Buried pipeline test system
By designing a buried pipeline test system that includes model test components, settlement control components and external load control components, simulating soil settlement and in-pipe pressure, the problem that existing systems cannot simulate the combined effect of ground settlement, external load and in-pipe pressure is solved. , effectively simulates the stress-strain response of buried pipeline-based soil system, and provides theoretical support for the construction and operation and maintenance of buried pipelines.
Patent Information
- Application Number
- CN202310522022.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-10
- Publication Date
- 2024-11-12
AI Technical Summary
The existing buried pipeline test system cannot effectively simulate the stress-strain response process of buried pipeline-based soil system under the combined action of ground settlement, external load and internal pressure, and cannot represent the real situation of pipeline buried in the soil.
A buried pipeline test system including model test components, settlement control components, pipeline pressure control components and external load control components was designed to monitor strain, settlement and settlement by simulating the effects of soil settlement, pressure and external loads in the pipeline. The soil pressure changes, providing the stress-strain response process of buried pipeline-based soil system.
This system can effectively simulate the stress-strain response process of buried pipeline-based soil system under ground settlement, internal pressure and external load, and provide theoretical and technical support for the construction and safe operation and maintenance of buried pipelines.
Smart Images

Figure CN118937091A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of buried pipeline testing, and in particular to a buried pipeline testing system under the effects of ground settlement, internal pipe pressure and external load. Background Art
[0002] Buried pipelines can generally be divided into gas pipelines and water supply (drainage) pipelines, and most of them run through underground areas with concentrated buildings and dense populations. Under the influence of various complex engineering environments, the pipeline disease mechanism is complex and the risk of safe operation and maintenance is high. For example, the medium transported by urban PE gas pipes is flammable and explosive, with a high risk factor and high risk. The influencing factors are many and complex. Once an accident occurs in the pipeline, it may cause poisoning of personnel, or even cause fires, explosions and other secondary disasters, causing serious losses and damage to the social economy and the personal safety of residents. Soil settlement, external load influence and internal pipe pressure are important factors that cause buried pipeline accidents. Therefore, studying the influence of factors such as soil settlement, external load influence and internal pipe pressure on buried pipelines can provide effective reference for the construction of buried pipelines and the safe operation and maintenance of pipelines. The invention patent "A method and device for simulating the settlement of in-service pipelines" with the applicant's announcement number CN102778395B provides a method and device for simulating the settlement of in-service pipelines. The test pipeline is bent and deformed by hanging a nominal weight, and the pipeline settlement is observed from the scale at the midpoint of the pipeline span to simulate the actual stress condition of the defective pipeline, thereby determining the actual pressure bearing capacity of the pipeline. Then, internal pressure is applied to the pipeline through a pressure pump to test the pressure bearing capacity of the pipeline under the combined action of internal pressure and bending load. However, since hanging a nominal weight cannot simulate the influence of soil pressure on the pipeline when the buried pipeline is located in the soil, it cannot represent the actual situation of the pipeline buried in the soil. Summary of the invention
[0003] The technical problem solved by the present invention is to provide a buried pipeline test system, which can not only simulate the stress-strain response process of the buried pipeline-subsoil system under the independent action of ground settlement, external load influence and internal pressure of the pipe, but also effectively simulate the stress-strain response process of the buried pipeline-subsoil system under the combined action of ground settlement, external load influence and internal pressure of the pipe, so as to provide an effective reference for the construction of buried pipelines and the safe operation and maintenance of pipelines.
