste heat in existing technologies, and improving the system's flexibility and economy.

CN118934122APending Publication Date: 2024-11-12HANGZHOU YINGJI POWER TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411086651.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

Existing thermal power generation technologies suffer from low energy efficiency and poor flexibility, failing to effectively utilize waste heat and steam generated by boilers for heat storage, release, and supply.

Method used

Design a plant-level coal-fired power plant cogeneration system that combines equipment such as boilers, back pressure machines, generators, thermal storage units, compressor units, and waste heat exchangers. Through steam compression for thermal storage, waste heat compression for thermal supply, and thermal storage release processes, flexible management and storage of thermal energy can be achieved.

Benefits of technology

It has improved the flexibility and energy efficiency of the cogeneration system, reduced steam production costs, improved power supply efficiency, promoted the transformation of coal-fired cogeneration plants into coal-fired power plants with combined energy storage, and enhanced the system's peak-shaving capacity and operational stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934122A_ABST
    Figure CN118934122A_ABST
Patent Text Reader

Abstract

The invention discloses a plant-level coal-electricity hybrid thermoelectric production system utilizing stored heat and waste heat. The plant-level coal-electricity hybrid thermoelectric production system is characterized in that a boiler is communicated with a steam inlet of a back pressure turbine to form a first steam supply pipeline; a steam exhaust port of the back pressure machine is divided into two paths, one path is communicated with a heat user to form a user direct external steam supply pipeline, and the other path is communicated with the heat storage unit through the first compressor unit to form a steam compression heat storage pipeline; the heat storage unit is communicated with a steam inlet of the back pressure machine to form a second steam supply pipeline; the back pressure turbine drives the generator to generate power by using steam supplied by the first and second steam supply pipelines; the flue gas waste heat exchanger is communicated with the boiler to form a waste heat recovery pipeline; the flue gas waste heat exchanger is communicated with the evaporation tank to form a waste heat pretreatment pipeline; the evaporation tank is communicated with the second compressor unit to form a waste heat compression pipeline and then is divided into two paths, one path is communicated with a heat user through the buffer tank to form a user waste heat external steam supply pipeline, and the other path is communicated with the heat storage unit through the first compressor unit to form a waste heat compression heat storage pipeline.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of thermal power production, and in particular relates to a plant-level coal-electricity hybrid thermal power production system and method utilizing heat storage and waste heat. Background Art

[0002] Thermal power plants cover multiple links when producing thermal power, mainly including combustion systems, steam generation, power conversion, power generation, heat energy distribution and control systems, etc., which can simultaneously utilize the electricity and heat energy generated during the combustion process, reducing energy waste. With the large-scale grid-connected power generation with a high proportion of renewable energy, coal-fired units need to undertake peak-shaving and dispatching tasks to ensure the stable operation of the power grid. In addition, with the rapid development of urbanization, the heat demand for heating by residents is also growing rapidly, which requires coal-fired units to carry out technical transformation in the direction of high heat-to-power ratio, high flexibility and energy saving.

[0003] At present, energy storage technology, as an emerging technology, has great development potential in the technical transformation of coal-fired units. Energy storage technology has the advantages of large scale, low cost and long life, and it is mature and easy to operate, and can be effectively coupled with coal-fired units. However, the existing thermal power production technology solutions have low energy utilization efficiency, poor flexibility and poor peak load regulation capabilities, and do not effectively and flexibly utilize the waste heat and steam generated by the boiler for heat storage and heat supply.

[0004] Based on the above technical problems, it is necessary to design a new plant-level coal-fired hybrid thermal power production system and method that utilizes heat storage and waste heat. Summary of the invention

[0005] The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a plant-level coal-electricity hybrid thermal power production system and method using heat storage and waste heat.

[0006] In order to solve the above technical problems, the technical solution of the present invention is:

[0007] The present invention provides a plant-level coal-electricity hybrid heat and power production system using heat storage and waste heat, comprising: a boiler, a back pressure machine, a generator, a heat storage unit, a first compressor unit, a second compressor unit, a first motor, a second motor, a flue gas waste heat exchanger, a buffer tank, an evaporation tank and a heat user;

[0008] The boiler has coal as input and main steam as output, and is connected with the steam inlet of the back pressure machine to form a first steam supply pipeline;

[0009] The exhaust port of the back pressure machine is divided into two paths, one of which is connected to the heat user to form a direct external steam supply pipeline for the user, and the other is connected to the heat storage unit through the first compressor unit to form a steam compression heat storage pipeline;

[0010] The first compressor group is driven by the first motor connected to the first compressor group; the second compressor group is driven by the second motor connected to the first compressor group;

