Synchronous rotating speed section operation control method and device for wind generating set

By monitoring the asynchronous generator speed and converter junction temperature in real time, setting protection thresholds, and gradually adjusting the actual limiting power of the wind turbine generator set, the problems of converter power device damage and reduced power generation yield were solved, and the safe and efficient operation of the wind turbine generator set was achieved.

CN118934448APending Publication Date: 2024-11-12XEMC WINDPOWER CO LTD
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202411242087.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In existing doubly-fed wind turbine generator sets, the power devices of the converter are prone to damage when operating for a long time in the synchronous speed range, which leads to a decrease in the power generation yield of the generator set, and the existing methods to avoid this problem result in the waste of wind energy.

Method used

By monitoring the speed of the asynchronous generator and the junction temperature of the power devices in the converter in real time, a protection threshold is set. When the junction temperature exceeds the limit, the actual power limit is reduced. After the junction temperature returns to normal, the actual power limit is gradually restored. Combined with power dispatch dead zone control, the operation strategy of the wind turbine generator set is optimized.

Benefits of technology

It effectively avoids damage to the power devices of the converter, reduces power generation losses, and enables the wind turbine generator to operate smoothly in the synchronous speed range, balancing converter safety and power generation performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934448A_ABST
    Figure CN118934448A_ABST
Patent Text Reader

Abstract

The invention discloses a synchronous rotating speed section operation control method and device for a wind generating set, and relates to the field of wind power generation control, and the method comprises the steps: determining a synchronous rotating speed interval according to the synchronous rotating speed of an asynchronous generator in the wind generating set and a corresponding rotating speed tolerance percentage; when the wind generating set carries out wind power generation, the real-time rotating speed of an asynchronous generator in the wind generating set is obtained; when the real-time rotating speed is in the synchronous rotating speed interval, detecting the junction temperature of a power device of a converter in the wind generating set; when the junction temperature of the power device is higher than a first protection threshold value, the actual limiting power of the current wind generating set is stored as initial limiting power; lowering the actual limiting power to the junction temperature protection power so as to reduce the junction temperature of the power device; and when the junction temperature of the power device is lower than the second protection threshold value, the actual limiting power of the wind generating set is called back to the initial limiting power. By implementing the method, the power generation loss of the unit can be reduced while the power device of the converter is prevented from being damaged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of wind power generation control, and in particular to a method and device for controlling synchronous speed segment operation of a wind power generator set. Background Art

[0002] Doubly-fed wind turbine generator (DFIG) is a type of speed-increasing wind turbine generator, and it accounts for a high proportion of wind turbine generators in service. Along with the market cost pressure, a large number of electrical-related problems of doubly-fed wind turbine generators have also been exposed in recent years. Among them, due to the cost control of the converter, when the wind turbine generator set works in the synchronous speed range for a long time, the PWM switching frequency of the power device of the converter will become lower. When the switching frequency becomes lower, the junction temperature of this low-cost converter power device will increase significantly, and the long-term high junction temperature will cause the power device to be damaged, affecting the normal operation of the wind turbine generator set.

[0003] In the related art, in order to extend the service life of the converter power devices, the wind turbine generator set will be prevented from operating in the synchronous speed range for a long time as much as possible. The related art will suppress the speed of the wind turbine generator set to make it lower than the synchronous speed range, accumulate it for a period of time, and then release the speed to a high speed higher than the synchronous speed range, so as to directly make the speed of the wind turbine generator set cross the synchronous speed range, thereby ensuring that the wind turbine generator set will not operate in the synchronous speed range.

[0004] However, due to the process of suppressing the rotation speed, the related technology will result in some waste of wind energy, leading to a decrease in the power generation yield of the wind turbine. Summary of the invention

[0005] The present application provides a synchronous speed section operation control method and device for a wind turbine generator set, which are used to reduce the power generation loss of the set while avoiding damage to the power devices of the converter.

[0006] In a first aspect, the present application provides a method for controlling the operation of a wind turbine generator set in a synchronous speed segment, which is applied to a generator control device, and the method includes: determining a synchronous speed interval based on the synchronous speed of an asynchronous generator in the wind turbine generator set and a corresponding speed tolerance percentage; when the wind turbine generator set is generating wind energy, obtaining the real-time speed of the asynchronous generator in the wind turbine generator set; when the real-time speed is in the synchronous speed interval, detecting the junction temperature of a power device of a converter in the wind turbine generator set; when the junction temperature of the power device is higher than a first protection threshold, storing the actual limited power of the current wind turbine generator set as the initial limited power; the actual limited power is the maximum output power set for the wind turbine generator set during the current operation, and the default value of the actual limited power is the rated power of the unit; lowering the actual limited power to the junction temperature protection power to reduce the junction temperature of the power device; when the junction temperature of the power device is lower than a second protection threshold, calling back the actual limited power of the wind turbine generator set to the initial limited power.

[0007] In the above embodiment, the generator control device determines whether the wind turbine generator set is in the synchronous speed range according to the real-time speed. When in this range, the junction temperature of the converter power device is monitored in real time. When the junction temperature exceeds the first protection threshold, the actual limit power is actively lowered to the junction temperature protection power to reduce the junction temperature of the power device. This method avoids the situation where the power device is damaged due to long-term high-temperature operation. At the same time, by storing the actual limit power of the current wind turbine generator set as the initial limit power, when the junction temperature is lower than the second protection threshold, the actual limit power is called back to the initial limit power, thereby minimizing the power generation loss of the wind turbine generator set.

[0008] In combination with some embodiments of the first aspect, in some embodiments, when the junction temperature of the power device is lower than the second protection threshold, the actual limit power of the wind turbine generator set is adjusted back to the initial limit power, specifically including: when the junction temperature of the power device is lower than the second protection threshold, obtaining the power difference between the junction temperature protection power and the initial limit power; dividing the power difference into multiple ordered power callback segments according to a preset power step; adding a power callback segment to the actual limit power according to the arrangement order of the multiple ordered power callback segments; if the junction temperature increase of the power device junction temperature is not higher than the preset abnormal threshold within the preset test time, adding the next power callback segment to the actual limit power until the actual limit power reaches the initial limit power.

[0009] In the above embodiment, when the junction temperature of the power device is lower than the second protection threshold, the generator control device first calculates the power difference between the junction temperature protection power and the initial limit power, and then divides the difference into multiple ordered power callback segments according to the preset power step. Then, according to the arrangement order of the power callback segments, the actual limit power is gradually increased, and the junction temperature increment is monitored within the preset test time after each increase to see whether it exceeds the abnormal threshold. If not, the next segment is continued to be increased until it is called back to the initial limit power. This progressive power callback method can avoid a sudden increase in power that causes a sudden rise in junction temperature, and can more smoothly and safely call back the power to the initial level, thereby minimizing power generation losses while ensuring the safety of power devices.

[0010] In combination with some embodiments of the first aspect, in some embodiments, after the step of adding a power callback segment to the actual power limit according to the arrangement order of multiple ordered power callback segments, the method also includes: if the junction temperature increase of the power device junction temperature is higher than the preset abnormal threshold within the preset test time, the actual power limit is reduced by one power callback segment until the actual power limit reaches the junction temperature protection power.

[0011] In the above embodiment, when the generator control device is gradually calling back the actual limited power, if it is detected that the junction temperature increment exceeds the abnormal threshold, the previous power callback segment is actively reduced until it falls back to the junction temperature protection power. This method is equivalent to setting a junction temperature abnormality detection mechanism during the callback process. Once it is found that the junction temperature rises too fast, the power is reduced in time to avoid the power device from entering the high temperature danger zone again due to blind callback. Through this mechanism, the safety of the power device is further improved, and the power callback process is also made more robust and controllable.

