Rainproof protection tool and process for wind power tower installation

By designing rain-proof protection tooling on the wind power tower and using the combined structure of limit nuts, sleeves and positioning barrels, the problem of bolts and nuts easily rusted during the installation of wind power tower is solved, and the stability of the equipment is improved and service life, and simplifies the fixation process.

CN118934467APending Publication Date: 2024-11-12SHANGDU COUNTY TIANSHUN WIND POWER EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411067291.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During the installation process of existing wind power towers, the hexagonal nuts and anchor bolts are exposed to the outside and are easily rusted by wind and rain, and the fixing process is cumbersome, which affects the stability and service life of the equipment.

Method used

A rain-proof protection tool is designed, including setting up a connecting ring and a support frame on the outer wall of the wind power tower, setting up multiple sets of bolts on the top of the support frame, setting up through holes on the inner wall of the connecting ring, and setting up bolts on the inner wall of the through holes, and passing through the limit nuts. The combined structure of the sleeve and the positioning cylinder is protected to prevent rainwater from entering and improve sealing and stability.

Benefits of technology

It effectively protects bolts and nuts, extends their service life, reduces the possibility of rainwater entering, improves the stability and installation efficiency of wind power towers, avoids contact between bolts and water, and reduces the risk of rust.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934467A_ABST
    Figure CN118934467A_ABST
Patent Text Reader

Abstract

The invention discloses a wind power tower installation rainproof protection tool, and relates to the technical field of wind power tower equipment, the wind power tower installation rainproof protection tool comprises a wind power tower body, a connecting ring and a support frame, the top of the support frame is provided with a plurality of groups of bolts, the outer wall of the wind power tower body is provided with the connecting ring, and the inner wall of the connecting ring is provided with a plurality of groups of through holes; a bolt is arranged on the inner wall of the through hole in a sleeving mode, a protection assembly for limiting the bolt is arranged at the top of the through hole, and the protection assembly comprises a limiting nut, a sleeve and a positioning cylinder. Through the arrangement of the protection assembly, hexagon nuts and foundation bolts on the outer wall of the wind power tower drum are protected, the surfaces of the bolts are prevented from being wetted by rainwater, then protection on the multiple sets of bolts on the top of the supporting frame is improved, the bolts are not prone to making contact with water, and the service life of the bolts is prolonged; and a worker does not need to sleeve the limiting nuts one by one.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of wind power tower equipment, and in particular to a wind power tower installation rainproof protection tool and a process thereof. Background Art

[0002] The wind turbine tower is the tower pole of wind power generation. It mainly plays a supporting role in the wind turbine generator set and absorbs the vibration of the set. The production process of the wind turbine tower is generally that the material is cut by a CNC cutting machine, the thick plate needs to be beveled, and the plate is rolled by the plate rolling machine. After confirmation, the inner and outer longitudinal seams are welded. After the roundness is checked, if there is a problem, a secondary rounding is performed. After the single-section cylinder is welded, the hydraulic group is used to spot weld the roller frame, and the inner and outer circumferential seams are welded, and the straightness and other tolerances are checked. After the flange is welded, non-destructive testing and flatness inspection of the weld are carried out. After sandblasting and painting, the internal parts are installed and the finished product is inspected, and then it is transported to the installation site.

[0003] Among them, the wind turbine tower with pre-embedded anchor bolt support frame connection method has the foundation anchor bolts pre-embedded in the foundation main body grouting material. During construction, the anchor bolt support frame is used to fix the through holes on the inner wall of the wind turbine tower on the outer wall of the bolts, and then the anchor bolts are limited by hexagonal nuts to fix the wind turbine tower.

