Steel cable reinforcing structure for water supply pipe of water plant in underwater large-depth complex terrain

By laying long steel cables and hoop structures on both sides of the bottom water supply pipe, the problem of heavy stress on the water supply pipes under large depth and complex terrain is solved, and the stable installation of the pipes and the service life are extended.

CN118935096APending Publication Date: 2024-11-12ZHEJIANG COSINE DESIGN CONSULTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411085133.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In the construction of water bottom water supply pipelines with large depths and complex terrain, the water supply pipeline is greatly affected by its own weight and is easily broken. The complex bottom terrain causes the pipeline to fail to fully contact the water bottom, which increases the construction difficulty and maintenance difficulties.

Method used

Long steel cables are arranged on both sides of the water supply pipeline, and steel cables are fixed through the hinge and pier structure to share the gravity and impact force of the pipeline, ensuring that the pipeline is stable to contact the bottom of the water and reducing stress, and extending its service life.

Benefits of technology

It effectively reduces the stress of the water supply pipe, prevents breakage and suspension, improves the stability and service life of the pipe, and reduces construction difficulty and maintenance costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118935096A_ABST
    Figure CN118935096A_ABST
Patent Text Reader

Abstract

The invention relates to a steel cable reinforcing structure for a water supply pipe of a water plant in an underwater large-depth complex terrain. The problem that safe use of the water supply pipe is difficult to guarantee during construction of the underwater water supply pipe in the large-depth complex terrain is solved. Hoops are arranged on the outer wall of a water supply pipeline at intervals of clamping, anchor blocks are poured on the bank at the corresponding positions of the two water outlet ends of the water supply pipeline, the upper surfaces of the anchor blocks are obliquely arranged, the water outlet ends of the water supply pipeline are fixed through the anchor blocks, each hoop is formed by splicing two half hoops, the two half hoops are symmetrical in structure, and the two ends of each half hoop extend outwards to form splicing arms respectively. The splicing arms at the two ends of the two half hoops are aligned and locked through locking bolts, the splicing arms of the two half hoops are oppositely provided with steel cable clamping grooves, and steel cables are clamped in the steel cable clamping grooves. The steel cables are arranged along the two sides of the underwater section of the water supply pipeline in a full-length mode, the steel cables are symmetrically arranged on the two sides of the water supply pipeline, steel cable fixing seats are symmetrically arranged on the two sides of the lower portion of the upper surface of the anchor block, and the ends of the steel cables are fixed to the steel cable fixing seats. The full-length steel cables are arranged on the two sides of the underwater section of the water supply pipeline to bear the gravity, impact force and pulling force originally borne by the pipeline, the stress of the pipeline can be greatly reduced, and the service life of the water supply pipeline is prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of engineering construction, and relates to a submerged pipe installation structure for an underwater water supply pipe, and in particular to a steel cable reinforcement structure for a water supply pipe of a water plant with a large underwater depth and complex terrain. Background Art

[0002] At present, the construction methods used for water supply pipelines crossing rivers, lakes and other waters are usually the following: pipe erection along the bridge, pipe erection on a separate pipe bridge, traction construction, pipe jacking construction and immersed pipe construction.

[0003] Pipe laying along the bridge requires considering the load of the pipeline when designing the bridge. This method is relatively inexpensive and convenient for maintenance and overhaul in the later stage. It is most widely used in municipal projects. If there happens to be a plan to lay a road or bridge in the waters where the pipeline needs to cross, pipe laying along the bridge is a relatively optimal solution.

[0004] A separate pipe bridge needs to be built for pipe racking. Although it is convenient for maintenance and repair in the later stage, its cost is very high. It is generally suitable for large-diameter pipelines crossing narrow rivers and when high pipeline safety requirements are required.

[0005] The pipelines of the traction method, pipe jacking method and immersed pipe construction are buried under the riverbed, which is inconvenient for later maintenance and inspection, and has high requirements for construction quality. At the same time, the safety of pipeline use is relatively lacking. Traction and pipe jacking have certain requirements for the width of the water area and geology. Too long a distance cannot be constructed in one go. Immersed pipe construction has little restrictions on the width of the water area and underwater geological conditions, but traditional immersed pipe construction is greatly affected by the depth of the water area. The greater the depth, the cost increases exponentially.