[0011] The heat storage unit is connected to the steam inlet of the back pressure machine to form a second steam supply pipeline;

[0012] The back pressure machine drives a generator to generate electricity using steam supplied by the first steam supply pipeline and the second steam supply pipeline;

[0013] The flue gas waste heat exchanger is connected to the boiler to form a waste heat recovery pipeline;

[0014] The flue gas waste heat exchanger is connected to the evaporation tank to form a waste heat pretreatment pipeline;

[0015] The evaporator is connected with the second compressor unit to form a waste heat compression pipeline, which is divided into two paths. One path is connected with the heat user through the buffer tank to form a user waste heat external steam supply pipeline, and the other path is connected with the heat storage unit through the first compressor unit to form a waste heat compression heat storage pipeline.

[0016] Furthermore, the heat storage unit includes a first heat storage unit and a second heat storage unit; the first heat storage unit and the second heat storage unit are connected; and the first heat storage unit is arranged close to the first compressor unit.

[0017] Further, the first heat storage unit includes a sensible heat storage tank and a phase change heat storage tank; the second heat storage unit includes a saturated water tank and a water pump;

[0018] The sensible heat storage tank is used to store the heat of superheated steam; the phase change heat storage tank is used to store the latent heat of steam; and the saturated water tank is used to store the condensed working fluid liquid.

[0019] Further, the sensible heat storage tank is connected with the first compressor unit; the sensible heat storage tank is connected with the phase change heat storage tank; the phase change heat storage tank is connected with the saturated water tank to form a heat storage pipeline; the saturated water tank is connected with the phase change heat storage tank and the sensible heat storage tank by starting the water pump to form a heat release pipeline.

[0020] Further, a first valve, a second valve and a third valve are provided on the pipeline connecting the back pressure machine and the first compressor unit;

[0021] A fourth valve and a fourteenth valve are provided on the pipeline connecting the second compressor unit and the buffer tank;

[0022] A fifteenth valve is provided on the pipeline connecting the buffer tank and the heat user;

[0023] A sixth valve and a thirteenth valve are provided on the pipeline connecting the first compressor unit and the heat storage unit;

[0024] A fifth valve is provided on the pipeline connecting the heat storage unit and the back pressure machine;

[0025] A seventh valve and an eighth valve are provided on the pipeline connecting the phase change heat storage tank and the saturated water tank;

[0026] A tenth valve is provided on the pipeline connecting the saturated water tank and the water pump;

[0027] A ninth valve is provided on the pipeline connecting the water pump and the seventh valve;

[0028] The pipeline connecting the flue gas waste heat exchanger and the evaporation tank is provided with an eleventh valve and a twelfth valve.

[0029] Furthermore, after the heat storage unit is connected to the steam inlet of the back compressor to form a second steam supply pipeline, it is used to release the heat stored in the steam compression heat storage pipeline and the waste heat compression heat storage pipeline.

[0030] Furthermore, the first compressor group and the second compressor group each include a plurality of compressors, and the plurality of compressors are connected in sequence.

[0031] The present invention also provides a plant-level coal-electricity hybrid heat and power production method using heat storage and waste heat, which uses the above-mentioned plant-level coal-electricity hybrid heat and power production system. The plant-level coal-electricity hybrid heat and power production method includes:

[0032] The boiler uses coal as input and outputs main steam to drive the back pressure machine. The back pressure machine uses the main steam to drive the generator to generate electricity, and a part of the exhaust steam after the back pressure machine is running is directly supplied to the heat users.

[0033] Steam compression heat storage process: another part of the exhaust steam after the back pressure machine is running is stored in the heat storage unit by starting the first compressor unit, opening the first valve, the second valve, the third valve, the thirteenth valve and the sixth valve, and closing the fourth valve and the fifth valve;

[0034] Waste heat compression heating process: obtain waste heat during boiler operation through flue gas waste heat exchanger, start the evaporator, the second compressor unit, the buffer tank, open the eleventh valve, the twelfth valve, the fourth valve, the fourteenth valve and the fifteenth valve, and close the first valve, the second valve and the third valve at the same time, compress the waste heat steam directly to the back pressure steam parameter, and supply waste heat steam to heat users;

[0035] Waste heat compression heat storage process: obtain waste heat during boiler operation through the flue gas waste heat exchanger, start the evaporator, the second compressor unit and the first compressor unit, open the eleventh valve, the twelfth valve, the fourth valve, the third valve, the thirteenth valve and the sixth valve, and close the first valve, the second valve, the fourteenth valve, the fifteenth valve and the fifth valve at the same time, and compress and store the waste heat in the heat storage unit;

