Device and method for measuring permeability coefficient of gravel pile
By designing a device and method for measuring the permeability coefficient of crushed stone piles, and using inclined pipes and Darcy's law for calculation, the problem of inaccurate measurement of the permeability coefficient of vibratory crushed stone piles in existing technologies has been solved, enabling the evaluation and accurate measurement of the foundation treatment effect.
Patent Information
- Application Number
- CN202411198916.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-15
AI Technical Summary
Existing technologies cannot accurately measure the permeability coefficient of vibro-compacted stone piles, especially in composite foundations, where commonly used methods are not applicable, making it impossible to assess the effectiveness of foundation treatment.
A device and method for measuring the permeability coefficient of crushed stone piles are designed. The permeability coefficient is calculated by using a second pipe set at an angle and a first pipe set at a height at a height, and then measured by combining Darcy's law.
It enables accurate measurement of the permeability coefficient of crushed stone piles, evaluation of foundation treatment effects, and is convenient, economical and practical to operate.
Smart Images

Figure CN118958254A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of geological survey, and in particular to a device and method for measuring the permeability coefficient of a gravel pile. Background Art
[0002] The use of dense gravel piles in soft clay foundations can not only improve the bearing capacity of the foundation by using the dense pile body and compaction effect, but also accelerate the drainage and consolidation of the foundation soil by using the good drainage performance of vibro-compacted gravel piles, improve the deformation capacity of the foundation, and reduce settlement and uneven settlement. At present, vibro-compacted gravel pile technology has been increasingly used in the field of foundation treatment, but with the increasing depth of reinforcement, the quality inspection of composite foundations and the evaluation of reinforcement effects are facing huge challenges. The permeability coefficient of gravel piles is an important indicator parameter for evaluating the quality of composite foundations and the effect of foundation reinforcement. Therefore, it is crucial to design a field test method that can more accurately obtain the permeability coefficient of gravel piles.
[0003] At present, the commonly used methods for soil permeability test are on-site borehole pumping test, water injection test and indoor permeability test, which are mainly for natural soil or test samples with small permeability coefficient differences. The soil of vibro-compacted crushed stone pile composite soft clay foundation is in a saturated state, and the permeability coefficient of the crushed stone pile is generally 10 -2 ~10 -3 The permeability coefficient of soft clay between piles is generally 10 -5 ~10 -6 Therefore, the commonly used on-site borehole pumping test, water injection test and indoor permeability test are not suitable for measuring the permeability coefficient of gravel piles, and it is impossible to accurately obtain the permeability coefficient of gravel piles. Summary of the invention
[0004] The present application provides a device and method for measuring the permeability coefficient of a gravel pile, so as to solve the technical problem that the commonly used method for permeability coefficient test of soil is not suitable for measuring the permeability coefficient of a gravel pile and cannot accurately obtain the permeability coefficient of a gravel pile.
[0005] In order to achieve the above-mentioned purpose, this application adopts the following technical solution.
[0006] On the one hand, a gravel pile permeability coefficient measuring device is provided, comprising a test gravel pile vertically arranged in a soft clay layer, above which a construction platform backfill layer is laid; and further comprising a first pipe and a second pipe; the first pipe passes through the construction platform backfill layer from top to bottom and is inserted into the top of the test gravel pile, the top of the first pipe is provided with a first pipe opening, the first pipe opening is higher than the top surface of the construction platform backfill layer, and an overflow hole is opened on the first pipe at a position lower than the first pipe opening and higher than the top surface of the construction platform backfill layer; the second pipe passes through the test gravel pile obliquely, the top of the second pipe is provided with a second pipe opening, the second pipe opening is not lower than the top surface of the construction platform backfill layer.
[0007] In some embodiments, the inclination angle α of the second pipe is in the range of 60°≤α≤80°.
[0008] In some embodiments, the lower end of the first pipe is inserted into the test gravel pile by 0.1 to 0.2 m.
[0009] In some embodiments, a plurality of gravel piles are vertically arranged in the soft clay layer, and the test gravel pile is one of the plurality of gravel piles.