[0004] The present invention provides a buried pipeline test system, comprising a pipeline with one end open and the other end closed, a model test assembly, a settlement control component, a pipeline internal pressure control assembly, an external load control assembly, a detection assembly and an external power supply;
[0005] The model test assembly comprises a box body, the box body comprises a bottom plate and side plates forming a frame-shaped structure, the bottom plate is slidably arranged in the frame-shaped structure formed by the side plates, and the side plates are provided with pipe installation holes; the box body is filled with soil, and the pipe crosses the box body through the pipe installation hole and is buried in the soil body;
[0006] The settlement control mechanism is at least one and is connected to the bottom plate, and is used to simulate soil settlement;
[0007] The pipeline internal pressure control component is connected to the open end of the pipeline and is used to simulate the pressure in the pipeline;
[0008] The external load control assembly is arranged above the model test assembly and is used to apply load to the soil to simulate various types of loads on the pipeline;
[0009] The detection assembly includes a strain sensor, a stratified settlement sensor, a soil pressure sensor and a moisture sensor; the strain sensor is arranged on the outer wall of the pipeline, and the deformation stratified settlement sensor, the soil pressure sensor and the moisture sensor are arranged in the box;
[0010] The external power supply is respectively connected to the strain sensor, the deformation stratification settlement sensor, the soil pressure sensor and the moisture sensor.
[0011] Furthermore, the bottom plate includes a plurality of bottom plate units connected end to end in sequence, and the plurality of settlement control mechanisms are respectively connected to the bottom plate units in a one-to-one correspondence to control the up and down sliding of the bottom plate units respectively.
[0012] As a preferred embodiment, the side panel is formed by detachably connecting a plurality of side panel segments.
[0013] Furthermore, a pipeline embedment depth adjustment component is provided on the side plate.
[0014] As a preferred embodiment, the pipeline buried depth adjustment component includes a pipeline support side plate, a slide rail I and a locking member I. The slide rail I is arranged on the side plate. A through hole is opened on the pipeline support side plate to form a pipeline mounting hole. The pipeline support side plate is slidably connected to the side plate through the slide rail I and fixed by the locking member I.
[0015] As a preferred embodiment, the pipeline support side plate is provided with four sliders with 1 / 4 circular notch corners, and the four circular notches enclose the pipeline installation hole. The slider is slidably connected to the pipeline support side plate through the slide rail II and fixed by the locking member II.
[0016] Furthermore, it also includes a PLC settlement controller and a base plate lifting sensor, the settlement control mechanism includes an electric push rod, the base plate lifting sensor is installed under the base plate to monitor the displacement of the base plate and is connected to the PLC settlement controller, the electric push rod is arranged under the base plate to adjust the height of the base plate, the motor of the electric push rod is connected to the PLC settlement controller, and the PLC settlement controller is connected to an external power supply.
[0017] Furthermore, the pipeline internal pressure control assembly includes a pressure connection ring, an air compressor and a pressure controller; the pressure connection ring is connected to the open end of the pipeline, and the other end is connected to the outlet end of the air compressor. The pressure connection ring and the air compressor are also connected to a pressure controller through a first branch pipe, and the air compressor and the pressure controller are connected to an external power supply.
[0018] Furthermore, the external load control component includes a pressure plate, a hydraulic cylinder, a hydraulic pump and an external load pressure controller; the pressure plate is arranged above the soil and contacts the hydraulic cylinder, the hydraulic cylinder is connected to the outlet end of the hydraulic pump, the outlet end of the hydraulic pump is connected to the external load pressure controller through a second branch pipe, and the hydraulic pump and the external load pressure controller are connected to an external power supply.
[0019] Furthermore, the external load control assembly also includes a pressure cross brace, a sliding guide rail and a column, the column is arranged on the outside of the box, the sliding guide rail is installed on the column along the length direction of the box, the hydraulic cylinder is arranged on the pressure cross brace, and the pressure cross brace is slidably connected to the sliding guide rail.
