Annular crane bracket mounting, positioning and checking method

By setting the reference points step by step and using a total station for measurement, combined with checking angle steel and reflective plates, the problem of large errors during the installation of the ring crane horns is solved, high-precision positioning inspection is achieved, and construction quality and progress are improved.

CN118936432AActive Publication Date: 2024-11-12CHINA NUCLEAR IND HUAXING CONSTR

Patent Information

Application Number
CN202410884783.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-03
Publication Date
2024-11-12
Estimated Expiration
2044-07-03

AI Technical Summary

Technical Problem

During the construction of nuclear power plants, there are problems such as large errors, high accuracy requirements and poor stability during the installation of ring cranes, especially when the tower height is large and the stability is poor, which affects the construction quality and progress.

Method used

A method of installation and positioning inspection of ring-hanging corff legs is adopted. By setting reference points step by step and using a total station for measurement, combined with the inspection of angle steel and reflective sheets, the axis and elevation of corff legs are accurately measured to ensure the accuracy and flatness of the installation position. , and improve measurement accuracy by forced centering the base and checking the angle steel.

Benefits of technology

It realizes the installation and positioning inspection of the ox leg with convenient measurement and high accuracy, reduces errors, improves construction quality and progress, and is flexible in the stand, does not occupy space in other construction processes, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118936432A_ABST
    Figure CN118936432A_ABST
Patent Text Reader

Abstract

The invention discloses a ring crane bracket mounting, positioning and checking method. The method comprises the steps of setting a first datum point on an equipment gate, erecting a total station, positioning an opposite first bracket mounting position, tapping and hoisting. Measuring the axis and the upper surface elevation of the first bracket; setting the upper surface of the first bracket as a second reference point as an elevation reference point; measuring coordinates of a second reference point through a total station at the first reference point, measuring a vertical angle and a distance, and calculating the elevation of an elevation reference point; erecting the total station on the second reference point, looking back the first reference point, and positioning a second bracket mounting position which is one third away from the second reference point from the circumference; and a hole is formed in the mounting position of the second bracket, hoisting is conducted, the axis and the upper surface elevation of the second bracket are measured, the upper surface of the second bracket is set as a third datum point after qualification, a fourth datum point is measured through the third datum point, and then the mounting positions of the other brackets are located respectively. According to the invention, the measurement precision is high, and the problem of high requirements on the mounting elevation and flatness of the bracket is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of nuclear power plant construction, and in particular to a method for installing, positioning and checking a ring-hanging corbel. Background Art

[0002] With the development of the national economy, the demand for energy is increasing, which has given nuclear power construction in my country a broad space and scale for development.

[0003] The bracket of the nuclear power plant is used to support the ring beam and is installed on the cylinder of the containment steel lining. The steel lining is a circular structure, and the bracket is high above the ground. When setting out, a center tower is generally used, and a total station is set up on the tower. According to the angle azimuth line, each position line is laid out. Whether the measurement and control work is perfect will directly affect the construction quality and progress of the bracket installation.

[0004] Since the tower is too high and has poor stability, it is difficult to ensure the accuracy requirements. The brackets are extremely densely distributed. During the ring hoisting operation, the ring hoisting brackets will bear huge dynamic loads, so the installation quality requirements are strict. How to reduce the error and improve the accuracy during the installation of the steel-lined ring hoisting bracket is a current problem; and when the bracket is installed, the containment concrete has not yet been poured, which makes the bracket easy to tilt forward during the installation process and difficult to adjust, which brings great difficulty to the measurement. Whether the measurement control work is perfect will directly affect the construction quality and progress of the bracket installation. Summary of the invention

[0005] The invention aims to provide a method for installing and positioning a ring-hanging corbel which is easy to use, can measure step by step and has high measuring accuracy.