[0036] Wherein, after the back pressure steam in the steam compression heat storage process and the waste heat steam in the waste heat compression heat storage process are processed by the sensible heat storage tank and the phase change heat storage tank in the heat storage unit, the seventh valve and the eighth valve are opened, and the ninth valve and the tenth valve are closed at the same time, and the condensed working fluid liquid is stored in the saturated water tank to perform steam compression heat storage and waste heat compression heat storage; the first compressor group is driven by a connected first motor; the second compressor group is driven by a connected second motor;

[0037] Heat storage release process: The heat storage unit starts the saturated water tank and the water pump, opens the tenth valve, the ninth valve, the seventh valve, the sixth valve and the fifth valve, and closes the eighth valve, the thirteenth valve and the first valve at the same time, releases the heat stored in the steam compression process and the heat stored in the waste heat compression process, and drives the back pressure machine to operate to achieve power generation and steam supply.

[0038] Furthermore, the waste heat compression heating process is operated during the off-peak electricity price period and the steam demand peak period; the waste heat compression heat storage process is operated during the off-peak electricity price period and the steam demand off-peak period; the heat storage release process is operated during the peak, peak electricity price period and the steam demand peak period; the steam compression heat storage process is operated during the peak, peak electricity price period and the steam demand off-peak period.

[0039] The beneficial effects of the present invention are:

[0040] (1) The plant-level coal-fired power generation system provided by the present invention organically combines boilers, back pressure machines, generators with heat storage technology, waste heat utilization technology and compressor units, establishes a back pressure machine power generation steam supply process, a steam compression heat storage process, a waste heat compression heat supply process, a waste heat compression heat storage process and a heat storage release process, and converts the heat that would otherwise be wasted into usable thermal energy resources by recovering and utilizing flue gas waste heat. In addition, by activating different compressor units and valve combinations, the system can switch between heating and heat storage and heat release modes according to real-time needs, providing a more flexible thermal energy management solution;

[0041] (2) The present invention utilizes the combined regulation of the compressor unit and the energy storage unit, valves and other equipment to store heat energy during off-peak electricity price periods or when there is a cheap heat source. Then, during peak electricity price periods or when the heat source output is insufficient, peak load shifting and valley filling and optimal utilization of energy are achieved, which greatly improves the power supply and steam supply regulation capabilities of the system, reduces steam production costs, improves power supply efficiency, and promotes the transformation of coal-fired thermal power plants into coal-fired power plants combined with energy storage.

[0042] (3) The heat storage unit of the present invention can bear fluctuating loads, and the boiler is responsible for the basic load, thereby improving the stability of boiler operation, extending the service life and improving the energy efficiency of the system. As the load demand changes, the system operates only one or a small number of boilers under low load conditions through the joint operation of various devices, rather than all of them. This can avoid the phenomenon of "a big horse pulling a small cart", reduce energy waste, and improve overall operating efficiency and economy;

[0043] (4) The present invention is used to ensure that the boiler works under stable conditions by combining the heat storage system with the steam compressor when external demand (electricity and steam) changes, thereby improving the flexible adjustment capability of thermal-electric decoupling and the economic and safety of the cogeneration system. At the same time, under certain conditions, the waste heat of boiler flue gas and off-peak electricity are used to generate steam for external steam and electricity supply, saving fuel costs and achieving the purpose of energy saving and carbon reduction.

[0044] Other features and advantages will be described in the following description, and partly become apparent from the description, or understood by practicing the invention. The purpose and other advantages of the invention are realized and obtained by the structures particularly pointed out in the description and the drawings.

[0045] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0047] Figure 1 It is a schematic diagram of a plant-level coal-electricity hybrid thermal power production system utilizing heat storage and waste heat according to the present invention.

[0048] Description of reference numerals:

[0049] 1. First valve; 2. Second valve; 3. Third valve; 4. Fourth valve; 5. Fifth valve; 6. Sixth valve; 7. Seventh valve; 8. Eighth valve; 9. Ninth valve; 10. Tenth valve; 11. Eleventh valve; 12. Twelfth valve; 13. Thirteenth valve; 14. Fourteenth valve; 15. Fifteenth valve; 16. Boiler; 17. Back pressure machine; 18. Generator; 19. Heat user; 20. First compressor unit; 21. First motor; 22. Heat storage unit; 23. Flue gas waste heat exchanger; 24. Evaporator; 25. Second compressor unit; 26. Second motor; 27. Buffer tank; 28. First heat storage unit; 29. ​​Second heat storage unit; 281. Sensible heat storage tank; 282. Phase change heat storage tank; 291. Saturated water tank; 292. Water pump. DETAILED DESCRIPTION

[0050] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0051] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "connected" and "interconnected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal connection of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances. In addition, the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence.

