Construction method for double-line bridge girder erection machine to transversely move single-line girder and drop single-line girder
Through the construction method of the two-line bridge stud machine, including transverse movement and vertical landing operations, the complexity and accuracy problems in single-line beam construction are solved, efficient and accurate construction is achieved, and the quality and safety of bridge construction are improved.
Patent Information
- Application Number
- CN202411124804.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-15
AI Technical Summary
In the prior art, when the two-line bridge stud machine performs the transverse movement and precise beam drop operation of single-line beams, there are problems such as complex operation, difficulty in ensuring accuracy, and low construction efficiency.
The construction method of a double-wire bridge tracing machine includes erecting a double-wire bridge tracing machine, hoisting a single-wire beam, installing a transverse shift assembly, starting a transverse shift mechanism, using sensors and laser positioning instruments for real-time monitoring and adjustment, vertical landing, and fixing and test to ensure accuracy and safety.
Efficient and precise construction has been achieved, the construction cycle has been shortened, the cost has been reduced, and the quality and safety of bridge construction have been improved.
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge construction, in particular to a construction method for a double-track bridge erecting machine to transversely move a single-track beam and drop the beam. Background Art
[0002] In bridge construction, for double-track bridge construction, double-track bridge erection machines are usually used to transport and install beams. Existing technical solutions have problems such as complex operation, difficult to ensure accuracy, and low construction efficiency when performing lateral movement and precise beam placement operations on single-track beams. Summary of the invention
[0003] 1. Technical issues to be resolved
[0004] In view of the deficiencies in the prior art, the present invention provides a construction method for transversely moving a single-line beam and dropping a double-line bridge erecting machine.
[0005] (II) Technical solution
[0006] To achieve the above object, the present invention provides the following technical solution: a construction method for transversely moving a single-line beam of a double-line bridge erecting machine, comprising the following steps:
[0007] Step 1: Install a double-line bridge-erecting machine: Install a double-line bridge-erecting machine on the bridge pier to make it span the construction section;
[0008] Step 2: Hoist the single-line beam: Hoist the single-line beam onto the double-line bridge-erecting machine through a lifting device to ensure its stability;
[0009] Step 3, preparation for transverse movement: install the transverse movement assembly on the transverse movement mechanism of the double-line bridge erecting machine, and fix the single-line beam on the transverse movement assembly;
[0010] Step 4: Transverse movement operation: start the transverse movement mechanism of the double-line bridge erecting machine to horizontally move the single-line beam to the predetermined beam drop position;
[0011] Step 5: Precise positioning: Use sensors and laser positioning instruments to monitor and adjust the lateral position of the single-line beam in real time;
[0012] Step 6, beam drop operation: after the single-line beam reaches the predetermined position, the vertical drop mechanism of the double-line bridge erecting machine is used to slowly drop the single-line beam onto the bridge pier to ensure that it is dropped smoothly;
[0013] Step 7, Fixing and testing: After the beam is dropped, the single-line beam is fixed and installed, and tested to ensure the accuracy and safety of the beam position, angle and load-bearing capacity.
[0014] Preferably, the detailed steps in step 1 include:
[0015] Step a1: Clean the construction site, ensure that the top area of the pier is clean and free of debris, and check the stability of the pier;
[0016] Step a2: Establish a temporary construction platform between the bridge piers to assist the erection process of the double-line bridge erecting machine;
[0017] Step a3: Align the base of the double-line bridge erecting machine with the top of the bridge pier and use bolts or other fixing devices to perform preliminary fixing;
[0018] Step a4: Use a level and theodolite to calibrate the bridge crane in the horizontal and vertical directions to ensure that the installation angle and position are accurate, and finally fix the double-line bridge crane to make it firm and stable.
[0019] Preferably, the detailed steps of step 2 include:
[0020] Step b1: Check the integrity of the single-line beam to ensure that there are no cracks or other damages on the beam;
[0021] Step b2: Install lifting points at both ends of the single-line beam and connect the lifting points through lifting cables;
[0022] Step b3, operate the crane to slowly lift the single-line beam to the top of the double-line bridge erecting machine, while ensuring the tightness and safety of the steel cables and lifting points;
[0023] Step b4: Place the single-line beam steadily on the transverse movement assembly of the double-line bridge-building machine. The operator monitors the lifting process in real time to ensure that there is no swing or tilt.