[0006] The present invention is achieved through the following technical solutions:

[0007] A method for checking the installation and positioning of a ring-hanging corbel comprises the following steps:

[0008] Set the first reference point at the equipment gate, set up a total station at the first reference point, locate the first corbel installation position opposite the first reference point; drill a hole at the first corbel installation position, hoist and install the first corbel, and check the position;

[0009] Measure the axis and upper surface elevation of the first corbel; after passing the test, set the upper surface of the first corbel as the second reference point as the plane and elevation reference point; determine the coordinates of the second reference point by using the total station at the first reference point, measure the vertical angle and distance, and calculate the elevation of the elevation reference point;

[0010] Set up the total station at the second reference point, look back at the first reference point, locate the second corbel installation position that is one-third of the circumference of the ring hanging from the second reference point; drill a hole at the second corbel installation position, hoist and install the second corbel, and check the position, measure the axis and upper surface elevation of the second corbel, and after passing the test, set the upper surface of the second corbel as the third reference point, measure the coordinates of the third reference point through the total station at the second reference point, and measure the elevation of the third reference point;

[0011] Set up the total station at the third reference point, look back at the second reference point, locate the third corbel installation position that is one-third of the circumference of the ring hanging from the second reference point, drill a hole at the third corbel installation position, hoist and install the third corbel, and check the position, measure the axis and upper surface elevation of the third corbel, and after passing the test, set the upper surface of the third corbel as the fourth reference point, determine the coordinates of the fourth reference point by the total station at the third reference point, and measure the elevation of the fourth reference point;

[0012] The second reference point, the third reference point and the fourth reference point are used to measure and check the distance. If they are qualified, the first to fourth reference points are used to locate the installation positions of the remaining corbels respectively.

[0013] A plane reference point tooling is set at each reference point; a plane reference point tooling is set at each reference point; the plane reference point tooling for the first reference point is supported horizontally by a channel steel as a mobile base, with supporting angle steels on both sides, a forced centering disk set on the upper surface, a centering hole set in the center of the forced centering disk, and the centering hole is used to install the lower bolts of the total station; fixed steel bars are set at the bottom of the channel steel; the fixed steel bars are threadedly connected to the forced centering disk, and the bottom is connected and fixed to the channel steel by nuts and gaskets, the plane reference point tooling for the second, third and fourth reference points is composed of a forced centering base, a forced centering disk is set on the top of the forced centering base, a centering hole is set in the center, and the centering hole is used to install the lower bolts of the total station; three fixed steel bars are set at the bottom of the forced centering base; the fixed steel bars are threadedly connected to the forced centering base, and the lower part is spot welded to the surface of the corbel.

[0014] Select two common reference points inside and outside the ring hanging circle as check points. The common reference points are known control points. Use the total station at the first reference point to look back at the first common reference point, measure the distance and direction angle, aim at the second common reference point, measure the distance and azimuth, calculate the coordinates of the first reference point, input the calculated coordinate value, re-aim at the second common reference point, set the azimuth, and set the elevation value.

[0015] By locating the center of the reactor building and setting the azimuth line, a coordinate system is established to determine the azimuth of the bracket in the reactor building. The X-axis is the 0°-180° direction axis of the coordinate system plane, the Y-axis is the 270°-90° direction axis of the coordinate system plane, and the Z-axis is the center axis of the reactor.

[0016] When the hole is opened at the installation position of the corbel, the coordinates of the upper point on the wall where the corbel is designed to be installed are (X, Y, H), and the calculation is:

[0017] R=(X-X0)COSα+(Y-Y0)SINα

[0018] T=-(X-X0)SINα+(Y-Y0)COSα

[0019] Among them, (X0, Y0) is the coordinate of the center of the reactor building; α is the azimuth angle of the bracket in the reactor building; R is the distance from the wall where the bracket is designed to be installed to the center of the reactor building; T is the azimuth deviation value.

[0020] If the T value is greater than the accuracy threshold, move the bracket installation position in the opposite direction of the deviation value, re-measure the coordinates to calculate the deviation value, and if it meets the requirements, mark it as the upper point.

[0021] Use the same method to measure the coordinates of the lower point on the wall where the corbel is designed to be installed, mark the lower point, connect the upper point and the lower point, measure the elevation lines on the left and right of the connecting line, mark the connecting line, and drill a hole according to the size of the corbel; hoist and install the corbel.

[0022] The inspection angle steel is used as an inspection tool, and the length of the inspection angle steel is the width of the contact between the inner side of the corbel and the steel lining plate; two measuring reflectors are set on the side of the inspection angle steel, and the length of the measuring reflector plate is the outer width of the corbel, and the two measuring reflectors are symmetrically distributed around the center of the inspection angle steel, and the bottom of the measuring reflector plate is flush with the bottom of the inspection angle steel; during inspection, the inspection angle steel is placed on the inner side of the corbel close to the steel lining wall plate and the outer side of the corbel close to the center of the reactor, so that the two ends of the inspection angle steel are aligned with the inner side of the corbel for inspection, and the two measuring reflectors of the inspection angle steel are aligned with the outer side of the corbel for inspection.