[0020] The present invention has the following beneficial effects: the test system can simulate the buried pipeline-subsoil system under real conditions through the model test component, the settlement control component simulates the settlement of the soil layer during the test, the pipeline internal pressure control component simulates the pressure in the buried pipeline, the external load control component simulates the various loads on the overlying soil layer of the buried pipeline during the test, and the detection component is used to monitor the strain change of the pipeline in the model test component, the displacement change of the fill, the change of the soil pressure, and the migration and redistribution of the soil moisture. It can effectively simulate the stress-strain response process of the buried pipeline-subsoil system under the action of ground settlement, internal pipe pressure and external load, and provide theoretical and technical support for the research of the buried pipeline-subsoil system. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 A schematic diagram of the structure of one of the buried pipeline test systems provided by the present invention;
[0022] Figure 2 A structural schematic diagram of another buried pipeline test system provided by the present invention;
[0023] Figure 3 for Figure 1 The schematic diagram of the box structure shown in ;
[0024] Figure 4 for Figure 1 or Figure 3 AA' section schematic diagram of the buried pipeline test system shown;
[0025] Figure 5 for Figure 1 or Figure 3 The BB' section schematic diagram of the buried pipeline test system shown;
[0026] Figure 6 for Figure 1 or Figure 3 The CC' section schematic diagram of the buried pipeline test system shown;
[0027] Figure 7 It is a structural schematic diagram of a pipeline buried depth adjustment component and a pipe diameter adjustment component;
[0028] Figure 8 It is a structural schematic diagram of a pipeline buried depth adjustment component;
[0029] Fig. 9 for Figure 1 The schematic diagram of the structure of the pressure connection ring of the buried pipeline test system is shown.
[0030] Figure numerals: 1-box; 101-bottom plate; 1011 bottom plate unit; 102-side plate; 1021-side plate opening; 1022-side plate section; 2-fastening member; 201-side plate through hole; 202-fastening screw; 203-fastening nut; 3-pipeline mounting hole; 301-pipeline supporting side plate; 302-slide rail I; 303-locking member I; 304-slider; 305-slide rail II; 306-locking member II; 4-pipeline; 5-soil; 6-strain sensor; 7-stratified settlement sensor; 8-soil pressure sensor; 9-moisture sensor; 11-horizontal push rod; 12-bottom plate lifting sensor; 13-first electrical lead; 14-motor; 15-PLC settlement control component; 16-pressure connecting ring; 1601-trumpet wide mouth; 1602-flexible pipe section; 1603-annular tightening bolt; 17-connecting section; 18-air compressor; 181-first branch pipe; 19-pipeline internal pressure controller; 20-pressure plate; 21-hydraulic cylinder; 23-hydraulic pump; 231-second branch pipe; 24-external load pressure controller; 25-pressure cross brace; 26-sliding guide rail; 27-column; 28-motor; 29-third power lead; 30-external power supply; 31-sensor lead; 32-data acquisition instrument; 33-electronic computer; 34-fourth power lead. DETAILED DESCRIPTION
[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0032] like Figure 2 As shown, the present invention provides a buried pipeline test system, including a pipeline 4 with one end open and the other end closed, a model test component, a settlement control mechanism, a pipeline internal pressure control component, an external load control component and an external power supply 30; the model test component includes a box body 1, the box body 1 includes a bottom plate 101 and side plates 102 that form a frame-shaped structure, the bottom plate 101 is slidably arranged in the frame-shaped structure formed by the side plates 102, the side plates 102 are provided with pipeline installation holes 3, the box body 1 is filled with soil 5, the pipeline 4 crosses the box body 1 through the installation hole 3 and is buried in the soil 5; the settlement control member is connected to the bottom plate 101 for simulating soil settlement; the pipeline internal pressure control component is connected to the open end of the pipeline 4 , used to simulate the pressure in the pipeline; the external load control component is arranged above the model test component, and is used to apply load to the soil 5 to simulate various types of loads above the pipeline; the detection component is used to monitor the changes in the strain of the pipeline in the model test component, the changes in the fill displacement, the changes in the soil pressure, and the migration and redistribution of soil moisture, including a strain sensor 6, a stratified settlement sensor 7, a soil pressure sensor 8 and a moisture sensor 9; the strain sensor 6 is arranged on the outer wall of the pipeline 4, the stratified settlement sensor 7, the soil pressure sensor 8 and the moisture sensor 9 are arranged in the box 1, and the external power supply 30 is respectively connected to the strain sensor 6, the stratified settlement sensor 7, the soil pressure sensor 8 and the moisture sensor 9.
