Pipeline sealing test and water adding integrated device

By designing integrated pipeline dense testing and water addition devices, the inflatable components and inspection components are used to quickly detect pipeline denseness, which solves the water leakage problem during water addition in the air conditioner circulating water system, shortens the construction period and avoids equipment damage.

CN118936790APending Publication Date: 2024-11-12CSSC HUANGPU WENCHONG SHIPBUILDING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411003969.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-11-12

Smart Images

  • Figure CN118936790A_ABST
    Figure CN118936790A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of pipeline testing, in particular to a pipeline sealing testing and water adding integrated device which comprises a communicating pipe, the communicating pipe is provided with a first branch pipe and a second branch pipe, the first branch pipe and the second branch pipe are both communicated with the communicating pipe, and one end of the communicating pipe can be communicated with a to-be-tested pipeline; the inflation assembly is communicated with the first branch pipe and used for inflating compressed gas into the to-be-tested pipeline, and a first switch valve is arranged between the inflation assembly and the first branch pipe in a series connection mode; the detection assembly is arranged on the second branch pipe and used for testing the air pressure or the water pressure of the to-be-tested pipeline; the water inlet pipe is communicated with the other end of the communicating pipe, and a second switch valve is arranged on the water inlet pipe. According to the invention, the tightness of the pipeline can be rapidly detected, so that a utility test is completed, the construction period can be shortened, and equipment damage is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pipeline testing, and in particular to an integrated pipeline tightness testing and water adding device. Background Art

[0002] During the shipbuilding process, after the piping system is installed and connected completely, an overall effectiveness test needs to be carried out, and the piping system needs to be filled with oil or water. Taking the air conditioning circulating water system as an example, it is necessary to carry out effectiveness tests on air conditioners, fan coil units and other equipment. According to the current construction process, after the integrity of the air conditioning circulating water system is handed over to the commissioning stage, the commissioning personnel will connect the water pump or the fire hose on the ship to the pipeline to add water to the pipeline. During the water adding process, the pipeline often leaks.

[0003] There are two main reasons for water leakage: First, the air conditioning circulating water system is widely distributed, involving many construction teams and work areas. Each construction team is only responsible for the installation and tightness test of the pipelines in its own area. Therefore, when the integrity of the entire air conditioning circulating water system is handed over, the docking interfaces constructed by each team are not tightly tested. Second, some equipment arrives and leaves the warehouse late, and the equipment has not been installed when the pipeline is tightly tested. Only blind plates can be installed at the connecting pipes, and the connecting pipes cannot be tightly tested. For the above reasons, the air conditioning circulating water system is prone to water leakage at the pipe docking interfaces and the connecting ports when adding water.

[0004] When water leakage occurs, the only way is to find the leak point and drain the water, find a plumber to repair the pipeline, and then re-add water for debugging after the repair. This not only delays the construction period and wastes working hours, but sometimes also causes water intrusion and damage to the equipment.

[0005] Therefore, a pipeline tightness test and water adding integrated device is needed to solve the above problems. Summary of the invention

[0006] The purpose of the present invention is to provide an integrated device for pipeline tightness testing and water adding, which can quickly detect the tightness of the pipeline, thereby completing the effectiveness test, shortening the construction period and avoiding equipment damage.

[0007] To achieve this object, the present invention adopts the following technical solutions:

[0008] Integrated device for pipeline tightness test and water addition, including:

[0009] A connecting pipe, wherein the connecting pipe is provided with a first branch pipe and a second branch pipe, the first branch pipe and the second branch pipe are both connected to the connecting pipe, and one end of the connecting pipe can be connected to the pipeline to be tested;

[0010] An inflatable component, the inflatable component is connected to the first branch pipe and is used to fill the pipeline to be tested with compressed gas, and a first switch valve is arranged in series between the inflatable component and the first branch pipe;

[0011] A detection component, arranged on the second branch pipe, for testing the air pressure or water pressure of the pipeline to be tested;

[0012] A water inlet pipe is connected to the other end of the connecting pipe, and a second switch valve is arranged on the water inlet pipe.

[0013] Furthermore, the inflation assembly includes a motor and an air compressor, the motor is transmission-connected to the air compressor, and the air compressor is connected to the first branch pipe.

[0014] Furthermore, the air compressor is connected to the first branch pipe through an air intake pipe, and the first switch valve is connected to the air intake pipe and the first branch pipe respectively.

[0015] Furthermore, the end of the air intake pipe away from the first switch valve has a first connecting joint, and the first connecting joint is connected to the air compressor.