[0023] When checking that the angle steel is placed on the outside of the corbel, measure the coordinates of the two reflective plates, obtain the first axis by the line connecting the midpoint of the coordinate average of the two reflective plates and the center of the reactor building, and measure the elevation of the upper surface of the outer side of the corbel; when checking that the angle steel is placed on the inner side of the corbel, measure the coordinates of the two reflective plates, obtain the second axis by the line connecting the midpoint of the coordinate average of the two reflective plates and the center of the reactor building, and measure the elevation of the upper surface of the inner side of the corbel; compare the deviation values ​​of the first axis and the second axis from the standard value, and the deviation values ​​of the upper surface elevation of the outer side of the corbel and the upper surface elevation of the inner side of the corbel from the standard value, and make corresponding adjustments if they do not meet the requirements, and fix them after they meet the requirements.

[0024] Compared with the prior art, the present invention has the following beneficial effects:

[0025] The present invention solves the difficult problems of corbel installation positioning inspection, especially the problem of high requirements for corbel installation elevation and flatness. The upper surface elevation is determined by inspection tooling, thereby ensuring the horizontal accuracy of the upper surface. Moreover, the mounting is flexible, the measurement is fast, the reference tooling mounting is unified, the inspection tool is easy to use, and the measurement accuracy is high.

[0026] Specifically, the ring hanging corbel installation positioning inspection method of the present invention has the following advantages:

[0027] 1. Convenient measurement. The instrument can be set up according to the construction sequence, or multiple groups can work simultaneously according to the needs to complete the entire installation positioning inspection work, which is conducive to ensuring the uniformity of measurement and avoiding the problems of the center frame of the positioning inspection total station setting up and the construction occupying the working surface, and the center frame height being too high affecting the accuracy;

[0028] 2. High measurement accuracy. The use of forced centering base and inspection angle steel can greatly improve the measurement accuracy. The coordinates of the center axis can be calculated by measuring the coordinates of the reflector on the inspection angle steel, and the overall position of the corbel can be accurately determined;

[0029] 3. Simple structure, easy processing, the inspection tool is composed of angle steel and reflective sheet, can be processed quickly, and the reference point base can be reused.

[0030] The invention has been tested on site and has reliable quality assurance, convenient and flexible construction, high precision, effectively ensuring the accuracy of positioning inspection, optimizing the construction progress, flexible station erection, and does not occupy the space of other construction processes, which helps to meet the needs of optimizing the construction progress and effectively meets the quality requirements for on-site construction. Compared with the original erection center point detection method, the construction efficiency is greatly improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 : Corbel plan layout

[0032] Figure 2 : Elevation drawing of the first reference point at the gate

[0033] Figure 3 :Plan view of the first reference point at the gate

[0034] Figure 4 : Plane diagram of the second, third and fourth reference points of the corbel

[0035] Figure 5 : Elevation diagram of the second, third and fourth reference points of the corbel

[0036] Figure 6 : Check the structural diagram of the angle steel.

[0037] In the figure, 1. corbel; 2. containment steel lining; 3. containment; 4. first reference point (equipment gate); 4-1. channel steel; 4-2. forced centering plate; 4-3. centering plate connecting screws; 4-4. connecting screw; 4-5. nut; 4-6. nut gasket; 4-7. total station; 4-8. supporting angle steel; 5. third reference point, 6. equipment gate; 7. equipment gate platform; 8. inspection angle steel; 8-1. ∠30×3 angle steel; 8-2. reflector, 9. second reference point, 10. fourth reference point. DETAILED DESCRIPTION

[0038] The above contents of the present invention are further described in detail below in the form of embodiments, but this should not be understood as the scope of the above subject matter of the present invention being limited to the following embodiments, and all technologies realized based on the above contents of the present invention belong to the scope of the present invention.