[0004] When the existing wind turbine tower uses hexagonal nuts to limit the anchor bolts, workers are required to put nuts on the outer walls of the bolts one by one, and then rotate the nuts to make the wind turbine tower fit with the support frame. However, after the fixation is completed, the bolts on the surface of the support frame and the nuts on the outer wall of the wind turbine tower are exposed to the outdoors. The nuts and bolts are prone to rust due to long-term wind and rain. Summary of the invention

[0005] Based on this, the purpose of the present invention is to provide a wind turbine tower installation rainproof protection tooling and process thereof to solve the technical problems mentioned in the above background technology.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a wind turbine tower installation rainproof protection tooling and process thereof, comprising a wind turbine tower body, a connecting ring and a support frame, the top of the support frame is provided with multiple groups of bolts, and the outer wall of the wind turbine tower body is provided with a connecting ring, the inner wall of the connecting ring is provided with multiple groups of through holes, the inner wall of the through hole is sleeved with bolts, and the top of the through hole is provided with a protective component for limiting the bolts, the protective component comprises a limiting nut, a sleeve and a positioning cylinder, the inner wall of the limiting nut is installed with a sleeve, and the inner wall of the sleeve is provided with a positioning cylinder, the inner wall of the positioning cylinder is provided with an internal thread, and the internal thread is meshed with the thread on the outer wall of the bolt.

[0007] By adopting the above technical scheme, the hexagonal nuts and anchor bolts on the outer wall of the wind turbine tower are protected to prevent the surface of the bolts from being wetted by rainwater, thereby improving the protection of multiple groups of bolts on the top of the support frame, making it difficult for the bolts to come into contact with water, thereby extending the service life of the bolts. By setting the limit nuts and sleeves, there is no need for the staff to set the limit nuts one by one. When the bolt is in the positioning tube, the limit nut is driven by the external drive device to rotate, so that the positioning tube rotates, and then the inner wall of the positioning tube is meshed with the outer wall of the bolt, so that the bolt is protected and rainwater is not easy to enter the wind turbine tower body.

[0008] Furthermore, a limiting ring is provided at one end of the limiting nut close to the connecting ring, and the limiting ring is in a trapezoidal shape.

[0009] By adopting the above technical solution, the limiting ring seals the gap between the through hole and the limiting nut, thereby improving the sealing performance of the inner wall of the wind power tower body.

[0010] Furthermore, the diameter of the sleeve is smaller than the diameter of the through hole, the sleeve is sleeved in the through hole, and the inner wall of the through hole is provided with an internal thread.

[0011] By adopting the above technical solution, the casing and the through-hole are threadedly connected, thereby improving the stability of the connection between the wind turbine tower body and the support frame.

[0012] Furthermore, one end of the sleeve located at the limiting ring is provided with an external thread, and the external thread is meshed with the inner wall of the through hole.

[0013] By adopting the above technical solution, the shaking of the wind turbine tower body in windy and rainy weather can be reduced, and the stability of the wind turbine tower body after installation can be improved.

[0014] Furthermore, a sleeve is fixedly installed on the inner wall of the limiting nut, and a positioning cylinder is fixedly installed on the inner wall of the sleeve.

[0015] By adopting the above technical solution, the stability among the three is effectively improved, and there is no need to disassemble and assemble the limiting nut multiple times.

[0016] Furthermore, the positioning tube is sleeved on the outer wall of the bolt, and the positioning tube is cylindrical and located on the inner wall of the sleeve.

[0017] By adopting the above technical solution, the sleeve limits the position of the positioning tube, and space for the bolt sleeve is reserved in the sleeve, thereby improving the protective effect of the protective assembly.

[0018] Furthermore, a slide groove is provided at one end of the limiting nut, and a positioning rod is provided on the inner wall of the slide groove.

[0019] By adopting the above technical solution, a slide groove is added at the bottom of the limiting nut, and a positioning rod is provided on the inner wall of the slide groove to limit the position of the protective component and improve the stability of the protective component during rotation.

[0020] Furthermore, a groove is provided on the inner wall of the slide slot, and one end of the positioning rod is movably connected to the groove.

[0021] By adopting the above technical solution, the groove is set to limit the position of one end of the positioning rod, and the positioning rod and the groove are movably connected, and the end of the positioning rod close to the groove is T-shaped.

[0022] A process for using a wind power tower rain protection tooling comprises the following steps:

[0023] S1: Welding process: a limit nut is welded and installed on the outer wall of the sleeve, and a limit ring is arranged at one end of the limit nut close to the positioning tube;

[0024] S2: Color film process: The outer wall of the casing is coated with a waterproof film, and the color of the waterproof film is fluorescent;

[0025] S3: Clamping process: When the bolt is sleeved in the through hole, the bolt is located on the inner wall of the positioning tube, and the limiting nut is rotated to make the positioning tube mesh with the bolt;

[0026] S4: Sealing process: When the limiting nut contacts the outer wall of the connecting ring, the limiting ring is located at the top of the through hole to seal the gap between the sleeve and the through hole.