[0024] Preferably, the detailed steps of step 3 include:
[0025] Step c1, installing a transverse movement assembly on the transverse movement track of the double-track bridge erecting machine, including a roller, a slider and a guide device;
[0026] Step c2, fix both ends of the single-line beam to the support points of the transverse movement assembly to ensure that the beam body will not tilt or shift during the transverse movement;
[0027] Step c3, check the fastening status of each connection point of the lateral movement device to ensure that all moving parts are in normal working condition;
[0028] Step c4: Set up a safety warning area on top of the bridge pier and around the double-line bridge-erecting machine to avoid accidents during the construction process.
[0029] Preferably, the detailed steps of step 7 include:
[0030] Step g1: After the single-line beam is dropped to the pier support, bolts, steel plates and other fixing devices are used to temporarily fix the beam body. After confirming that the beam body will not move, the connection between the transverse movement assembly and the landing device is released;
[0031] Step g2: Use precision measuring instruments to test the geometric position, horizontality and verticality of the single-line beam to ensure that the beam position meets the design requirements. If there is any deviation, use adjustment devices such as jacks to make minor adjustments until all indicators meet the standards.
[0032] Step g3: Perform final welding and bolt tightening operations to ensure the stability and bearing capacity of the connection between the single-line beam and the bridge pier, and perform anti-corrosion and waterproofing treatment on the fixing points to ensure durability and safety in long-term use.
[0033] (III) Beneficial effects
[0034] Compared with the prior art, the present invention provides a construction method for transversely moving a single-line beam and dropping a double-line bridge erecting machine, which has the following beneficial effects:
[0035] The construction method of the double-line bridge erecting machine to move the single-line beam horizontally and drop the beam is suitable for various bridge construction occasions, especially those large-scale projects that require frequent horizontal movement and precise beam dropping operations. Its efficient and precise construction characteristics greatly shorten the construction period, reduce construction costs, and improve the quality and safety of bridge construction. DETAILED DESCRIPTION
[0036] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0037] A construction method for transversely moving a single-line beam and dropping a double-line bridge erecting machine comprises the following steps:
[0038] Step 1: Install a double-line bridge-erecting machine: Install a double-line bridge-erecting machine on the bridge pier to make it span the construction section; the specific steps are:
[0039] Step a1: Clean the construction site, ensure that the top area of the pier is clean and free of debris, and check the stability of the pier;
[0040] Step a2: Establish a temporary construction platform between the bridge piers to assist the erection process of the double-line bridge erecting machine;
[0041] Step a3: Align the base of the double-line bridge erecting machine with the top of the bridge pier and use bolts or other fixing devices to perform preliminary fixing;
[0042] Step a4: Use a level and theodolite to calibrate the bridge crane in the horizontal and vertical directions to ensure that the installation angle and position are accurate, and finally fix the double-line bridge crane to make it firm and stable;
[0043] Step 2: Hoist the single-line beam: Hoist the single-line beam onto the double-line bridge-erecting machine through a lifting device to ensure its stability; the specific steps are:
[0044] Step b1: Check the integrity of the single-line beam to ensure that there are no cracks or other damages on the beam;
[0045] Step b2: Install lifting points at both ends of the single-line beam and connect the lifting points through lifting cables;
[0046] Step b3, operate the crane to slowly lift the single-line beam to the top of the double-line bridge erecting machine, while ensuring the tightness and safety of the steel cables and lifting points;
[0047] Step b4: Place the single-line beam steadily on the transverse movement assembly of the double-line bridge-building machine. The operator monitors the lifting process in real time to ensure that there is no swing or tilt.
