Offshore wind power fan blade replacement method

Through inverted "Y" locking and flat suspender fixing technology, the blade replacement process of offshore wind turbines is simplified, complex and low-efficiency problems in the existing technology are solved, and efficient, low-cost and safe construction of single-blade replacement is achieved.

CN118934511APending Publication Date: 2024-11-12中交海峰风电发展股份有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411315075.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing technology of replacement of offshore wind turbine blades is complex and inefficient. Especially when the overall removal of single blades is damaged, the construction time is long, the economic cost is high, and the construction platform and meteorological conditions are strictly required.

Method used

The impeller is locked in the inverted "Y" shape and the blades are fixed and removed with a flat suspender, which simplifies the single blade replacement process, reduces the construction complexity and cost, adapts to severe weather conditions, and improves the detailed sea sweeping and positioning planning. Construction efficiency.

Benefits of technology

The construction ability of light lifting weight, low cost and adapting to severe weather during single blade replacement is realized, the tool requirements are simplified, and construction efficiency and safety are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118934511A_ABST
    Figure CN118934511A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of offshore wind power fan blade replacement, and discloses an offshore wind power fan blade replacement method which comprises the steps that S1, a blade is lighted to a platform ship; s2, construction and sea sweeping are carried out, the site needs to be explored before construction, sea sweeping is carried out according to site conditions, and a sea sweeping report is formed after sea sweeping is completed; s3, a platform ship enters a point; s4, impeller turning and locking are conducted, the unit impeller is made to be in an inverted-Y-shaped mode, the to-be-replaced blade is located at the vertical upward position, and a lightning protection assembly of the to-be-replaced blade is disassembled; s5, old blades are dismantled; s6, new blades are installed; and S7, performing recovery and defect elimination, and performing acceptance inspection of torque and the like and reinstallation of an electrical circuit. According to the method for replacing the blades of the offshore wind power fan, required blade tools are simple, single-blade replacement is carried out, the single-blade lifting weight is light, the requirement for the standard of a ship machine is low, and the method has the advantage of being low in cost, adapts to severe weather conditions and can be safely constructed under the higher wind power level.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of offshore wind turbine blade replacement, and in particular to an offshore wind turbine blade replacement method. Background Art

[0002] With the recognition of the huge consumption of traditional energy and environmental pollution, offshore wind energy has its unique advantages and has gradually become a renewable energy source that is widely valued worldwide. A large number of offshore wind turbines will enter the production and operation stage. What cannot be ignored is that more and more offshore wind turbines are experiencing failures, and reports of wind turbine blade damage are becoming more and more frequent, which greatly affects the power generation revenue of wind farms. As the capacity of offshore wind power units develops towards large-scale development, single-unit failures such as blade damage will generate a lot of economic losses.

[0003] The replacement of offshore wind turbine blades usually adopts the method of replacing the impeller as a whole, that is, the hub and three blades are dismantled as a whole and hoisted onto a self-elevating platform ship, and the blades are replaced on the platform ship. The operation is complicated, and high requirements are placed on construction equipment. The lifting capacity and deck area of ​​the construction platform ship are high, and strict requirements are placed on meteorological conditions. In the condition where only a single blade needs to be replaced, the overall dismantling has low construction efficiency and takes a long time. Summary of the invention

[0004] In view of the deficiencies in the prior art, the present invention provides a method for replacing blades of an offshore wind turbine, which solves the problems mentioned in the above background.

[0005] The present invention provides the following technical solution: a method for replacing blades of an offshore wind turbine, comprising:

[0006] Step S1, the blades are transferred to a platform ship;

[0007] Step S2, construction sea sweeping: before construction, the site needs to be surveyed and sea sweeping is carried out according to the site conditions. After the sea sweeping is completed, a sea sweeping report is generated;

[0008] Step S3, the platform ship enters the point;

[0009] Step S4, the impeller is turned and locked, so that the impeller of the unit is in an inverted "Y" shape, wherein the blade to be replaced is located in a vertical upward position, and the lightning protection assembly of the blade to be replaced is removed;

[0010] Step S5, removing the old blades;

[0011] Step S6, installing new blades;

[0012] Step S7, restore and eliminate faults, conduct torque acceptance and electrical circuit reinstallation.

[0013] Preferably, in step S1, the new blades that have passed the acceptance test are transferred to a construction platform ship and fixed.