[0033] A model test assembly is provided to simulate the pipeline-soil system in actual working conditions, and the pipeline 4 is buried in the model test assembly and filled with soil to simulate the actual buried pipeline. The type of the soil 5 can be selected according to the actual situation to be simulated; a settlement control component is provided below the model test assembly to simulate the soil settlement process caused by groundwater transfer, buildings and other factors in actual working conditions. The settlement control component can use a lift, an electric jack or a manual jack to control and adjust the height of the bottom plate 101; a pipeline internal pressure control component is provided at the open end of the pipeline 4 buried in the model test assembly, and the fluid pressure is used to simulate the influence of the internal pressure on the pipeline when the pipeline is passed through water or ventilation. The internal pressure control component can use an air compressor, an air pump or a press machine; on the model test assembly An external load control component is set up to simulate the load influence of factors such as buildings, people flow, vehicles, etc. above the buried pipeline in actual working conditions on the buried pipeline. The types of external loads include uniformly distributed loads and concentrated loads, etc. The external load control can be achieved by artificially applying weights or counterweights or using equipment loading. In order to detect the strain changes and displacement changes of the pipeline 4, the settlement at different depths in the soil 5, the soil pressure changes and the moisture changes in the soil under various influencing factors, a detection component is set up in the model test component to detect the changes in the pipeline strain caused by soil settlement, pipeline internal pressure and external loads. The detection component includes a strain sensor 6, a deformation layer settlement sensor 7, a soil pressure sensor 8 and a moisture sensor 9; the strain sensor 6 is set on the outer wall of the pipeline 4, specifically as follows Figure 1-Figure 3 As shown, the strain sensor 6 is symmetrically arranged on the upper and lower sides of the same cross section of the pipeline 4, and is arranged on multiple cross sections of the pipeline 4. The deformation layered settlement sensor 7 is arranged at the upper, middle and lower positions of the soil body 5. The soil pressure sensor 8 and the moisture sensor 9 are arranged in the soil body 5 according to the required test points. The strain sensor 6 is used to monitor the strain evolution process of the buried pipeline. The deformation layered settlement sensor 7 is used to monitor the displacement change of the fill at different depths during the test and the deformation response of the buried pipeline. The soil pressure sensor 8 is used to monitor the soil pressure transmission in the fill during the test, and reflects a dissipation characteristic of the base soil to the force through the pressure analysis. The moisture sensor 9 is used to monitor the migration and redistribution of moisture in the fill during the test. Finally, the monitored data transmitted by each sensor in the detection component is collected and processed to obtain the stress-strain response process of the buried pipeline-base soil system. The above-mentioned collection and processing of the monitored data transmitted by each sensor can be collected and processed manually, or a data collector and computer automatic processing can be used, such as Figure 1 and Figure 2As shown in the figure, each sensor is connected to the data acquisition instrument 32 through a communication connection or a sensor lead, and the data measured by the sensor is sent to the data acquisition instrument in real time. The data acquisition instrument transmits the relevant information to the computer through the communication connection. The computer processes the obtained data to obtain the stress-strain response process and relationship of the buried pipeline under the action of ground settlement, internal pressure of the pipe and external load; the buried pipeline test system composed of the above-mentioned various components can effectively simulate the stress-strain response mechanism, multi-physical field coupling mechanism and action process of the buried pipeline-subsoil system under the action of ground settlement, internal pressure of the pipe and external load, which can be specifically the water-mechanical coupling mechanism and action process, and can be widely used in the buried pipeline-subsoil system test under various engineering environments, providing theoretical and technical support for the research of buried pipeline-subsoil system.
[0034] The above-mentioned base plate 101 can be composed of a whole plate or multiple sub-plates. Since the whole base plate 101 cannot simulate the uneven settlement of soil in actual working conditions, the base plate 101 includes multiple base plate units 1011 connected end to end in sequence, and the multiple settlement control mechanisms are respectively connected to the base plate units 1011 to respectively control the up and down sliding of the base plate units 1011; since each base plate unit 1011 can slide independently without affecting each other, the influence of the uneven settlement of the soil 5 on the pipeline 4 can be simulated by individually controlling different base plate units 1011 to slide up and down to different degrees.