[0048] Step 3: Preparation for transverse movement: Install the transverse movement assembly on the transverse movement mechanism of the double-line bridge erecting machine, and fix the single-line beam on the transverse movement assembly; the specific steps are as follows:
[0049] Step c1, installing a transverse movement assembly on the transverse movement track of the double-track bridge erecting machine, including a roller, a slider and a guide device;
[0050] Step c2, fix both ends of the single-line beam to the support points of the transverse movement assembly to ensure that the beam body will not tilt or shift during the transverse movement;
[0051] Step c3, check the fastening status of each connection point of the lateral movement device to ensure that all moving parts are in normal working condition;
[0052] Step c4: Set up a safety warning area on top of the bridge pier and around the double-line bridge-erecting machine to avoid accidents during the construction process.
[0053] Step 4: Transverse movement operation: Start the transverse movement mechanism of the double-line bridge erecting machine to horizontally move the single-line beam to the predetermined beam drop position; the specific steps are:
[0054] Step d1, start the transverse movement motor, gradually increase the power, slowly drive the single-line beam and the transverse movement assembly to move horizontally, and set a transverse movement limit device to prevent the single-line beam from moving beyond a predetermined position;
[0055] Step d2: Use sensors, laser positioning equipment and GPS systems to monitor the lateral trajectory of the single-line beam to ensure that it moves along the set path. The operator adjusts the lateral speed and direction in real time in the control room to avoid deviation caused by external forces.
[0056] Step 5: Precise positioning: Use sensors and laser positioning instruments to monitor and adjust the lateral position of the single-line beam in real time; the specific steps are:
[0057] When the single-line beam approaches the predetermined position, the fine adjustment mechanism is used for fine adjustment to ensure that the final position of the single-line beam completely coincides with the designed position. The position and angle of the single-line beam are accurately measured by a laser rangefinder and a high-precision level to ensure its perfect docking with the pier support.
[0058] Step 6, beam drop operation: after the single-line beam reaches the predetermined position, the vertical drop mechanism of the double-line bridge erecting machine is used to slowly drop the single-line beam onto the bridge pier to ensure that it is dropped smoothly;
[0059] Step f1, confirm that the single-line beam has reached the predetermined position, check the stability of the beam body, start the vertical landing device of the double-line bridge crane, and prepare for beam landing;
[0060] Step f2: operate the hydraulic jack and other lowering mechanisms to gradually lower the single-line beam, ensuring that the beam descends at a uniform speed to avoid the impact caused by a sudden drop. Use the slow speed mode and perform more precise control when the single-line beam approaches the pier support to ensure smooth contact.
[0061] Step 7, Fixing and testing: After the beam is dropped, the single-line beam is fixed and installed, and tested to ensure the accuracy and safety of the beam position, angle and load-bearing capacity. The specific steps are as follows:
[0062] Step g1: After the single-line beam is dropped to the pier support, bolts, steel plates and other fixing devices are used to temporarily fix the beam body. After confirming that the beam body will not move, the connection between the transverse movement assembly and the landing device is released;
[0063] Step g2: Use precision measuring instruments to test the geometric position, horizontality and verticality of the single-line beam to ensure that the beam position meets the design requirements. If there is any deviation, use adjustment devices such as jacks to make minor adjustments until all indicators meet the standards.
[0064] Step g3: Perform final welding and bolt tightening operations to ensure the stability and bearing capacity of the connection between the single-line beam and the bridge pier, and perform anti-corrosion and waterproofing treatment on the fixing points to ensure durability and safety in long-term use.
[0065] In order to explain in detail the possible application scenarios, technical principles, specific schemes that can be implemented, and the purposes and effects that can be achieved, the following is a detailed description in conjunction with the specific embodiments listed. The embodiments described herein are only used to more clearly illustrate the technical solutions of the present application, and are therefore only used as examples, and cannot be used to limit the scope of protection of the present application.
[0066] Reference to "embodiment" herein means that the specific features, structures or characteristics described in conjunction with the embodiment may be included in at least one embodiment of the present application. The term "embodiment" appearing in various places in the specification does not necessarily refer to the same embodiment, nor does it particularly limit its independence or association with other embodiments. In principle, in the present application, as long as there is no technical contradiction or conflict, the various technical features mentioned in the embodiments can be combined in any way to form a corresponding implementable technical solution.
[0067] Unless otherwise defined, the technical terms used in this document have the same meanings as those generally understood by those skilled in the art to which this application belongs; the use of relevant terms in this document is only for describing specific embodiments and is not intended to limit this application.
