Energy-saving management method and system based on electric power big data
Through a comprehensive analysis of power input data, equipment operation data and environmental data, energy saving output value is calculated to optimize the energy input of power equipment, the problem that power equipment often fails to operate normally is solved, and energy saving effect and operating efficiency are improved.
Patent Information
- Application Number
- CN202411426511.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-14
- Publication Date
- 2024-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The prior art cannot conduct a comprehensive analysis of the operation of power equipment based on power input data, power equipment operation data and operating environment data, resulting in power equipment being unable to operate in normal state.
The power data acquisition module collects power input data, power equipment operation data and operating environment data, conducts power equipment operation abnormality assessment and environmental abnormality assessment, and calculates energy saving output value to optimize the energy input of power equipment.
It improves the energy-saving effect and the operating efficiency of power equipment to ensure that the power equipment operates under normal conditions.
Smart Images

Figure CN118941124A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of data processing systems for supervision, and specifically relates to an energy-saving management method and system based on power big data. Background Art
[0002] Energy conservation management based on power big data uses big data technology and analysis methods to optimize and manage energy systems to achieve more efficient and energy-saving energy utilization. Energy conservation management based on power big data can help enterprises and institutions reduce energy costs and energy waste, while also helping to improve energy security and sustainability. Through the analysis and use of power big data, intelligent and efficient energy management can be achieved, contributing to environmental protection and sustainable development.
[0003] For example, the patent with application publication number CN116384622A discloses a carbon emission monitoring method and device based on power big data. This application scheme is based on high-frequency, multi-dimensional power big data, and makes full use of frequency conversion, model inference, seasonal adjustment and other technologies to infer the high-frequency energy consumption data of provinces, cities, key industries and households, so as to achieve high-frequency monitoring of carbon emissions in regions, key industries and households, accurately track the "carbon footprint" of enterprises, and gain insight into the "carbon flow" within enterprises. In addition, starting from multiple dimensions such as region, industry, and time, the carbon emissions of industrial enterprises in the target area are monitored, and then through horizontal comparison, the backward links of enterprise energy consumption are accurately located, and the blockages and leakages of enterprise energy consumption are discovered, guiding enterprises to accurately and scientifically reduce carbon emissions, and improving the level of enterprise carbon asset management in a targeted manner, so as to achieve energy conservation and efficiency improvement for the whole society, and bring considerable direct climate and environmental benefits;
[0004] At the same time, for example, the patent with application publication number CN115115091A involves a smart energy management and control platform for the park based on panoramic display. The management and control platform includes a perception layer, a transmission layer, a platform layer and a user layer, wherein the platform layer includes an operation monitoring module, an intelligent operation and inspection module, an energy efficiency management module, a value-added service management module, an equipment asset management module, a system management module, a statistical analysis module, a comprehensive energy management module and a dispatching and repair management module. This invention uses cloud computing, big data, 5G and other technologies, and relies on the concept of "Internet of Things +" to monitor the power data, environmental control parameters and equipment operation status of each distribution room in the park in real time, collect and analyze them in a centralized manner, which can improve the real-time operation monitoring level of power supply equipment, timely warn of faults, realize energy monitoring and energy efficiency analysis, provide value-added services for energy conservation in the park, and realize power quality monitoring at the same time, and provide suggestions for optimizing power quality in the factory area.
[0005] The above patents all have the problems raised by this background technology: the existing technology is unable to conduct a comprehensive analysis of the operation status of power equipment based on power input data, power equipment operation data and operating environment data, resulting in the power equipment often being unable to operate in a normal state. The above problems exist in the existing technology. In order to solve these problems, this application designs an energy-saving management method and system based on power big data. Summary of the invention
[0006] In view of the deficiencies in the prior art, the present invention proposes an energy-saving management method and system based on power big data.
[0007] To achieve the above object, the present invention provides the following technical solutions:
[0008] An energy-saving management method based on power big data includes the following specific steps:
[0009] S1. Collect power input data, power equipment operation data and operation environment data through the power data acquisition module, and transmit the data to the power management platform;
[0010] S2, importing the acquired power input data and power equipment operation data into the power equipment operation abnormality coefficient evaluation strategy to perform power equipment operation abnormality evaluation;
[0011] S3, importing the acquired operating environment data into the power environment anomaly assessment strategy to conduct power environment anomaly assessment;
[0012] S4, substituting the evaluated power equipment operation abnormality coefficient and power environment operation abnormality coefficient into the energy-saving output value calculation formula to output the energy-saving output value;
[0013] S5. Obtain the energy-saving output value, and input energy into the power equipment according to the obtained energy-saving output value.