[0012] In combination with some embodiments of the first aspect, in some embodiments, after the step of determining the synchronous speed range based on the synchronous speed of the asynchronous generator in the wind turbine generator set and the corresponding speed tolerance percentage, the method also includes: determining the power scheduling dead zone corresponding to the wind turbine generator set based on the synchronous speed range; obtaining the scheduling limit power issued by the power grid, and determining the operating limit power based on the scheduling limit power and the power scheduling dead zone; using the operating limit power as the actual limit power, and controlling the wind turbine generator set to generate wind energy.

[0013] In the above embodiment, after determining the synchronous speed interval, the generator control device also determines the power scheduling dead zone corresponding to the wind turbine generator set according to the interval. When the power grid issues a scheduling limit power, if the power is within the scheduling dead zone, the lower limit of the power dead zone is used as the actual operation limit power. By using the scheduling dead zone, the speed can be controlled to deviate from the synchronous interval to a certain extent, the number of adjustments can be reduced, and the wind turbine generator set can be operated as smoothly as possible, which is beneficial to the safety and power generation efficiency of the unit.

[0014] In combination with some embodiments of the first aspect, in some embodiments, the power scheduling dead zone corresponding to the wind turbine generator set is determined according to the synchronous speed range, specifically including: determining the output power of the wind turbine generator set at the synchronous speed as the center of the power dead zone; determining the upper limit and the lower limit of the power dead zone according to the power tolerance percentage and the power dead zone center, and obtaining the power scheduling dead zone; the power tolerance percentage is lower than the speed tolerance percentage.

[0015] In the above embodiment, the generator control device directly uses the output power of the wind turbine generator set at the synchronous speed as the center of the power dead zone, and then determines the upper and lower limits according to the given power tolerance percentage. The power tolerance percentage here is set lower than the speed tolerance percentage. The power is more sensitive to the change of speed, and the power control dead zone is further compressed, in order to use the wind farm level energy management while meeting the power limit of the power grid, and improve the friendliness of the power grid.

[0016] In combination with some embodiments of the first aspect, in some embodiments, the dispatching limit power issued by the power grid is obtained, and the operating limit power is determined based on the dispatching limit power and the power scheduling dead zone, specifically including: obtaining the dispatching limit power issued by the power grid, and determining whether the dispatching limit power is within the power scheduling dead zone; if the dispatching limit power is not within the power scheduling dead zone, the dispatching limit power is used as the operating limit power; if the dispatching limit power is within the power scheduling dead zone, the lower limit of the power dead zone is used as the operating limit power.

[0017] In the above embodiment, when the dispatch power is within the power dispatch dead zone, the generator control device directly uses the lower limit of the power dead zone as the operating limit power instead of the dispatch value. This approach makes full use of the margin of the dead zone and minimizes the number of power adjustments in the synchronous speed section. On the other hand, when the dispatch power is lower than the lower limit of the dead zone, the dispatch value is directly used as the operating power. While maintaining stable operation as much as possible in the synchronous speed section, the needs of power grid dispatch are also taken into account.

[0018] In combination with some embodiments of the first aspect, in some embodiments, after the step of adjusting the actual limited power of the wind turbine generator set to the initial limited power when the junction temperature of the power device is lower than the second protection threshold, the method also includes: recording the time when the actual limited power is adjusted back to the initial limited power, which is the first time; obtaining the time when the junction temperature of the power device is higher than the first protection threshold again, which is the second time; when the time difference between the second time and the first time is lower than the preset time difference, adjusting the junction temperature protection power based on the preset protection rule.

[0019] In the above embodiment, after the actual power limit is successfully adjusted back to the initial power limit, the generator control device records the adjustment time and monitors the time when the subsequent junction temperature exceeds the first protection threshold again. If the interval between these two times is less than the preset time difference, the junction temperature rises too fast this time, and the current junction temperature protection power needs to be adjusted, usually by further reducing the protection power to match the current heat dissipation state of the wind turbine generator set.

[0020] In a second aspect, an embodiment of the present application provides a generator control device, which includes: one or more processors and a memory; the memory is coupled to the one or more processors, the memory is used to store computer program code, the computer program code includes computer instructions, and the one or more processors call the computer instructions to enable the generator control device to execute the method described in the first aspect and any possible implementation method of the first aspect.

[0021] In a third aspect, an embodiment of the present application provides a computer program product comprising instructions, which, when the computer program product is run on a generator control device, enables the generator control device to execute the method described in the first aspect and any possible implementation of the first aspect.

[0022] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, comprising instructions, which, when executed on a generator control device, cause the generator control device to execute the method described in the first aspect and any possible implementation of the first aspect.

[0023] It can be understood that the generator control device provided in the second aspect, the computer program product provided in the third aspect, and the computer storage medium provided in the fourth aspect are all used to execute the method provided in the embodiment of the present application. Therefore, the beneficial effects that can be achieved can refer to the beneficial effects in the corresponding method, which will not be repeated here.

[0024] One or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages: 1. Since a method based on junction temperature detection and power limiting control of converter power devices is adopted when the real-time speed of the asynchronous generator is in the synchronous speed range, the power limiting control can be timely reduced to protect the converter when the junction temperature exceeds the first protection threshold, and the power limiting control can be timely adjusted to avoid power generation loss when the junction temperature returns to below the second protection threshold, which effectively solves the problem in the prior art that either the converter junction temperature is ignored, resulting in damage to the converter, or the power generation efficiency is reduced due to limitation of the speed, thereby realizing the optimization control of synchronous speed section operation that takes into account both converter safety and power generation performance.

[0025] 2. Since the actual limited power is gradually adjusted back to the initial limited power in segments, and the junction temperature change is detected in real time during the adjustment process, whether to continue the adjustment or reduce the adjustment power again is determined according to whether the junction temperature is abnormal. Therefore, the limited power can be restored to the initial level required for operation in the synchronous speed range in the shortest time and in the smoothest way, while minimizing the power generation loss and preventing the junction temperature rebound. This effectively solves the problem in the prior art that the single-step adjustment is prone to cause junction temperature fluctuations, and the slow linear adjustment is prone to prolong the power generation loss time, thereby achieving unified optimization of the efficiency and safety of the adjustment process.

[0026] 3. Since the method of adaptively adjusting the junction temperature protection power of the converter according to the actual operating conditions of the wind turbine set, that is, recording the triggering time interval of the junction temperature protection, is adopted, the rationality of the current protection power can be objectively evaluated, which can avoid converter damage caused by insufficient protection and reduce power generation efficiency caused by excessive protection. It effectively solves the problem in the prior art that the junction temperature protection power depends on experience settings and it is difficult to take into account both converter safety and power generation performance, thereby realizing self-optimization control of converter junction temperature protection. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a flow chart of a synchronous speed section operation control method of a wind turbine generator set in an embodiment of the present application; Figure 2 is another flow chart of the synchronous speed section operation control method of the wind turbine generator set in the embodiment of the present application; Figure 3 It is a schematic diagram of the structure of a physical device of the generator control device in the embodiment of the present application. DETAILED DESCRIPTION

[0028] The terms used in the following embodiments of the present application are only for the purpose of describing specific embodiments, and are not intended to be used as limitations to the present application. As used in the specification of the present application, the singular expressions "one", "a kind of", "above", "the" and "this" are intended to also include plural expressions, unless there is a clear indication to the contrary in the context. It should also be understood that the term "and / or" used in the present application refers to any or all possible combinations comprising one or more of the listed items.

[0029] In the following, the terms "first" and "second" are used for descriptive purposes only and are not to be understood as suggesting or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features, and in the description of the embodiments of the present application, unless otherwise specified, "plurality" means two or more.

[0030] It should be noted that the generator control device described in this article, i.e. the control device, refers to the main controller PLC (Programmable Logic Controller) of the wind turbine generator set in practical applications. PLC is a digital computing and operating electronic system specially designed for use in industrial environments. It uses a type of programmable memory to store programs internally, execute user-oriented instructions such as logical operations, sequential control, timing, counting and arithmetic operations, and control various types of mechanical equipment or production processes through digital or analog input / output.

