Highway bridge high-pressure-bearing precast beam component and mounting method
By adopting the matching structure of support beam components and support plate components in highway bridges, the capacity-bearing performance of the intermediate area is improved, and the problem of reduced pressure performance in the central load-bearing part of the bridge is solved, which extends the service life and improves safety and installation efficiency.
Patent Information
- Application Number
- CN202411467886.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-21
- Publication Date
- 2024-11-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The pressure bearing performance of the central load-bearing part of the high-pressure working state will decrease under long-term high-pressure working conditions, which will easily cause safety hazards.
Using mutually fitted support beam assembly and support plate assembly, the support beam assembly serves as the gravity bearing structure of the bridge at the center point. The intermediate area can be lifted through movable connection and reinforcement of prefabricated beams. The main support beam and support base pass through rotating bearing seats and elasticity. The top column is fitted, and a rotating bearing seat is installed at the bottom of the main support beam to suit long-term use.
It significantly improves the capacity of the weakest intermediate area in the bridge, extends the service life, ensures the stability and safety of the bridge, while simplifying the installation process and improving maintenance convenience.
Smart Images

Figure CN118958113A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of highway bridge construction, and in particular to a high-pressure-bearing prefabricated beam component of a highway bridge and an installation method thereof. Background Art
[0002] Highway bridges are built for the passage of vehicles and pedestrians on expressways. Made of steel, reinforced concrete, or wood, they are designed to withstand heavy rolling loads of up to 8,000 tons. The width of the driving section depends on the expected intensity and speed of traffic, as well as the shape and span of the bridge (typically 7-21 meters). Sidewalks are at least 1 meter wide.
[0003] The common types of existing highway bridges are beam bridges, arch bridges, rigid frame bridges, etc. It has become a trend to use high-strength prefabricated steel structures for on-site assembly. Its advantages are: 1. Prefabricated parts can be prefabricated in the factory, with a higher degree of automation, reducing manual intervention, and can be assembled and connected with each other on the construction site, which has a stronger integrity and higher efficiency and precision, and the finished product has better completion and integrity; 2. During the production process of prefabricated parts, high-strength steel with higher purity can be used for prefabrication. Compared with the mixture of reinforced concrete, high-strength steel has stronger load-bearing performance and rigidity, and longer service life.
[0004] However, in highway bridge construction, due to the strong integrity of prefabricated parts, the supporting strength of the complete body is reflected in the connections between the prefabricated parts. The prefabricated parts are mostly connected with high-strength prefabricated components to ensure the strength of the connections.
[0005] The invention patent with Chinese patent application number 202210691911.8 discloses an improved bridge stress panel prefabricated component, including a box panel and a box body installed under the box panel, and the box body cross-section is a trapezoidal structure; the bridge panel is formed by integrally casting between the box panel and the box body, and the stress mechanism set on the box body is tensioned so that the box panel and the box body can withstand greater pressure, thereby ensuring the supporting performance of the box panel; the guide mechanism is lifted up by the stress mechanism, and then the guide mechanism moves upward, and the guide mechanism drives the tensioning mechanism to move upward, and then the tensioning mechanism itself is tightened, so that the tensioning mechanism tightens the box panel, which plays a role in stabilizing the box panel, and the limiting mechanism is able to touch the stress mechanism downward, and then the limiting mechanism will be engaged with the pier, so that the performance of the pier supporting the box body is better. The technical solution proposed in the above invention is to increase the stability of the long bridge panel headquarters by adding prefabricated components due to the large stress they bear; however, its structure is relatively complex, which will inevitably lead to cumbersome maintenance procedures in the later stages. Moreover, for large-scale infrastructure such as bridges, their service life is at least more than ten years, so the requirements for their structural stability are more stringent. At the same time, due to their aesthetics and practicality, arch bridges with upward protruding middle parts are gradually withdrawing from the market and being replaced by flat bridges. The flat bridges have much higher requirements for the load-bearing performance of their central parts than arch bridges. Summary of the Invention
[0006] Therefore, based on the above concept, the present invention proposes a high-pressure-bearing prefabricated beam component and installation method for highway bridges, which solves the technical problem that the pressure-bearing performance of the central load-bearing part of the highway bridge decreases under long-term high-pressure working conditions, which easily causes safety hazards.