[0014] A further improvement of the present invention is that S1 comprises the following specific steps:
[0015] S11, collecting power input data of the power equipment through the power data collection terminal, wherein the power input data includes input voltage and input current data, collecting power equipment operation data through the power equipment operation data collection terminal, wherein the power equipment operation data includes output data of the output end of the power equipment, and storing them in the first storage module. Here, an example of power equipment operation data is given, such as the output data of the lighting lamp is the brightness of the lamp body;
[0016] S12, collecting operating environment data of the power equipment during operation through the operating environment collection terminal, and storing the collected operating environment data in a second storage module, wherein the operating environment data includes temperature, humidity and noise intensity data;
[0017] S13, transmitting the data stored in the first storage module and the second storage module to the power management platform.
[0018] A further improvement of the present invention is that the specific content of the power equipment operation abnormality coefficient evaluation strategy in S2 is as follows:
[0019] S21, acquiring power input data of the power equipment and output data of the output end of the power equipment, importing the acquired power input data into the power input-output data calculation formula of the power equipment to calculate the rated output data of the power equipment corresponding to the power input data, and acquiring the rated output data of the power equipment corresponding to the power input data;
[0020] S22, substituting the rated output data of the power equipment corresponding to the acquired power input data and the acquired output data of the output end of the power equipment into the power equipment operation abnormality coefficient evaluation formula to calculate the power equipment operation abnormality coefficient, the power equipment operation abnormality coefficient evaluation formula is: , where T is the operating time of the power equipment, dt is the time integral, is the output data of the output terminal of the power equipment at time t, is the power input data of the power equipment at time t, where: The formula for calculating the power input-output data of the power equipment;
[0021] It should be noted here that the calculation formula for the power input-output data of the power equipment can be obtained based on the experiment of the equipment. It is a conventional technical means in this field, and the specific experimental process will not be described in detail here.
[0022] A further improvement of the present invention is that the specific content of the power environment abnormality assessment strategy in S3 is:
[0023] The operating environment data of the power equipment during operation is obtained, and the obtained operating environment data is substituted into the power environment operation abnormality coefficient calculation formula to calculate the power environment operation abnormality coefficient, wherein the power environment operation abnormality coefficient calculation formula is: , where T is the operating time of the power equipment, n is the number of types of operating environment data, is the start time of the equipment operation, is the proportion coefficient of the i-th operating environment data, is the i-th operating environment data at time t, The closest one in the data security range of the i-th operating environment The value of is the maximum value in the data security range of the i-th operating environment, is the minimum value in the safe range of the i-th operating environment data, and dt is the time integral.
[0024] A further improvement of the present invention is that the step of substituting the evaluated power equipment operation abnormality coefficient and power environment operation abnormality coefficient into the energy-saving output value calculation formula to output the energy-saving output value includes the following specific contents:
[0025] S41, obtaining the calculated power equipment operation abnormality coefficient and power environment operation abnormality coefficient, and importing them into the overall abnormality value calculation formula to calculate the overall abnormality value, wherein the overall abnormality value calculation formula is: ,in, is the proportion of abnormal operation of power equipment, is the proportion of abnormal operation of the power environment, among which: ;
[0026] S42, obtaining the calculated overall abnormal value, and importing the overall abnormal value and the rated power of the power equipment into the energy-saving output value calculation formula to output the energy-saving output value, wherein the energy-saving output value calculation formula is: ,in, is the rated power of the power equipment, and exp() is the power of e.
[0027] A further improvement of the present invention is that S5 includes the following specific contents:
[0028] The calculated energy-saving output value is obtained, and the electric energy output module is controlled to output the energy-saving output value to the electric equipment to make the electric equipment operate.