[0035] The side panels 102 can be integral side panels or spliced side panels. To facilitate the control of the length of the box and to cooperate with each bottom plate unit, the side panels 102 are composed of multiple side panel segments 1022 that can be detachably connected. The detachable connection method can be a latch, mortise and tenon structure, etc. Figure 4 and Figure 5 As shown, the detachable connection method can be specifically as follows: a plurality of side panel through-holes 201 are reserved on the side of the side panel segment 1022, and two adjacent side panel segments 1022 are connected as a whole by fastening screws 202 and fastening nuts 203. When in use, the number of side panel segments 1022 can be increased or decreased according to actual conditions to control the total length of the box, thereby being closer to the actual working environment.
[0036] In order to facilitate adjustment of the buried depth of the pipeline, a pipeline buried depth adjustment component is provided on the side plate 102 .
[0037] As a preferred embodiment, the pipeline buried depth adjustment component includes a pipeline support side plate 301, a slide rail I 302 and a locking member I 303, wherein the slide rail I 302 is arranged on the side plate 102, a through hole is opened on the pipeline support side plate 301 to form a pipeline installation hole 3, and the pipeline support side plate 301 is slidably connected to the side plate 102 through the slide rail I 302 and fixed through the locking member I 303; Figure 8 As shown, the side plate 102 is provided with an opening 1021 (i.e., the portion surrounded by the dotted line), and the two slide rails Ⅰ302 are arranged on both sides of the opening 1021 with the opening 1021 as the center. The pipe support side plate 301 is slidably installed on the slide rail Ⅰ302 and fixed by a locking member Ⅰ303. The length of the pipe support side plate 301 is at least twice the length of the opening 1021 and covers the opening 1021. The pipe support side plate 301 is provided with a pipe installation hole 3. When the pipe support side plate 301 slides along the slide rail Ⅰ302, the pipe installation hole 3 coincides with the opening 1021, and the pipe 4 can be installed transversely in the box body 1. The movement of the pipe installation hole 3 is driven by sliding the pipe support side plate 301 to achieve the purpose of adjusting the buried depth of the pipe. The buried depth adjustment range of the buried pipe 4 is H; the above-mentioned pipe support side plate 301 can be as follows Figure 8 The whole board shown can also be divided into two upper and lower boards, or can be as shown in Figure 7 The four sub-boards are shown.
[0038] In order to adapt to the installation of pipelines with different diameters, four sliders 304 with 1 / 4 circular corners are provided on the pipeline support side plate 301. The four circular corners enclose the pipeline installation hole 3. The slider 304 is slidably connected to the pipeline support side plate 301 through the slide rail II 305 and fixed through the locking piece II 306; Figure 7 As shown, four sliders 304 with 1 / 4 circular notch corners are slidably installed on the pipeline support side plate 301 through the slide rail II 305, and the four circular notch corners enclose the pipeline installation hole 3. Since the sliders 304 with 1 / 4 circular notch corners can slide on the pipeline support side plate 301 along the slide rail II 305, the distance between the circular notch corners on the sliders 304 is adjusted by sliding the sliders 304, thereby adjusting the size of the pipeline installation hole 3 enclosed by the circular notch corners, and fixing it through the clamping piece II 306 to adapt to the test of pipelines with different diameters.