[0006] The steps of the traditional immersed tube construction process are: construction preparation → measurement and layout, positioning → dredger in place → underwater pipeline trench excavation → pipeline foundation soft foundation treatment → laying of pipeline cushion foundation → floating the connected pipeline to the top of the trench by boat → pipeline sinking and installation → masonry of pipeline ancillary structures → pipeline pressure testing → trench backfilling and weighting → embankment repair → project acceptance.

[0007] Traditional immersed tube construction requires dredgers to dig trenches for pipelines. When the water depth is large, long-arm excavators are needed to cooperate with large ships to meet the construction conditions. After the pipeline is sunk and installed, backfilling and weighting are required to prevent the pipeline from shifting. The traditional immersed tube construction process has high requirements for construction conditions and a long construction period. The underwater operation accounts for a large proportion of the total, and the construction difficulty and cost are relatively high.

[0008] For the laying of cross-lake water supply pipelines in waters with long spans, great depths and complex underwater terrain, such as Qiandao Lake, there are basically no bridges suitable for laying pipes on such lakes; the span of a separate pipe bridge is large, the cost is high, and it will affect the navigation of ships; since the lake depth is more than 30 meters, the towing method and the jacking method are not applicable; and traditional immersed pipe construction is difficult to implement because it exceeds the maximum depth of the dredger's trenching construction.

[0009] The Chinese patent previously applied by the applicant, with publication number CN113175017A and publication date July 27, 2021, discloses a deep-water underwater water supply pipe sinking construction process. This solution adopts a construction method of laying counterweights on both sides of the water supply pipe to ensure the stability of the underwater water supply pipe to resist lateral impact, with less underwater operations, and low construction difficulty and cost. However, due to the great depth of the lake, the length of the connecting section of the water supply pipe extending from the shore to the bottom of the water is large, and the weight is heavy. The pipe is subject to great force due to its own weight and is easily broken; and the underwater terrain is complex. No matter how the pipe laying route is chosen, there will almost inevitably be cliffs or gullies along the pipe, which will cause part of the pipe to be unable to contact the bottom of the water but to be in a suspended state, which is susceptible to the pressure of the turning of the water flow in the pipe and the lateral impact of the underwater undercurrent. Moreover, in such deep and complex terrain, once a water supply pipe breaks, it is almost impossible to repair it. Therefore, how to ensure the safe use of the water supply pipe is the focus of water supply pipe installation in such terrain. Summary of the invention

[0010] The purpose of the present invention is to solve the problem that underwater water supply pipes in great depths and complex terrain are affected by the water supply pipes' own weight and the complex underwater terrain, the water supply pipes are subjected to large forces and the force conditions are complex, and the existing construction methods are difficult to ensure the safe use of the water supply pipes. A steel cable reinforcement structure for water supply pipes in water plants in underwater great depths and complex terrain is provided, which distributes the force of the water supply pipes themselves to the steel cables on both sides to achieve reinforcement and extend the service life of the water supply pipes.

[0011] The technical solution adopted by the present invention to solve its technical problems is: a steel cable reinforcement structure of a water supply pipe of a water plant with a large underwater depth and complex terrain, comprising a water supply pipe, wherein a clamp is arranged at intervals of an outer wall of the water supply pipe, anchor piers are cast on the shore at corresponding positions of the two water outlet ends of the water supply pipe, the upper surface of the anchor pier is arranged inclined, and the water outlet end of the water supply pipe is fixed by the anchor pier, the clamp is formed by splicing two half hoops, the two half hoops are symmetrical in structure, and splicing arms are respectively extended outward at both ends of the half hoops, the splicing arms at both ends of the two half hoops are respectively aligned and locked by locking bolts, and the splicing arms of the two half hoops are relatively provided with steel cable clamping grooves, and a steel cable is clamped in the steel cable clamping groove; the steel cable is arranged along both sides of the underwater section of the water supply pipe, and the steel cable is symmetrically arranged on both sides of the water supply pipe, and the lower part of the upper surface of the anchor pier is symmetrically provided with steel cable fixing seats, and the ends of the steel cable are fixed on the steel cable fixing seats.