[0007] To achieve the above objectives, the present invention adopts the following technical solutions: a high-pressure prefabricated beam component for a highway bridge, comprising a supporting beam assembly and a supporting plate assembly that cooperate with each other, wherein the supporting plate assembly serves as the pavement support surface of the bridge, and is paved with cement or asphalt to form the pavement, and the supporting beam assembly serves as the central gravity-bearing structure of the bridge, bearing the gravity from the supporting plate assembly and the pedestrians and vehicles above it during use; The support plate assembly and the support beam assembly are movably connected, the support plate assembly is used to connect the two ends of the plane road, the support beam assembly is arranged at the center position of the support plate assembly, and the bottom of the support beam assembly is connected to the ground; The support plate assembly includes a first road plate surface and a second road plate surface of identical structure, a central support beam component, a left reinforcing component, and a right reinforcing component. A plurality of prefabricated reinforcing beams are provided below the first road plate surface and the second road plate surface. The central support beam component is used to connect the first road plate surface and the second road plate surface. The left reinforcing component is provided on a side edge of the first road plate surface away from the second road plate surface. The right reinforcing component is provided on a side edge of the second road plate surface away from the first road plate surface. The support beam assembly includes a main support beam, a left support beam, a right support beam and a support base, the support base is fixedly connected to the ground, a main connection groove and a secondary connection groove are opened on the upper surface of the support base, the secondary connection grooves are symmetrically arranged on both sides of the main connection groove, the main connection groove is connected to the main support beam, and the secondary connection grooves are respectively connected to the left support beam and the right support beam; One end of the main support beam is connected to the support base, and the other end is connected to the central support beam member; one end of the left support beam is connected to the support base, and the other end is connected to the left reinforcement member; one end of the right support beam is connected to the support base, and the other end is connected to the right reinforcement member; The main support beam improves its coordination with the support base under the action of the support plate assembly and the pressure above it.
[0008] Furthermore, each of the reinforced prefabricated beams is arranged along the length direction of the first highway slab and the second highway slab, and the distance between two adjacent reinforced prefabricated beams is the same.
[0009] Furthermore, the width of the central support beam component in the horizontal plane accounts for one-fifth to one-quarter of the width of the first highway slab.
[0010] Furthermore, the central support beam component includes an upper support beam and a lower support beam that are clamped together, the upper support beam and the lower support beam are locked by bolts, and the vertical cross-sections of the upper support beam and the lower support beam after being fitted together are I-shaped, and the first highway plate surface and the second highway plate surface are clamped on both sides of the central support beam component.
[0011] Furthermore, the structures of the left reinforcing member and the right reinforcing member are symmetrical to each other. The left reinforcing member includes a left upper beam and a left lower beam that are snap-fitted to each other, and the right reinforcing member includes a right upper beam and a right lower beam that are snap-fitted to each other. The left upper beam and the left lower beam are locked together by bolts, and the right upper beam and the right lower beam are locked together by bolts. Protective fences are provided on the left upper beam and the right upper beam.
[0012] Furthermore, an extended clamping portion is provided on the main support beam, and the extended clamping portion extends toward the left reinforcing member and the right reinforcing member respectively and is clamped with the left lower beam and the right lower beam respectively.
[0013] Furthermore, a rotating bearing seat is provided at the bottom of the main support beam, and the rotating bearing seat rotates horizontally 360° along the central axis of the main support beam. A first thread is provided on the outer circumferential side of the rotating bearing seat, and a second thread is provided on the inner circumferential side of the main connecting groove, and the first thread and the second thread are engaged with each other.
[0014] Furthermore, a plurality of elastic top columns are provided on the outer circumferential side surface of the rotating bearing seat, and the elastic top columns are arranged at intervals along the spiral direction of the first thread. A plurality of arc grooves are provided on the inner circumferential side surface of the main connecting groove, and the arc grooves are arranged at intervals along the spiral direction of the second thread. The elastic top columns and the arc grooves cooperate with each other.