[0052] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0053] Example 1

[0054] like Figure 1 As shown, this embodiment 1 provides a plant-level coal-electricity hybrid heat and power production system using heat storage and waste heat, including: a boiler 16, a back pressure machine 17, a generator 18, a heat user 19, a first compressor unit 20, a first motor 21, a heat storage unit 22, a flue gas waste heat exchanger 23, an evaporation tank 24, a second compressor unit 25, a second motor 26 and a buffer tank 27;

[0055] The boiler 16 has coal as input and main steam as output, and is connected with the steam inlet of the back pressure machine 17 to form a first steam supply pipeline;

[0056] The exhaust port of the back pressure machine 17 is divided into two paths, one of which is connected to the heat user 19 to form a direct steam supply pipeline for the user, and the other is connected to the heat storage unit 22 through the first compressor unit 20 to form a steam compression heat storage pipeline;

[0057] The first compressor unit 20 is driven by the first motor 21 connected thereto; the second compressor unit 25 is driven by the second motor 22 connected thereto;

[0058] The heat storage unit 22 is connected to the steam inlet of the back pressure machine 17 to form a second steam supply pipeline;

[0059] The back pressure machine 17 drives the generator 18 to generate electricity using the steam supplied by the first steam supply pipeline and the second steam supply pipeline;

[0060] The flue gas waste heat exchanger 23 is connected to the boiler 16 to form a waste heat recovery pipeline;

[0061] The flue gas waste heat exchanger 23 is connected to the evaporation tank 24 to form a waste heat pretreatment pipeline;

[0062] The evaporator 24 is connected with the second compressor unit 25 to form a waste heat compression pipeline, which is divided into two paths. One path is connected with the heat user 19 through the buffer tank 27 to form a user waste heat external steam supply pipeline, and the other path is connected with the heat storage unit 22 through the first compressor unit 20 to form a waste heat compression heat storage pipeline.

[0063] In this embodiment, the heat storage unit 22 includes a first heat storage unit 28 and a second heat storage unit 29 ; the first heat storage unit 28 and the second heat storage unit 29 are connected; and the first heat storage unit 28 is disposed close to the first compressor unit 20 .

[0064] In this embodiment, the first heat storage unit 22 includes a sensible heat storage tank 281 and a phase change heat storage tank 282; the second heat storage unit 29 includes a saturated water tank 291 and a water pump 292;

[0065] The sensible heat storage tank 281 is used to store the heat of superheated steam; the phase change heat storage tank 282 is used to store the latent heat of steam; and the saturated water tank 291 is used to store the condensed working fluid liquid.

[0066] It should be noted that the sensible heat storage tank 281 is mainly used to store heat obtained by heating solid or liquid media, which store energy by simply increasing the temperature without changing their phase. The medium in the sensible heat storage tank is usually a material with a high heat capacity such as water, oil, sand, rock or concrete. When heat needs to be released, the previously stored heat is released by cooling these media.

[0067] The phase change heat storage tank 282 uses the latent heat of the phase change material during the phase change process to store and release heat. When the phase change material is heated to its phase change temperature, it changes from solid to liquid, and this process absorbs a large amount of thermal energy, i.e., latent heat. Conversely, when the phase change material cools, it resolidifies from liquid to solid, releasing the latent heat previously absorbed.

[0068] The saturated water tank 291 is usually used to store saturated water condensed from steam, that is, water that is in liquid state but close to boiling temperature at a specific pressure. In the steam power cycle, steam condenses into saturated water after doing work. This part of water needs to be collected and reheated to become steam again for continued circulation. The role of the saturated water tank 291 is to store condensed water in this process to ensure that there is enough working fluid liquid supply in the system. It can also be used as a temporary thermal energy storage because the saturated water itself carries a lot of heat.

[0069] The water pump 292 extracts saturated water from the saturated water tank 291, and subsequently releases heat energy to meet part of the steam supply demand and power generation demand.

[0070] In this embodiment, the sensible heat storage tank 281 is connected to the first compressor unit 20; the sensible heat storage tank 281 is connected to the phase change heat storage tank 282; the phase change heat storage tank 282 is connected to the saturated water tank 291 to form a heat storage pipeline; the saturated water tank 291 is connected to the phase change heat storage tank 282 and the sensible heat storage tank 281 by starting the water pump 292 to form a heat release pipeline.