[0027] In summary, the present invention mainly has the following beneficial effects:

[0028] 1. The present invention protects the hexagonal nuts and anchor bolts on the outer wall of the wind turbine tower by setting a protective component to prevent the surface of the bolts from being wetted by rainwater, thereby improving the protection of multiple groups of bolts on the top of the support frame, making it difficult for the bolts to contact with water, thereby extending the service life of the bolts.

[0029] 2. The present invention eliminates the need for workers to set limit nuts one by one through the provision of limit nuts and sleeves. When the bolt is located in the positioning tube, the limit nut is driven by an external drive device to rotate the positioning tube, thereby causing the inner wall of the positioning tube to mesh with the outer wall of the bolt, thereby protecting the bolt and preventing rainwater from entering the wind turbine tower body. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 This is a schematic diagram of the installation of a wind power tower body of the present invention;

[0031] Figure 2 It is a schematic diagram of the position of the protection component of the present invention;

[0032] Figure 3It is a schematic diagram of the structure of the protection component of the present invention;

[0033] Figure 4 It is a schematic diagram of the position of the limiting ring of the present invention;

[0034] Figure 5 It is a cross-sectional schematic diagram of the limiting nut, sleeve and positioning tube of the present invention;

[0035] Figure 6 It is an enlarged view of point A of the present invention.

[0036] In the figure: 1. Wind turbine tower body; 2. Connecting ring; 3. Through hole; 4. Protective assembly; 40. Limiting nut; 41. Casing; 42. Positioning cylinder; 43. Limiting ring; 44. Slide groove; 45. Positioning rod; 46. Groove; 47. External thread; 5. Support frame. DETAILED DESCRIPTION

[0037] The following will be combined with the accompanying drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0038] The following describes an embodiment of the present invention based on its overall structure.

[0039] Embodiment 1

[0040] A rainproof protection tool for installing a wind turbine tower, such as Figure 1-Figure 6 As shown, it includes a wind turbine tower body 1, a connecting ring 2 and a support frame 5, a plurality of bolts are arranged on the top of the support frame 5, and a connecting ring 2 is arranged on the outer wall of the wind turbine tower body 1, a plurality of through holes 3 are arranged on the inner wall of the connecting ring 2, bolts are sleeved on the inner wall of the through hole 3, and a protective component 4 for limiting the bolts is arranged on the top of the through hole 3, the protective component 4 includes a limiting nut 40, a sleeve 41 and a positioning cylinder 42, a sleeve 41 is installed on the inner wall of the limiting nut 40, and a positioning cylinder 42 is arranged on the inner wall of the sleeve 41, and an inner thread is arranged on the inner wall of the positioning cylinder 42, and an internal thread is meshed with the thread on the outer wall of the bolt, through the protective component The arrangement of component 4 protects the hexagonal nuts and anchor bolts on the outer wall of the wind turbine tower to prevent the surface of the bolts from being wetted by rainwater, thereby improving the protection of multiple groups of bolts on the top of the support frame 5, making it difficult for the bolts to come into contact with water, thereby extending the service life of the bolts. Through the arrangement of the limit nut 40 and the sleeve 41, there is no need for the staff to set the limit nut 40 one by one. When the bolt is located in the positioning tube 42, the limit nut 40 is driven by an external drive device to rotate so that the positioning tube 42 rotates, thereby making the inner wall of the positioning tube 42 mesh with the outer wall of the bolt, thereby protecting the bolt and preventing rainwater from entering the wind turbine tower body 1.

[0041] See also Figure 5, Figure 6 A limiting ring 43 is provided at one end of the limiting nut 40 close to the connecting ring 2, and the limiting ring 43 is trapezoidal in shape. The limiting ring 43 seals the gap between the through hole 3 and the limiting nut 40 to improve the sealing performance of the inner wall of the wind power tower body 1.