[0010] On the other hand, a method for measuring permeability using the above-mentioned gravel pile permeability measuring device is provided, comprising the following steps:
[0011] Drain the water in the second pipe and inject water into the first pipe at the same time until the water level in the first pipe rises to the overflow port and remains constant;
[0012] Obtain the value of the water level in the second pipeline at each sampling time;
[0013] The permeability coefficient K of the test gravel pile is calculated according to the following formula:
[0014]
[0015] Where K is the permeability coefficient of the test gravel pile, H1 and H2 are the distances between the second pipe opening and the position where the second pipe enters and exits the test gravel pile, respectively; t1 and t2 are the first sampling time and the second sampling time, respectively; S1 is the distance from the water level in the second pipe to the second pipe opening at time t1, and S2 is the distance from the water level in the second pipe to the second pipe opening at time t2; Z1 is the length of the second pipe, Z2 and Z3 are the heights from the first pipe opening and the overflow port to the top surface of the backfill soil layer of the construction platform, respectively; φ is the diameter of the second pipe; D is the diameter of the test gravel pile; d is the horizontal distance between the second pipe opening and the first pipe opening; α is the inclination angle of the second pipe.
[0016] In some embodiments, the step of draining the water in the second pipe and injecting water into the first pipe comprises:
[0017] Use a plug to plug the location where the test gravel pile is inserted into the second pipe;
[0018] Drain the water in the second pipe;
[0019] Water is poured into the first pipe, and the plug is pulled out when the overflow port begins to return water evenly.
[0020] The present application has at least the following technical effects or advantages: the present application can effectively measure the permeability coefficient of the gravel pile and evaluate the treatment effect of the vibro-compacted gravel pile foundation. Secondly, the present application also has the technical advantages of convenient implementation, accurate measurement data and good economy. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 This is a schematic diagram of the structure of a device for measuring the permeability coefficient of a gravel pile in one embodiment of the present application;
[0022] Figure 2 This is a schematic diagram of various parameters of a gravel pile permeability coefficient measuring device in one embodiment of the present application;
[0023] Figure 3 It is a top view of a device for measuring the permeability coefficient of a gravel pile in one embodiment of the present application;
[0024] Figure 4 This is a schematic diagram of the structure of a gravel pile composite foundation layer in one embodiment of the present application. DETAILED DESCRIPTION
[0025] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0026] Embodiment 1
[0027] like Figure 1-Figure 4 As shown, a device for measuring the permeability coefficient of a gravel pile includes a plurality of gravel piles 2 vertically arranged in a soft clay layer 1, wherein one of the gravel piles 2 is a test gravel pile 21, a construction platform backfill soil layer 3 is laid above the soft clay layer 1, and an underlying stratum 4 is arranged below. It also includes a first pipe 5 and a second pipe 6, wherein the first pipe 5 penetrates the construction platform backfill soil layer 3 from top to bottom and is inserted into the top of the test gravel pile 21, a first pipe opening 51 is arranged at the top of the first pipe 5, and the first pipe opening 51 is higher than the top surface of the construction platform backfill soil layer 3, and an overflow hole 52 is opened at a position lower than the first pipe opening 51 and higher than the top surface of the construction platform backfill soil layer 3 on the first pipe 5. The second pipe 6 obliquely penetrates the test gravel pile 21, and a second pipe opening 61 is arranged at the top of the second pipe 6, and the second pipe opening 61 should not be lower than the top surface of the construction platform backfill soil layer 3. The value range of the inclination angle α of the second pipe 6 is 60°≤α≤80°. The lower end of the first pipe 5 is inserted into the test gravel pile by 0.1 to 0.2 m. Figure 1In the figure, 7 is the groundwater level and 8 is the plug.
[0028] Preferably, the first pipeline and the second pipeline are geological drilled holes, and the inner diameter of the hole is preferably controlled within the range of 110 mm to 160 mm. The second pipeline is provided with a steel flower pipe in the gravel pile body section, and the other sections are steel casings, and the entire first pipeline is steel casings.
[0029] Embodiment 2
[0030] The method for measuring the permeability coefficient of a gravel pile of the present invention is to calculate the permeability coefficient of the gravel pile by utilizing the change in the water level in the second pipe. The test method combines the indoor variable head test method and the on-site water injection test method. The gravel pile can be considered as homogeneous coarse-grained soil. The water flow rate in the pile is relatively slow and belongs to the laminar flow state. Therefore, it is feasible to obtain the permeability coefficient by using this method based on the variable head test and the on-site water injection test based on Darcy's law. Relative to the gravel pile, the soft clay between the piles is a relatively impermeable layer. During the test period, the groundwater recharge from the composite foundation around the gravel pile to the gravel pile and the discharge from the gravel pile to the composite foundation are very small and can be ignored. Therefore, it can be considered that the amount of water measured in the inclined borehole is the discharge of the gravel pile test section under the action of different heads.