[0031] In the control system architecture of wind turbines, PLC is in a core dominant position. It is connected to the control units of various subsystems such as converters, variable pitch systems, and variable pitch systems through buses or communication cables, and is responsible for summarizing and coordinating the overall control strategy of wind turbines. PLC collects various signals such as wind speed, rotation speed, power, voltage, current, etc. from the subsystem control units, runs the pre-compiled control program, gives a series of control instructions, and then sends them to each subsystem for execution, thereby realizing the control of the entire process of wind turbine start and stop, grid connection, power limit, power control, fault protection, etc. Taking the converter as an example, it is usually equipped with an independent converter controller to perform specific functions such as PWM modulation (Pulse Width Modulation) and current loop control. The converter controller accepts the unified scheduling and power instructions of the PLC.

[0032] The PLC and the converter controller exchange data in real time through standard communication protocols such as industrial Ethernet and CAN bus. The PLC transmits the calculated key parameters such as the operating limit power and junction temperature protection power to the converter controller through the communication cable. The converter controller adjusts the PWM modulation ratio and the on-time of the switch tube accordingly, thereby changing the converter output voltage and active / reactive current, and finally accurately controls the output power of the converter to be consistent with the instructions of the PLC. At the same time, the converter controller will also report the state quantities such as the IGBT (Insulated Gate Bipolar Transistor) junction temperature and capacitor voltage to the PLC in a timely manner so that the PLC can optimize the control scheme.

[0033] In the application scenario of this implementation, due to converter cost control, when the wind turbine generator set operates in the synchronous speed range for a long time, the PWM switching frequency of the converter's power devices (such as IGBT, etc.) will become lower. When the switching frequency becomes lower, the junction temperature of this low-cost converter power device will increase significantly. Long-term high junction temperature will cause damage to the power device and affect the normal operation of the wind turbine generator set.

[0034] In the related art, in order to extend the service life of the converter power devices, the wind turbine generator set will be prevented from operating in the synchronous speed range for a long time as much as possible. The related art will suppress the speed of the wind turbine generator set, making the speed lower than the synchronous speed range, and then release the speed to a high speed higher than the synchronous speed range after a period of accumulation, so as to directly make the speed of the wind turbine generator set cross the synchronous speed range, thereby ensuring that the wind turbine generator set will not operate in the synchronous speed range. However, due to the process of suppressing the speed in the related art, some wind energy will be wasted, resulting in a decrease in the power generation yield of the wind turbine generator set.

[0035] By adopting the synchronous speed section operation control method of the wind turbine generator set in the embodiment of the present application, when the wind turbine generator set is generating electricity, it can be determined whether it is in the synchronous speed range according to the real-time speed of the asynchronous generator. When it is in the synchronous speed range, the junction temperature of the converter power device is monitored in real time. When the junction temperature is too high, the actual limit power is lowered to reduce the junction temperature and avoid damage to the power device. At the same time, the actual limit power is promptly adjusted back after the junction temperature returns to normal to reduce the loss of power generation.

[0036] See also Figure 1 , which is a flow chart of a method for controlling operation of a wind turbine generator set in the synchronous speed section in an embodiment of the present application.

[0037] S101. Determine a synchronous speed range according to a synchronous speed of an asynchronous generator in a wind turbine generator set and a corresponding speed tolerance percentage.

[0038] The synchronous speed n s It refers to the speed value when the rotor speed of the asynchronous generator is synchronized with the grid frequency, which is usually determined by the number of pole pairs of the asynchronous generator and the grid frequency, that is, Where f is the frequency of the grid current and P is the number of magnetic pole pairs. Speed ​​tolerance percentage n tolp Indicates the actual operating speed of the asynchronous generator relative to the synchronous speed n s The value deviation range is used to indicate the width of the synchronous speed range. The synchronous speed range refers to the speed range of the asynchronous generator within a certain range near the synchronous speed. c When it is in this interval, that is, n s *(1-n tolp ) <n c <n s *(1+n tolp ), the wind turbine is considered to be in quasi-synchronous operation. For example, if the synchronous speed n s is 1500rpm, speed tolerance percentage n tolp If the synchronous speed is 5%, the synchronous speed range is 1425rpm to 1575rpm.

[0039] Specifically, the control device first obtains the rated synchronous speed of the asynchronous generator of the wind turbine, which is determined by the design parameters of the asynchronous generator and can be found in the equipment initialization data such as factory data. Then, the control device sets the speed tolerance percentage according to the actual application requirements. The percentage is usually determined based on the unit operation experience and efficiency optimization requirements. Finally, the control device sets the synchronous speed n s Centered on the rotation speed tolerance percentage n tolp , calculate the upper and lower limits of the synchronous speed range, that is, the upper limit value n s-up =n s *(1+n tolp ), lower limit value n s-low =n s *(1-n tolp ). In the subsequent steps, this interval will be used as the basis for judging whether the wind turbine is in a quasi-synchronous operation state, corresponding to different control strategies.

[0040] In some embodiments, the synchronous speed range can be determined in a variety of ways: Optionally, the control device can directly call the factory parameters of the asynchronous generator to obtain its synchronous speed n s The operator then manually inputs the speed tolerance percentage based on experience, and the control device substitutes it into the formula to calculate the synchronous speed range; optionally, the control device can also access the equipment management system of the wind farm to automatically obtain the synchronous speed n of each wind turbine s and speed tolerance percentage parameter n tolp , directly loaded into the control logic. It is understandable that other methods can also be used to achieve the setting of the synchronous speed range, such as analyzing the historical operation data of the wind turbine through big data, autonomously optimizing the synchronous speed range parameters, etc., which are not limited here.

[0041] S102: When the wind turbine generator set generates wind energy, obtain the real-time rotation speed of the asynchronous generator in the wind turbine generator set.

[0042] Wind power generation refers to the process of wind turbines converting wind energy into electrical energy and transmitting it to the grid when they are connected to the grid. Real-time speed refers to the actual speed of the asynchronous generator rotor, which is usually measured in real time by speed sensors such as encoders and is used to indicate the current operating status of the wind turbine.

[0043] Specifically, the control device constantly monitors the grid-connected status of the wind turbine to determine whether it is in a normal power generation process. When the wind turbine is connected to the grid for power generation, the control device will obtain the speed feedback value of the asynchronous generator rotor in real time as the real-time operating speed n of the unit. cThe speed signal is usually collected in real time by encoders, speed sensors and other equipment and transmitted to the control device. The data sampling frequency can be set according to actual needs, usually 10 times per second or higher. The real-time speed n c , which can be used as the basic basis for judging whether the wind turbine has entered the synchronous speed range in the subsequent steps.

[0044] S103: When the real-time rotation speed is in the synchronous rotation speed range, detecting the junction temperature of the power devices of the converter in the wind turbine generator set.

[0045] Among them, the power device junction temperature T j Refers to the actual operating temperature of power devices such as IGBT in the converter, which is usually measured in real time by the temperature sensor built into the converter. It is used to indicate the heating status and health level of the converter, and generally takes the maximum temperature value among all components. The temperature sensor is generally closely attached to the power device and can accurately reflect its junction temperature changes.

[0046] Specifically, the control device compares the asynchronous generator speed n in real time. c With synchronous speed range (n s-low , n s-up ), determine whether the current speed is within this range (n s-low , n s-up Once the wind turbine enters the synchronous speed range, the control device will immediately trigger the temperature detection of the converter power device. The built-in temperature sensor of the converter will collect the actual operating temperature of power devices such as IGBT in real time and transmit the junction temperature data T j The junction temperature information obtained by the control device will be used as the basis for judging whether to start the converter temperature rise protection in the subsequent control steps. The temperature detection process runs through the entire process of quasi-synchronous operation of the wind turbine set, so as to timely discover and deal with the converter temperature rise risk.