[0014] Preferably, in step S2, it is determined whether there are shipwrecks, obstacles, sand pits and other factors affecting the construction on the seabed, and the flatness of the seabed for each machine position is analyzed. The cleaning work of the construction sea area is planned and arranged in detail according to the report content, and the wind turbine blade replacement construction is guided according to the scanning report.

[0015] Preferably, in step S3, the platform ship is in place to determine the hydrological and meteorological conditions, and is in place by means of DP positioning, anchoring, etc. The platform ship is in place to determine the hydrological and meteorological conditions, and is in place by means of DP positioning, anchoring, etc. Before the platform ship enters the site for operation, the approach direction and pile insertion position of the original machine position operating ship are collected, and the approach point in this direction should be avoided as much as possible during operation. The center of the platform main crane is not less than 50m away from the center of the machine position; after the wind turbine pile foundation is completed, a trestle is set up between the wind turbine pile foundation and the platform ship to form an up and down passage between the platform ship and the machine position.

[0016] Preferably, in step S4;

[0017] Impeller turning: Install blade guards and a 30T×15m double-eye flat protective sling on the two blades at 4 o'clock and 8 o'clock in the inverted "Y" shape. The installation position is the blade reinforcement area, 52m away from the blade root. It is determined by calculation that the other end of the tail sling at the 4 o'clock position is connected to the main crane, and the other end of the tail sling at the 8 o'clock position is connected to the auxiliary crane. First use the main crane to lift the blade at the 4 o'clock position upward by 45°, and then use another auxiliary crane to lift the other blade originally at the 8 o'clock position. The two cranes lift at the same time, and the lifting force of a single crane on the blade shall not exceed 18 tons;

[0018] Impeller locking: When the vertically upward blades, that is, the old blades to be replaced, rotate to the horizontal 0° position, the impeller is locked and the crane unloads the force.

[0019] Preferably, when turning the two blades, the load-bearing capacity should be verified, and it is strictly forbidden to exceed the designed load-bearing capacity of the blades.

[0020] Preferably, the step S5 comprises:

[0021] Step S51, using a flat sling to fix the replacement blade: the construction personnel take the hanging basket to the top of the old blade to be replaced, the crane slowly approaches the blade to be replaced, and the front and rear of the blade are locked with a flat sling, and the other ends of the slings at the two locations are respectively hung on the hanging beam, and the hanging beam is fixed to the main hook of the crane through the sling. The sling can be wound around and tied, or punched and inserted into the sling for lifting. The punching and insertion of the sling requires determining the lifting point of the blade to be replaced, and no less than 2 holes are constructed;

[0022] Step S52, dismantling bolts: the construction personnel wear labor protection safety equipment and enter the wheel hub to dismantle the old blades. After the bolts connecting the blades and the wheel hub are loosened, they can be twisted by hand without removing the nuts;

[0023] Step S53, lifting the old blade: After the main crane lifts the blade to evenly distribute the force, all bolts are removed. After the bolts are removed, the crane begins to slowly rotate outward so that the root of the blade begins to separate from the hub. After the blade is completely separated from the end face of the hub pitch bearing, the blade is lifted onto the platform ship by the crane and fixed.

[0024] Preferably, in step S51, the hook head of the crane and the suspended blade are in a vertical state without any deviation, and wind-blocking ropes are tied in advance to the edge buckles and blade roots of the blade to control the swing of the blade.

[0025] Preferably, in step S53, the crane needs to move slowly when removing the blades, and the crane stops moving after the bolts come out of the blade flange surface, and then continues to move after the blades are in a stable state.

[0026] Preferably, step S6 comprises:

[0027] Step S61, cleaning: use a clean rag and cleaning agent to clean the dirt and oil on the blade, use an angle grinder and a grinding disc to grind off the burrs on the blade flange, clean the flange surface, screw the blade bolt and rubber ring into the bolt hole of the blade root flange, screw the short thread side into the blade bolt hole, equip each bolt with 3 rubber rings, adjust the blade bolt to the blade flange surface to a suitable distance, and install 3 blade positioning fixtures on the blade, starting from the leading edge zero point and evenly distributed at about 120°;

[0028] Step S62, glue application: Apply two circles of flat weatherproof sealant on the outer side of the blade flange installation surface. To prevent the sealant from curing, apply the sealant within 30 minutes before the blade is lifted and installed;

[0029] Step S63, lifting the new blade: Use a single-blade lifting beam to lift the new blade. At a distance of 1m to 1.3m from the blade root flange surface, use a 40t×34m×500mm flat lifting belt to wrap around the blade root circle. The other end of the lifting belt is connected to the electric hoist at the front end of the lifting beam. At a distance of about 52m from the blade root flange surface, use a 60t×25m×500mm flat lifting belt to pass through the blade. The other end of the lifting belt is connected to the lifting point at the rear end of the lifting beam. Adjust the length of the lifting belt to keep the front and rear of the lifting beam level.

