Method for discharging melt from smelting furnace
By setting slag discharge ports and nickel discharge ports in the melting furnace and using cooling water sleeves and graphite bushings, the spray gun parameters are controlled and the melt is discharged at intervals, the furnace wall erosion caused by melt emission is solved, and the continuous production is achieved and safety, and extend the service life of the furnace wall and reduce production costs.
Patent Information
- Application Number
- CN202411157929.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-12
AI Technical Summary
Melt emissions in metallurgical processes cause severe erosion of the melting furnace discharge port, affecting the production cycle and safety, and the inability to form a spare slag nickel port, resulting in a short service life of the furnace wall and posing a safety hazard.
By setting the slag discharge port and nickel discharge port in the smelting furnace into the upper and lower rows, using a vertical cooling water jacket and an integrated graphite bushing, controlling the oxygen rich state and air volume of the spray gun, slag and low ice nickel are discharged at intervals, and the discharge port is extended to use life.
The continuity and safety of the smelting furnace production are achieved, the remaining service time of the discharge port is clarified, the service life of the furnace wall is extended, and the production cost is reduced.
Smart Images

Figure CN118936049A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of non-ferrous metal pyrometallurgical nickel smelting, and in particular to a method for discharging melt from a smelting furnace. Background Art
[0002] The discharge of the melt in the metallurgical process is related to many factors. The master controller of the smelting furnace needs to control the temperature in the smelting furnace, the height of the molten pool, the iron-silicon ratio and other process parameters to achieve conditions that are conducive to the discharge of the melt. In the process of discharging the melt, because the melt in the smelting furnace is extremely corrosive, the position of the discharge port of the smelting furnace is severely corroded and relatively weak, which seriously affects the production cycle and poses a safety hazard. Due to the separation of the slag-nickel port, a spare slag-nickel port cannot be formed, resulting in a short service life of the furnace wall and a safety hazard. Summary of the invention
[0003] In order to ensure the production continuity of the smelting furnace, clarify the remaining service life of the discharge port, ensure safe production and extend the production cycle, the present invention provides a method for discharging melt from a smelting furnace, by modifying the discharge port and changing the discharge mode to extend the service life of the furnace wall, specifically providing the following technical solutions:
[0004] A method for discharging a melt from a smelting furnace, wherein a device for discharging a melt from a smelting furnace comprises a slag discharge port and a nickel discharge port, wherein the slag discharge port and the nickel discharge port are arranged in a row. The method for discharging a melt comprises the following steps:
[0005] Step 1, controlling the amount of smelting furnace charge, fuel rate, oxygen-rich content of the spray gun, and controlling the spray gun air volume, oxygen air volume and sleeve air volume;
[0006] Step 2: When the spray gun position exceeds 1800mm, discharge the slag through the slag discharge port for 30-45 minutes, and discharge low nickel matte through the nickel discharge port at intervals of 10-15 minutes, with a discharge time of 8-15 minutes.
[0007] Preferably, both the slag discharge port and the nickel discharge port are provided with cooling water jackets, a vertical water jacket structure is adopted to fit the furnace wall, circulating cooling water is passed into the water jacket, and an integrated graphite bushing is used to penetrate the water jacket port and insert into the furnace wall.
[0008] Compared with the prior art, the present invention has the following beneficial effects:
[0009] 1. The discharge method provided by the present invention adopts a vertical discharge device, and the slag and nickel can be discharged separately by utilizing the characteristics of slag and nickel, thereby ensuring production continuity, clarifying the remaining use time of the discharge port, and ensuring safe production.
[0010] 2. The present invention integrates the transformation of the smelting discharge melt so that the slag discharge port and the nickel discharge port are in the upper and lower rows, and reduces the erosion of the discharge port furnace wall by combining opening and preparation. When one group reaches the end of its service life, it is immediately replaced by the next group for continued use. During use, the spare port can be filled with ramming material for maintenance to ensure the continuity of production. The discharge ports are all provided with cooling water jackets. The vertical water jackets greatly reduce the use temperature of the discharge ports and extend the life of the furnace wall, thereby achieving the purpose of extending the service life of the discharge port furnace wall, making the smelting furnace of the smelter efficient and safe, effectively extending the production time and reducing the production cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 The figure is a structural diagram of a device for discharging melt from a smelting furnace used in the present invention.