[0012] The traditional water supply pipe structure has never had a structure with reinforced steel cables on both sides of the water supply pipe. This structure is applicable to waters with great depth and complex underwater terrain to solve the following three problems: 1. The sinking of the water supply pipe requires the use of the pipe's own weight. If the pipe's own weight is insufficient, a counterweight needs to be set on the outside of the water supply pipe to help the pipe sink smoothly and ensure that the pipe will not float up when it is empty. When the water depth is large, the gravity of the water supply pipe and the gravity of the counterweight in the step distance from the river bank to the bottom of the water will produce a huge tensile load on the water supply pipe. If the water supply pipe cannot withstand the gravity load, it will be broken; 2. After the construction of the water supply pipe, since the water supply pipe is not directly and completely in contact with the bottom of the water, it will continue to sink during long-term use, but the anchor pier can only fix the water outlet of the water supply pipe after waiting for a limited time, and the long-term continuous sinking of the pipe will form an increasingly large tensile force on the water supply pipe. Therefore, the steel cables on both sides of the water supply pipe can be To share this kind of continuous pulling force and avoid the water supply pipeline from being damaged; 3. When the terrain of the water area is complex, especially in artificial reservoirs such as Qiandao Lake, there are gullies and cliffs in the terrain of the water area. The layout route of the water supply pipeline can hardly avoid these terrains. When the water supply pipeline passes through these terrains, part of the pipeline will not be able to touch the bottom, but will be in a suspended state. This section of the water supply pipeline is suspended, which is not only affected by gravity to form a curvature, but also generates pressure in the curved section due to the turning of the internal water flow. It will also be impacted by irregular underwater undercurrents. The situation is very complicated and can easily cause the pipeline to crack. This structure lays full-length steel cables on both sides of the underwater section of the water supply pipeline to withstand the gravity, impact force and tension originally borne by the pipeline itself, which can greatly reduce the stress on the pipeline and extend the service life of the water supply pipeline.

[0013] Preferably, the clamp includes a stainless steel clamp and a concrete clamp. The stainless steel clamp is used to fix the steel cable, and the concrete clamp mainly acts as a counterweight to assist the water supply pipeline in sinking and prevent the water supply pipeline from floating.

[0014] Preferably, the stainless steel clamp splicing arm is provided with locking bolts on the inner side and the outer side of the cable clamp groove respectively.

[0015] Preferably, the concrete clamp is provided with a locking bolt on the outer side of the steel cable clamp groove.

[0016] Preferably, a rubber gasket is provided between the inner wall of the steel cable clamping groove and the steel cable.

[0017] Preferably, a rubber gasket is provided between the inner wall of the clamp and the outer wall of the water supply pipe.

[0018] Preferably, the steel cable fixing seat is a T-shaped support with the horizontal side on top and the straight side facing downward for fixing the steel cable. The steel cable fixing seat is made of steel plate, and the steel cable fixing seat is anchored on the anchor pier with steel bars.

[0019] Preferably, a turnbuckle bolt with adjustable tightness is provided between the end of the steel cable and the steel cable fixing seat.

[0020] Preferably, the water supply pipeline adopts a wire mesh skeleton PE pipe, and the joints of adjacent water supply pipelines are hot-melt welded.

[0021] Preferably, at least one stainless steel expansion joint is provided in the water supply pipe above the anchor pier.

[0022] The present invention arranges full-length steel cables on both sides of the underwater section of the water supply pipeline to bear the gravity, impact force and tension originally borne by the pipeline itself, which can greatly reduce the stress on the pipeline and extend the service life of the water supply pipeline. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The present invention will be further described below in conjunction with the accompanying drawings.

[0024] Figure 1 It is a schematic diagram of the structure of a water outlet end of a water supply pipeline of the present invention.