[0029] It should be noted here that the method of determining the percentage of abnormal operation of power equipment, the percentage of abnormal operation of power environment and the percentage coefficient of the i-th operating environment data is as follows: 5000 sets of power equipment operation data and operating environment data are obtained, and at the same time, the power data that can enable the normal operation of the equipment is obtained, and the obtained power equipment operation data and operating environment data are substituted into the energy-saving output value calculation formula to calculate the energy-saving output value, and the calculated energy-saving output value and the power data that can enable the normal operation of the equipment are imported into the fitting software to output the percentage of abnormal operation of power equipment, the percentage of abnormal operation of power environment and the percentage coefficient of the i-th operating environment data that meet the highest judgment accuracy.
[0030] An energy-saving management system based on electric power big data is implemented based on the above-mentioned energy-saving management method based on electric power big data, and specifically includes: a data acquisition module, an equipment operation abnormality assessment module, an environmental abnormality assessment module, an energy output calculation module, an energy output module and a control module. The data acquisition module is used to collect power input data, power equipment operation data and operating environment data through the power data acquisition module, and transmit the data to the power management platform. The equipment operation abnormality assessment module is used to import the acquired power input data and power equipment operation data into the power equipment operation abnormality coefficient assessment strategy to perform power equipment operation abnormality assessment. The environmental abnormality assessment module is used to import the acquired operating environment data into the power environment abnormality assessment strategy to perform power environment abnormality assessment.
[0031] A further improvement of the present invention is that the energy output calculation module is used to substitute the evaluated abnormal operation coefficient of the power equipment and the abnormal operation coefficient of the power environment into the energy-saving output value calculation formula to output the energy-saving output value, and the energy output module is used to obtain the obtained energy-saving output value and input the energy of the power equipment according to the obtained energy-saving output value.
[0032] A further improvement of the present invention is that the control module is used to control the operation of the data acquisition module, the equipment operation abnormality assessment module, the environment abnormality assessment module, the energy output calculation module and the energy output module.
[0033] An electronic device comprises: a processor and a memory, wherein the memory stores a computer program that can be called by the processor;
[0034] The processor executes the above-mentioned energy-saving management method based on power big data by calling the computer program stored in the memory.
[0035] A computer-readable storage medium stores instructions, which, when executed on a computer, enable the computer to execute an energy-saving management method based on electric power big data as described above.
[0036] Compared with the prior art, the present invention has the following beneficial effects:
[0037] The present invention collects power input data, power equipment operation data and operation environment data through a power data acquisition module, and transmits the data to a power management platform, imports the acquired power input data and power equipment operation data into a power equipment operation abnormality coefficient evaluation strategy to perform power equipment operation abnormality evaluation, imports the acquired operation environment data into a power environment abnormality evaluation strategy to perform power environment abnormality evaluation, substitutes the evaluated power equipment operation abnormality coefficient and power environment operation abnormality coefficient into an energy-saving output value calculation formula to output the energy-saving output value, obtains the energy-saving output value, and inputs energy of the power equipment according to the obtained energy-saving output value, thereby improving the energy-saving effect and the operation efficiency of the power equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 This is a flow chart of an energy-saving management method based on power big data of the present invention;
[0039] Figure 2 This is a specific flow chart of step S1 of an energy-saving management method based on power big data of the present invention;
[0040] Figure 3 This is a specific flow chart of step S2 of an energy-saving management method based on power big data of the present invention;
[0041] Figure 4 This is a schematic diagram of the framework of an energy-saving management system based on power big data in the present invention. DETAILED DESCRIPTION
[0042] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0043] Example 1