[0039] A method for checking the installation and positioning of a ring-hanging corbel comprises the following steps:

[0040] A first reference point 4 is set at the equipment gate 6, a total station 4-7 is set up at the first reference point 4, and the first bracket installation position opposite to the first reference point 4 is located; a hole is opened at the first bracket installation position, the first bracket is hoisted and installed, and the position is checked;

[0041] Measure the axis and upper surface elevation of the first corbel; after passing the test, set the upper surface of the first corbel as the second reference point as the plane and elevation reference point; determine the coordinates of the second reference point 9 by the total station 4-7 at the first reference point 4, measure the vertical angle and distance, and calculate the elevation of the elevation reference point;

[0042] Set up the total station 4-7 at the second reference point, look back at the first reference point 4, locate the second corbel installation position that is one-third of the circumference of the ring hanging from the second reference point 9; open a hole at the second corbel installation position, hoist and install the second corbel, and check the position, measure the axis and upper surface elevation of the second corbel, and after passing the test, set the upper surface of the second corbel as the third reference point 5, measure the coordinates of the third reference point 5 through the total station 4-7 at the second reference point, and measure the elevation of the third reference point 5;

[0043] Set up the total station 4-7 at the third reference point 5, look back at the second reference point 9, locate the third corbel installation position which is one third of the circumference of the ring hanging from the second reference point, drill a hole at the third corbel installation position, hoist and install the third corbel, and check the position, measure the axis line and upper surface elevation of the third corbel, and if qualified, set the upper surface of the third corbel as the fourth reference point 10, determine the coordinates of the fourth reference point 10 by the total station 4-7 at the third reference point 5, and measure the elevation of the fourth reference point 10; wherein, the fourth reference point 10 can also be located by the second reference point 9.

[0044] The second reference point 9, the third reference point 5 and the fourth reference point 10 are measured for distance verification. If qualified, the first to fourth reference points are used to locate the installation positions of the remaining corbels respectively.

[0045] Plane reference point tooling is set at each reference point; the plane reference point tooling of the first reference point 4 is supported horizontally by channel steel 4-1 as a mobile base, with supporting angle steels 4-8 on both sides, a forced centering plate 4-2 is set on the upper surface, a centering hole is set in the center of the forced centering plate 4-2, and the centering hole is used to install the lower bolts of the total station 4-7; fixed steel bars are set at the bottom of the channel steel 4-1; the fixed steel bars are threadedly connected to the forced centering plate 4-2, and the bottom is connected and fixed to the channel steel 4-1 by nuts 4-5 and gaskets. The plane reference point tooling of the second, third and fourth reference points is composed of a forced centering base, a forced centering plate 4-2 is set on the top of the forced centering base, a centering hole is set in the center, and the centering hole is used to install the lower bolts of the total station 4-7; three fixed steel bars are set at the bottom of the forced centering base; the fixed steel bars are threadedly connected to the forced centering base, and the lower part is spot welded to the surface of the corbel.

[0046] Select two common reference points inside and outside the ring hanging circle as check points. The common reference points are known control points. Use the total station 4-7 at the first reference point 4 to look back at the first common reference point, measure the distance and direction angle, aim at the second common reference point, measure the distance and azimuth, calculate the coordinates of the first reference point 4, input the calculated coordinate value, re-aim at the second common reference point, set the azimuth, and set the elevation value.

[0047] By locating the center of the reactor building and setting the azimuth line, a coordinate system is established to determine the azimuth of the bracket in the reactor building. The X-axis is the 0°-180° direction axis of the coordinate system plane, the Y-axis is the 270°-90° direction axis of the coordinate system plane, and the Z-axis is the center axis of the reactor.

[0048] When the hole is opened at the installation position of the corbel, the measurement coordinates of the upper point on the wall where the corbel is designed to be installed are (X, Y, H), and the calculation is:

[0049] R=(X-X0)COSα+(Y-Y0)SINα

[0050] T=-(X-X0)SINα+(Y-Y0)COSα

[0051] Among them, (X0, Y0) is the coordinate of the center of the reactor building; α is the azimuth angle of the bracket in the reactor building; R is the distance from the wall where the bracket is designed to be installed to the center of the reactor building; T is the azimuth deviation value.

[0052] If the T value is greater than the accuracy threshold, move the bracket installation position in the opposite direction of the deviation value, re-measure the coordinates to calculate the deviation value, and if it meets the requirements, mark it as the upper point.

[0053] Use the same method to measure the coordinates of the lower point on the wall where the corbel is designed to be installed, mark the lower point, connect the upper point and the lower point, measure the elevation lines on the left and right of the connecting line, mark the connecting line, and drill a hole according to the size of the corbel; hoist and install the corbel.