[0025] Figure 2 It is a side view of a pier structure of the present invention.

[0026] Figure 3 It is a plan view of a pier structure of the present invention.

[0027] Figure 4 It is a schematic diagram of a stainless steel clamp on a water supply pipe of the present invention.

[0028] Figure 5 It is a cross-sectional view of the position of a stainless steel clamp of the present invention.

[0029] Figure 6 It is a schematic diagram of a concrete clamp on a water supply pipe of the present invention.

[0030] Figure 7It is a cross-sectional view of the position of a concrete hoop of the present invention.

[0031] In the figure: 1. anchor pier, 2. water supply pipe, 3. pipe guide groove, 4. stainless steel expansion joint, 5. steel cable fixing seat, 6. basket bolt, 7. steel cable, 8. water supply pipe joint, 9. stainless steel clamp, 10. rubber gasket, 11. steel cable clamp groove, 12. locking bolt, 13. concrete clamp, 14. embedded clamp, 15. hot melt welding device. DETAILED DESCRIPTION

[0032] The present invention will be further described below through specific embodiments in conjunction with the accompanying drawings.

[0033] Embodiment: A steel cable reinforcement structure for a water supply pipe in a water plant with large depth and complex terrain, such as Figure 1-7 This case has been implemented in the Qiandao Lake water supply project and continues to operate normally. This structure is suitable for the layout of water supply pipelines in waters with large depths and complex bottom terrain, such as Qiandao Lake.

[0034] The structure includes a water supply pipe 2 arranged across the waters of Qiandao Lake. A clamp is provided at intervals on the outer wall of the water supply pipe 2. A anchor pier 1 is cast on the shore at the corresponding positions of the two water outlets of the water supply pipe 2. The upper surface of the anchor pier is inclined. The water outlet of the water supply pipe is fixed by the anchor pier 1. Figure 1 , 2 As shown in Figure 3, a semicircular pipe guide groove 3 is provided in the center of the upper surface of the pier, and the water supply pipe 2 is arranged along the pipe guide groove 3. The bottom surface of the pipe guide groove 3 is evenly provided with embedded clamps 14. The embedded clamps 14 are half clamps. After the water supply pipe 2 is installed, it will naturally settle for 1-3 months, and then another half clamp will be used to cooperate with the embedded clamp 14 to lock the water supply pipe 2. At least one stainless steel expansion joint 4 is provided in the water supply pipe above the pier 1 to adapt to the small sinking of the water supply pipe.

[0035] The clamp of the outer wall of the water supply pipe 2 is formed by splicing two half hoops. The two half hoops have symmetrical structures. Splicing arms are extended outward at both ends of the half hoops. The splicing arms at both ends of the two half hoops are aligned and locked by locking bolts 12. The splicing arms of the two half hoops are relatively provided with steel cable clamping grooves 11, in which steel cables 7 are clamped; a rubber gasket 10 is provided between the inner wall of the steel cable clamping groove 11 and the steel cables 7. A rubber gasket 10 is provided between the inner wall of the clamp and the outer wall of the water supply pipe 2. The steel cables 7 are arranged along the length of both sides of the underwater section of the water supply pipe 2, and the steel cables are symmetrically arranged on both sides of the water supply pipe. Steel cable fixing seats 5 are symmetrically arranged on both sides of the lower part of the upper surface of the anchor pier 1, and the ends of the steel cables 7 are fixed on the steel cable fixing seats 5. The steel cable fixing seats 5 are T-shaped supports, with the horizontal side of the T-shaped supports on the top and the straight side facing down for fixing the steel cables 7. The steel cable fixing seats are made of steel plates, and the steel cable fixing seats are anchored on the anchor pier 1 with steel bars. A turnbuckle bolt 6 with adjustable tightness is arranged between the end of the steel cable 7 and the steel cable fixing seat 5 .