[0042] See also Figure 2-Figure 5 The diameter of the sleeve 41 is smaller than the diameter of the through hole 3, and the sleeve 41 is sleeved in the through hole 3, and the inner wall of the through hole 3 is provided with an internal thread, and the sleeve 41 and the through hole 3 are threadedly connected to improve the stability of the connection between the wind power tower body 1 and the support frame 5.

[0043] See also Figure 3-Figure 5 An end of the sleeve 41 located at the limiting ring 43 is provided with an external thread 47, and the external thread 47 is engaged with the inner wall of the through hole 3, thereby reducing the shaking of the wind turbine tower body 1 in windy and rainy weather and improving the stability of the wind turbine tower body 1 after installation.

[0044] See also Figure 3-Figure 5 A sleeve 41 is fixedly installed on the inner wall of the limiting nut 40, and a positioning tube 42 is fixedly installed on the inner wall of the sleeve 41. The limiting nut 40, the sleeve 41 and the positioning tube 42 are fixedly connected, which effectively improves the stability among the three, and there is no need to disassemble and assemble the limiting nut 40 multiple times.

[0045] See also Figure 5 The positioning tube 42 is sleeved on the outer wall of the bolt, and the positioning tube 42 is cylindrical and located on the inner wall of the sleeve 41. The sleeve 41 limits the position of the positioning tube 42, and a space for the bolt to be sleeved is reserved in the sleeve 41, thereby improving the protective effect of the protective component 4.

[0046] A process for using a wind power tower rain protection tooling comprises the following steps:

[0047] S1: Welding process: a limit nut is welded and installed on the outer wall of the sleeve, and a limit ring is arranged at one end of the limit nut close to the positioning tube;

[0048] S2: Color film process: The outer wall of the casing is coated with a waterproof film, and the color of the waterproof film is fluorescent;

[0049] S3: Clamping process: When the bolt is sleeved in the through hole, the bolt is located on the inner wall of the positioning tube, and the limiting nut is rotated to make the positioning tube mesh with the bolt;

[0050] S4: Sealing process: When the limiting nut contacts the outer wall of the connecting ring, the limiting ring is located at the top of the through hole to seal the gap between the sleeve and the through hole.

[0051] Embodiment 2

[0052] See also Figure 2-Figure 6The difference between the second embodiment and the first embodiment is that on the basis of retaining the first embodiment, a slide groove 44 is additionally provided at the bottom of the limiting nut 40, and a positioning rod 45 is provided on the inner wall of the slide groove 44 to limit the position of the protective component 4 and improve the stability of the protective component 4 during rotation:

[0053] A slide groove 44 is provided at the bottom of the limiting nut 40, and two groups of positioning rods 45 are provided on the inner wall of the slide groove 44. Secondly, a groove 46 is provided on the inner wall of the limiting nut 40 near the slide groove 44. One end of the positioning rod 45 is engaged with the groove 46 to limit the position of the positioning rod 45. A circular hole engaged with the positioning rod 45 is provided on the inner wall of the connecting ring 2, and a spring is provided in the circular hole to limit the position of the positioning rod 45. Therefore, when the protective component 4 moves downward, the setting of the positioning rod 45 improves the stability of the protective component 4 during movement.

[0054] The working principle of the present invention is:

[0055] When the wind turbine tower body 1 is placed on the top of the support frame 5, multiple groups of bolts on the top of the support frame 5 are sleeved on the inner wall of the connecting ring 2 through the through holes 3, so that the bolts are located on the inner wall of the positioning tube 42, and the positioning tube 42 is sleeved on the outer wall of the bolts. Then the line personnel use the external drive device to rotate the limit nut 40, so that the external thread 47 on the outer wall of the sleeve 41 is meshed with the inner wall of the through hole 3, and the outer wall of the bolt is meshed with the inner wall of the positioning tube 42. While improving the installation stability of the bolts and nuts, the nuts and bolts are effectively protected and the probability of rusting of the two is reduced. Secondly, the integrated setting of the limit nut 40 and the sleeve 41 does not require the staff to sleeve the limit nut 40 again, which greatly improves the work efficiency and thus improves the installation stability of the wind turbine tower body 1.