[0054] The inspection angle steel 8 is used as an inspection tool, and the length of the inspection angle steel 8 is the width of the contact between the inner side of the corbel and the steel lining plate; two measuring reflectors 8-2 are set on the side of the inspection angle steel 8, and the length of the measuring reflector plate 8-2 is the outer width of the corbel, and the two measuring reflectors 8-2 are symmetrically distributed around the center of the inspection angle steel 8, and the bottom of the measuring reflector plate 8-2 is flush with the bottom of the inspection angle steel 8; during inspection, the inspection angle steel 8 is placed on the inner side of the corbel close to the steel lining wall plate and the outer side of the corbel close to the center of the reactor, so that the two ends of the inspection angle steel 8 are aligned with the inner side of the corbel for inspection, and the two measuring reflectors 8-2 of the inspection angle steel 8 are aligned with the outer side of the corbel for inspection.

[0055] When checking that the angle steel 8 is placed on the outside of the corbel, measure the coordinates of the two reflective sheets 8-2, obtain the first axis by the line connecting the midpoint of the coordinate average value of the two reflective sheets 8-2 and the center of the reactor building, and measure the elevation of the upper surface of the outer side of the corbel; when checking that the angle steel 8 is placed on the inner side of the corbel, measure the coordinates of the two reflective sheets 8-2, obtain the second axis by the line connecting the midpoint of the coordinate average value of the two reflective sheets 8-2 and the center of the reactor building, and measure the elevation of the upper surface of the inner side of the corbel; compare the deviation values ​​of the first axis and the second axis from the standard value, and the deviation values ​​of the upper surface elevation of the outer side of the corbel and the upper surface elevation of the inner side of the corbel from the standard value, and make corresponding adjustments if they do not meet the requirements, and fix them after they meet the requirements.

[0056] The present invention is further described in detail below in conjunction with specific embodiments:

[0057] The coordinate measurement in the embodiments all adopts the total station 4-7, and the elevation measurement in the embodiments all adopts the precision level.

[0058] The steel lining of a nuclear power plant has a radius of R23.4m and a circumference of 147064mm. There are a total of 45 ring-hanging brackets, each weighing 4.5t. The ring-hanging brackets are evenly distributed at the +37.82m elevation of the steel lining wall plate, and are evenly distributed at intervals of 3.268m (8°) along the steel lining wall plate. The width of the bracket at the contact point with the steel lining is 950mm, and the other side is 565mm. The center elevation of the equipment gate 6 is +20.800m. The positioning inspection process is as follows:

[0059] 1. Set the first reference point 4 at the equipment gate 6. The first reference point 4 is set at the equipment gate 6. It is supported horizontally by the No. 8 channel steel 4-1 as a mobile base, and the double-sided ∠50×5 support angle steel 4-8 is set. The upper surface is provided with a forced centering plate 4-2. The centering plate is made of a 20mmΦ200 stainless steel round plate with a centering hole in the center. The lower part is provided with 3 supporting and fixing Φ16 steel bars. The steel bar is M14 threaded and the centering plate is provided with M14 screw holes for connection. The lower part is connected and fixed with the channel steel 4-1 by nuts 4-5 and washers.

[0060] 2. Locate the reference point opposite the bracket 1, set up the total station 4-7 at the first reference point 4, look back at the first common reference point, measure the distance and azimuth, look back at a known point RXA (7007.0604, 2987.5401), measure the coordinates and distance 16.8326m, azimuth 12°13'26.2", rotate clockwise to aim at the second common reference point, measure the distance and azimuth, and measure another known point RXB (6990.6224, 2991.3722 ) coordinates and distance 14.6395m, azimuth 76°38'55.5"; calculate the coordinates of the measuring site RXJ1 (6993.8603, 2977.0953) according to the measured values; calculate the coordinates of the first reference point 4, enter the calculated coordinate values, re-aim at the second common reference point, set the azimuth 102°46'41.2", and set the elevation value; measure the upper coordinates of the bull leg position (7005.8987, 3022.6754, 38.6505), and calculate:

[0061] R=(7005.8987-7000)COS75.5°+(3022.6754-3000)SIN75.5°=23.4301m

[0062] T=-(7005.8987-7000)SIN75.5°+(3022.6754-3000)COS75.5°=-0.0333m

[0063] (X0, Y0) The center coordinates of the reactor building are (7000, 3000), and the azimuth angle α of the bracket in the reactor building is 75.5°;

[0064] T value -0.0333m, greater than the accuracy requirement, the clockwise movement deviation value is 0.0333m, and the measured coordinates are (7005.8684, 3002.6851, 38.6515)