[0071] In this embodiment, a first valve 1, a second valve 2 and a third valve 3 are provided on the pipeline connecting the back pressure machine 17 and the first compressor unit 20;

[0072] The pipeline connecting the second compressor unit 25 and the buffer tank 27 is provided with a fourth valve 4 and a fourteenth valve 14;

[0073] A fifteenth valve 15 is provided on the pipeline connecting the buffer tank 27 and the heat user 19;

[0074] A sixth valve 6 and a thirteenth valve 13 are provided on the pipeline connecting the first compressor unit 20 and the heat storage unit 22;

[0075] A fifth valve 5 is provided on the pipeline connecting the heat storage unit 22 and the back pressure machine 17;

[0076] The pipeline connecting the phase change heat storage tank 282 and the saturated water tank 291 is provided with a seventh valve 7 and an eighth valve 8;

[0077] A tenth valve 10 is provided on the pipeline connecting the saturated water tank 291 and the water pump 292;

[0078] A ninth valve 9 is provided on the pipeline connecting the water pump 292 and the seventh valve 7;

[0079] The pipeline connecting the flue gas waste heat exchanger 23 and the evaporation tank 24 is provided with an eleventh valve 11 and a twelfth valve 12 .

[0080] In this embodiment, after the heat storage unit 22 is connected to the steam inlet of the back compressor 17 to form a second steam supply pipeline, it is used to release the heat stored in the steam compression heat storage pipeline and the waste heat compression heat storage pipeline.

[0081] In this embodiment, the first compressor group 20 and the second compressor group 25 each include a plurality of compressors, and the plurality of compressors are connected in sequence.

[0082] Example 2

[0083] This embodiment provides a plant-level coal-electricity hybrid heat and power production method using heat storage and waste heat, which uses the plant-level coal-electricity hybrid heat and power production system in Example 1. The plant-level coal-electricity hybrid heat and power production method includes:

[0084] The boiler 16 uses coal as input and outputs main steam to drive the back pressure machine 17 to operate. The back pressure machine 17 uses the main steam to drive the generator 18 to generate electricity, and a part of the exhaust steam after the back pressure machine 17 operates is directly supplied to the heat user 19.

[0085] Steam compression heat storage process: another part of the exhaust steam after the back pressure machine 17 is running is stored in the heat storage unit 22 by starting the first compressor unit 20, opening the first valve 1, the second valve 2, the third valve 3, the thirteenth valve 13 and the sixth valve 6, and closing the fourth valve 4 and the fifth valve 5;

[0086] Waste heat compression heating process: the waste heat in the operation process of the boiler 16 is obtained through the flue gas waste heat heat exchanger 23, and the evaporator 24, the second compressor unit 25, and the buffer tank 27 are started, the eleventh valve 11, the twelfth valve 12, the fourth valve 4, the fourteenth valve 14 and the fifteenth valve 15 are opened, and the first valve 1, the second valve 2 and the third valve 3 are closed at the same time, and the waste heat steam is directly compressed to the back pressure steam parameter, and the waste heat is supplied to the heat user 19;

[0087] Waste heat compression heat storage process: the waste heat in the operation process of the boiler 16 is obtained through the flue gas waste heat exchanger 23, and the evaporator 24, the second compressor unit 25 and the first compressor unit 20 are started, the eleventh valve 11, the twelfth valve 12, the fourth valve 4, the third valve 3, the thirteenth valve 13 and the sixth valve 6 are opened, and the first valve 1, the second valve 2, the fourteenth valve 14, the fifteenth valve 15 and the fifth valve 5 are closed at the same time, and the waste heat is compressed and stored in the heat storage unit 22;

[0088] Among them, the heat storage unit 22 processes the back pressure steam in the steam compression heat storage process and the waste heat steam in the waste heat compression heat storage process in the sensible heat storage tank 281 and the phase change heat storage tank 282 in sequence, then opens the seventh valve 7 and the eighth valve 8, and closes the ninth valve 9 and the tenth valve 10, and stores the condensed working fluid liquid in the saturated water tank 291 to perform steam compression heat storage and waste heat compression heat storage; the first compressor unit 20 is driven by the connected first motor 21; the second compressor unit 25 is driven by the connected second motor 22;

[0089] Heat storage release process: The heat storage unit 22 starts the saturated water tank 291 and the water pump 292, opens the tenth valve 10, the ninth valve 9, the seventh valve 7, the sixth valve 6 and the fifth valve 5, and closes the eighth valve 8, the thirteenth valve 13 and the first valve 1, so as to release the heat stored in the steam compression process and the heat stored in the waste heat compression process, and drives the back pressure machine 17 to operate to realize power generation and steam supply.