[0068] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A construction method for transversely moving a single-line beam and dropping a double-line bridge erecting machine, characterized in that: The steps include: Step 1: Install a double-line bridge-erecting machine: Install a double-line bridge-erecting machine on the bridge pier to make it span the construction section; Step 2: Hoist the single-line beam: Hoist the single-line beam onto the double-line bridge-erecting machine through a lifting device to ensure its stability; Step 3, preparation for transverse movement: install the transverse movement assembly on the transverse movement mechanism of the double-line bridge erecting machine, and fix the single-line beam on the transverse movement assembly; Step 4: Transverse movement operation: start the transverse movement mechanism of the double-line bridge erecting machine to horizontally move the single-line beam to the predetermined beam drop position; Step 5: Precise positioning: Use sensors and laser positioning instruments to monitor and adjust the lateral position of the single-line beam in real time; Step 6, beam drop operation: after the single-line beam reaches the predetermined position, the vertical drop mechanism of the double-line bridge erecting machine is used to slowly drop the single-line beam onto the bridge pier to ensure that it is dropped smoothly; Step 7, Fixing and testing: After the beam is dropped, the single-line beam is fixed and installed, and tested to ensure the accuracy and safety of the beam position, angle and load-bearing capacity.
2. The construction method for transversely moving a single-line beam of a double-line bridge erecting machine according to claim 1 is characterized in that: The detailed steps in step 1 include: Step a1: Clean the construction site, ensure that the top area of the pier is clean and free of debris, and check the stability of the pier; Step a2: Establish a temporary construction platform between the bridge piers to assist the erection process of the double-line bridge erecting machine; Step a3: Align the base of the double-line bridge erecting machine with the top of the bridge pier and use bolts or other fixing devices to perform preliminary fixing; Step a4: Use a level and theodolite to calibrate the bridge crane in the horizontal and vertical directions to ensure that the installation angle and position are accurate, and finally fix the double-line bridge crane to make it firm and stable.
3. The construction method for transversely moving a single-line beam of a double-line bridge erecting machine according to claim 2 is characterized in that: The detailed steps of step 2 include: Step b1: Check the integrity of the single-line beam to ensure that there are no cracks or other damages on the beam; Step b2: Install lifting points at both ends of the single-line beam and connect the lifting points through lifting cables; Step b3, operate the crane to slowly lift the single-line beam to the top of the double-line bridge erecting machine, while ensuring the tightness and safety of the steel cables and lifting points; Step b4: Place the single-line beam steadily on the transverse movement assembly of the double-line bridge-building machine. The operator monitors the lifting process in real time to ensure that there is no swing or tilt.
4. The construction method for transversely moving a single-line beam of a double-line bridge erecting machine according to claim 3 is characterized in that: The detailed steps of step 3 include: Step c1, installing a transverse movement assembly on the transverse movement track of the double-track bridge erecting machine, including a roller, a slider and a guide device; Step c2, fix both ends of the single-line beam to the support points of the transverse movement assembly to ensure that the beam body will not tilt or shift during the transverse movement; Step c3, check the fastening status of each connection point of the lateral movement device to ensure that all moving parts are in normal working condition; Step c4: Set up a safety warning area on top of the bridge pier and around the double-line bridge-erecting machine to avoid accidents during the construction process.
5. The construction method for transversely moving a single-line beam of a double-line bridge erecting machine according to claim 4 is characterized in that: The detailed steps of step 7 include: Step g1: After the single-line beam is dropped to the pier support, bolts, steel plates and other fixing devices are used to temporarily fix the beam body. After confirming that the beam body will not move, the connection between the transverse movement assembly and the landing device is released; Step g2: Use precision measuring instruments to test the geometric position, horizontality and verticality of the single-line beam to ensure that the beam position meets the design requirements. If there is any deviation, use adjustment devices such as jacks to make minor adjustments until all indicators meet the standards. Step g3: Perform final welding and bolt tightening operations to ensure the stability and bearing capacity of the connection between the single-line beam and the bridge pier, and perform anti-corrosion and waterproofing treatment on the fixing points to ensure durability and safety in long-term use.