[0031] A method for measuring permeability using the above-mentioned gravel pile permeability measuring device comprises the following steps:
[0032] Drain the water in the second pipe and inject water into the first pipe at the same time until the water level in the first pipe rises to the overflow port and remains constant;
[0033] Obtain the value of the water level in the second pipeline at each sampling time;
[0034] The permeability coefficient K of the test gravel pile is calculated according to the following formula:
[0035]
[0036] Where K is the permeability coefficient of the test gravel pile, H1 and H2 are the distances between the second pipe mouth and the position where the second pipe enters and exits the test gravel pile, respectively; t1 and t2 are the first sampling time and the second sampling time, respectively; S1 is the distance from the water level in the second pipe to the second pipe mouth at time t1, and S2 is the distance from the water level in the second pipe to the second pipe mouth at time t2; Z1 is the length of the second pipe, Z2 and Z3 are the heights from the first pipe mouth and overflow port to the top surface of the backfill soil layer of the construction platform, respectively; φ is the diameter of the second pipe; D is the diameter of the test gravel pile; d is the horizontal distance between the second pipe mouth and the first pipe mouth; α is the inclination angle of the second pipe. The above hole depth, distance, height, diameter and time data can be measured on site, such as Figure 2 shown.
[0037] Specifically, the steps of draining the water in the second pipe and injecting water into the first pipe include:
[0038] Use a plug to plug the location where the test gravel pile is inserted into the second pipe;
[0039] Drain the water in the second pipe;
[0040] Water is poured into the first pipe, and the plug is pulled out when the overflow port begins to return water evenly.
[0041] like Figure 1 As shown, the pipe wall of the first pipe is a steel casing. By continuously injecting water into the first pipe, a stable water head will be formed in the steel casing. Part of the injected water will be discharged to the second pipe through the test gravel pile. By observing the water level changes in the directional second pipe, the permeability coefficient of the gravel pile can be obtained.
[0042] Second pipeline inclination
[0043] Length of injection path
[0044] Assume that the distance from the water level in the second pipe to the second pipe opening at time t is △h (m), then the water head difference acting on both ends of the gravel pile test section at time t is △h. After a micro-period dt, the water level in the directional inclined borehole rises dh, then the micro-increment of water flowing into the second pipe during the dt period is
[0045] According to Darcy's law, the amount of infiltration through the gravel pile during the period dt is:
[0046]
[0047] In formula 3: i is the permeability gradient of the gravel pile; K is the permeability coefficient of the gravel pile; A is the cross-sectional area of the gravel pile.
[0048] According to the principle of water flow continuity, dV e =dV0, that is
[0049]
[0050] Integrate both sides of Formula 4
[0051]
[0052] The permeability coefficient of the gravel column is obtained
[0053]
[0054] In Formula 7, △h1 and △h2 are the vertical distances (m) from the water level in the second pipe to the second pipe opening at time t1 and t2 respectively.
[0055] △h1=S1sinα+Z3 Formula 8
[0056] △h2=S2sinα+Z3 Formula 9
[0057] In Formula 8 and Formula 9, S1 and S2 are the distances (m) from the water level in the second pipe to the second pipe opening at time t1 and t2, respectively.
[0058] Substituting Formula 2, Formula 8, and Formula 9 into Formula 7, we can obtain:
[0059]
[0060] In the description provided herein, a large number of specific details are described. However, it is understood that embodiments of the present invention can be practiced without these specific details. In some instances, well-known methods, structures and techniques are not shown in detail so as not to obscure the understanding of this description.
[0061] Similarly, it should be understood that in order to streamline the present disclosure and aid in understanding one or more of the various inventive aspects, in the above description of exemplary embodiments of the present invention, various features of the present invention are sometimes grouped together into a single embodiment, figure, or description thereof. However, this disclosed method should not be interpreted as reflecting the intention that the claimed invention requires more features than those expressly recited in each claim. Rather, as reflected in the claims, inventive aspects lie in less than all of the features of the individual embodiments previously disclosed. Therefore, the claims that follow the detailed description are hereby expressly incorporated into the detailed description, with each claim itself serving as a separate embodiment of the present invention.