[0015] Furthermore, an inclined transition surface is provided on the elastic top column.
[0016] A method for installing a high-pressure prefabricated beam component of a highway bridge comprises the following steps: S1. Assemble the support plate assembly: first, lay the lower support beam flat on the ground, align the first and second road plate surfaces and lay them flat on both sides of the lower support beam, then snap-fit the upper and lower support beams together and fasten them with bolts to form a central support beam component and preliminarily secure the first and second road plate surfaces; install the left and right reinforcement components in the same manner; S2. Install the protective fence: Fix the protective fence on the left upper beam and the right upper beam. At the same time, you can install the protective fence or green belt fence on the upper support beam simultaneously. S3. Install the support beam assembly: excavate the ground foundation, place the support base on the cement foundation and secure it with reinforced bolts; then place the main support beam, left support beam, and right support beam in the main connection groove and auxiliary connection groove respectively; S4. The support plate assembly is coordinated with the support beam assembly; positioning grooves are excavated on the curbs on both sides in advance and hard-formed with cement to place and fix the support plate assembly. The support plate assembly is lifted by a crane and placed in the positioning groove. At the same time, the main support beam, left support beam and right support beam are fixedly connected to the central beam component, left reinforcement component and right reinforcement component respectively. The installation is now completed.
[0017] By adopting the above technical solution, the beneficial effects of the present invention are: 1. Compared with the existing prefabricated beam structures in the field of bridges, the present invention has better pressure-bearing performance and longer service life. Specifically, through the coordinated support plate assembly and support beam assembly, the weakest middle area of the bridge can have better pressure-bearing performance, thereby improving the safety of bridge use. The present invention is a prefabricated component as a whole, which greatly improves the installation efficiency. The road surface adopts the method of separating the first highway plate surface and the second highway plate surface from each other, in order to separate the pressure of the two and avoid the risk of deformation caused by excessive pressure of the overall prefabricated component. Support beam assemblies are provided for supporting the pressure of the first highway plate surface and the second highway plate surface. The prefabricated beam bridge During use, the center of the beam is the center of pressure in both the length and width directions. The reason is that both sides of the bridge can contact the ground, while the center is far away from the ground. At the same time, the center in the width direction serves as the expressway, and the traffic volume above it is the largest during daily use, which also makes it the focus of pressure. Therefore, the present invention arranges a support beam assembly at the center position to improve the pressure-bearing performance of the bridge during overall use, so as to ensure its stability and service life. The main support beam in the support beam assembly serves as a supporting component that directly contacts the center of the bridge. It can continuously perform fine-tuning after being subjected to pressure from above, so that it will not shake, thereby ensuring that its supporting performance always remains excellent.
[0018] 2. The present invention is provided with reinforcing prefabricated beams at the lower bottom surfaces of the first highway slab and the second highway slab. The function of the reinforcing prefabricated beams is reflected in that they are in direct contact with the first highway slab and the second highway slab, and are arranged along the length direction of the first highway slab and the second highway slab, playing a role similar to that of steel bars in a house structure, thereby improving the stability of the bridge during use. In addition, the I-beams are arranged at intervals, which can simplify materials while ensuring that the supporting performance does not change.
[0019] 3. In the present invention, the width of the central support beam component in the horizontal plane accounts for one-fifth to one-quarter of the width of the first highway slab, in order to ensure the contact area between it and the first highway slab and the second highway slab and thus ensure its support stability.
[0020] 4. The central support beam member, the left reinforcement member and the right reinforcement member in the present invention are divided into two upper and lower spliced bodies, the purpose of which is to ensure the flexibility of installation while improving the convenience of subsequent bridge maintenance.
[0021] 5. In the present invention, an extended clamping part is provided on the support beam, wherein the extended clamping part mainly cooperates with the central support beam component to make the cooperation between the first highway plate surface and the second highway plate surface tighter, and ensure that the two will not produce gaps due to the vibration transmitted by the running of the car above, thereby affecting the stability of the overall structure, that is, the central support beam component from the center.