[0030] Step S64, blade hub docking: when the blade approaches the hub system, align the position of the blade and the inner ring of the pitch bearing to ensure that they are basically concentric, and continue to move the blade close to the hub system until the bolts installed on the blade are about 10 mm away from the pitch bearing, operate the pitch operating box to rotate the inner ring of the pitch bearing, so that the zero position hole of the inner ring of the pitch bearing is aligned with the zero position mark of the leading edge of the blade. After the blade zero position is expected to be aligned, start the crane and slowly move the blade close to the pitch bearing so that the blade bolts are inserted into the pitch bearing mounting holes. During the operation, prevent the threads of the blade bolts from being damaged, and screw the round nuts into the blade root bolts through the process holes;

[0031] Step S65, disassembling the sling: all nuts must be screwed in through the process holes, and the sling can be disassembled after the first set of bolts are stretched.

[0032] Compared with the prior art, the present invention has the following beneficial effects:

[0033] The present invention can replace a single blade, the lifting weight of the single blade is light, the standard requirement for the ship engine is low, the cost advantage is low, the invention can adapt to adverse weather conditions, and the construction can be carried out safely under higher wind force levels. The construction tools and equipment are simple, the tooling is simple, and the application range is wide. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 It is a flow chart of the present invention;

[0035] Figure 2 This is a specific flow chart for removing old blades in the present invention;

[0036] Figure 3 This is a specific flow chart for installing new blades in the present invention;

[0037] Figure 4 It is a schematic diagram of the single blade removal structure of the present invention.

[0038] In the figure: 1. Flat sling; 2. Lifting beam; 3. Blade; 4. Crane. DETAILED DESCRIPTION

[0039] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0040] See also Figure 1-4 , a method for replacing blades of an offshore wind turbine comprises: step S1, transferring the blade 3 to a platform ship;

[0041] Step S2, construction sea sweeping: before construction, the site needs to be surveyed and sea sweeping is carried out according to the site conditions. After the sea sweeping is completed, a sea sweeping report is generated;

[0042] Step S3, the platform ship enters the point;

[0043] Step S4, the impeller is turned and locked, so that the impeller of the unit is in an inverted "Y" shape, wherein the blade 3 to be replaced is located in a vertical upward position, and the lightning protection component of the blade 3 to be replaced is removed;

[0044] Step S5, removing the old blade 3;

[0045] Step S6, installing a new blade 3;

[0046] Step S7, restore and eliminate faults, conduct torque acceptance and electrical circuit reinstallation.

[0047] In step S1, the new blades 3 that have passed the inspection are transferred to the construction platform ship and fixed.

[0048] In step S2, determine whether there are shipwrecks, obstacles, sand pits and other factors that affect the construction on the seabed, analyze the flatness of the seabed at each machine position, plan and arrange the cleaning work of the construction sea area in detail according to the report content, and guide the replacement construction of the wind turbine blades 3 according to the scanning report.

[0049] In step S3, the platform ship is in place to determine the hydrological and meteorological conditions, and is in place by means of DP positioning, anchoring, etc. DP positioning, that is, dynamic positioning, Dynamic Positioning, referred to as DP, is an advanced ship navigation and control system, which aims to keep the ship stable at a predetermined position by automatically controlling the ship's propellers, rudders, fins and other equipment. The platform ship is in place to determine the hydrological and meteorological conditions, and is in place by means of DP positioning, anchoring, etc. Before the platform ship enters the site for operation, the approach direction and pile insertion position of the original machine position operating ship are collected, and the approach point in this direction should be avoided as much as possible during operation. The center of the platform main crane 4 is not less than 50m away from the center of the machine position; after the wind turbine pile foundation is completed, a trestle is set up between the wind turbine pile foundation and the platform ship to form an up and down channel between the platform ship and the machine position.