[0090] It should be noted that during the steam compression heat storage process, when the steam (usually low-pressure steam) discharged after the back pressure machine 17 is running enters the first compressor unit 20, the compressor increases its pressure through compression. High-pressure steam can store more energy, so at the same volume, its enthalpy value is higher and more heat can be stored. In addition, during the compression process, the temperature of the steam will increase with the increase in pressure, because the mechanical energy consumed by the compression work is converted into the internal energy of the steam, which is manifested as an increase in temperature. By increasing the pressure and temperature of the steam, the first compressor unit 20 effectively increases the energy density of the steam. Once the steam is compressed and raised to a higher pressure and temperature, it can be directed to the heat storage unit 22 for storage, where the steam can maintain its high enthalpy state until it is needed.

[0091] In the waste heat compression heat storage process, the first compressor unit 20 is mainly responsible for compressing the low-pressure steam obtained through the flue gas waste heat exchanger 23 to a higher pressure, so as to increase the energy density of the steam, so as to more effectively store it in the heat storage unit 22. The heat storage capacity and efficiency of the heat storage unit 22 are improved, so that the system can release more heat when needed.

[0092] During the waste heat compression heating process, the task of the second compressor unit 25 is to compress the low-pressure steam to the back pressure steam parameters, that is, the steam pressure and temperature required by the heat user 19. This is done to directly meet the heating needs of the heat user and improve energy utilization efficiency.

[0093] In the waste heat compression heat storage process and the waste heat compression heating process, the first compressor unit 20 and the second compressor unit 25 are dedicated to recovering and utilizing the flue gas waste heat, converting the heat that would otherwise be wasted into usable thermal energy resources, and by enabling different compressor units and valve combinations, the system can switch between heating and heat storage modes according to real-time needs, providing a more flexible thermal energy management solution.

[0094] Through the joint regulation of the first compressor unit 20, the second compressor unit 25, the heat storage unit 22, valves and other equipment, thermal energy can be stored during off-peak electricity price periods or when there is a cheap heat source, and then during peak electricity price periods or when the heat source output is insufficient, peak shaving and valley filling and optimal utilization of energy can be achieved, greatly improving the system's power supply and steam supply regulation capabilities, reducing steam production costs, improving power supply efficiency, and promoting the transformation of coal-fired thermal power plants to coal-fired power plants combined with energy storage. In addition, the boiler 16 is responsible for the basic load, and the heat storage unit 22 bears the fluctuating load, which improves the stability of boiler operation, extends its life and improves the system's energy efficiency. Considering the setting of the heat storage unit 22, the setting of the standby boiler during actual operation can be reduced, and even the standby boiler can be eliminated.

[0095] In actual operation, heat demand may change due to seasonal changes, production cycles, or fluctuations in user demand. When heat demand is lower than the designed maximum load, if the full boiler capacity is still used, a "big horse pulling a small cart" situation will occur, that is, using equipment with too much capacity to handle a smaller workload, which will lead to energy waste and increased operating costs. Through reasonable design and intelligent control, the system can run only one or a small number of boilers under low load conditions, instead of all. This can avoid the "big horse pulling a small cart" phenomenon, reduce energy waste, and improve overall operating efficiency and economy.

[0096] In addition, the main function of the evaporation tank 24 is to use the heat obtained from the flue gas waste heat exchanger 23 to evaporate the water therein and generate steam. Specifically:

[0097] Heat conversion: The evaporator 24 receives the heat transferred from the flue gas waste heat exchanger 23 and uses the heat to heat water to turn it into steam. This is the process of converting heat energy into steam potential energy;

[0098] Steam generation: Water is converted into steam by heating inside the evaporation tank 24. This process requires precise temperature and pressure control to ensure that the quality of the steam (temperature, pressure and dryness) meets the standards for subsequent compression and use.

[0099] The buffer tank 27 plays a role in stabilizing steam supply and regulating pressure during the waste heat compression heating process, including:

[0100] Stable pressure and flow: The buffer tank 27 can store a certain amount of steam, thereby smoothing the steam supply when demand fluctuates, avoiding sudden changes in pressure and flow, and ensuring that downstream equipment (such as heat users) receive a stable steam supply;

[0101] Instantaneous demand response: When the heat user suddenly increases the steam demand, the buffer tank 27 can immediately provide part of the steam without waiting for the compressor to respond and increase production, which is very important for maintaining system stability and quickly responding to demand changes;

[0102] System protection: The buffer tank 27 also acts as part of the system to help protect the compressor and other key equipment from shocks and pressure fluctuations caused by instantaneous high demand, thus extending the life of the equipment;

[0103] Thermal energy storage: Although the main function is not long-term heat storage, to a certain extent, buffer tanks can temporarily store thermal energy to cope with short-term imbalances in supply and demand.