[0036] The clamps on the outer wall of the water supply pipe 2 include a stainless steel clamp 9 and a concrete clamp 13. Figure 4 , 5 As shown, the stainless steel clamp 9 is provided with locking bolts 12 on the inner and outer sides of the cable clamp groove 11. Figure 6 , 7 As shown, the concrete hoop 13 is provided with a locking bolt 12 on the outer side of the steel cable clamping groove 11 .

[0037] The water supply pipeline 2 adopts a wire mesh skeleton PE pipe, such as Figure 4 As shown, adjacent water supply pipe joints 8 are heat-melted by a heat-melt welding device 15. The closest distance between the clamp and the water supply pipe joint 8 is not less than 1 meter.

[0038] The stainless steel clamps 9 are arranged on the water supply pipe 2 at intervals of 2-4 meters, and the concrete clamps 13 are arranged on the water supply pipe 2 at intervals of 4-6 meters.

Claims

1. A steel cable reinforcement structure for a water supply pipe of a water plant in an underwater large depth and complex terrain, comprising a water supply pipe, wherein a clamp is provided at intervals on the outer wall of the water supply pipe, and anchor piers are cast on the shore at corresponding positions of the two water outlets of the water supply pipe, and the upper surface of the anchor pier is inclined, and the water outlet of the water supply pipe is fixed by the anchor pier, characterized in that: The clamp is formed by splicing two half hoops, and the two half hoops are symmetrical in structure. Splicing arms are respectively extended outward at both ends of the half hoops. The splicing arms at both ends of the two half hoops are respectively aligned and locked by locking bolts. The splicing arms of the two half hoops are oppositely provided with steel cable clamping grooves, and steel cables are clamped in the steel cable clamping grooves; the steel cables are arranged along the full length of both sides of the underwater section of the water supply pipeline, and the steel cables are symmetrically arranged on both sides of the water supply pipeline, and steel cable fixing seats are symmetrically arranged on both sides of the lower part of the upper surface of the anchor pier, and the ends of the steel cables are fixed on the steel cable fixing seats.

2. According to claim 1, a steel cable reinforcement structure for water supply pipes in a water plant with large underwater depth and complex terrain, characterized in that: The clamps include stainless steel clamps and concrete clamps.

3. The steel cable reinforcement structure for water supply pipes in a water plant with large underwater depth and complex terrain according to claim 2 is characterized by: The stainless steel clamping hoop split arm is provided with locking bolts on the inner side and the outer side of the cable clamping groove respectively.

4. The steel cable reinforcement structure for water supply pipes in a water plant with large underwater depth and complex terrain according to claim 2 is characterized by: The concrete hoop is provided with a locking bolt on the outer side of the steel cable clamping groove.

5. The steel cable reinforcement structure for water supply pipes in a water plant with large underwater depth and complex terrain according to claim 1 is characterized by: A rubber gasket is arranged between the inner wall of the steel cable clamping groove and the steel cable.

6. The steel cable reinforcement structure for water supply pipes in a water plant with large underwater depth and complex terrain according to claim 1 is characterized by: A rubber gasket is arranged between the inner wall of the clamp and the outer wall of the water supply pipe.

7. The steel cable reinforcement structure for water supply pipes in a water plant with large underwater depth and complex terrain according to claim 1 is characterized by: The steel cable fixing seat is a T-shaped support, the horizontal side of the T-shaped support is on the top, and the straight side is downward for fixing the steel cable. The steel cable fixing seat is made of steel plate, and the steel cable fixing seat is anchored on the pier with steel bars.

8. The steel cable reinforcement structure for water supply pipes in a water plant with large underwater depth and complex terrain according to claim 1 is characterized by: A turnbuckle bolt with adjustable tightness is arranged between the end of the steel cable and the steel cable fixing seat.

9. The steel cable reinforcement structure for water supply pipes in a water plant with large underwater depth and complex terrain according to claim 1 is characterized by: The water supply pipeline adopts a wire mesh skeleton PE pipe, and the joints of adjacent water supply pipelines are hot-melt welded.

10. The steel cable reinforcement structure for water supply pipes in a water plant with large underwater depth and complex terrain according to claim 1 is characterized by: At least one stainless steel expansion joint is arranged in the water supply pipe above the town pier.