[0047] In some embodiments, the detection of the junction temperature of the power device of the converter can be achieved in a variety of ways: optionally, the control device can directly access the temperature sensor of the converter and read the junction temperature data in real time through the communication protocol; optionally, the control device can also establish a data link with the converter's own protection unit to periodically obtain the junction temperature information uploaded by the converter. It is understandable that other methods can also be used to detect the temperature of the power device of the converter, such as installing an infrared thermometer outside the converter to remotely monitor the surface temperature of the power device, etc., which is not limited here.

[0048] S104: When the junction temperature of the power device is higher than the first protection threshold, the actual power limit of the current wind turbine generator set is stored as the initial power limit.

[0049] Among them, the first protection threshold T j-upIt refers to the temperature threshold that triggers the temperature rise protection of the converter power device. It is usually determined based on factors such as device material properties and design margin. It is used to indicate the temperature critical point at which the converter begins to have the risk of temperature rise and protective measures need to be taken. lim1 Refers to the actual limit power P of the wind turbine when the converter temperature rise protection is started. c , reflecting the maximum output capacity of the unit before protection.

[0050] Specifically, the control device continuously monitors the junction temperature T of the power device of the converter. j and the preset first protection threshold T j-up When the junction temperature T j Exceeding the first protection threshold T j-up , it indicates that the converter has a risk of temperature rise and protection control is urgently needed. At this time, the control device will immediately record the actual power limit of the current wind turbine and store it as the initial power limit. The initial power limit data will be used as the power basis for restoring the normal operation of the wind turbine in the subsequent control steps. It should be noted that the actual power limit can be obtained in a variety of ways, such as directly collecting the current active power set value of the wind turbine, or reading the corresponding parameters from the control system database.

[0051] In some embodiments, the initial power limit of the wind turbine can be stored in a variety of ways: Optionally, the control device can create an initial power limit table in a local database, and each time the temperature rise protection is triggered, the current actual power limit value is written into the table and marked with a corresponding timestamp; Optionally, the control device can also use a cloud server to upload the initial power limit to a remote data center for unified storage and management. It is understandable that other methods can also be used to store the initial power limit, such as writing data into a non-volatile memory such as the EEPROM and Flash of the controller, which is not limited here.

[0052] S105. Lower the actual power limit to the junction temperature protection power to reduce the junction temperature of the power device.

[0053] Among them, the junction temperature protection power P j-safe Refers to the maximum allowable output power of the wind turbine set to suppress the temperature rise of the converter. It is usually lower than the rated power of the unit and is determined based on factors such as the heat dissipation conditions and temperature rise characteristics of the converter. It is used to indicate the power upper limit of the wind turbine set in the protection state. c That is, by reducing the maximum output power of the wind turbine, the heat generated by the converter is reduced, thus achieving the purpose of suppressing temperature rise.

[0054] Specifically, when the junction temperature of the converter power device T j Exceeding the first protection threshold T j-upAfter that, the control device will immediately perform power limit protection. The control device first retrieves the preset junction temperature protection power value P from the protection strategy library. j-safe , and then send this value to the control system of the wind turbine as the new actual limit power P lim2 The wind turbine generator system is based on the updated actual limit power P j-safe (P lim2 ), and reduce its output power accordingly. Usually, the active power setting value of the converter is limited to the junction temperature protection power P j-safe (P lim2 ) or less. As the output power of the wind turbine decreases, the heat generated by the converter power devices also decreases, and the junction temperature T j It will gradually fall back to a safe range until the temperature rise protection is released.

[0055] S106: When the junction temperature of the power device is lower than the second protection threshold, adjust the actual limit power of the wind turbine generator set back to the initial limit power.

[0056] Among them, the second protection threshold T j-low Refers to the temperature threshold for releasing the temperature rise protection of the converter power device. The second protection threshold T j-low Below the first protection threshold T j-up , which is determined based on factors such as device temperature characteristics and operating margin, and is used to indicate the critical temperature point at which the converter temperature rise risk has been eliminated and normal operation can be restored. Calling back the actual power limit means canceling the power limit protection and restoring the maximum output power of the wind turbine to the level before protection, so that it can resume normal power generation capacity.

[0057] Specifically, after the converter enters the power limit protection, the control device will continuously monitor the junction temperature T j changes and the second protection threshold T j-low When the junction temperature T j Drop to the second protection threshold T j-low When the inverter temperature rise risk is below 0.004, it indicates that the inverter temperature rise risk has been eliminated and the wind turbine can resume normal operation. At this time, the control device will terminate the power limit protection and read the initial power limit P of the wind turbine from the storage location. lim1 , and resend the value to the wind turbine to replace the junction temperature protection power P j-safe (P lim2 ), so that the actual limit power P of the wind turbine c Pullback to the protection level before P lim1 .

[0058] In some embodiments, the actual limit power of the wind turbine can be adjusted back in a variety of ways: Optionally, the control device can adjust the initial limit power P lim1 The junction temperature protection power P j-safe (Plim2 ) is sent to the wind turbine as a power increase instruction, so that it gradually increases the output power to the initial level; optionally, the control device can also j Drop to the second protection threshold T j-low After that, directly modify the power limit parameter in the wind turbine control system back to the initial power limit P lim1 It is understandable that other methods can also be used to release the power limit protection, such as increasing the power limit in stages according to the real-time operating conditions of the wind turbine generator set until it returns to the initial level, etc., which is not limited here.

[0059] In the above embodiments, the embodiments of the present application provide a method for controlling the synchronous speed section operation of a wind turbine generator set. The method first determines the synchronous speed interval, and monitors in real time whether the speed of the asynchronous generator is in the interval during the power generation process of the wind turbine generator set; when it is in the interval, the junction temperature T of the converter power device is further adjusted. j Monitor and protect against junction temperature T j Too high will cause damage to the power device. At the same time, the junction temperature T j After returning to normal, the actual power limit will be adjusted back in time to reduce power generation losses; when the speed of the asynchronous generator is not in the synchronous speed range, the operation of the wind turbine can be controlled according to the normal power dispatch strategy.

[0060] In the actual implementation process, power callback may involve many factors. If the callback method is not appropriate, the junction temperature warning may be triggered again soon, resulting in low generator efficiency. Especially when the wind turbine generator set is restricted to a certain power range due to grid instructions, how to reasonably control the power becomes a major problem. The following is a further and more specific description of the process of the method provided by this implementation. Please refer to Figure 2 , is another flow chart of the synchronous speed section operation control method of a wind turbine generator set in an embodiment of the present application.

[0061] S201. Determine a synchronous speed range according to the synchronous speed of the asynchronous generator in the wind turbine generator set and the corresponding speed tolerance percentage.

[0062] Referring to step S101 , the generator control device determines a synchronous speed range.

[0063] S202: Determine a power dispatch dead zone corresponding to the wind turbine generator set according to the synchronous speed range.

[0064] Among them, the power scheduling dead zone refers to the power regulation prohibited interval set when the wind turbine is in quasi-synchronous operation to avoid the power devices of the converter from burning out due to temperature rise, which usually corresponds to the synchronous speed interval; when the output power is above this interval, the speed of the generator will be in the super-synchronous working area and can work normally; when the output power is below this interval, due to the small power, the temperature rise of the power devices of the converter is not obvious, or is within the tolerable range.

[0065] Specifically, after determining the synchronous speed range of the wind turbine, the control device will calculate the power dispatch dead zone. Through the pre-established mapping relationship between the synchronous speed range and the power dispatch dead zone, the control device can quickly match the power dispatch dead zone range corresponding to the current wind turbine. This mapping relationship is usually constructed based on the rated parameters of the wind turbine, and a table lookup method is used to achieve fast matching.