[0039] In order to realize automatic simulation of soil settlement and obtain actual data of soil settlement, the buried pipeline test system also includes a PLC settlement controller and a bottom plate lifting sensor. The settlement control component includes an electric push rod 11. The bottom plate lifting sensor 12 is installed under the bottom plate 101 to monitor the displacement of the bottom plate 101 and is connected to the PLC settlement controller 15. The electric push rod 11 is arranged under the bottom plate 101 to adjust the height of the bottom plate 101. The motor 14 of the electric push rod 11 is connected to the PLC settlement controller, and the PLC settlement controller 15 is connected to the external power supply 30. The existing electric push rod 11 has its own motor. In order to control the lifting and lowering of the electric push rod 11, the PLC settlement controller 15 is connected to the motor 14 of the electric push rod 11, such as Figure 1 and Figure 2As shown, only the motor 14 of an electric push rod 11 is drawn for example. By programming and inputting instructions in the PLC settlement controller 15, the motor 14 is controlled to control the lifting and lowering of the electric push rod 11 to control the vertical movement of the base plate 101. At the same time, a base plate lifting sensor 12 is provided on the base plate 101 for real-time monitoring of the displacement of the base plate 101, determining the settlement amount of the formation during the experiment, and feeding back to the PLC settlement controller 15 whether the electric push rod 11 has completed the lifting and lowering instructions, thereby controlling the automatic start and stop of the electric push rod 11; the PLC settlement control component 15 is connected to the motor 14 of the electric push rod 11, and by setting different program modes, such as displacement control, rate control, etc., the forward and reverse rotation and rate of the motor 14 are controlled, thereby realizing automatic control of the lifting and lowering of the electric push rod 11 under the base plate 101.
[0040] At the same time, if the bottom plate 101 is composed of multiple bottom plate units 1011, four electric push rods 11 and bottom plate lifting sensors 12 with the same position as the electric push rods 11 are arranged under each bottom plate unit 1011, and the motor 14 of the electric push rod 11 and the bottom plate lifting sensor 12 are connected to the PLC settlement controller 15 through the first power lead 13 or connected to the PLC settlement controller 15 through a wireless connection; the purpose of arranging an electric push rod under each bottom plate unit 1011 is to individually adjust the lifting of each bottom plate unit 1011 to simulate the real The uneven settlement of the soil is caused by the bottom plate lifting sensor 12 under each bottom plate unit 1011, which is consistent with the electric push rod 11 in orientation. The purpose is to detect the displacement of each bottom plate unit 1011 in real time, determine the settlement of the stratum during the experiment, and feed back the displacement of the bottom plate unit 1011 to the PLC settlement controller 15 to determine whether the electric push rod 11 has completed the lifting instruction, and then control the start and stop of the motor 14 to realize automatic control of the lifting and lowering of the bottom plate unit 1011, thereby simulating the different settlement of soil at different positions in actual working conditions.
[0041] In order to simulate the influence of the internal pressure of the buried pipeline on the pipeline when it is in use, that is, when transporting gas or liquid, the pipeline internal pressure control component includes a pressure connecting ring 16, an air compressor 18 and a pressure controller 19; the pressure connecting ring 16 is connected to the open end of the pipeline 4, and the other end is connected to the outlet end of the air compressor 18, and a pressure controller 19 is also provided between the pressure connecting ring 161 and the air compressor 18, and the air compressor 18 and the pressure controller 19 are connected to an external power supply 30. The pressure connecting ring 16 is connected to the open end of the pipeline 4, and the other end is connected to the outlet end of the air compressor 18. If the distance between the pipeline 4 and the outlet end of the air compressor 18 is far, the pressure connecting ring 16 can also be connected to the outlet end of the air compressor 18 through the connecting section 17. A pressure controller 19 is also provided between the pressure connecting ring 161 and the air compressor 18 through the first branch pipe 181. The pressure controller 19 can be directly arranged between the two, or it can be arranged between the outlet end of the air compressor 18 and the pressure connecting ring 16 through the first branch pipe 181, so as to control the gas production effect of the air compressor 18 in real time through gas production modes such as pressure rate, pressure time course and maximum pressure, thereby simulating the actual pressure changes in the pipeline during actual use, that is, when transporting gas or liquid.
[0042] In order to ensure the tightness of the connection between the pressure connecting ring and the pipeline, the pressure connecting ring 16 is trumpet-shaped. The connection between the pressure connecting ring 16 and the air compressor 18 is a trumpet-shaped narrow mouth, and the connection between the pressure connecting ring 16 and the pipeline 4 is a trumpet-shaped wide mouth 1601. The trumpet-shaped wide mouth 1601 is extended along the outer side of the pipeline and is provided with a flexible tube section 1602. The outer wall of the flexible tube section 1602 is provided with an annular tightening bolt 1603. Since the flexible tube section 1602 has a certain self-contraction property, it can be connected to the pipeline 4 of different diameters. The tight connection between the flexible tube section 1602 and the pipeline 4 is ensured by arranging an annular tightening bolt 1603 outside the flexible tube section.