[0050] In step S4;

[0051] Impeller turning: Install blade 3 guard plates and a 30T×15m double-eye flat protective sling on the two blades 3 at 4 o'clock and 8 o'clock in the inverted "Y" shape. The installation position is the reinforcement area of ​​blade 3, 52m away from the blade root. It is determined by calculation that the other end of the tail sling at 4 o'clock is connected to the main crane 4, and the other end of the tail sling at 8 o'clock is connected to the auxiliary crane 4. First use the main crane 4 to lift the blade 3 at 4 o'clock upward by 45°, and then use another auxiliary crane to lift the other blade 3 originally at 8 o'clock. The two cranes 4 lift at the same time, and the lifting force of a single crane 4 on the blade 3 shall not exceed 18 tons;

[0052] Impeller locking: When the vertically upward blade 3, that is, the old blade 3 to be replaced, rotates to the horizontal 0° position, the impeller is locked and the crane 4 unloads the force.

[0053] When turning the two blades 3, the load-bearing capacity should be verified and it is strictly forbidden to exceed the designed load-bearing capacity of the blades 3.

[0054] Step S5 comprises:

[0055] Step S51, using a flat sling 1 to fix the replacement blade 3: the construction personnel take the hanging basket to the top of the old blade 3 to be replaced, the crane slowly approaches the blade 3 to be replaced, and the flat sling 1 is used to lock the front and rear of the blade 3, and the other ends of the slings at the two locations are respectively hung on the hanging beam 2, and the hanging beam 2 is fixed to the main hook of the crane 4 through the sling. The lifting can be carried out by winding and tying the sling, punching and wearing the sling, wherein the punching and wearing of the sling requires determining the lifting point of the blade 3 to be replaced, and the construction is not less than 2 holes;

[0056] Step S52, dismantling bolts: the construction personnel wear labor protection safety equipment and enter the wheel hub to dismantle the old blade 3. After the bolts connecting the blade 3 and the wheel hub are loosened, they can be twisted by hand without removing the nuts;

[0057] Step S53, lifting the old blade 3: After the main crane 4 lifts the blade 3 and applies force evenly, all the bolts are removed. After the bolts are removed, the crane 4 begins to rotate slowly outward so that the root of the blade 3 begins to separate from the hub. After the blade 3 is completely separated from the end face of the hub pitch bearing, the blade 3 is lifted onto the platform ship by the crane 4 and fixed.

[0058] In step S51, the hook head of the crane 4 and the suspended blade 3 are in a vertical state without any deviation, and wind-blocking ropes are tied in advance at the edge buckles and blade roots of the outer periphery of the blade 3 to control the swing of the blade 3.

[0059] In step S53, the crane needs to move slowly when removing the blade 3. When the bolts are out of the flange surface of the blade 3, the crane stops moving first, and then continues to move after the state of the blade 3 is stable.

[0060] Step S6 includes:

[0061] Step S61, cleaning: use a clean rag and a cleaning agent, the cleaning agent is an existing product, for example, HP769 cleaning agent, to clean the dirt and oil stains on the blade 3, use an angle grinder and a grinding disc to grind off the burrs on the flange of the blade 3, clean the flange surface, screw the bolts and rubber rings of the blade 3 into the bolt holes of the blade root flange, screw the short thread side into the bolt holes of the blade 3, and equip each bolt with 3 rubber rings, adjust the bolts of the blade 3 to the flange surface of the blade 3 to a suitable distance, for example, 398-399mm, and install 3 blade 3 positioning tools, such as positioning pins, on the blade 3, starting from the leading edge zero point and evenly distributed at about 120°;

[0062] Step S62, glue application: Apply two circles of flat weatherproof sealant on the outer side of the flange mounting surface of the blade 3. The flat weatherproof sealant can be an existing product, such as Dow Corning 7097 sealant. To prevent the sealant from curing, apply the sealant within 30 minutes before lifting and installing the blade 3.

[0063] Step S63, lifting the new blade 3: Use the single blade 3 lifting beam 2 to lift the new blade 3. At a distance of 1m to 1.3m from the blade root flange surface, use a 40t×34m×500mm flat lifting belt 1 to wrap around the blade root circle. The other end of the lifting belt is connected to the electric hoist at the front end of the lifting beam 2. At a distance of about 52m from the blade root flange surface, use a 60t×25m×500mm flat lifting belt 1 to pass through the blade 3. The other end of the lifting belt is connected to the rear end lifting point of the lifting beam 2. Adjust the length of the lifting belt to keep the front and rear of the lifting beam 2 horizontal.