[0066] In some embodiments, the generator control device determines the output power of the wind turbine generator set at the synchronous speed as the power dead zone center; according to the power tolerance percentage P dp and power dead zone center P s , determine the upper limit of the power dead zone P up And the power dead zone lower bound P low , the power scheduling dead zone is obtained; the power tolerance percentage is lower than the speed tolerance percentage, that is, P dp <n tolp .

[0067] Among them, synchronous speed refers to the rotor speed of the wind turbine when the wind turbine is connected to the grid, which is usually determined by the grid frequency and the number of generator poles, and is used to indicate the nominal operating speed of the wind turbine when connected to the grid. The power dead zone center refers to the output active power of the generator at the synchronous speed, indicating the set output power of the wind turbine at the standard synchronous speed. The power tolerance percentage refers to the maximum percentage by which the actual output power of the generator is allowed to deviate from the center of the power dead zone, which is used to determine the width of the power scheduling dead zone. The upper limit of the power dead zone and the lower limit of the power dead zone respectively represent the upper limit and lower limit of the power scheduling dead zone, which are used to define the effective range of the scheduling limit power issued by the power grid. For example, if the power dead zone center P s For 1000kW, the power tolerance percentage P dp If the power dead zone upper limit P is 3%, up is 1030kW, the lower limit of the power dead zone is P low It is 970kW, and the area between the two is the power scheduling dead zone.

[0068] Specifically, the generator control device will determine the output power of the generator at the synchronous speed and record it as the center of the power dead zone. At the same time, the control device reads the preset power tolerance percentage parameter from the local configuration file, and obtains two power values ​​based on the power dead zone center and the upper and lower offset tolerance percentages through multiplication and addition and subtraction calculations, which are used as the upper and lower limits of the power dead zone respectively. The closed interval range defined by the upper and lower limits is the power scheduling dead zone determined autonomously by the generator control device. This dead zone represents the acceptable scheduling power fluctuation range of the wind turbine under nominal conditions. It is worth noting that since the wind turbine adopts power scheduling dead zone control, the power dead zone interval tolerance percentage is less than the synchronous speed interval tolerance percentage of the converter, which can minimize the power scheduling dead zone range and is conducive to compatibility with the upper energy management platform.

[0069] In some embodiments, the power dispatch dead zone can be determined in a variety of ways: Optionally, the generator control device can adopt a fixed value setting method, directly burn fixed power dead zone center and tolerance percentage parameters before leaving the factory, and directly call these parameters to calculate the upper and lower limits of the dead zone during grid-connected operation; Optionally, the generator control device can also adopt a self-learning method, during the grid-connected debugging stage, record the output power under multiple synchronous speed conditions, obtain the power dead zone center through statistics, and then automatically match the appropriate tolerance percentage to finally obtain the upper and lower limits of the dead zone. It is understandable that other methods can also be used to determine the power dispatch dead zone, such as the online optimization method, that is, by establishing a power-speed static model of the wind turbine, solving the optimal dead zone parameters under the current working conditions, which is not limited here.

[0070] S203: Obtain the dispatching limit power issued by the power grid, and determine the operating limit power based on the dispatching limit power and the power dispatching dead zone.

[0071] Among them, the scheduling limit power P g-lim It refers to the maximum allowable output power instruction issued by the grid dispatching agency to the wind turbine, which is usually determined based on factors such as the real-time load level of the grid and the new energy absorption capacity, and is used to indicate the upper limit of the active power transmitted by the wind turbine to the grid. lim It refers to the maximum output power that a wind turbine can actually execute after taking into account the power scheduling dead zone constraints. It is a comprehensive analysis result of the scheduling limit power and the unit's own operating status. It is used to indicate the real-time output power upper limit of the wind turbine.

[0072] Specifically, the control device periodically obtains the dispatching limit power value P issued by the power grid dispatching organization through the communication interface. g-lim , as the upper limit of wind turbine power. At the same time, the control device detects the power dispatch dead zone (P low , P up), to determine whether it is in the power limit adjustment state. If the unit is currently operating with a power limit of P g-lim Not falling into the scheduling dead zone (P low , P up ), then the dispatch limit power P g-lim As the operating limit power P lim ; If the unit's current operating power limit P g-lim Located in the scheduling dead zone (P low , P up ), in order to avoid converter damage, the limit power P is reduced. lim To the lower limit of power dead zone P low .

[0073] In some embodiments, the operation limit power of the wind turbine can be determined in a variety of ways: Optionally, the control device can determine whether the scheduling limit power falls into the power scheduling dead zone through simple logical comparison. If so, the scheduling limit power is selected as the operation limit power, otherwise the current power is locked; Optionally, the control device can also use a dynamic optimization algorithm to search for the best operation limit power online with power generation efficiency and frequency regulation performance as the objective function. It is understandable that other methods can also be used to generate the operation limit power, such as pre-offline calculation of the optimal limit power under various working conditions, online direct table lookup, etc., which are not limited here.

[0074] In some embodiments, the generator control device obtains the dispatching limit power issued by the power grid and determines whether the dispatching limit power is within the power dispatching dead zone; if the dispatching limit power is not within the power dispatching dead zone, the dispatching limit power is used as the operating limit power; if the dispatching limit power is within the power dispatching dead zone, the lower limit of the power dead zone is used as the operating limit power.

[0075] Among them, the scheduling limit power P g-lim It refers to the maximum allowable output power instruction issued by the grid dispatching agency to the wind turbine generator set, which is usually determined based on factors such as the real-time load balance of the grid and the new energy absorption capacity, and is used to control the active power output of the wind turbine generator set to the grid. lim It refers to the final power limit setting value used when the generator actually performs power control. It takes into account both the dispatching power limit issued by the power grid and the safe and stable operation requirements of the wind turbine itself. It is used to guide the control system to adjust the stable output power of the wind rotor power, generator excitation, etc.

[0076] Specifically, the control instructions and status information are transmitted in real time between the generator control device and the grid dispatching main station through the communication line. When the grid issues a new dispatching limit power, the generator control device immediately obtains the value and compares it with the autonomously determined power dispatching dead zone. If the dispatching limit power is higher than the upper limit of the dead zone or lower than the lower limit of the dead zone, it indicates that the generator is outside the output power of the synchronous speed, that is, it is in the safe output power range. At this time, the control device will directly use the dispatching limit power as the new operating limit power and send it to the unit control system. The control system will readjust the wind rotor pitch angle, generator excitation current, etc. accordingly, so that the output power of the wind turbine unit can quickly track to the dispatching limit power to meet the grid dispatching requirements. On the contrary, if the dispatching limit power falls within the dead zone range, it indicates that the generator may be within the synchronous speed. At this time, the control device will select the lower limit of the dead zone as the new operating limit power to avoid the fault of excessive temperature rise of the converter caused by excessive power. After the control device sends the lower limit of the dead zone, the unit control system immediately starts the power limit control, and by adjusting the wind rotor and generator, the stable output power is not higher than the lower limit of the dead zone, ensuring the smooth operation of the unit.

[0077] In some embodiments, the operating limit power can be determined in a variety of ways: Optionally, the generator control device can adopt a static interval judgment method, that is, only compare the size relationship between the scheduling limit power and the upper and lower limits of the dead zone, and select the scheduling limit power or the lower limit of the dead zone as the final operating limit power; Optionally, the generator control device can also adopt a dynamic trend prediction method, that is, continuously track the changing trend of the scheduling limit power in multiple scheduling cycles. If it is predicted that the scheduling limit power will continue to exceed the dead zone in the future, it will be selected as the operating limit power, otherwise the lower limit value of the dead zone will still be used. It is understandable that other methods can also be used to determine the operating limit power, such as introducing a machine learning algorithm, analyzing historical operating data, and autonomously deciding how to balance the relationship between the scheduling limit power and the safety of the unit under different working conditions, which is not limited here.