[0012] In the above figures, 1 is the slag discharge port, and 2 is the nickel discharge port. DETAILED DESCRIPTION
[0013] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0014] Example 1
[0015] The present invention provides a method for discharging melt from a smelting furnace, wherein the device for discharging melt from a smelting furnace is as follows: Figure 1 As shown, the device for discharging the melt in the smelting furnace includes a slag discharge port 1 and a nickel discharge port 2, which are arranged in an upper and lower row. Both the slag discharge port 1 and the nickel discharge port 2 are provided with cooling water jackets, and a vertical water jacket structure is adopted to fit the furnace wall. Circulating cooling water is introduced into the water jacket, and an integrated graphite bushing is used to penetrate the water jacket port and insert into the furnace wall.
[0016] The method for discharging a melt from a smelting furnace provided by the present invention comprises the following steps: feeding a material at a rate of 28 t / h to 35 t / h, controlling a fuel rate of 4500 kg / h to 5000 kg / h, spray gun oxygen enrichment at 42% to 48%, spray gun air volume at 9800 Nm3 / h to 11000 Nm3 / h, oxygen air volume at 4200 Nm3 / h to 5500 Nm3 / h, and sleeve air volume at 4600 Nm3 / h to 5000 Nm3 / h; observing Spray gun position: When the spray gun position is too high, contact the operator to burn the slag port, discharge the slag in the furnace from the slag discharge port 1, and flow into the sedimentation furnace; when the ice nickel surface in the furnace is too high, contact the operator to burn the nickel port, discharge the ice nickel in the furnace from the nickel discharge port 2, and flow into the sedimentation furnace. In actual production, when the spray gun position exceeds 1800mm, discharge the slag through the slag discharge port 1, the discharge time of the slag discharge port is 30 minutes, and the low ice nickel is discharged through the nickel discharge port 2 at intervals of 10 minutes, and the discharge time is 8 minutes. Repeat the slag and nickel discharge, check the erosion of the furnace wall at the discharge port, and generally replace the discharge port every 7-9 months to achieve the purpose of extending the production cycle. The slag discharge port and the nickel discharge port are in a row, and the erosion of the furnace wall of the discharge port is reduced by combining opening and preparation. When one group reaches the end of its service life, it is immediately replaced by the next group for continued use. During use, the spare port can be filled with ramming material for maintenance to ensure the continuity of production. The slag discharge port and the nickel discharge port are both provided with cooling water jackets. The vertical water jackets greatly reduce the operating temperature of the slag discharge port and the nickel discharge port, extend the life of the furnace wall, and achieve the purpose of extending the service life of the furnace wall of the discharge port, so that the smelting furnace of the smelter is efficient and safe, effectively extending the production time and reducing the production cost.
[0017] Example 2
[0018] Different from Example 1, when the spray gun position exceeds 1800mm, slag is discharged through the slag discharge port for 40 minutes, and low nickel matte is discharged through the nickel discharge port at intervals of 12 minutes for 10 minutes.
[0019] Example 3
[0020] Different from Example 1, when the spray gun position exceeds 1800mm, slag is discharged through the slag discharge port, and the discharge time of the slag discharge port is 45 minutes. Low nickel matte is discharged through the nickel discharge port at intervals of 15 minutes, and the discharge time is 15 minutes. The above is only a specific implementation method of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be obvious to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features applied for herein.
Claims
1. A method for discharging a melt from a smelting furnace, characterized in that: The device for discharging the melt from the smelting furnace used comprises a slag discharge port and a nickel discharge port, wherein the slag discharge port and the nickel discharge port are arranged in a row. The method for discharging the melt comprises the following steps: Step 1, controlling the feeding amount of the smelting furnace, the fuel rate, the oxygen rich content of the spray gun, and controlling the spray gun air volume, oxygen air volume and sleeve air volume; Step 2: When the spray gun position is too high, discharge the slag through the slag discharge port for 30-45 minutes, and discharge low nickel matte through the nickel discharge port at intervals of 10-15 minutes for 8-15 minutes.
2. A method for discharging a melt from a smelting furnace according to claim 1, characterized in that: Both the slag discharge port and the nickel discharge port are equipped with cooling water jackets. The vertical water jacket structure is fitted to the furnace wall. Circulating cooling water is passed into the water jacket, and an integrated graphite bushing is inserted into the furnace wall through the water jacket port.