[0044] See also Figure 1-Figure 3 , an embodiment provided by the present invention: an energy-saving management method based on power big data, which comprises the following specific steps:
[0045] S1. Collect power input data, power equipment operation data and operation environment data through the power data acquisition module, and transmit the data to the power management platform;
[0046] S2, importing the acquired power input data and power equipment operation data into the power equipment operation abnormality coefficient evaluation strategy to perform power equipment operation abnormality evaluation;
[0047] S3, importing the acquired operating environment data into the power environment anomaly assessment strategy to conduct power environment anomaly assessment;
[0048] S4, substituting the evaluated power equipment operation abnormality coefficient and power environment operation abnormality coefficient into the energy-saving output value calculation formula to output the energy-saving output value;
[0049] S5, obtaining the obtained energy-saving output value, and inputting energy of the power equipment according to the obtained energy-saving output value;
[0050] In this embodiment, S1 includes the following specific steps:
[0051] S11, collecting power input data of the power equipment through the power data collection terminal, wherein the power input data includes input voltage and input current data, collecting power equipment operation data through the power equipment operation data collection terminal, wherein the power equipment operation data includes output data of the output end of the power equipment, and storing them in the first storage module. Here, an example of power equipment operation data is given, such as the output data of the lighting lamp is the brightness of the lamp body;
[0052] S12, collecting operating environment data of the power equipment during operation through the operating environment collection terminal, and storing the collected operating environment data in a second storage module, wherein the operating environment data includes temperature, humidity and noise intensity data;
[0053] S13, transmitting the data stored in the first storage module and the second storage module to the power management platform;
[0054] In this embodiment, the specific content of the power equipment operation abnormality coefficient evaluation strategy in S2 is as follows:
[0055] S21, acquiring power input data of the power equipment and output data of the output end of the power equipment, importing the acquired power input data into the power input-output data calculation formula of the power equipment to calculate the rated output data of the power equipment corresponding to the power input data, and acquiring the rated output data of the power equipment corresponding to the power input data;
[0056] S22, substituting the rated output data of the power equipment corresponding to the acquired power input data and the acquired output data of the output end of the power equipment into the power equipment operation abnormality coefficient evaluation formula to calculate the power equipment operation abnormality coefficient, the power equipment operation abnormality coefficient evaluation formula is: , where T is the operating time of the power equipment, dt is the time integral, is the output data of the output terminal of the power equipment at time t, is the power input data of the power equipment at time t, where: The formula for calculating the power input-output data of the power equipment;
[0057] For the selection of parameters of the above formula, in order to calculate the power equipment operation abnormality coefficient, the power input-output data of the power equipment is selected to reflect the power equipment operation abnormality. The applicant has the following considerations:
[0058] 1. Fault prevention and detection: By real-time monitoring and analysis of the power input-output data of power equipment, abnormal conditions of equipment, such as overload, short circuit, voltage fluctuation, etc., can be discovered in time. These data can provide important basis for preventive maintenance and troubleshooting of equipment, thereby avoiding or reducing the occurrence of equipment failures and ensuring the stable operation of the power system.
[0059] 2. Efficiency optimization: By analyzing the power input-output data, we can understand the equipment's operating efficiency and energy utilization. If we find that the equipment is inefficient or wastes energy, we can make adjustments and optimizations in time to improve the equipment's operating efficiency and energy utilization and reduce production costs.
[0060] 3. Safety management: The safe operation of power equipment is crucial to the stability of the entire power system. By monitoring and analyzing the power input-output data, safety hazards of equipment, such as overvoltage and overcurrent, can be discovered in a timely manner, so that appropriate measures can be taken to ensure the safe operation of the equipment.
[0061] 4. Data analysis and prediction: A large amount of power input-output data can provide a basis for data analysis and prediction. By deeply mining and analyzing these data, we can discover the laws and trends of equipment operation, predict possible equipment failures and problems, and take measures to prevent and deal with them in advance.