[0078] S204: Control the wind turbine generator set to generate wind energy using the operating limit power as the actual limit power.

[0079] Among them, the actual limit power P c It refers to the upper limit of active power used by wind turbines in actual control execution, usually determined by the operating limit power P lim Determine, used to characterize the real-time maximum power generation capacity of the unit. Controlling wind turbines to generate wind energy requires the control system to adjust the wind turbine's pitch angle, generator excitation, converter reactive power and other operating parameters in real time according to the actual power limit, and control the unit's output power within the actual power limit, so as to achieve efficient conversion of wind energy into electrical energy and transmit it to the power grid.

[0080] Specifically, the control device will operate the limited power Plim Assign the active power upper limit setting value to the wind turbine control system as the current actual limit power P c . After the unit control system detects the change in the actual power limit, it immediately starts the corresponding tracking control strategy. By issuing real-time control instructions to the pitch system and converter, the control system continuously monitors the real-time output power of the wind turbine and compares it with the actual power limit. Once it is found that the real-time output power exceeds the power limit, the control system will respond quickly, adjust the pitch angle to reduce the wind rotor power, or adjust the converter operating parameters to limit the generator output power, to ensure that the unit always operates stably within the actual power limit. At the same time, the control system feeds back the measured power data of the wind turbine to the control device in real time for subsequent control processes and status monitoring.

[0081] S205. When the wind turbine generator set generates wind energy, obtain the real-time rotation speed of the asynchronous generator in the wind turbine generator set.

[0082] Referring to step S102, the generator control device monitors the real-time speed n of the wind turbine generator. c .

[0083] S206: When the real-time rotation speed is in the synchronous rotation speed range, detecting the junction temperature of the power device of the converter in the wind turbine generator set.

[0084] Referring to step S103, the generator control device monitors the junction temperature T j .

[0085] S207: When the junction temperature of the power device is higher than the first protection threshold, store the actual limited power of the current wind turbine generator set as the initial limited power.

[0086] Referring to step S104, the generator control device will j Higher than the first protection threshold T j-up When the initial limit power P is stored lim1 .

[0087] S208. Lower the actual power limit to the junction temperature protection power to reduce the junction temperature of the power device.

[0088] Referring to step S105, the generator control device will lower the actual limit power P lim .

[0089] S209: When the junction temperature of the power device is lower than the second protection threshold, obtain the junction temperature protection power P j-safe The power difference between the initial limit power and the

[0090] Among them, the power difference ΔP represents the junction temperature protection power P j-safe (P lim2) and the initial limiting power P lim1 The difference reflects the reduced power generation capacity of the wind turbine during the converter temperature rise protection period.

[0091] Specifically, when the wind turbine performs the junction temperature protection power P j-safe (P lim2 ) is running, the control device continuously monitors the junction temperature changes of the converter power devices. j Drop to the second protection threshold T j-low When the temperature rise risk of the converter is below 0.04, it indicates that the converter temperature rise risk has been basically eliminated and the wind turbine can gradually resume normal operation power. The control device sets the current junction temperature protection power P j-safe (P lim2 ) and the previously stored initial limit power P lim1 Subtract the power difference during the protection period to obtain the power difference. The power difference data will be used in the subsequent control steps to generate callback instructions to gradually restore the power generation capacity of the wind turbine. At the same time, the control device also calculates the junction temperature T j The status information restored to a safe level is fed back to the wind farm monitoring system so that the operation and maintenance personnel can understand the latest operating status of the unit.

[0092] S210: Divide the power difference into a plurality of ordered power callback segments according to a preset power step.

[0093] Where, the power step length ΔP i It refers to the power amplitude increased each time in the process of gradually restoring the power generation capacity of the wind turbine. It is usually set according to factors such as the regulation capacity of the unit and the grid connection requirements. It is used to control the rate and granularity of the wind turbine to gradually release power. i It means dividing the power difference into several continuous power intervals, each interval corresponds to a power callback operation, which is used to represent the execution steps of gradually restoring the power generation capacity of the wind turbine.

[0094] Specifically, after the control device obtains the power difference caused by the junction temperature protection, it immediately starts the calculation of the power callback segment. According to the preset power step, the control device divides the power difference into several equal or regular power intervals, and the width of each interval is the size of the power step.

[0095] For example, if the power difference ΔP is 100kW, the power step ΔP i If it is 0.2, it can be divided into 5 orderly power callback segments P i , is 20kW. The order of segmentation is based on the junction temperature protection power P j-safe (P lim2 ) and increase the power step by 20kW each time until the initial limit power P is reached. lim1For example, a regular power interval can be set. If the power difference ΔP is 100kW, the preset power step ΔP i If 0.2, 0.6, and 0.2 are used, 100 kW can be divided into three orderly power callback segments P i , that is, 20kW, 60kW and 20kW. According to this rule, after detecting that the 20kW callback is effective, 60kW can be directly called back to ensure the efficiency of the callback. This regular division of the preset power step can be set and adjusted by the staff or background developers; in some embodiments, the preset power step can also be set to 0.6, 0.2, 0.2 or 0.2, 0.2, 0.6, etc.

[0096] S211. According to the arrangement order of the plurality of ordered power callback segments, a power callback segment is added for the actual limited power.

[0097] Among them, the actual limit power P lim During the junction temperature protection, the power has been reduced to the junction temperature protection power P j-safe (P lim2 ). Add a power callback segment P in sequence i , which means the protection power P from the junction temperature j-safe (P lim2 ), and gradually increase the actual limit power P each time according to the order of power callback segments. lim , until it finally returns to the initial limit power P lim1 .

[0098] Specifically, after generating the ordered power callback segments, the control device immediately starts the control process of gradually restoring the power generation capacity of the wind turbine. First, the control device reads the first segment value of the power callback segment sequence and compares it with the current actual limit power (i.e., the junction temperature protection power P j-safe (P lim2 )) are added to obtain a new actual power limit value. The control device sends the new actual power limit to the wind turbine control system and synchronously updates the actual power limit parameters recorded locally. After receiving the new power limit setting value, the unit control system starts the power limit control strategy, gradually increases the wind rotor power input or increases the generator excitation, so that the power output upper limit of the wind turbine can rise steadily and finally stabilize at the actual power limit value after adding a new callback segment.

[0099] In some embodiments, the segmented callback of the actual power limit can be realized in a variety of ways: Optionally, the control device can use a timed triggering method to add a callback segment to the actual power limit every fixed time period until the initial power limit P is reached. lim1 .

[0100] S212: If the junction temperature increment of the power device is not higher than the preset abnormal threshold value within the preset test time, the next power callback segment is added to the actual limit power until the actual limit power reaches the initial limit power.

[0101] The preset test time refers to the time after each increase in the actual limit power to evaluate the junction temperature T of the converter power device. j The observation time set according to the change is usually determined based on the dynamic characteristics of the converter cooling system and is used to determine whether the current callback segment will cause the junction temperature T j The preset abnormal threshold refers to the temperature change amplitude value that triggers the abnormal junction temperature, which is usually based on the second protection threshold T j-low The junction temperature increment refers to the maximum increment of the temperature of the power device of the converter within the preset test time.

[0102] Specifically, each time a callback segment P is added i After the actual power is limited, the control device immediately starts the junction temperature impact assessment. During the preset test time, the control device continuously collects the junction temperature data of the converter power device and calculates the junction temperature T during the test. j The maximum increase value is compared with the preset abnormal threshold. If the junction temperature increase is not higher than the abnormal threshold, it indicates that the current actual power limit level has not yet posed a challenge to the converter heat dissipation, and the wind turbine output can continue to be increased. The control device will read the next segment value of the power callback segment sequence, repeat the control action of S211, and increase the actual power limit again. According to the above rules, the control device will continuously increase multiple callback segments to achieve a step-by-step increase in the actual power limit until it returns to the initial power limit P lim1 level.