[0065] Calculate the deviation value

[0066] R=(7005.8684-7000)COS75.5°+(3022.6851-3000)SIN75.5°=23.4319m

[0067] T=-(7005.8684-7000)SIN75.5°+(3022.6851-3000)COS75.5°=-0.0016m

[0068] Meet the requirements and mark the points;

[0069] According to the above steps, the coordinates of the lower point are (7005.8652, 3022.6841, 36.8451), and the calculated deviation value is R = (7005.8652-7000)COS75.5°+(3022.6841-3000)SIN75.5°=23.4301m

[0070] T=-(7005.8652-7000)SIN75.5°+(3022.6841-3000)COS75.5°=0.0013m

[0071] Meet the requirements and mark the points;

[0072] Mark the connection points; measure the elevation lines on the left and right of the connection, mark the connection, and drill holes according to the size of the corbel; hoist and install the corbel;

[0073] 3. Position inspection, measure the axis of the corbel and the elevation of the upper surface; align the left and right reflective sheets 8-2 of the inspection tool with the left and right edges of the corbel, and measure the coordinates of the reflective sheet 8-2. The inspection tool is the inspection angle steel 8, the angle steel model is ∠30×3, and the length is 950mm, the width of the contact between the inner side of the corbel and the steel lining plate; two measuring reflective sheets 8-2 are set on the side of the angle steel, and one is set on the top of the outer width of the corbel, located 282.5mm on both sides of the center, and the bottom of the reflective sheet 8-2 is flush with the bottom of the angle steel; measure the coordinates of the two reflective sheets 8-2 at the center of the corbel near the reactor

[0074] (7005.8405, 3021.4509, 37.8205),

[0075] (7005.2936, 3021.5928, 37.8231),

[0076] Converted coordinates

[0077] (22.2300, -0.2836, 37.8205)

[0078] (22.2304, 0.2814, 37.8231)

[0079] Corbel axis = (-0.2836 + 0.2814) / 2 = -0.0011

[0080] Measure the 8-2 coordinates of the two reflectors where the corbel is located against the steel lining wall panel.

[0081] (7006.1302, 3022.5833, 37.8232)

[0082] (7005.5825, 3022.7211, 37.8235)

[0083] Converted coordinates

[0084] (23.3988, -0.2805, 37.8232)

[0085] (23.3951, 0.2842, 37.8235)

[0086] Corbel axis = (-0.2805 + 0.2842) / 2 = 0.0018m

[0087] Axis deviation -0.0011, 0.0018 meets the requirements

[0088] Elevation deviation: MAX(37.8205, 37.8231, 37.8232, 37.8235)-MIN(37.8205, 37.8231, 37.8232, 37.8235)=0.0030m

[0089] Meet the requirements

[0090] Welding and fixing after meeting the requirements

[0091] 4. After passing the test, weld and fix the corbel, set the second plane reference point 9 tooling and elevation reference point on the upper surface of the corbel. The reference point is set at the observation stand on the outer side of the upper surface of the corbel. A forced centering plate 4-2 is set on the upper surface. The centering plate is made of a 20mmΦ200 stainless steel round plate with a centering hole in the center. Three Φ16 supporting and fixing steel bars are set at the bottom. The steel bars are connected to the centering plate with M14 threads, and the lower part is spot welded to the surface of the corbel. Determine the plane coordinates of the second reference point 5 RXJ2 (7005.4168, 3021.6741); use the total station 4-7 to measure the vertical angle of 21°49ˊ38.8″ and the distance of 46.0523, and calculate the elevation of the elevation reference point 46.0523tg (21°49ˊ38.8″) + 19.7298-0.2031 = 37.9719m

[0092] The instrument elevation is 19.7298m, and the prism height is 0.2031m;

[0093] 5. Set up the second reference point 9 tooling of the total station 4-7 on the corbel plane, look back at the first reference point 4, set the azimuth angle to 255°28ˊ00.1″, locate the corbel one-third of the circumference from the second reference point 5, open a hole, hoist and install, check the position, and measure the corbel axis and upper surface elevation, using the same method as step 2;

[0094] 6. After passing the test, set the third reference point 5 tooling on the corbel, and use a precision level to measure the elevation reference point; determine the plane coordinates of the third reference tooling RXJ3 (7016.0510, 2984.5035, 37.9705); locate another corbel that is one-third of the circumference away from the reference point, open a hole, hoist and install, check the position, and measure the corbel axis and upper surface elevation, using the same method as step 2;