[0104] In this embodiment, the waste heat compression heating process is operated during the off-peak electricity price period and the steam demand peak period; the waste heat compression heat storage process is operated during the off-peak electricity price period and the steam demand off-peak period; the heat storage release process is operated during the peak, peak electricity price period and the steam demand peak period; the steam compression heat storage process is operated during the peak, peak electricity price period and the steam demand off-peak period.

[0105] In actual applications, during peak and peak electricity price periods and periods of peak steam demand, the heat storage release process can be used to release the stored heat, and cooperate with the boiler to achieve power generation and steam supply; during off-peak electricity price periods and periods of peak steam demand, the waste heat compression heating process can be used to comprehensively utilize low-priced electricity and flue gas waste heat, improve the external steam supply capacity, and meet peak steam demand; during peak and peak electricity price periods and periods of low steam demand, the steam compression heat storage process can be used to compress and store part of the exhaust steam after the back pressure machine is operated, while ensuring power generation, storing excess steam for use during peak steam demand, and realizing flexible adjustment of thermal and electric decoupling; during off-peak electricity price periods and periods of low steam demand, the waste heat compression heat storage process can be used to drive the compressor using off-peak electricity to compress and store the waste heat for use during peak and peak electricity price periods and periods of peak steam demand.

[0106] In several embodiments provided in the present application, it should be understood that the disclosed system and method can also be implemented in other ways. The system embodiments described above are merely schematic. For example, the flowcharts and block diagrams in the accompanying drawings show the possible architecture, functions and operations of the systems, methods and computer program products according to multiple embodiments of the present invention. In this regard, each box in the flowchart or block diagram can represent a module, a program segment or a part of the code, and a part of the module, program segment or code contains one or more executable instructions for implementing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two consecutive boxes can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram and / or flowchart, and the combination of boxes in the block diagram and / or flowchart can be implemented with a dedicated hardware-based system that performs a specified function or action, or can be implemented with a combination of dedicated hardware and computer instructions.

[0107] In addition, the functional modules in each embodiment of the present invention can be integrated together to form an independent part, or each module can exist separately, or two or more modules can be integrated to form an independent part. If the function is implemented in the form of a software functional module and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art or the part of the technical solution can be embodied in the form of a software product, which is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the methods of each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, RandomAccess Memory), disk or optical disk and other media that can store program codes.

[0108] Based on the above ideal embodiments of the present invention, the relevant staff can make various changes and modifications without departing from the technical concept of the present invention through the above description. The technical scope of the present invention is not limited to the contents of the specification, and its technical scope must be determined according to the scope of the claims.

Claims

1. A plant-level coal-electricity hybrid heat and power production system using heat storage and waste heat, It is characterized in that include: Boiler, back pressure machine, generator, heat storage unit, first compressor unit, second compressor unit, first motor, second motor, flue gas waste heat exchanger, buffer tank, evaporation tank and heat user; The boiler has coal as input and main steam as output, and is connected with the steam inlet of the back pressure machine to form a first steam supply pipeline; The exhaust port of the back pressure machine is divided into two paths, one of which is connected to the heat user to form a direct external steam supply pipeline for the user, and the other is connected to the heat storage unit through the first compressor unit to form a steam compression heat storage pipeline; The first compressor group is driven by the first motor connected to the first compressor group; the second compressor group is driven by the second motor connected to the first compressor group; The heat storage unit is connected to the steam inlet of the back pressure machine to form a second steam supply pipeline; The back pressure machine drives a generator to generate electricity using steam supplied by the first steam supply pipeline and the second steam supply pipeline; The flue gas waste heat exchanger is connected to the boiler to form a waste heat recovery pipeline; The flue gas waste heat exchanger is connected to the evaporation tank to form a waste heat pretreatment pipeline; The evaporator is connected with the second compressor unit to form a waste heat compression pipeline, which is divided into two paths. One path is connected with the heat user through the buffer tank to form a user waste heat external steam supply pipeline, and the other path is connected with the heat storage unit through the first compressor unit to form a waste heat compression heat storage pipeline.

2. The plant-level coal-electricity hybrid heat and power production system according to claim 1, It is characterized in that The heat storage unit includes a first heat storage unit and a second heat storage unit; the first heat storage unit and the second heat storage unit are connected; and the first heat storage unit is arranged close to the first compressor unit.

3. The plant-level coal-electricity hybrid heat and power production system according to claim 2, It is characterized in that The first heat storage unit includes a sensible heat storage tank and a phase change heat storage tank; the second heat storage unit includes a saturated water tank and a water pump; The sensible heat storage tank is used to store the heat of superheated steam; the phase change heat storage tank is used to store the latent heat of steam; and the saturated water tank is used to store the condensed working fluid liquid.