[0103] In some embodiments, the influence of junction temperature on the power callback process can be monitored in a variety of ways: Optionally, the control device can determine whether the junction temperature increment exceeds the abnormal threshold through simple threshold comparison, and decide whether to continue to increase the actual power limit accordingly; Optionally, the control device can also deploy a junction temperature prediction model to estimate the junction temperature T in real time after adding callback segments. j future changing trends and take control measures in advance.

[0104] In some embodiments, the generator control device records the actual limit power and returns it to the initial limit power P lim1 The time is the first time t1; obtain the junction temperature T of the power device j Again higher than the first protection threshold T j-upThe time is the second time t2; when the time difference Δt between the second time t2 and the first time t1 is lower than the preset time difference Δt0, the junction temperature protection power P is adjusted based on the preset protection rule. j-safe .

[0105] The first time t1 indicates that the actual power limit of the wind turbine generator set is restored to the initial power limit P before protection for the first time after the converter junction temperature protection ends. lim1 The second time t2 refers to the time when the junction temperature of the power device of the converter exceeds the first protection threshold T again after the above recovery. j-up The moment when the unit enters the converter temperature rise risk state again. The preset time difference Δt0 refers to the time when the junction temperature protection power P is triggered to adjust. j-safe The minimum interval between the two key time points is usually determined based on the thermal characteristic time constant of the converter cooling system. When the interval between the second time t2 and the first time t1 is less than the preset threshold, it means that the wind turbine has just resumed normal operation power and the converter junction temperature T j It enters the high-risk area again, and the original junction temperature protection power P j-safe The parameter may be too high and needs to be further reduced to suppress the junction temperature rebound. The preset protection rule means that at the junction temperature T j When the temperature exceeds the limit repeatedly, adjust the junction temperature protection power P j-safe A series of decision logics and control strategies, usually including reducing the amplitude coefficient of protection power, shortening the execution time of protection power, increasing the duration of protection power, etc., such as reducing the junction temperature protection power by 10kW, shortening the junction temperature protection response to within 5s, and increasing the junction temperature protection time by 10min, can be used to enhance the over-temperature protection effect of the converter.

[0106] Specifically, after successfully restoring the power level of the wind turbine generator set, the generator control device immediately records the current timestamp as the first time t1. This timestamp indicates that the unit has ended the junction temperature protection state and returned to the initial limit power P lim1 Normal operation under control. However, the control device will continue to monitor the junction temperature data of the converter power device. Once the junction temperature value T j Exceeds the first protection threshold T again j-up , immediately triggering a new junction temperature protection process, and recording the current timestamp as the second time t2. The control device subtracts the second time t2 from the first time t1 to obtain the actual time interval Δt between the two junction temperature exceeding events, and compares it with the preset time difference threshold Δt0. If the actual interval is less than the preset threshold, it indicates that the previously executed junction temperature protection power P j-safeThe solution is not effective enough to suppress the inverter junction temperature rebound for a long time. At this time, the control device will call the preset protection rule to protect the current junction temperature power P j-safe For example, the junction temperature protection power P j-safe The calculation coefficient of the protection power is further reduced from the original 90% to 80% to obtain a lower new protection power value; at the same time, the duration of the new protection power is extended from the original 5 minutes to 10 minutes to delay the process of restoring normal power. These adjusted new protection power plans are sent to the unit control system again to restart the power limit protection, further reduce the output level of the wind turbine and the heat generation power of the converter, in order to completely eliminate the junction temperature T j The hidden danger of repeatedly exceeding the standard.

[0107] In some embodiments, the junction temperature protection power P can be triggered in a variety of ways. j-safe Adjustment: Optionally, the generator control device can adopt a fixed interval triggering method, that is, after the junction temperature protection, if the junction temperature T is detected within a fixed time interval j If the temperature exceeds the standard again, the preset protection rule is activated to adjust the protection power, otherwise the original protection scheme is maintained unchanged; optionally, the generator control device can also adopt an adaptive interval triggering method, that is, according to the frequency and amplitude of the junction temperature exceeding the standard, the triggering interval between two junction temperature exceeding the standard is dynamically shortened, and the adjustment strategy of the protection power is optimized in real time. It is understandable that other methods can also be used to trigger the junction temperature protection power P j-safe For example, in combination with external environmental factors such as weather forecast, the junction temperature protection power P is actively lowered under special conditions such as high temperature or fixed wind speed. j-safe To prevent the risk of temperature rise, no limitation is given here.

[0108] S213. If the junction temperature increment of the power device is higher than the preset abnormal threshold within the preset test time, the actual limit power is reduced by a previous power callback segment until the actual limit power reaches the junction temperature protection power.

[0109] Among them, the junction temperature increment is higher than the abnormal threshold, indicating that the current actual power limit of the wind turbine has significantly increased the heat dissipation pressure of the converter power devices. j The temperature starts to rise rapidly, which may lead to a new round of temperature rise risk. It is necessary to take power reduction measures in time. Reducing the previous power callback segment means gradually reducing the actual limit power in the opposite order of increasing the callback segment, reducing one callback segment each time until it falls back to the junction temperature protection power P. j-safe level.

[0110] Specifically, when the control device detects that the junction temperature increase exceeds the abnormal threshold during the test period of a certain callback segment, the power callback process will be interrupted immediately. The control device will subtract the callback segment value added in the previous step from the latest actual limit power to obtain the reduced actual limit power. The new actual limit power is sent to the wind turbine control system and the local record of the control device is updated. The unit control system obtains the reduced limit power setting value and will start the limit power control again, reduce the wind rotor power input or lower the generator excitation, so that the active output of the wind turbine decreases steadily and finally stabilizes at the actual limit power value after reducing one callback segment. If the new actual limit power is still higher than the junction temperature protection power P j-safe The control device will continue to monitor the junction temperature change and reduce the callback segment again if necessary until the actual limit power falls back to the initial junction temperature protection power P j-safe level.

[0111] In the embodiment of the present application, the synchronous speed interval is determined according to the synchronous speed of the asynchronous generator in the wind turbine generator set and the corresponding speed tolerance percentage, and when the real-time speed is in the synchronous speed interval, the junction temperature T of the power device of the converter in the wind turbine generator set is detected. j , at the power device junction temperature T j Higher than the first protection threshold T j-up When the actual power limit of the current unit is stored as the initial power limit P lim1 And lower the actual limit power to the junction temperature protection power P j-safe , to reduce the junction temperature T of the power device j , so when the power device junction temperature T j When it is too high, the junction temperature T of the power device can be reduced by reducing the actual limiting power of the wind turbine. j , effectively solving the long-term junction temperature T j The problem of power device damage caused by too high a temperature is solved, thereby achieving the goal of reducing the power loss of the unit while avoiding damage to the power device of the converter. j Below the second protection threshold T j-low When the actual power limit of the wind turbine generator set is adjusted back to the initial power limit P in stages lim1 , so when the power device junction temperature T j After returning to normal, the actual limited power of the unit can be restored smoothly and safely, effectively solving the problem of directly releasing the rotation speed in related technologies leading to a sudden change in the unit's output power, thereby achieving more stable and controllable adjustment of the wind turbine.

[0112] The following describes the generator control device in the embodiment of the present invention from the perspective of hardware processing. Figure 3, is a schematic diagram of a physical device structure of a generator control device in an embodiment of the present application.

[0113] It should be noted that Figure 3 The structure of the generator control device shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present invention.