[0043] In order to simulate the load on the overlying soil layer of the buried pipeline in actual working conditions, the external load control component includes a pressure plate 20, a hydraulic cylinder 21, a hydraulic pump 23 and an external load pressure controller 24; the pressure plate 20 is arranged above the soil body 5 and contacts the hydraulic cylinder 21, the hydraulic cylinder 21 is connected to the outlet end of the hydraulic pump 23, the hydraulic pump 23 is connected to the external load pressure controller 24, and the hydraulic pump 23 and the external load pressure controller 24 are connected to an external power supply 30; wherein the connection mode between the hydraulic cylinder 21 and the outlet end of the hydraulic pump 23 is a telescopic connection, the pressure generated by the external load control component is transmitted to the soil body 5 of the model test component through the pressure plate 20, and different external loads (such as impact load, creep load, etc.) can be applied to the hydraulic cylinder 21 through the mode setting of the external load pressure controller 24 (i.e., force control or displacement control) to simulate various loads encountered in actual working conditions.
[0044] In order to facilitate the adjustment of the load application position, the external load control assembly further includes a pressure cross brace 25, a sliding guide rail 26 and a column 27. The column 27 is arranged outside the box body 1, and the sliding guide rail 26 is installed on the column 27 along the length direction of the box body 1. The hydraulic cylinder is arranged on the pressure cross brace 25, and the pressure cross brace 25 is slidably connected with the sliding guide rail 26. The sliding of the pressure cross brace 25 along the sliding guide rail 26 drives the movement of the hydraulic cylinder 21 to adjust the load application position. The adjustment of the pressure cross brace 25 can be manually adjusted or machine controlled, such as Figure 1 As shown in the figure, the pressure cross brace 25 is connected to the motor 28, and the pressure cross brace 25 is driven by the motor 28 to move. The above-mentioned column 27 can adopt a lifting structure to facilitate adjusting the height position of the hydraulic cylinder 21 to adapt to applying loads to soil bodies 5 at different heights.
[0045] In addition, the motor 14, the PLC sedimentation control component 15, the air compressor 18, the pipeline pressure controller 19, the hydraulic press 23, the external load pressure controller 24 and the electric motor 28 are connected to the external power supply 30 through the third power lead 29, and the data acquisition instrument 32 and the electronic computer 33 are connected to the external power supply 30 through the fourth power lead 34, and the external power supply 30 provides electrical energy for the above-mentioned electrical appliances.
Claims
1. A buried pipeline test system, characterized in that: It comprises a pipeline (4) with one end open and the other end closed, a model test component, a settlement control mechanism, a pipeline internal pressure control component, an external load control component, a detection component and an external power supply (30); The model test assembly comprises a box (1), the box (1) comprising a bottom plate (101) and side plates (102) forming a frame-shaped structure, the bottom plate (101) being slidably arranged in the frame-shaped structure formed by the side plates (102) up and down, the side plates (102) being provided with pipe installation holes (3); the box (1) is filled with soil (5), the pipe (4) passes through the box (1) through the pipe installation hole (3) and is buried in the soil (5); The settlement control mechanism is at least one and is connected to the bottom plate (101) and is used to simulate soil settlement; The pipeline internal pressure control component is connected to the open end of the pipeline (4) and is used to simulate the pressure in the pipeline; The external load control component is arranged above the model test component and is used to apply a load to the soil (5) to simulate various types of loads on the pipeline; The detection component comprises a strain sensor (6), a stratified settlement sensor (7), a soil pressure sensor (8) and a moisture sensor (9); the strain sensor (6) is arranged on the outer wall of the pipeline (4), and the stratified settlement sensor (7), the soil pressure sensor (8) and the moisture sensor (9) are arranged in the box (1); The external power source (30) is respectively connected to the strain sensor (6), the layered settlement sensor (7), the soil pressure sensor (8) and the moisture sensor (9).