[0022] 6. In the present invention, the bottom of the main support beam is structurally improved to enable it to adapt to the long-term use of the bridge. The essential reason is that the main support beam is the most important pressure-bearing component of the bridge. Whether it is stable directly leads to the stability of the entire bridge and is directly related to the safety of the bridge. At the same time, since the material of the prefabricated beam components is very mature and reliable high-strength composite steel is used, the vibration caused by the pressure above it is negligible. However, for prefabricated parts, they are different from reinforced concrete structures. They are made of metal parts spliced together. Long-term vibration will also cause their internal structure to loosen. Therefore, the bottom of the main support beam is structurally improved, specifically: a rotating bearing seat is provided, so that the rotating bearing seat is directly connected to the support base. The rotating bearing seat can rotate 360° on the horizontal plane along the central axis of the main support beam, but its stability in the vertical direction remains unchanged. A first thread is provided on the outer circumferential side of the rotating bearing seat, and a second thread is provided in the main connecting groove on the support base. The main support beam is made by the cooperation of the first thread and the second thread. The cam is screwed to the support base in a screw-type manner. There is a certain margin after the two are connected. At this time, the two are already in a tightly fitted state. The reason is that an elastic top column is provided on the outer circumferential side surface of the rotating bearing seat, and an arc groove is provided on the inner circumferential side surface of the main connecting groove. The elastic top column and the arc groove cooperate with each other to ensure that the main support beam and the support base are locked with each other and do not loosen. When the upper pressure increases, the support plate assembly is subjected to force and transmitted to the main support beam. The main support beam continues to rotate downward and screws together slightly. The elastic top column and the arc groove reach the next state of cooperation. It ensures that even if the support plate assembly is slightly deformed under high-intensity pressure and transmits the high-intensity pressure downward to the main support beam, the main support beam can always tightly connect the support plate assembly and the support base to achieve the three-in-one and no shaking. It is well known that the main risk of prefabricated beam components when used as a whole after cooperation is local loose vibration, which will directly lead to instability of the overall structure. The present invention completely eliminates the occurrence of this situation, thereby improving the stability and service life of the bridge.
[0023] 7. The present invention simultaneously proposes an installation method for the high-pressure-bearing prefabricated beam components of the highway bridge. This method pre-processes the terrain so that the two ends of the support plate assembly can be fixed against the two ends of the road trough for installation. At the same time, the support plate assembly and the support beam assembly are pre-assembled and then directly installed on the construction site. The pre-installation adopts mechanized automatic installation. The overall process simplifies labor and improves efficiency, and avoids excessive manual intervention to reduce the accuracy of the fit between mechanical components. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Other features, objects and advantages of the present invention will become more apparent upon reading the detailed description of non-limiting embodiments with reference to the following drawings: Figure 1 It is a three-dimensional diagram of the overall structure of the present invention; Figure 2 for Figure 1 Enlarged view of point A in the middle; Figure 3 A top view of the support rod base in the present invention; Figure 4 This is a schematic diagram of the side structure of the support plate assembly in the present invention; Figure 5 This is a schematic structural diagram of the support beam assembly in the present invention; Figure 6 This is a schematic diagram of the coordination structure between the main support beam and the support base in the present invention; Figure 7 for Figure 6 Enlarged view of point B in the middle; Figure 8 This is a schematic diagram of the matching structure between the rotating bearing seat and the main connecting groove in the present invention; Figure 9 for Figure 8 Enlarged view of point C in the middle; Figure 10 This is a flow chart of the installation method in the present invention. DETAILED DESCRIPTION
[0025] In order to make the technical means, creative features, objectives and effects achieved by the present invention easier to understand, the present invention is further described below in conjunction with specific implementation methods.