[0095] 7. After passing the test, set the fourth reference point 10 tooling on the corbel, use a precision level to measure the elevation reference point, and determine the plane coordinates of the fourth reference tooling RXJ4 (6978.5542, 2993.8476, 37.9711), the method is the same as step 2;

[0096] 8. Second, third and fourth reference point measurement distance verification

[0097] RXJ2-RXJ3 theory = 38.6619m, RXJ2-RXJ3 actual = 38.6632m, deviation 38.6619-38.6632 = -0.0013m RXJ2-RXJ4 theory = 38.6670m, RXJ2-RXJ4 actual = 38.6659m, deviation 38.6670-38.6659 = 0.0011m RXJ3-RXJ4 theory = 38.6435m; RXJ3-RXJ4 actual = 38.6442m, deviation 38.6435-38.6442 = -0.0007m The deviations are all less than 2mm, meeting the accuracy requirements;

[0098] 9. After passing the test, locate other corbels on the second, third and fourth reference points respectively, drill holes, install and hoist, check the positions, and measure the corbel axis and upper surface elevation until passing the test. The method is the same as step five.

[0099] The present invention has high measurement accuracy. It adopts a forced centering base. The point accuracy of instrument installation is improved from 1mm to 0.3mm. By adopting an inspection tool, the accuracy can reach 0.5mm. The coordinates of the central axis can be calculated by measuring the coordinates, and the overall position of the corbel can be accurately determined.

[0100] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any technician familiar with the profession, without departing from the scope of the technical solution of the present invention, according to the technical essence of the present invention, any simple modification, equivalent replacement and improvement made to the above embodiment still falls within the protection scope of the technical solution of the present invention.

Claims

1. A method for checking the installation and positioning of a ring-hanging corbel, characterized in that: The following steps are involved: Set the first reference point at the equipment gate, set up a total station at the first reference point, locate the first corbel installation position opposite the first reference point; drill a hole at the first corbel installation position, hoist and install the first corbel, and check the position; Measure the axis and upper surface elevation of the first corbel; after passing the test, set the upper surface of the first corbel as the second reference point as the plane and elevation reference point; determine the coordinates of the second reference point by using the total station at the first reference point, measure the vertical angle and distance, and calculate the elevation of the elevation reference point; Set up the total station at the second reference point, look back at the first reference point, locate the second corbel installation position that is one-third of the circumference of the ring hanging from the second reference point; drill a hole at the second corbel installation position, hoist and install the second corbel, and check the position, measure the axis and upper surface elevation of the second corbel, and after passing the test, set the upper surface of the second corbel as the third reference point, measure the coordinates of the third reference point through the total station at the second reference point, and measure the elevation of the third reference point; Set up the total station at the third reference point, look back at the second reference point, locate the third corbel installation position that is one-third of the circumference of the ring hanging from the second reference point, drill a hole at the third corbel installation position, hoist and install the third corbel, and check the position, measure the axis and upper surface elevation of the third corbel, and after passing the test, set the upper surface of the third corbel as the fourth reference point, determine the coordinates of the fourth reference point by the total station at the third reference point, and measure the elevation of the fourth reference point; The second reference point, the third reference point and the fourth reference point are used to measure and check the distance. If they are qualified, the first to fourth reference points are used to locate the installation positions of the remaining corbels respectively.

2. The method for installing and positioning a ring-hanging corbel according to claim 1 is characterized in that: A plane reference point tooling is set at each reference point; the plane reference point tooling of the first reference point is supported horizontally by a channel steel as a mobile base, with supporting angles on both sides, a forced centering disk on the upper surface, a centering hole in the center of the forced centering disk, and the centering hole is used to install the lower bolts of the total station; fixed steel bars are set at the bottom of the channel steel; the fixed steel bars are threadedly connected to the forced centering disk, and the bottom is connected and fixed to the channel steel by nuts and gaskets. The plane reference point tooling of the second, third and fourth reference points is composed of a forced centering base, a forced centering disk is set on the top of the forced centering base, a centering hole is set in the center, and the centering hole is used to install the lower bolts of the total station; three fixed steel bars are set at the bottom of the forced centering base; the fixed steel bars are threadedly connected to the forced centering base, and the lower part is spot welded to the surface of the corbel.