[0062] In summary, it is very necessary to select the power input-output data of power equipment to reflect the abnormal operation of power equipment;
[0063] As for the design of the evaluation formula for the abnormal operation coefficient of power equipment, T is the operation time of the power equipment, dt is the time integral, is the output data of the output terminal of the power equipment at time t, is the power input data of the power equipment at time t, where: The calculation formula for the power input-output data of the power equipment is that it is reasonable to reflect the abnormal operation coefficient of the power equipment during a period of time by integrating the difference between the output data of the output end of the power equipment during a period of time and the standard output data;
[0064] Here, a specific embodiment is used to reflect the above power equipment operation abnormality coefficient evaluation formula. For example, the input voltage of the power equipment is 220V, the input current is 12A, the standard output current is 10.8A, and the output current of each detection cycle during the operation of the power equipment is 10.7A, 10.6A, 10.6A, and 10.7A respectively. The power equipment operation abnormality coefficient is imported into the power equipment operation abnormality coefficient evaluation formula to calculate that the power equipment operation abnormality coefficient is 0.0013;
[0065] It should be noted that the power input-output data calculation formula of the power equipment can be obtained based on the experiment of the equipment, which is a conventional technical means in the field, and the specific experimental process will not be described in detail here;
[0066] In this embodiment, the specific content of the power environment abnormality assessment strategy in S3 is:
[0067] The operating environment data of the power equipment during operation is obtained, and the obtained operating environment data is substituted into the power environment operation abnormality coefficient calculation formula to calculate the power environment operation abnormality coefficient, wherein the power environment operation abnormality coefficient calculation formula is: , where T is the operating time of the power equipment, n is the number of types of operating environment data, is the start time of the equipment operation, is the proportion coefficient of the i-th operating environment data, is the i-th operating environment data at time t, The closest one in the data security range of the i-th operating environment The value of is the maximum value in the data security range of the i-th operating environment, is the minimum value in the safe range of the i-th operating environment data, and dt is the time integral;
[0068] For the selection of the above parameters, in order to calculate the power environment operation abnormality coefficient, the applicant selects the operating environment data to reflect the power environment operation abnormality coefficient, and has the following considerations:
[0069] 1. Real-time monitoring and early warning: The operating environment data can monitor various parameters of the power system in real time, such as temperature, humidity, pressure, vibration, etc. By analyzing these data, abnormal conditions of power equipment, such as overheating, overload, mechanical failure, etc., can be discovered in time, so as to give early warning and prevent the occurrence or expansion of failures;
[0070] 2. Fault analysis and location: Operating environment data can provide rich fault information to help operation and maintenance personnel analyze the cause of the fault and locate the fault. This is of great significance for quickly restoring the normal operation of the power system and reducing the impact of the fault on the power grid;
[0071] 3. Optimize operation strategy: By analyzing the operating environment data, we can understand the operating status of the power system and the performance of the equipment, and provide a basis for optimizing the operation strategy. For example, according to the operating temperature and load conditions of the equipment, we can adjust the operation mode of the equipment to improve the operating efficiency and life of the equipment;
[0072] 4. Improve safety and stability: Operating environment data can reflect the safety and stability of the power system. By monitoring and analyzing these data, potential safety hazards and unstable factors can be discovered in a timely manner, and appropriate measures can be taken to deal with them, ensuring the safe and stable operation of the power system;
[0073] In summary, it is very necessary to select operating environment data to reflect the abnormal operation of the power environment;
[0074] In this formula: T is the operating time of the power equipment, n is the number of types of operating environment data, is the start time of the equipment operation, is the proportion coefficient of the i-th operating environment data, is the i-th operating environment data at time t, The closest one in the data security range of the i-th operating environment The value of is the maximum value in the data security range of the i-th operating environment, is the minimum value in the safe range of the i-th operating environment data, dt is the time integral, and it is reasonable for the applicant to reflect the abnormal operation of the power environment during a period of time by integrating the difference between the operating environment data of a period of time and the standard operating environment data;
[0075] It should be noted that the above steps are explained here by a specific embodiment: The following are answers to these questions:
[0076] 1. Temperature range: Computers should generally work at room temperature between 15℃ and 35℃, and the ideal temperature range is between 20℃ and 25℃. Temperatures that are too low or too high may have adverse effects on the computer, such as causing slow operation, hardware damage, or data loss;
[0077] 2. Humidity range: The relative humidity of the computer room should be controlled between 20% and 80%, and the ideal range is 40% to 70%. Too high or too low humidity may cause damage to the computer, such as causing circuit board short circuits and hardware damage;
[0078] 3. Cleanliness: The computer working environment should be kept clean and free from excessive dust. Dust will affect the reading and writing functions of the computer and shorten its service life;
[0079] 4. Vibration and noise: The computer should not be operated in an environment with large vibration and noise to prevent component damage or data loss;
[0080] 5. Power supply stability: Computers require stable voltage and the power supply should not be interrupted during operation. Unstable voltage can cause a variety of problems, such as hardware damage, data loss, etc. An uninterruptible power supply (UPS) should be equipped to continue to power the computer after a power outage, so that operators can process and save data in time;
[0081] 6. Electromagnetic interference: Computers should avoid interference from strong electromagnetic fields to prevent data corruption or hardware failure;
[0082] Substitute the data into the specific embodiment for calculation;
[0083] In this embodiment, substituting the evaluated power equipment operation abnormality coefficient and power environment operation abnormality coefficient into the energy-saving output value calculation formula to output the energy-saving output value includes the following specific contents:
[0084] S41, obtaining the calculated power equipment operation abnormality coefficient and power environment operation abnormality coefficient, and importing them into the overall abnormality value calculation formula to calculate the overall abnormality value, wherein the overall abnormality value calculation formula is: ,in, is the proportion of abnormal operation of power equipment, is the proportion of abnormal operation of the power environment, among which: ;
[0085] It should be noted here that the method for obtaining the abnormal operation ratio of power equipment and the abnormal operation ratio of power environment has been pointed out below;
[0086] S42, obtaining the calculated overall abnormal value, and importing the overall abnormal value and the rated power of the power equipment into the energy-saving output value calculation formula to output the energy-saving output value, wherein the energy-saving output value calculation formula is: ,in, is the rated power of the power equipment, exp() is the power of e;
[0087] In this embodiment, S5 includes the following specific contents:
[0088] The calculated energy-saving output value is obtained, and the electric energy output module is controlled to output the energy-saving output value to the electric equipment to make the electric equipment operate.