[0026] See also Figures 1-10 The present invention provides a high-pressure prefabricated beam component for a highway bridge, comprising a supporting beam assembly and a supporting plate assembly that cooperate with each other. The supporting plate assembly serves as the pavement support surface of the bridge, and is paved with cement or asphalt to form a pavement. The supporting beam assembly serves as the central gravity-bearing structure of the bridge, bearing the gravity from the supporting plate assembly and the pedestrians and vehicles above it during use. The support plate assembly and the support beam assembly are movably connected, the support plate assembly is used to connect the two ends of the plane road, the support beam assembly is arranged at the center position of the support plate assembly, and the bottom of the support beam assembly is connected to the ground; The support plate assembly includes a first highway plate surface 1 and a second highway plate surface 2 of identical structure, a central support beam component 3, a left reinforcing component 4, and a right reinforcing component 5. A plurality of reinforcing prefabricated beams 11 are provided below the first highway plate surface 1 and the second highway plate surface 2. The central support beam component 3 is used to connect the first highway plate surface 1 and the second highway plate surface 2. The left reinforcing component 4 is provided on an edge of the first highway plate surface 1 away from the second highway plate surface 2. The right reinforcing component 5 is provided on an edge of the second highway plate surface 2 away from the first highway plate surface 1. The support beam assembly includes a main support beam 6, a left support beam 7, a right support beam 8 and a support base 9. The support base 9 is fixedly connected to the ground. A main connecting groove 91 and a secondary connecting groove 92 are provided on the upper surface of the support base 9. There are two secondary connecting grooves 92, which are symmetrically arranged on both sides of the main connecting groove 91. The main connecting groove 91 is connected to the main support beam 6, and the secondary connecting grooves 92 are respectively connected to the left support beam 7 and the right support beam 8; One end of the main support beam 6 is connected to the support base 9, and the other end is connected to the central support beam member 3; one end of the left support beam 7 is connected to the support base 9, and the other end is connected to the left reinforcement member 4; one end of the right support beam 8 is connected to the support base 9, and the other end is connected to the right reinforcement member 5; The main support beam 6 improves its fit with the support base 9 under the pressure of the support plate assembly and the pressure above it.
[0027] Each of the reinforced prefabricated beams 11 is arranged along the length direction of the first highway slab 1 and the second highway slab 2. The spacing between two adjacent reinforced prefabricated beams 11 is the same. The width of the central support beam component 3 in the horizontal plane accounts for one-fifth of the width of the first highway slab 1, ensuring that the contact area between the two is sufficient.
[0028] The central support beam component 3 includes an upper support beam 31 and a lower support beam 32 that are snap-fitted to each other, and the upper support beam 31 and the lower support beam 32 are locked by bolts. The vertical cross-section of the upper support beam 31 and the lower support beam 32 after being matched is an I-shape, and the first highway slab 1 and the second highway slab 2 are snap-fitted to both sides of the central support beam component 3; the left side reinforcement component 4 and the right side reinforcement component 5 are symmetrical in structure, and the left side reinforcement component 4 includes a left side upper beam 41 and a left side lower beam 42 that are snap-fitted to each other, and the right side reinforcement component 5 includes a right side upper beam 51 and a right side lower beam 52 that are snap-fitted to each other, and the left side upper beam 41 and the left side lower beam 42 are locked by bolts, and the right side upper beam 51 and the right side lower beam 52 are locked by bolts, and a protective fence 43 is provided on the left side upper beam 41 and the right side upper beam 51.
[0029] The main support beam 6 is provided with an extended clamping portion 61, which extends toward the left reinforcing member 4 and the right reinforcing member 5 and is clamped with the left lower beam 42 and the right lower beam 52 respectively; The bottom 6 of the main support beam is provided with a rotating bearing seat 62, and the rotating bearing seat 62 rotates horizontally 360° along the central axis of the main support beam 6. A first thread 621 is provided on the outer circumferential side surface of the rotating bearing seat 62, and a second thread 911 is provided on the inner circumferential side surface of the main connecting groove 91. The first thread 621 and the second thread 911 are engaged with each other. A plurality of elastic top columns 622 are provided on the outer circumferential side surface of the rotating bearing seat 62, and the elastic top columns 622 are arranged at intervals along the spiral direction of the first thread 621. A plurality of arc grooves 912 are provided on the inner circumferential side surface of the main connecting groove 91, and the arc grooves 912 are arranged at intervals along the spiral direction of the second thread 911. The elastic top column 622 and the arc groove 912 cooperate with each other, and an inclined transition surface 6221 is provided on the elastic top column 622.