2. A buried pipeline testing system as claimed in claim 1, characterized in that: The bottom plate (101) comprises a plurality of bottom plate units (1011) connected end to end in sequence, and the plurality of settlement control mechanisms are respectively connected to the bottom plate units (1011) in a one-to-one correspondence to respectively control the up and down sliding of the bottom plate units (1011).
3. A buried pipeline testing system as claimed in claim 2, characterized in that: The side panel (102) is formed by detachably connecting a plurality of side panel segments (1022).
4. A buried pipeline testing system as claimed in claim 1, characterized in that: The side plate (102) is provided with a pipeline embedment depth adjustment component.
5. A buried pipeline test system as claimed in claim 4, characterized in that: The pipeline buried depth adjustment component comprises a pipeline supporting side plate (301), a slide rail I (302) and a locking member I (303); the slide rail I (302) is arranged on the side plate (102); a through hole is opened on the pipeline supporting side plate (301) to form a pipeline mounting hole (3); the pipeline supporting side plate (301) is slidably connected to the side plate (102) through the slide rail I (302) and is fixed through the locking member I (303).
6. A buried pipeline testing system as claimed in claim 5, characterized in that: The pipeline support side plate (301) is provided with four sliders (304) with 1 / 4 circular notch corners, and the four circular notches enclose a pipeline installation hole (3). The sliders (304) are slidably connected to the pipeline support side plate (301) through a slide rail II (305) and fixed through a locking member II (306).
7. A buried pipeline testing system as claimed in claim 1, characterized in that: The invention also comprises a PLC settlement controller (15) and a bottom plate lifting sensor (12), wherein the settlement control mechanism comprises an electric push rod (11), the bottom plate lifting sensor (12) is installed below the bottom plate (101) for monitoring the displacement of the bottom plate (101) and is connected to the PLC settlement controller (15), the electric push rod (11) is arranged below the bottom plate (101) for adjusting the height of the bottom plate (101), the motor (14) of the electric push rod (11) is connected to the PLC settlement controller (15), and the PLC settlement controller (15) is connected to an external power supply (30).
8. A buried pipeline testing system as claimed in claim 1, characterized in that: The pipeline internal pressure control component comprises a pressure connecting ring (16), an air compressor (18) and a pressure controller (19); the pressure connecting ring (16) is connected to the open end of the pipeline (4), and the other end is connected to the outlet end of the air compressor (18); the pressure connecting ring (16) and the air compressor (18) are also connected to the pressure controller (19) via a first branch pipe (181); the air compressor (18) and the pressure controller (19) are connected to an external power supply (30).
9. A buried pipeline testing system as claimed in claim 1, characterized in that: The external load control assembly comprises a pressure plate (20), a hydraulic cylinder (21), a hydraulic pump (23) and an external load pressure controller (24); the pressure plate (20) is arranged above the soil body (5) and in contact with the hydraulic cylinder (21); the hydraulic cylinder (21) is connected to the outlet end of the hydraulic pump (23); the outlet end of the hydraulic pump (23) is connected to the external load pressure controller (24) via a second branch pipe (231); the hydraulic pump (23) and the external load pressure controller (24) are connected to an external power source (30).
10. A buried pipeline testing system as claimed in claim 9, characterized in that: The external load control assembly further comprises a pressure cross brace (25), a sliding guide rail (26) and a column (27), wherein the column (27) is arranged outside the box body (1), the sliding guide rail (26) is installed on the column (27) along the length direction of the box body (1), the hydraulic cylinder (21) is arranged on the pressure cross brace (25), and the pressure cross brace (25) is slidably connected to the sliding guide rail (26).
Citation Information
Patent Citations
In-service pipeline settlement simulation test method and device
CN102778395B
Cited By
Experimental device for simulating surface load and foundation settlement
CN120908077A
Experimental method and experimental device for simulating deformation of buried pipeline
CN122084400A
An experimental method and apparatus for simulating the deformation of buried pipelines.
CN122084400B