[0016] Furthermore, it also includes a supporting frame, in which the motor and the air compressor are both fixedly arranged.

[0017] Furthermore, the detection component includes a pressure gauge, and the pressure gauge is connected to the second branch pipe.

[0018] Furthermore, a third switch valve is provided between the pressure gauge and the second branch pipe, and the third switch valve is respectively connected to the second branch pipe and the pressure gauge.

[0019] Furthermore, a connecting flange is fixedly provided at one end of the connecting pipe away from the water inlet pipe.

[0020] Furthermore, the connecting flange and the connecting pipe are an integrated structure.

[0021] Furthermore, a second connecting joint is provided at one end of the water inlet pipe away from the connecting pipe, and the second connecting joint is used for docking with a water pump.

[0022] Beneficial effects of the present invention:

[0023] The present invention provides a pipeline tightness test and water-adding integrated device, wherein a first branch pipe and a second branch pipe are arranged on a connecting pipe, an air-filling assembly is connected to the first branch pipe, and is used to fill compressed gas into the pipeline to be tested, and a first switch valve is arranged in series between the air-filling assembly and the first branch pipe. A detection assembly is arranged on the second branch pipe, and is used to test the air pressure or water pressure of the pipeline to be tested. The water inlet pipe is connected to the other end of the connecting pipe, and a second switch valve is arranged on the water inlet pipe. When the pipeline to be tested is tested for tightness, the air-filling assembly and the first switch valve are opened, and the second switch valve is closed at the same time. After a certain amount of compressed air is filled into the pipeline to be tested, the air-filling assembly and the first switch valve are closed, and the air pressure change is detected by the detection assembly to determine whether there is a leak. After the test is qualified, the first switch valve is closed, and the second switch valve is opened, and the water inlet pipe can be used to fill water into the pipeline to be tested. Through the above arrangement, the tightness of the pipeline can be quickly detected, thereby completing the utility test, and the construction period can be shortened to avoid water damage to the equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments of the present invention. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the contents of the embodiments of the present invention and these drawings without paying any creative work.

[0025] Figure 1 It is a schematic diagram of a pipeline tightness test and water adding integrated device of the present invention.

[0026] In the figure:

[0027] 1. Connecting pipe; 11. First branch pipe; 12. Second branch pipe; 13. Connecting flange; 2. Inflating assembly; 21. Motor; 22. Air compressor; 23. Support frame; 3. Water inlet pipe; 31. Second connecting joint; 4. Air inlet pipe; 41. First connecting joint; 5. First switch valve; 6. Second switch valve; 7. Third switch valve; 8. Detection assembly; 81. Pressure gauge. DETAILED DESCRIPTION

[0028] Before any embodiments of the application are explained in detail, it is to be understood that the application is not limited in its application to the details of construction and the arrangement of components set forth in the following description or illustrated in the above drawings.

[0029] In this application, the terms "comprises", "includes", "has" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device that includes a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of more restrictions, an element defined by the sentence "comprises a ..." does not exclude the presence of other identical elements in the process, method, article or device that includes the element.

[0030] In the present application, the terms "connect", "combine", "couple", and "install" may refer to direct connection, combination, coupling, or installation, or indirect connection, combination, coupling, or installation. For example, direct connection refers to two parts or components being connected together without the need for an intermediate piece, and indirect connection refers to two parts or components being connected to at least one intermediate piece respectively, and the two parts or components being connected via the intermediate piece. In addition, "connect" and "couple" are not limited to physical or mechanical connections or couplings, and may include electrical connections or couplings.

[0031] In the present application, it will be understood by those of ordinary skill in the art that relative terms (e.g., "about," "approximately," "substantially," etc.) used in conjunction with quantities or conditions include the values ​​and have the meaning indicated by the context. For example, the relative terms include at least the degree of error associated with the measurement of a specific value, the tolerances caused by manufacturing, assembly, and use associated with a specific value, and the like. Such terms should also be considered to disclose a range defined by the absolute values ​​of the two endpoints. Relative terms may refer to plus or minus a certain percentage (e.g., 1%, 5%, 10% or more) of the indicated value. Numerical values ​​that do not use relative terms should also be disclosed as specific values ​​with tolerances. In addition, "substantially" may refer to plus or minus a certain degree (e.g., 1 degree, 5 degrees, 10 degrees or more) on the basis of the indicated angle when expressing a relative angular position relationship (e.g., substantially parallel, substantially perpendicular).

[0032] In this application, it will be understood by those skilled in the art that the function performed by a component can be performed by one component, multiple components, one part, or multiple parts. Similarly, the function performed by a part can also be performed by one part, one component, or a combination of multiple parts.