3. The method for installing and positioning a ring-hanging corbel according to claim 1, characterized in that: Select two common reference points inside and outside the ring hanging circle as check points. The common reference points are known control points. Use the total station at the first reference point to look back at the first common reference point, measure the distance and direction angle, aim at the second common reference point, measure the distance and azimuth, calculate the coordinates of the first reference point, input the calculated coordinate value, re-aim at the second common reference point, set the azimuth, and set the elevation value.

4. The method for installing and positioning a ring-hanging corbel according to claim 1 is characterized in that: By locating the center of the reactor building and setting the azimuth line, a coordinate system is established to determine the azimuth of the bracket in the reactor building. The X-axis is the 0°-180° direction axis of the coordinate system plane, the Y-axis is the 270°-90° direction axis of the coordinate system plane, and the Z-axis is the center axis of the reactor.

5. The method for installing and positioning a ring-hanging corbel according to claim 4 is characterized in that: When the hole is opened at the installation position of the corbel, the measurement coordinates of the upper point on the wall where the corbel is designed to be installed are (X, Y, H), and the calculation is: R=(X-X0)COSα+(Y-Y0)SINα T=-(X-X0)SINα+(Y-Y0)COSα Among them, (X0, Y0) is the coordinate of the center of the reactor building; α is the azimuth angle of the bracket in the reactor building; R is the distance from the wall where the bracket is designed to be installed to the center of the reactor building; T is the azimuth deviation value. If the T value is greater than the accuracy threshold, move the bracket installation position in the opposite direction of the deviation value, re-measure the coordinates to calculate the deviation value, and if it meets the requirements, mark it as the upper point.

6. The method for checking the installation and positioning of the ring-hanging corbel according to claim 5 is characterized in that: Use the same method to measure the coordinates of the lower point on the wall where the corbel is designed to be installed, mark the lower point, connect the upper point and the lower point, measure the elevation lines on the left and right of the connecting line, mark the connecting line, and drill a hole according to the size of the corbel; hoist and install the corbel.

7. The method for installing and positioning a ring-hanging corbel according to claim 1, characterized in that: The inspection angle steel is used as an inspection tool, and the length of the inspection angle steel is the width of the contact between the inner side of the corbel and the steel lining plate; two measuring reflectors are set on the side of the inspection angle steel, and the length of the measuring reflector plate is the outer width of the corbel, and the two measuring reflectors are symmetrically distributed around the center of the inspection angle steel, and the bottom of the measuring reflector plate is flush with the bottom of the inspection angle steel; during inspection, the inspection angle steel is placed on the inner side of the corbel close to the steel lining wall plate and the outer side of the corbel close to the center of the reactor, so that the two ends of the inspection angle steel are aligned with the inner side of the corbel for inspection, and the two measuring reflectors of the inspection angle steel are aligned with the outer side of the corbel for inspection.

8. The method for checking the installation and positioning of the ring-hanging corbel according to claim 7 is characterized in that: When checking that the angle steel is placed on the outside of the corbel, measure the coordinates of the two reflective plates, obtain the first axis by the line connecting the midpoint of the coordinate average of the two reflective plates and the center of the reactor building, and measure the elevation of the upper surface of the outer side of the corbel; when checking that the angle steel is placed on the inner side of the corbel, measure the coordinates of the two reflective plates, obtain the second axis by the line connecting the midpoint of the coordinate average of the two reflective plates and the center of the reactor building, and measure the elevation of the upper surface of the inner side of the corbel; compare the deviation values ​​of the first axis and the second axis from the standard value, and the deviation values ​​of the upper surface elevation of the outer side of the corbel and the upper surface elevation of the inner side of the corbel from the standard value, and make corresponding adjustments if they do not meet the requirements, and fix them after they meet the requirements.

Citation Information

Patent Citations

  • Mounting structure and mounting method of ring crane bracket

    CN106836829A

  • Nuclear power station polar bridge crane control network, and establish method thereof

    CN108278998A

  • Steel lining bracket positioning method

    CN113324532A

  • Method for quickly installing supporting bracket on LNG ship tail shaft section and tail shaft section

    CN115158584A

  • Simple positioning method for mounting arch rib bracket of steel pipe arch truss

    CN116638246A

Cited By

  • Narrow space positioning method based on double lifting measuring devices

    CN120721048A

  • A narrow space positioning method based on double-lift measuring device

    CN120721048B