4. The plant-level coal-electricity hybrid heat and power production system according to claim 3, It is characterized in that The sensible heat storage tank is connected with the first compressor unit; the sensible heat storage tank is connected with the phase change heat storage tank; the phase change heat storage tank is connected with the saturated water tank to form a heat storage pipeline; the saturated water tank is connected with the phase change heat storage tank and the sensible heat storage tank by starting the water pump to form a heat release pipeline.

5. The plant-level coal-electricity hybrid heat and power production system according to claim 1, It is characterized in that A first valve, a second valve and a third valve are provided on a pipeline connecting the back pressure machine and the first compressor unit; A fourth valve and a fourteenth valve are provided on the pipeline connecting the second compressor unit and the buffer tank; A fifteenth valve is provided on the pipeline connecting the buffer tank and the heat user; A sixth valve and a thirteenth valve are provided on the pipeline connecting the first compressor unit and the heat storage unit; A fifth valve is provided on the pipeline connecting the heat storage unit and the back pressure machine; A seventh valve and an eighth valve are provided on the pipeline connecting the phase change heat storage tank and the saturated water tank; A tenth valve is provided on the pipeline connecting the saturated water tank and the water pump; A ninth valve is provided on the pipeline connecting the water pump and the seventh valve; The pipeline connecting the flue gas waste heat exchanger and the evaporation tank is provided with an eleventh valve and a twelfth valve.

6. The plant-level coal-electricity hybrid heat and power production system according to claim 1, It is characterized in that After the heat storage unit is connected to the steam inlet of the back compressor to form a second steam supply pipeline, it is used to release the heat stored in the steam compression heat storage pipeline and the waste heat compression heat storage pipeline.

7. The plant-level coal-electricity hybrid heat and power production system according to claim 1, It is characterized in that The first compressor group and the second compressor group each include a plurality of compressors, and the plurality of compressors are connected in sequence.

8. A plant-level coal-electricity hybrid thermal power production method using heat storage and waste heat, It is characterized in that The invention comprises a plant-level coal-electricity hybrid heat and power production system as described in claims 1 to 7, wherein the plant-level coal-electricity hybrid heat and power production method comprises: The boiler uses coal as input and outputs main steam to drive the back pressure machine. The back pressure machine uses the main steam to drive the generator to generate electricity, and a part of the exhaust steam after the back pressure machine is running is directly supplied to the heat users. Steam compression heat storage process: another part of the exhaust steam after the back pressure machine is running is stored in the heat storage unit by starting the first compressor unit, opening the first valve, the second valve, the third valve, the thirteenth valve and the sixth valve, and closing the fourth valve and the fifth valve; Waste heat compression heating process: obtain waste heat during boiler operation through flue gas waste heat exchanger, start the evaporator, the second compressor unit, the buffer tank, open the eleventh valve, the twelfth valve, the fourth valve, the fourteenth valve and the fifteenth valve, and close the first valve, the second valve and the third valve at the same time, compress the waste heat steam directly to the back pressure steam parameter, and supply waste heat steam to heat users; Waste heat compression heat storage process: obtain waste heat during boiler operation through the flue gas waste heat exchanger, start the evaporator, the second compressor unit and the first compressor unit, open the eleventh valve, the twelfth valve, the fourth valve, the third valve, the thirteenth valve and the sixth valve, and close the first valve, the second valve, the fourteenth valve, the fifteenth valve and the fifth valve at the same time, and compress and store the waste heat in the heat storage unit; Wherein, after the back pressure steam in the steam compression heat storage process and the waste heat steam in the waste heat compression heat storage process are processed by the sensible heat storage tank and the phase change heat storage tank in the heat storage unit, the seventh valve and the eighth valve are opened, and the ninth valve and the tenth valve are closed at the same time, and the condensed working fluid liquid is stored in the saturated water tank to perform steam compression heat storage and waste heat compression heat storage; the first compressor group is driven by a connected first motor; the second compressor group is driven by a connected second motor; Heat storage release process: The heat storage unit starts the saturated water tank and the water pump, opens the tenth valve, the ninth valve, the seventh valve, the sixth valve and the fifth valve, and closes the eighth valve, the thirteenth valve and the first valve at the same time, releases the heat stored in the steam compression process and the heat stored in the waste heat compression process, and drives the back pressure machine to operate to achieve power generation and steam supply.

9. The plant-level coal-electricity hybrid thermal power production method according to claim 8, It is characterized in that The waste heat compression heating process is operated during the off-peak electricity price period and the peak steam demand period; the waste heat compression heat storage process is operated during the off-peak electricity price period and the off-peak steam demand period; the heat storage release process is operated during the peak, peak electricity price period and the peak steam demand period; the steam compression heat storage process is operated during the peak, peak electricity price period and the off-peak steam demand period.