[0033] In the present application, the terms "upper", "lower", "left", "right", "front", "back" and other directional words are described based on the orientation and positional relationship shown in the accompanying drawings, and should not be understood as limiting the embodiments of the present application. In addition, in the context, it is also necessary to understand that when it is mentioned that an element is connected to another element "upper" or "lower", it can not only be directly connected to another element "upper" or "lower", but also indirectly connected to another element "upper" or "lower" through an intermediate element. It should also be understood that directional words such as upper side, lower side, left side, right side, front side, back side, etc. not only represent the positive orientation, but can also be understood as the lateral orientation. For example, the bottom can include directly below, lower left, lower right, lower front, and lower back, etc.

[0034] In the process of ship construction, in order to quickly test the tightness of the pipeline, so as to complete the effectiveness test, shorten the construction period and avoid equipment damage, such as Figure 1 As shown, the present invention provides a pipeline tightness test and water adding integrated device. The pipeline tightness test and water adding integrated device comprises a connecting pipe 1, an air filling component 2, a detection component 8 and a water inlet pipe 3.

[0035] Among them, the connecting pipe 1 is fixedly provided with a first branch pipe 11 and a second branch pipe 12, both of which are connected to the connecting pipe 1, and one end of the connecting pipe 1 can be connected to the pipeline to be tested. The inflation component 2 is connected to the first branch pipe 11, and is used to fill the pipeline to be tested with compressed gas, and a first switch valve 5 is arranged in series between the inflation component 2 and the first branch pipe 11. The detection component 8 is arranged on the second branch pipe 12, and is used to test the air pressure or water pressure of the pipeline to be tested. The water inlet pipe 3 is connected to the other end of the connecting pipe 1, and a second switch valve 6 is arranged on the water inlet pipe 3.

[0036] When conducting a tightness test on the pipeline to be tested, open the inflation component 2 and the first switch valve 5, and close the second switch valve 6 at the same time. After a certain amount of compressed air is filled into the pipeline to be tested, close the inflation component 2 and the first switch valve 5, and detect the air pressure change through the detection component 8 to determine whether there is a leak. After the test is qualified, close the first switch valve 5, open the second switch valve 6, and then use the water inlet pipe 3 to fill water into the pipeline to be tested. Through the above settings, the tightness of the pipeline can be quickly tested, thereby completing the utility test, and the construction period can be shortened to avoid water damage to the equipment.

[0037] Furthermore, the inflation component 2 includes a motor 21 and an air compressor 22, the motor 21 is transmission-connected to the air compressor 22, and the air compressor 22 is connected to the first branch pipe 11. The air compressor 22 is driven by the motor 21 to work, so that compressed air is introduced into the pipeline to be tested for tightness testing. Since the pressure can be quickly increased during the test, the gas fills the pipeline to be tested, and the detection component 8 can be used to effectively detect the air pressure change of the pipeline to be tested, so as to quickly determine whether there is a leak. Through the above arrangement, the tightness of the pipeline can be quickly detected, thereby completing the utility test, and the construction period can be shortened. Moreover, since the equipment does not need to be immersed in water, damage to the equipment is avoided.

[0038] Furthermore, the air compressor 22 is connected to the first branch pipe 11 through the air intake pipe 4, and the first switch valve 5 is respectively connected to the air intake pipe 4 and the first branch pipe 11. By setting the air intake pipe 4, it is convenient for the air compressor 22 to be connected to the first branch pipe 11. By controlling the switch of the first switch valve 5, it can be controlled whether to ventilate the pipeline to be tested.

[0039] Furthermore, the end of the air intake pipe 4 away from the first switch valve 5 has a first connection joint 41, and the first connection joint 41 is connected to the air compressor 22. By providing the first connection joint 41, the air intake pipe 4 and the air compressor 22 are conveniently connected.

[0040] Furthermore, the pipeline tightness test and water adding integrated device also includes a support frame 23, and the motor 21 and the air compressor 22 are fixedly arranged in the support frame 23. By providing the support frame 23, it is convenient to install the motor 21 and the air compressor 22. Moreover, it is convenient to move during use.