[0056] Furthermore, a slide groove 44 is opened on the inner wall of the limit nut 40, so that the positioning rod 45 on the inner wall of the slide groove 44 is engaged with the groove 46, thereby limiting the position of the positioning rod 45. When the limit nut 40 moves downward, the positioning rod 45 is also located in the connecting ring 2, thereby effectively improving the stability of the protective component 4 during rotation.

[0057] Although an embodiment of the present invention has been shown and described, this specific embodiment is only an explanation of the present invention and is not a limitation of the invention. The specific features, structures, materials or characteristics described may be combined in a suitable manner in any one or more embodiments or examples. After reading this specification, those skilled in the art may make modifications, substitutions and variations to the embodiments without creative contribution as needed without departing from the principles and purpose of the present invention. However, as long as they are within the scope of the claims of the present invention, they are protected by patent law.

Claims

1. A rainproof protection tool for installing a wind turbine tower, comprising a wind turbine tower body (1), a connecting ring (2) and a supporting frame (5), characterized in that: A plurality of groups of bolts are arranged at the top of the support frame (5), and a connecting ring (2) is arranged on the outer wall of the wind turbine tower body (1), a plurality of groups of through holes (3) are arranged on the inner wall of the connecting ring (2), bolts are sleeved on the inner wall of the through hole (3), and a protective component (4) for limiting the position of the bolts is arranged at the top of the through hole (3), the protective component (4) comprises a limiting nut (40), a sleeve (41) and a positioning cylinder (42), the inner wall of the limiting nut (40) is installed with a sleeve (41), and the inner wall of the sleeve (41) is provided with a positioning cylinder (42), the inner wall of the positioning cylinder (42) is provided with an internal thread, and the internal thread is meshed with the thread on the outer wall of the bolt.

2. A rainproof protection tool for wind turbine tower installation according to claim 1, characterized in that: A limiting ring (43) is provided at one end of the limiting nut (40) close to the connecting ring (2), and the limiting ring (43) is in a trapezoidal shape.

3. A rainproof protection tool for installing a wind turbine tower according to claim 1, characterized in that: The diameter of the sleeve (41) is smaller than the diameter of the through hole (3), the sleeve (41) is sleeved in the through hole (3), and the inner wall of the through hole (3) is provided with an internal thread.

4. A rainproof protection tool for installing a wind turbine tower according to claim 1, characterized in that: An end of the sleeve (41) located on the limiting ring (43) is provided with an external thread (47), and the external thread (47) is meshed with the inner wall of the through hole (3).

5. The rainproof protection tooling for wind turbine tower installation according to claim 1, characterized in that: A sleeve (41) is fixedly mounted on the inner wall of the limiting nut (40), and a positioning cylinder (42) is fixedly mounted on the inner wall of the sleeve (41).

6. The rainproof protection tooling for wind turbine tower installation according to claim 1, characterized in that: The positioning tube (42) is sleeved on the outer wall of the bolt, and the positioning tube (42) is cylindrical and located on the inner wall of the sleeve (41).

7. The rainproof protection tooling for wind turbine tower installation according to claim 1, characterized in that: A slide groove (44) is provided at one end of the limiting nut (40), and a positioning rod (45) is provided on the inner wall of the slide groove (44).

8. A rainproof protection tool for installing a wind turbine tower according to claim 7, characterized in that: The inner wall of the slide groove (44) is provided with a groove (46), and one end of the positioning rod (45) is movably connected to the groove (46).

9. A process for using a wind power tower rain protection tooling, characterized in that The process of installing the rainproof protection tooling for a wind turbine tower according to any one of claims 1 to 8 comprises the following steps: S1: Welding process: a limit nut is welded and installed on the outer wall of the sleeve, and a limit ring is arranged at one end of the limit nut close to the positioning tube; S2: Color film process: The outer wall of the casing is coated with a waterproof film, and the color of the waterproof film is fluorescent; S3: Clamping process: When the bolt is sleeved in the through hole, the bolt is located on the inner wall of the positioning tube, and the limiting nut is rotated to make the positioning tube mesh with the bolt; S4: Sealing process: When the limiting nut contacts the outer wall of the connecting ring, the limiting ring is located at the top of the through hole to seal the gap between the sleeve and the through hole.