[0064] Step S64, blade 3 hub docking: when blade 3 approaches the hub system, align the position of blade 3 and the inner ring of the pitch bearing to ensure that they are basically concentric, and continue to move blade 3 close to the hub system until the bolts installed on blade 3 are about 10 mm away from the pitch bearing, operate the pitch operating box to rotate the inner ring of the pitch bearing, so that the zero position hole of the inner ring of the pitch bearing is aligned with the zero position mark of the leading edge of blade 3. After the zero position of blade 3 is expected to be aligned, start crane 4 and slowly move blade 3 close to the pitch bearing, so that the bolts of blade 3 are inserted into the mounting holes of the pitch bearing. During the operation, prevent the threads of the bolts of blade 3 from being damaged, and screw the M42 round nut into the blade root bolt through the process hole;

[0065] Step S65, disassembling the sling: all nuts must be screwed in through the process holes, and the sling can be disassembled after the first set of bolts are stretched.

[0066] To replace a single blade 3, the lifting weight of a single blade 3 is light, the requirements for ship machinery standards are low, it has a low cost advantage, it can adapt to adverse weather conditions, it can be safely constructed under higher wind levels, the construction tools and equipment requirements are simple, the tooling is simple, and the application range is wide.

[0067] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A method for replacing blades of an offshore wind turbine, characterized in that: include: Step S1, the blade (3) is transferred to a platform ship; Step S2, construction sea sweeping: before construction, the site needs to be surveyed and sea sweeping is carried out according to the site conditions. After the sea sweeping is completed, a sea sweeping report is generated; Step S3, the platform ship enters the point; Step S4, the impeller is turned and locked, so that the impeller of the unit is in an inverted "Y" shape, wherein the blade (3) to be replaced is located in a vertically upward position, and the lightning protection component of the blade (3) to be replaced is removed; Step S5, removing the old blade (3); Step S6, installing a new blade (3); Step S7, restore and eliminate faults, conduct torque acceptance and electrical circuit reinstallation.

2. The offshore wind turbine blade replacement method according to claim 1, characterized in that: In the step S1, the new blades (3) that have passed the inspection are transferred to the construction platform ship and fixed.

3. The offshore wind turbine blade replacement method according to claim 1, characterized in that: In step S2, it is determined whether there are shipwrecks, obstacles, sand pits and other factors that affect the construction on the seabed, and the flatness of the seabed at each machine position is analyzed. According to the report content, a detailed plan is arranged for the cleaning work of the construction sea area, and the wind turbine blade (3) replacement construction is guided according to the scanning report.

4. The offshore wind turbine blade replacement method according to claim 1, characterized in that: In step S3, the platform ship determines the hydrological and meteorological conditions when it is in place, and adopts DP positioning, anchoring and other methods to be in place. Before the platform ship enters the site for operation, the approach direction and pile insertion position of the original machine position operation ship are collected, and the approach point in this direction should be avoided as much as possible during operation. The center of the platform main crane (4) is not less than 50m away from the center of the machine position; After the wind turbine pile foundation is completed, a trestle is built between the wind turbine pile foundation and the platform ship to form an up and down passage between the platform ship and the machine position.

5. The offshore wind turbine blade replacement method according to claim 1, characterized in that: In the step S4; Impeller turning: Install blade (3) guard plates and a 30T×15m double-eye flat protective sling on the two blades (3) at 4 o'clock and 8 o'clock in the inverted "Y" shape. The installation position is the blade (3) reinforcement area, 52m away from the blade root. It is determined by calculation that the other end of the tail sling at the 4 o'clock position is connected to the main crane (4), and the other end of the tail sling at the 8 o'clock position is connected to the auxiliary crane (4). First, use the main crane (4) to lift the blade (3) at the 4 o'clock position upward by 45°, and then use another auxiliary crane to lift the other blade (3) originally at the 8 o'clock position. The two cranes (4) lift at the same time. The lifting force of a single crane (4) on the blade (3) shall not exceed 18 tons; Impeller locking: When the vertically upward blade (3), that is, the old blade (3) to be replaced, rotates to the horizontal 0° position, the impeller is locked and the crane (4) unloads the force.

6. The offshore wind turbine blade replacement method according to claim 5, characterized in that: When the two blades (3) are turned, the load-bearing capacity should be verified, and it is strictly forbidden to exceed the designed load-bearing capacity of the blades (3).