[0041] Further, the detection component 8 includes a pressure gauge 81, and the pressure gauge 81 is connected to the second branch pipe 12. In the present embodiment, the pressure gauge 81 can detect air pressure and water pressure. After the air is inflated to the set time, the first switch valve 5 and the inflatable component 2 are closed, and the pressure gauge 81 detects the air pressure in the pipeline to be tested. If the air pressure drop value is within the set range within the set time, it indicates that the tightness of the pipeline to be tested is within the set range. If the pressure drop exceeds the set range, it means that the tightness of the pipeline to be tested does not meet the requirements, and the pipeline to be tested needs to be detected to determine the leakage point and repair until the pressure drops to normal. And because the pressure gauge 81 is arranged on the second branch pipe 12, when performing water injection operation, there is no need to observe the water pressure at the equipment, which facilitates the smooth progress of water injection operation.

[0042] Furthermore, a third switch valve 7 is provided between the pressure gauge 81 and the second branch pipe 12, and the third switch valve 7 is respectively connected to the second branch pipe 12 and the pressure gauge 81. By providing the third switch valve 7, the pressure gauge 81 can be connected to or disconnected from the connecting pipe 1.

[0043] Furthermore, a connecting flange 13 is fixedly provided at one end of the connecting pipe 1 away from the water inlet pipe 3. The connecting flange 13 is provided to facilitate docking of the connecting pipe 1 with the pipeline to be tested.

[0044] Furthermore, the connecting flange 13 and the connecting pipe 1 are an integrated structure. Through the above arrangement, the stability of the connection between the connecting flange 13 and the connecting pipe 1 can be ensured, and the manufacturing is convenient. During the installation process, the process is saved, thereby further improving the efficiency of the test.

[0045] Furthermore, a second connection joint 31 is provided at one end of the water inlet pipe 3 away from the connecting pipe 1, and the second connection joint 31 is used to connect with the water pump. By providing the second connection joint 31, it is convenient to quickly connect with the water pump, so that after completing the tightness test, it can quickly switch to the water injection mode, thereby shortening the construction period.

[0046] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.

Claims

1. Pipeline tightness test and water adding integrated device, characterized in that: include: A connecting pipe (1), wherein the connecting pipe (1) is provided with a first branch pipe (11) and a second branch pipe (12), the first branch pipe (11) and the second branch pipe (12) are both connected to the connecting pipe (1), and one end of the connecting pipe (1) can be connected to a pipeline to be tested; an inflatable component (2), the inflatable component (2) being in communication with the first branch pipe (11) and being used for filling the pipeline to be tested with compressed gas, a first switch valve (5) being arranged in series between the inflatable component (2) and the first branch pipe (11); A detection component (8), arranged on the second branch pipe (12), for testing the air pressure or water pressure of the pipeline to be tested; A water inlet pipe (3), the water inlet pipe (3) being connected to the other end of the connecting pipe (1), and a second switch valve (6) being provided on the water inlet pipe (3).

2. The pipeline tightness test and water adding integrated device according to claim 1 is characterized in that: The inflation assembly (2) comprises a motor (21) and an air compressor (22); the motor (21) is transmission-connected to the air compressor (22); and the air compressor (22) is connected to the first branch pipe (11).

3. The pipeline tightness test and water adding integrated device according to claim 2 is characterized in that: The air compressor (22) is connected to the first branch pipe (11) via an air intake pipe (4), and the first switch valve (5) is respectively connected to the air intake pipe (4) and the first branch pipe (11).

4. The pipeline tightness test and water adding integrated device according to claim 3 is characterized in that: The end of the air intake pipe (4) away from the first switch valve (5) has a first connecting joint (41), and the first connecting joint (41) is connected to the air compressor (22).

5. The pipeline tightness test and water adding integrated device according to claim 2, characterized in that: It also includes a support frame (23), in which the motor (21) and the air compressor (22) are both fixedly arranged.

6. The pipeline tightness test and water adding integrated device according to claim 1, characterized in that: The detection assembly (8) comprises a pressure gauge (81), and the pressure gauge (81) is connected to the second branch pipe (12).

7. The pipeline tightness test and water adding integrated device according to claim 6, characterized in that: A third switch valve (7) is provided between the pressure gauge (81) and the second branch pipe (12), and the third switch valve (7) is respectively connected to the second branch pipe (12) and the pressure gauge (81).

8. The pipeline tightness test and water adding integrated device according to claim 1, characterized in that: A connecting flange (13) is fixedly provided at one end of the connecting pipe (1) away from the water inlet pipe (3).

9. The pipeline tightness test and water adding integrated device according to claim 8, characterized in that: The connecting flange (13) and the connecting pipe (1) are an integrated structure.

10. The pipeline tightness test and water adding integrated device according to claim 1, characterized in that: A second connection joint (31) is provided at one end of the water inlet pipe (3) away from the connecting pipe (1), and the second connection joint (31) is used for connecting to a water pump.