[0030] The present invention simultaneously proposes a method for installing the above-mentioned high-pressure prefabricated beam components of the highway bridge, which includes the following steps: S1. Assemble the support plate assembly. First, lay the lower support beam 32 flat on the ground. Align the first road plate 1 and the second road plate 2 and lay them flat on both sides of the lower support beam 32. Then, snap-fit the upper support beam 31 and the lower support beam 32 together and fasten them with bolts to form the central support beam member 3 and preliminarily secure the first road plate 1 and the second road plate 2. Install the left reinforcement member 4 and the right reinforcement member 5 in the same manner. S2, installation of protective fence; the protective fence 43 is fixedly installed on the left upper beam 41 and the right upper beam 51, and the protective fence or green belt fence can be installed simultaneously on the upper support beam 31; S3. Install the support beam assembly: excavate the ground foundation, place the support base 9 on the cement foundation and fix it with reinforced bolts; then place the main support beam 6, left support beam 7 and right support beam 8 in the main connection groove 91 and the auxiliary connection groove 92 respectively; S4. The support plate assembly cooperates with the support beam assembly; positioning grooves are excavated on the curbs on both sides in advance and hard-formed with cement to place and fix the support plate assembly. The support plate assembly is lifted by a crane and placed in the positioning groove. At the same time, the main support beam 6, the left support beam 7 and the right support beam 8 are fixedly connected to the central beam component 3, the left reinforcement component 4 and the right reinforcement component 5 respectively. The installation is now completed.
[0031] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the present invention. Therefore, from all perspectives, the embodiments should be regarded as illustrative and non-restrictive. The scope of the present invention is defined by the appended claims, not the foregoing description, and it is intended that all variations that come within the meaning and range of equivalents of the claims be included within the present invention. Any reference signs in the claims should not be construed as limiting the claim to which they relate.
[0032] In addition, it should be understood that although this specification is described in terms of implementation methods, not every implementation method contains only one independent technical solution. This narrative method of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment can also be appropriately combined to form other implementation methods that can be understood by those skilled in the art.
Claims
1. A high-pressure prefabricated beam component for a highway bridge, characterized in that: It includes a supporting beam assembly and a supporting plate assembly that cooperate with each other. The supporting plate assembly serves as the pavement support surface of the bridge, and forms the pavement after paving cement or asphalt. The supporting beam assembly serves as the center point gravity bearing structure of the bridge, and bears the gravity from the supporting plate assembly and pedestrians and vehicles above it during use; The support plate assembly and the support beam assembly are movably connected, the support plate assembly is used to connect the two ends of the plane road, the support beam assembly is arranged at the center position of the support plate assembly, and the bottom of the support beam assembly is connected to the ground; The support plate assembly comprises a first road plate surface and a second road plate surface of the same structure, a central support beam component, a left reinforcing component and a right reinforcing component, a plurality of reinforcing prefabricated beams are arranged below the first road plate surface and the second road plate surface, the central support beam component is used to connect the first road plate surface and the second road plate surface, the left reinforcing component is arranged on a side edge of the first road plate surface away from the second road plate surface, and the right reinforcing component is arranged on a side edge of the second road plate surface away from the first road plate surface; The support beam assembly comprises a main support beam, a left support beam, a right support beam and a support base, wherein the support base is fixedly connected to the ground, and a main connection groove and a secondary connection groove are provided on the upper surface of the support base, wherein the secondary connection grooves are two in number and are symmetrically arranged on both sides of the main connection groove, the main connection groove is connected to the main support beam, and the secondary connection grooves are respectively connected to the left support beam and the right support beam; One end of the main support beam is connected to the support base, and the other end is connected to the central support beam member; one end of the left support beam is connected to the support base, and the other end is connected to the left reinforcement member; one end of the right support beam is connected to the support base, and the other end is connected to the right reinforcement member; The main support beam improves its coordination with the support base under the pressure of the support plate assembly and the pressure above it.
2. The high-pressure prefabricated beam component for a highway bridge according to claim 1 is characterized in that: Each of the reinforced prefabricated beams is arranged along the length direction of the first highway slab and the second highway slab, and the distance between two adjacent reinforced prefabricated beams is the same.