7. The offshore wind turbine blade replacement method according to claim 1, characterized in that: The step S5 comprises: Step S51, using a flat sling (1) to fix the replacement blade (3): the construction personnel take a hanging basket to the top of the old blade (3) to be replaced, the crane slowly approaches the blade (3) to be replaced, and uses the flat sling (1) to lock the front and rear of the blade (3), and hangs the other ends of the slings at the two locations on the hanging beam (2), respectively. The hanging beam (2) is fixed to the main hook of the crane (4) through the sling, and the lifting can be carried out by winding and tying the sling, punching and inserting the sling, wherein the punching and inserting of the sling requires determining the lifting point of the blade (3) to be replaced, and the construction is not less than 2 holes; Step S52, dismantling the bolts: the construction personnel wear labor protection safety equipment and enter the wheel hub to dismantle the old blade (3). After the bolts connecting the blade (3) and the wheel hub are loosened, they can be twisted by hand without removing the nuts; Step S53, lifting the old blade (3): After the main crane (4) lifts the blade (3) to ensure uniform force, all bolts are removed. After the bolts are removed, the crane (4) begins to slowly rotate outward, so that the root of the blade (3) begins to separate from the hub. After the blade (3) is completely separated from the end face of the hub pitch bearing, the crane (4) is used to lift the blade (3) onto the platform ship and fix it.

8. The offshore wind turbine blade replacement method according to claim 7, characterized in that: In step S51, the hook head of the crane (4) and the suspended blade (3) are in a vertical state without any deviation, and wind-blocking ropes are tied in advance to the outer edge buckles and blade roots of the blade (3) to control the swing of the blade (3).

9. The offshore wind turbine blade replacement method according to claim 7, characterized in that: In step S53, the crane needs to move slowly when removing the blade (3). When the bolt is out of the flange surface of the blade (3), the crane stops moving first, and then continues to move after the blade (3) is in a stable state.

10. The offshore wind turbine blade replacement method according to claim 1, characterized in that: The step S6 comprises: Step S61, cleaning: Use a clean rag and cleaning agent to clean the dirt and oil stains on the blade (3), use an angle grinder and a grinding disc to grind off the burrs on the flange of the blade (3), clean the flange surface, screw the blade (3) bolts and rubber rings into the bolt holes of the blade root flange, screw the short thread side into the bolt holes of the blade (3), and equip each bolt with 3 rubber rings. Adjust the blade (3) bolts to the blade (3) flange surface to a suitable distance, and install 3 blade (3) positioning fixtures on the blade (3) at an angle of about 120°, starting from the leading edge zero point; Step S62, glue application: Apply two circles of flat weatherproof sealant on the outer side of the flange mounting surface of the blade (3). To prevent the sealant from curing, apply the sealant within 30 minutes before the blade (3) is lifted and installed; Step S63, lifting the new blade (3): use the single blade (3) lifting beam (2) to lift the new blade (3), use a 40t×34m×500mm flat lifting belt (1) to wrap around the blade root at a distance of 1m to 1.3m from the blade root flange surface, and connect the other end of the lifting belt to the electric hoist at the front end of the lifting beam (2). At a distance of about 52m from the blade root flange surface, use a 60t×25m×500mm flat lifting belt (1) to pass through the blade (3), and connect the other end of the lifting belt to the rear end lifting point of the lifting beam (2). Adjust the length of the lifting belt to keep the front and rear of the lifting beam (2) level; Step S64, blade (3) hub docking: when the blade (3) approaches the hub system, align the position of the blade (3) and the inner ring of the pitch bearing to ensure that they are basically concentric, and continue to move the blade (3) closer to the hub system until the bolts installed on the blade (3) are about 10 mm away from the pitch bearing, operate the pitch operating box to rotate the inner ring of the pitch bearing, so that the zero position hole of the inner ring of the pitch bearing is aligned with the zero position mark of the leading edge of the blade (3). After the blade (3) is expected to be aligned at zero position, start the crane (4) and slowly move the blade (3) closer to the pitch bearing so that the bolts of the blade (3) are inserted into the mounting holes of the pitch bearing. During the operation, the threads of the bolts of the blade (3) must be prevented from being damaged, and the round nut is screwed into the root bolt through the process hole; Step S65, disassembling the sling: all nuts must be screwed in through the process holes, and the sling can be disassembled after the first set of bolts are stretched.