[0089] It should be noted that the method for taking the values of the abnormal operation ratio of power equipment, the abnormal operation ratio of power environment and the ratio coefficient of the i-th operating environment data is as follows: 5000 sets of power equipment operation data and operating environment data are obtained, and the power data that can make the equipment operate normally are obtained at the same time, and the obtained power equipment operation data and operating environment data are correspondingly substituted into the energy-saving output value calculation formula to calculate the energy-saving output value, and the calculated energy-saving output value and the power data that can make the equipment operate normally are imported into the fitting software to output the abnormal operation ratio of power equipment, the abnormal operation ratio of power environment and the ratio coefficient of the i-th operating environment data that meet the highest judgment accuracy;
[0090] Through this embodiment, it is possible to achieve the following: collecting power input data, power equipment operation data and operation environment data through the power data acquisition module, and transmitting the data to the power management platform, importing the acquired power input data and power equipment operation data into the power equipment operation abnormality coefficient evaluation strategy to conduct power equipment operation abnormality evaluation, importing the acquired operation environment data into the power environment abnormality evaluation strategy to conduct power environment abnormality evaluation, substituting the evaluated power equipment operation abnormality coefficient and power environment operation abnormality coefficient into the energy-saving output value calculation formula to output the energy-saving output value, obtaining the obtained energy-saving output value, and inputting energy of the power equipment according to the obtained energy-saving output value, thereby improving the energy-saving effect and the operation efficiency of the power equipment.
[0091] Example 2
[0092] like Figure 4 As shown, an energy-saving management system based on electric power big data is implemented based on the above-mentioned energy-saving management method based on electric power big data, and specifically includes: a data acquisition module, an equipment operation abnormality assessment module, an environmental abnormality assessment module, an energy output calculation module, an energy output module and a control module, the data acquisition module is used to collect power input data, power equipment operation data and operation environment data through the power data acquisition module, and transmit the data to the power management platform, the equipment operation abnormality assessment module is used to import the acquired power input data and power equipment operation data into the power equipment operation abnormality coefficient assessment strategy to conduct power equipment operation abnormality assessment, and the environmental abnormality assessment module is used to import the acquired operation environment data into the power environment abnormality assessment strategy to conduct power environment abnormality assessment; the energy output calculation module is used to substitute the evaluated power equipment operation abnormality coefficient and power environment operation abnormality coefficient into the energy-saving output value calculation formula to output the energy-saving output value, and the energy output module is used to obtain the obtained energy-saving output value, and input the energy of the power equipment according to the obtained energy-saving output value; the control module is used to control the operation of the data acquisition module, the equipment operation abnormality assessment module, the environmental abnormality assessment module, the energy output calculation module and the energy output module.
[0093] Example 3
[0094] This embodiment provides an electronic device, including: a processor and a memory, wherein the memory stores a computer program that can be called by the processor;
[0095] The processor executes the above-mentioned energy-saving management method based on power big data by calling the computer program stored in the memory.