[0114] like Figure 3 As shown, the generator control device includes a central processing unit (CPU) 301, which can perform various appropriate actions and processes according to the program stored in the read-only memory (ROM) 302 or the program loaded from the storage part 308 to the random access memory (RAM) 303, such as executing the method described in the above embodiment. In the RAM 303, various programs and data required for system operation are also stored. The CPU 301, the ROM 302 and the RAM 303 are connected to each other through a bus 304. The input / output (I / O) interface 305 is also connected to the bus 304.

[0115] The following components are connected to the I / O interface 305: an input section 306 including an audio input device, a button switch, etc.; an output section 307 including a liquid crystal display (LCD) and an audio output device, an indicator light, etc.; a storage section 308 including a hard disk, etc.; and a communication section 309 including a network interface card such as a LAN (Local Area Network) card, a modem, etc. The communication section 309 performs communication processing via a network such as the Internet. A drive 310 is also connected to the I / O interface 305 as needed. A removable medium 311, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 310 as needed so that a computer program read therefrom is installed into the storage section 308 as needed.

[0116] In particular, according to an embodiment of the present invention, the process described above with reference to the flowchart can be implemented as a computer software program. For example, an embodiment of the present invention includes a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program includes a computer program for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from a network through a communication section 309, and / or installed from a removable medium 311. When the computer program is executed by a central processing unit (CPU) 301, various functions defined in the present invention are performed.

[0117] It should be noted that specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM), a flash memory, an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination thereof. In the present invention, a computer-readable storage medium may be any tangible medium containing or storing a program that may be used by or in conjunction with an instruction execution system, apparatus, or device.

[0118] The flowcharts and block diagrams in the accompanying drawings illustrate the possible architecture, functions and operations of the systems, methods and computer program products according to various embodiments of the present invention. Each box in the flowchart or block diagram may represent a module, a program segment, or a part of a code, and the above-mentioned module, program segment, or a part of a code contains one or more executable instructions for implementing the specified logical functions. It should also be noted that in some alternative implementations, the functions marked in the box may also occur in an order different from that marked in the accompanying drawings.

[0119] Specifically, the generator control device of this embodiment includes a processor and a memory. The memory stores a computer program. When the computer program is executed by the processor, the synchronous speed range operation control method of the wind turbine generator set provided in the above embodiment is implemented.

[0120] As another aspect, the present invention further provides a computer-readable storage medium, which may be included in the generator control device described in the above embodiment; or may exist independently without being assembled into the generator control device. The above storage medium carries one or more computer programs, and when the above one or more computer programs are executed by a processor of the generator control device, the generator control device implements the synchronous speed section operation control method of the wind turbine generator set provided in the above embodiment.

[0121] As described above, the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present application.

[0122] As used in the above embodiments, the term "when..." may be interpreted to mean "if..." or "after..." or "in response to determining..." or "in response to detecting...", depending on the context. Similarly, the phrases "upon determining..." or "if (the stated condition or event) is detected" may be interpreted to mean "if determining..." or "in response to determining..." or "upon detecting (the stated condition or event)" or "in response to detecting (the stated condition or event)", depending on the context.

[0123] Those skilled in the art can understand that to implement all or part of the processes in the above-mentioned embodiments, the processes can be completed by computer programs to instruct related hardware, and the programs can be stored in computer-readable storage media. When the programs are executed, they can include the processes of the above-mentioned method embodiments. The aforementioned storage media include: ROM or random access memory RAM, magnetic disk or optical disk and other media that can store program codes.

Claims

1. A method for controlling the synchronous speed section operation of a wind turbine generator set, characterized in that: Applied to a generator control device, the method comprises: Determine a synchronous speed range according to the synchronous speed of the asynchronous generator in the wind turbine generator set and the corresponding speed tolerance percentage; When the wind turbine generator set generates wind energy, obtaining the real-time rotation speed of the asynchronous generator in the wind turbine generator set; When the real-time speed is within the synchronous speed range, detecting the junction temperature of a power device of a converter in the wind turbine generator set; When the junction temperature of the power device is higher than the first protection threshold, the actual power limit of the wind generator set is stored as the initial power limit; the actual power limit is the maximum output power set by the wind generator set during the current operation, and the default value of the actual power limit is the rated power of the wind generator set; Lowering the actual limited power to the junction temperature protection power to reduce the junction temperature of the power device; When the junction temperature of the power device is lower than a second protection threshold, the actual limit power of the wind generator set is adjusted back to the initial limit power.

2. The method according to claim 1, characterized in that When the junction temperature of the power device is lower than the second protection threshold, calling back the actual limit power of the wind turbine generator set to the initial limit power specifically includes: When the junction temperature of the power device is lower than a second protection threshold, obtaining a power difference between the junction temperature protection power and the initial limit power; Dividing the power difference into a plurality of ordered power callback segments according to a preset power step; According to the arrangement order of the plurality of ordered power callback segments, adding a power callback segment to the actual limited power; If the junction temperature increment of the power device is not higher than the preset abnormal threshold within the preset test time, the next power callback segment is added to the actual limit power until the actual limit power reaches the initial limit power.

3. The method according to claim 2, characterized in that After the step of adding a power callback segment to the actual power limit according to the arrangement order of the plurality of ordered power callback segments, the method further includes: If the junction temperature increment of the power device junction temperature is higher than the preset abnormal threshold within the preset test time, the actual limit power is reduced by a previous power callback segment until the actual limit power reaches the junction temperature protection power.

4. The method according to claim 1, characterized in that: After the step of determining the synchronous speed range according to the synchronous speed of the asynchronous generator in the wind turbine generator set and the corresponding speed tolerance percentage, the method further includes: Determining a power dispatch dead zone corresponding to the wind turbine generator set according to the synchronous speed range; Obtaining the dispatching limit power issued by the power grid, and determining the operating limit power based on the dispatching limit power and the power dispatching dead zone; The wind turbine generator set is controlled to generate wind energy using the operating limit power as the actual limit power.

5. The method according to claim 4, characterized in that Determining the power dispatch dead zone corresponding to the wind turbine generator set according to the synchronous speed range specifically includes: Determining the output power of the wind turbine generator set at the synchronous speed as the power dead zone center; According to the power tolerance percentage and the center of the power dead zone, the upper limit and the lower limit of the power dead zone are determined to obtain the power scheduling dead zone; the power tolerance percentage is lower than the speed tolerance percentage.

6. The method according to claim 5, characterized in that The obtaining of the dispatching limit power issued by the power grid and determining the operation limit power based on the dispatching limit power and the power dispatching dead zone specifically includes: Obtaining the dispatching limit power issued by the power grid, and determining whether the dispatching limit power is within the power dispatching dead zone; If the scheduling limit power is not within the power scheduling dead zone, the scheduling limit power is used as the operation limit power; If the scheduling limit power is within the power scheduling dead zone range, the lower limit of the power dead zone is used as the operation limit power.

7. The method according to claim 1, characterized in that After the step of adjusting the actual power limit of the wind turbine generator set to the initial power limit when the junction temperature of the power device is lower than the second protection threshold, the method further includes: Record the time when the actual power limit returns to the initial power limit, which is the first time; Obtaining the time when the junction temperature of the power device is higher than the first protection threshold again as the second time; When the time difference between the second time and the first time is lower than a preset time difference, the junction temperature protection power is adjusted based on a preset protection rule.

8. A generator control device, characterized in that: The generator control device comprises: one or more processors and a memory; the memory is coupled to the one or more processors, the memory is used to store computer program code, the computer program code comprises computer instructions, and the one or more processors call the computer instructions so that the generator control device executes the method as described in any one of claims 1-7.

9. A computer-readable storage medium comprising instructions, characterized in that: When the instruction is executed on a generator control device, the generator control device is caused to execute the method according to any one of claims 1 to 7.

10. A computer program product, characterized in that When the computer program product runs on a generator control device, the generator control device is caused to execute the method according to any one of claims 1 to 7.

Citation Information

Cited By

  • Converter equipment and control method thereof