3. The high-pressure prefabricated beam component for a highway bridge according to claim 2 is characterized in that: The width of the central supporting beam member in the horizontal plane accounts for one fifth to one quarter of the width of the first highway deck.
4. The high-pressure prefabricated beam component for a highway bridge according to claim 3 is characterized in that: The central support beam component includes an upper support beam and a lower support beam that are clipped together. The upper support beam and the lower support beam are locked together by bolts. After the upper support beam and the lower support beam are clipped together, their vertical cross-sections are I-shaped. The first highway slab surface and the second highway slab surface are clipped together on both sides of the central support beam component.
5. The high-pressure prefabricated beam component for a highway bridge according to claim 4, characterized in that: The structures of the left reinforcing component and the right reinforcing component are symmetrical to each other. The left reinforcing component includes a left upper beam and a left lower beam that are snap-fitted to each other, and the right reinforcing component includes a right upper beam and a right lower beam that are snap-fitted to each other. The left upper beam and the left lower beam are locked by bolts, and the right upper beam and the right lower beam are locked by bolts. Protective fences are arranged on the left upper beam and the right upper beam.
6. The high-pressure prefabricated beam component for a highway bridge according to claim 5, characterized in that: The main support beam is provided with an extended clamping portion, which extends toward the left reinforcing member and the right reinforcing member respectively and is clamped with the left lower beam and the right lower beam respectively.
7. The high-pressure prefabricated beam component for a highway bridge according to claim 6, characterized in that: A rotating bearing seat is arranged at the bottom of the main support beam, and the rotating bearing seat can rotate horizontally 360° along the central axis of the main support beam. A first thread is arranged on the outer circumferential side surface of the rotating bearing seat, and a second thread is arranged on the inner circumferential side surface of the main connecting groove, and the first thread and the second thread are meshed with each other.
8. The high-pressure prefabricated beam component for a highway bridge according to claim 7, characterized in that: A plurality of elastic top columns are arranged on the outer circumferential side surface of the rotating bearing seat, and the elastic top columns are arranged at intervals along the spiral direction of the first thread. A plurality of arc grooves are arranged on the inner circumferential side surface of the main connecting groove, and the arc grooves are arranged at intervals along the spiral direction of the second thread. The elastic top columns and the arc grooves cooperate with each other.
9. The high-pressure prefabricated beam component for a highway bridge according to claim 8, characterized in that: The elastic top column is provided with an inclined transition surface.
10. A method for installing a high-pressure prefabricated beam component for a highway bridge as claimed in claim 9, characterized in that: The following steps are involved: S1. Assemble the support plate assembly; first lay the lower support beam flat on the ground, and lay the first road plate surface and the second road plate surface flush on both sides of the lower support beam, and then clamp the upper support beam and the lower support beam together and fix them with bolts to form a central support beam component and preliminarily fix the first road plate surface and the second road plate surface; install the left reinforcement component and the right reinforcement component in the same way; S2. Installation of protective fence: The protective fence is fixedly installed on the left upper beam and the right upper beam, and the protective fence or green belt fence can be installed on the upper support beam at the same time; S3, support beam assembly installation: excavate the ground foundation, place the support base on the cement foundation and fix it by reinforcing bolts; then place the main support beam, left support beam and right support beam in the main connection groove and the auxiliary connection groove respectively; S4. The support plate assembly cooperates with the support beam assembly. Positioning grooves are excavated on the curbs on both sides in advance and hard-formed with cement to place and fix the support plate assembly. The support plate assembly is lifted by a crane and placed in the positioning groove. At the same time, the main support beam, left support beam and right support beam are fixedly connected to the central beam component, the left reinforcement component and the right reinforcement component respectively. The installation is now completed.
Citation Information
Patent Citations
Improved bridge stress panel prefabricated part
CN114960421A
Prefabricated beam structure, fabricated temporary bridge and mounting method thereof
CN111254802A
Combined light swivel bridge structure and construction method thereof
CN118704365A
A highway bridge support beam reinforcement device
CN209162629U
Supporting equipment for bridge construction in field of bridge engineering
CN211312230U