[0096] The electronic device may have relatively large differences due to different configurations or performances, and may include one or more processors (Central Processing Units, CPU) and one or more memories, wherein the memory stores at least one computer program, and the computer program is loaded and executed by the processor to implement an energy-saving management method based on power big data provided by the above method embodiment. The electronic device may also include other components for realizing the functions of the device. For example, the electronic device may also have components such as a wired or wireless network interface and an input and output interface to input and output data. This embodiment will not be described in detail here.
[0097] Example 4
[0098] This embodiment provides a computer-readable storage medium having a rewritable computer program stored thereon;
[0099] When the computer program runs on a computer device, the computer device executes the above-mentioned energy-saving management method based on power big data.
[0100] For example, the computer readable storage medium can be a read-only memory (ROM), a random access memory (RAM), a compact disc (CD-ROM), a magnetic tape, a floppy disk, an optical data storage device, etc.
[0101] It should be understood that in the various embodiments of the present application, the size of the serial numbers of the above-mentioned processes does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0102] It should be understood that determining B based on A does not mean determining B only based on A. B can also be determined based on A and / or other information.
[0103] The above embodiments can be implemented in whole or in part by software, hardware, firmware or any other combination. When implemented by software, the above embodiments can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions or computer programs. When a computer instruction or computer program is loaded or executed on a computer, a process or function according to an embodiment of the present invention is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network or other programmable device. Computer instructions can be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium. For example, computer instructions can be transmitted from one website, computer, server or data center to another website, computer, server or data center through a wired network or / and a wireless network. The computer-readable storage medium can be any available medium that can be accessed by a computer or a data storage device such as a server or data center that contains one or more available media sets. The available medium can be a magnetic medium (for example, a floppy disk, a hard disk, a tape), an optical medium (for example, a DVD) or a semiconductor medium. The semiconductor medium can be a solid-state hard disk.
[0104] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed in the present invention can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.
[0105] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0106] In the several embodiments provided by the present invention, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic, for example, the division of units is only one way of division, and there may be other ways of division in actual implementation, for example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0107] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0108] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.
[0109] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0110] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. An energy-saving management method based on power big data, characterized in that: It includes the following specific steps: S1. Collect power input data, power equipment operation data and operation environment data through the power data acquisition module, and transmit the data to the power management platform; S2, importing the acquired power input data and power equipment operation data into the power equipment operation abnormality coefficient evaluation strategy to perform power equipment operation abnormality evaluation; S3, importing the acquired operating environment data into the power environment anomaly assessment strategy to conduct power environment anomaly assessment; S4, substituting the evaluated power equipment operation abnormality coefficient and power environment operation abnormality coefficient into the energy-saving output value calculation formula to output the energy-saving output value; S5. Obtain the energy-saving output value, and input energy into the power equipment according to the obtained energy-saving output value.
2. The energy-saving management method based on power big data according to claim 1, characterized in that: The S1 comprises the following specific steps: S11, collecting power input data of the power equipment through the power data collection terminal, wherein the power input data includes input voltage and input current data, and collecting power equipment operation data through the power equipment operation data collection terminal, wherein the power equipment operation data includes output data of the output end of the power equipment, and storing them in the first storage module; S12, collecting operating environment data of the power equipment during operation through the operating environment collection terminal, and storing the collected operating environment data in a second storage module, wherein the operating environment data includes temperature, humidity and noise intensity data; S13, transmitting the data stored in the first storage module and the second storage module to the power management platform.
3. The energy-saving management method based on power big data according to claim 2, characterized in that: The specific contents of the power equipment operation abnormality coefficient evaluation strategy in S2 are as follows: S21, acquiring power input data of the power equipment and output data of the output end of the power equipment, importing the acquired power input data into the power input-output data calculation formula of the power equipment to calculate the rated output data of the power equipment corresponding to the power input data, and acquiring the rated output data of the power equipment corresponding to the power input data; S22, substituting the rated output data of the power equipment corresponding to the acquired power input data and the acquired output data of the output end of the power equipment into the power equipment operation abnormality coefficient evaluation formula to calculate the power equipment operation abnormality coefficient, the power equipment operation abnormality coefficient evaluation formula is: , where T is the operating time of the power equipment, dt is the time integral, is the output data of the output terminal of the power equipment at time t, is the power input data of the power equipment at time t, where: This is the calculation formula for the power input-output data of the power equipment.