[0062] Furthermore, those skilled in the art will appreciate that although some embodiments described herein include certain features included in other embodiments but not other features, the combination of features from different embodiments is meant to be within the scope of the present invention and to form different embodiments.
[0063] As used herein, unless otherwise specified, the use of ordinal numbers "first," "second," "third," etc. to describe common objects merely indicates that different instances of similar objects are involved, and is not intended to imply that the objects so described must have a given order in time, space, order, or in any other manner.
[0064] Although the present invention has been described according to a limited number of embodiments, it will be apparent to those skilled in the art, with the benefit of the above description, that other embodiments may be envisioned within the scope of the invention thus described. In addition, it should be noted that the language used in this specification is selected primarily for readability and teaching purposes, rather than for explaining or defining the subject matter of the present invention. Therefore, many modifications and variations will be apparent to those skilled in the art without departing from the scope and spirit of the appended claims. The disclosure of the present invention is illustrative, not restrictive, with respect to the scope of the present invention, which is defined by the appended claims.
[0065] Finally, it should be noted that the present invention does not explain in detail the common knowledge recognized by technicians in this field. The above is only a specific embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A device for measuring the permeability coefficient of a gravel pile, comprising a test gravel pile vertically arranged in a soft clay layer, wherein a construction platform backfill soil layer is laid above the soft clay layer; characterized in that: It also includes a first pipe and a second pipe; the first pipe passes through the backfill layer of the construction platform from top to bottom and is inserted into the top of the test gravel pile, the top of the first pipe is provided with a first pipe opening, the first pipe opening is higher than the top surface of the backfill layer of the construction platform, and an overflow hole is opened on the first pipe at a position lower than the first pipe opening and higher than the top surface of the backfill layer of the construction platform; the second pipe obliquely passes through the test gravel pile, the top of the second pipe is provided with a second pipe opening, the second pipe opening is not lower than the top surface of the backfill layer of the construction platform.
2. The method for measuring the permeability coefficient of a gravel pile according to claim 1, characterized in that: The inclination angle α of the second pipeline is in the range of 60°≤α≤80°.
3. The method for measuring the permeability coefficient of a gravel pile according to claim 1 or 2, characterized in that: The lower end of the first pipe is inserted into the test gravel pile by 0.1 to 0.2 m.
4. The method for measuring the permeability coefficient of a gravel pile according to claim 1 or 2, characterized in that: A plurality of gravel piles are vertically arranged in the soft clay layer, and the test gravel pile is one of the plurality of gravel piles.
5. A method for measuring permeability using the device for measuring permeability of a gravel pile according to any one of claims 1 to 4, characterized in that: The steps include: Drain the water in the second pipe and inject water into the first pipe at the same time until the water level in the first pipe rises to the overflow port and remains constant; Obtain the value of the water level in the second pipeline at each sampling time; The permeability coefficient K of the test gravel pile is calculated according to the following formula: Where K is the permeability coefficient of the test gravel pile, H1 and H2 are the distances between the second pipe opening and the position where the second pipe enters and exits the test gravel pile, respectively; t1 and t2 are the first sampling time and the second sampling time, respectively; S1 is the distance from the water level in the second pipe to the second pipe opening at time t1, and S2 is the distance from the water level in the second pipe to the second pipe opening at time t2; Z1 is the length of the second pipe, Z2 and Z3 are the heights from the first pipe opening and the overflow port to the top surface of the backfill soil layer of the construction platform, respectively; φ is the diameter of the second pipe; D is the diameter of the test gravel pile; d is the horizontal distance between the second pipe opening and the first pipe opening; α is the inclination angle of the second pipe.
6. The method for measuring the permeability coefficient of a gravel pile according to claim 5, characterized in that: The steps of draining the water in the second pipe and injecting water into the first pipe include: Use a plug to plug the location where the test gravel pile is inserted into the second pipe; Drain the water in the second pipe; Water is poured into the first pipe, and the plug is pulled out when the overflow port begins to return water evenly.