4. The energy-saving management method based on power big data according to claim 3 is characterized in that: The specific content of the power environment abnormality assessment strategy in S3 is: The operating environment data of the power equipment during operation is obtained, and the obtained operating environment data is substituted into the power environment operation abnormality coefficient calculation formula to calculate the power environment operation abnormality coefficient, wherein the power environment operation abnormality coefficient calculation formula is: , where T is the operating time of the power equipment, n is the number of types of operating environment data, is the start time of the equipment operation, is the proportion coefficient of the i-th operating environment data, is the i-th operating environment data at time t, The closest one in the data security range of the i-th operating environment The value of is the maximum value in the data security range of the i-th operating environment, is the minimum value in the safe range of the i-th operating environment data, and dt is the time integral.
5. The energy-saving management method based on power big data according to claim 4, characterized in that: Substituting the evaluated power equipment operation abnormality coefficient and power environment operation abnormality coefficient into the energy-saving output value calculation formula to output the energy-saving output value includes the following specific contents: S41, obtaining the calculated power equipment operation abnormality coefficient and power environment operation abnormality coefficient, and importing them into the overall abnormality value calculation formula to calculate the overall abnormality value, wherein the overall abnormality value calculation formula is: ,in, is the proportion of abnormal operation of power equipment, is the proportion of abnormal operation of the power environment, among which: ; S42, obtaining the calculated overall abnormal value, and importing the overall abnormal value and the rated power of the power equipment into the energy-saving output value calculation formula to output the energy-saving output value, wherein the energy-saving output value calculation formula is: ,in, is the rated power of the power equipment, and exp() is the power of e.
6. The energy-saving management method based on power big data according to claim 5, characterized in that: The S5 includes the following specific contents: The calculated energy-saving output value is obtained, and the electric energy output module is controlled to output the energy-saving output value to the electric equipment to make the electric equipment operate.
7. An energy-saving management system based on electric power big data, which is implemented based on the energy-saving management method based on electric power big data as claimed in any one of claims 1 to 6, characterized in that: It specifically includes: a data acquisition module, an equipment operation abnormality assessment module, an environmental abnormality assessment module, an energy output calculation module, an energy output module and a control module. The data acquisition module is used to collect power input data, power equipment operation data and operating environment data through the power data acquisition module, and transmit the data to the power management platform. The equipment operation abnormality assessment module is used to import the acquired power input data and power equipment operation data into the power equipment operation abnormality coefficient assessment strategy to perform power equipment operation abnormality assessment. The environmental abnormality assessment module is used to import the acquired operating environment data into the power environment abnormality assessment strategy to perform power environment abnormality assessment.
8. An energy-saving management system based on power big data as described in claim 7, characterized in that: The energy output calculation module is used to substitute the evaluated abnormal operation coefficient of the power equipment and the abnormal operation coefficient of the power environment into the energy-saving output value calculation formula to output the energy-saving output value. The energy output module is used to obtain the obtained energy-saving output value and input the energy of the power equipment according to the obtained energy-saving output value.
9. An energy-saving management system based on power big data as described in claim 8, characterized in that: The control module is used to control the operation of the data acquisition module, the equipment operation abnormality assessment module, the environment abnormality assessment module, the energy output calculation module and the energy output module.
10. An electronic device, characterized in that: include: A processor and a memory, wherein the memory stores a computer program that can be called by the processor; The processor executes the energy-saving management method based on power big data described in any one of claims 1 to 6 by calling the computer program stored in the memory.
11. A computer-readable storage medium, characterized in that: Instructions are stored, and when the instructions are executed on a computer, the computer executes an energy-saving management method based on electric power big data as described in any one of claims 1 to 6.
Citation Information
Patent Citations
Data acquisition and analysis method and real-time analysis system for terminal motors
CN109061470A
Power flow calculation method for power distribution network with new energy grid connection
CN117318064A
Indoor equipment monitoring system for wireless base station and monitoring method thereof
CN117499957A
Chlorination process practical training safety control system and control method
CN118151621A
Intelligent government affair big data analysis system and method based on artificial intelligence
CN118333359A
Cited By
Equipment abnormity early warning and multi-dimensional management system based on IBMS
CN120634063A
An IBMS-based device anomaly early warning and multi-dimensional management system
CN120634063B