Construction method of large high-position cantilever supporting system

By combining multiple support methods of large high-level cantilever support systems, the safety and efficiency problems of traditional foundation pit support methods in complex environments are solved, and the stability and universality of high-level cantilever support is achieved, reducing the Construction costs and impact on the surrounding environment.

CN118958311APending Publication Date: 2024-11-15CHINA FIRST METALLURGICAL GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411337639.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

In the underground space development of traditional high-rise buildings, foundation pit support methods are diverse and space occupies a large amount, resulting in conflicts with old buildings and underground pipelines, affecting construction safety and efficiency, and unable to meet construction needs in complex environments.

Method used

The construction method of a large high-level cantilever support system is adopted, and through various support methods such as cast-in piles, high-pressure rotary spray piles, crown beams, column piles, steel lattice columns, and force transmission belts, combined with the steel brace replacement design, according to the foundation pit The surrounding environment is excavated and supported in different areas to avoid impact on surrounding buildings and pipelines.

Benefits of technology

It improves the safety and universality of support systems in complex environments, reduces construction costs, reduces the impact on surrounding buildings and pipelines, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958311A_ABST
    Figure CN118958311A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method of a large-scale high-position cantilever supporting system, which relates to the technical field of building construction, and comprises the following steps: constructing a peripheral supporting structure, constructing an inner side support, constructing an underground main body structure, and performing second concrete support construction on the nearby direction without a building and a supporting structure in the process, and profile steel support changing construction is conducted on at least one direction with an original building or a supporting structure of the original building nearby. Different supporting forms are adopted according to different surrounding environments of the foundation pit, and the safety of the large high-position cantilever supporting system under the complex environment condition is improved by adopting multiple forms of deep foundation pit supporting schemes and combining multiple supporting modes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building construction, and in particular to a construction method of a large-scale high-position cantilever support system. Background Art

[0002] At present, with the development of urban construction, the number of high-rise buildings in urban areas is gradually increasing. Due to the requirements of use function and development of underground space, high-rise buildings are generally designed with underground space of larger plane size and depth. The development of underground space involves the safety of deep foundation pits of buildings, which is especially important for densely built areas located on soft soil foundations.

[0003] Due to the different environments around the foundation pit, the support forms adopted by the foundation pit are also different. One of them is that the old building is supported by anchor cables, and the new building is too close to the old building, so part of the anchor cable is located in the new foundation pit. The new foundation pit adopts reinforced concrete beam internal support, and this type of support method requires a certain space in the foundation pit, which conflicts with the anchor cable support of the old foundation pit and the underground structure of the new building. With the continuous increase in the number of buildings, such situations will become more and more common. Traditional methods have disadvantages or cannot meet construction needs, and the construction process will also cause impacts such as deformation of underground pipelines on surrounding buildings, municipal roads and underground pipelines. Summary of the invention

[0004] In view of the above-mentioned deficiencies in the related technologies, the present application provides a construction method for a large-scale high-position cantilever support system.

[0005] The construction method of the large-scale high-position cantilever support system provided in this application adopts the following technical solution: A construction method for a large-scale high-position cantilever support system comprises the following steps: Construction of external support structure: Carry out cast-in-place piles and high-pressure jet grouting piles to enclose the foundation pit area, and carry out cap beam construction to connect the tops of cast-in-place piles and high-pressure jet grouting piles; Inner support construction, column pile construction is carried out in the foundation pit area, and steel lattice column construction is carried out in the vertical direction on the top of the column pile; For the construction of the underground main structure, the earthwork is excavated to the design elevation of the bottom of the first supporting beam, and the first purlin construction, the first supporting beam construction, the first concrete support construction on the four sides and the plank road construction are carried out. The earthwork is excavated to the design elevation of the second supporting beam, and the second purlin construction and the second supporting beam construction are carried out. For the position without nearby buildings and supporting structures, the second concrete support construction is carried out. The earthwork is excavated to the design elevation of the base, and the steel support replacement construction is carried out for at least one position with the original building / its supporting structure nearby; Construction of the base plate, exterior wall and floor slab, construction of the base plate and exterior wall, construction of the force transfer belt, after the concrete strength of the base plate and the force transfer belt reaches the design requirements, remove the second purlin, the second supporting beam and the second concrete support, and then carry out the construction of the second-basement exterior wall and the second-basement floor slab, backfill the second-basement force transfer belt and construct the force transfer belt to connect the second-basement floor slab and the outer supporting structure, and then remove the first supporting beam, the first concrete support, the first purlin and the steel lattice column, and then carry out the construction of the first-basement exterior wall and the first-basement floor slab, construct the force transfer belt to connect the first-basement floor slab and the crown beam, and finally remove the steel support and backfill the force transfer belt to the top elevation of the first-basement floor slab.

[0006] Preferably, the construction of cast-in-place piles and high-pressure rotary jet piles includes the following steps: firstly, cast-in-place piles are constructed at intervals to surround the foundation pit area, and then at least one high-pressure rotary jet pile construction is carried out between two adjacent cast-in-place piles to connect the two adjacent cast-in-place piles.

[0007] Preferably, the crown beam construction comprises the following steps: performing demolition construction on the tops of the cast-in-place piles and high-pressure rotary jet piles, and after clearing and chiseling, tying the crown beam reinforcement and pouring concrete to form the crown beam.

[0008] Preferably, the excavation of the foundation pit area is carried out in zones and layers. The foundation pit area is divided into four zones according to four directions, and the foundation pit area is divided into four layers along its depth direction according to the design elevation of the bottom of the crown beam, the design elevation of the bottom of the first supporting beam, and the design elevation of the bottom of the second supporting beam, and excavated in sequence.

[0009] Preferably, the first support beam comprises a first connecting beam and a first support arranged horizontally and vertically, the first support is connected to the first surrounding purlin, and the two ends of the first concrete support are respectively connected to the first surrounding purlin and the first connecting beam; the second support beam comprises a second connecting beam and a second support arranged horizontally and vertically, the second support is connected to the second surrounding purlin, and the two ends of the second concrete support are respectively connected to the second surrounding purlin and the second connecting beam.

[0010] Preferably, the base is pre-embedded with a positioning steel plate, and the steel brace replacement construction includes the following steps: constructing the third perimeter purlin, and fixing the two ends of the steel brace to the third perimeter purlin and the positioning steel plate respectively.

[0011] Preferably, the base plate and exterior wall construction includes setting up connected formwork for the base plate area and the exterior wall area together, and pouring concrete at the same time. During this process, a construction space is reserved between the top of the exterior wall and the third purlin.

[0012] Preferably, the location of the steel support replacement construction is where the foundation pit is adjacent to a building.

[0013] Preferably, one end of the steel lattice column close to the column pile is embedded in the top of the column pile.

[0014] Preferably, a ramp for connecting the plank road is provided on the first supporting beam.

[0015] In summary, the present application includes at least one of the following beneficial technical effects: 1. This application adopts different support forms according to the different environments around the foundation pit. By adopting various forms of deep foundation pit support schemes, in the case of a high cantilever without supporting one floor slab on the crown beam, a variety of support methods are combined to improve the safety of large-scale high-position cantilever support systems under complex environmental conditions.

[0016] 2. This application adopts the design of replacing multiple supports by partially replacing the steel support construction, and utilizes the stabilizing effect of the original building support structure on the foundation pit structure, thereby reducing construction costs and improving construction efficiency; 3. The combination of multiple support methods in this application is conducive to the construction of the support system in a narrow foundation pit support construction site, and improves the universality of the support system construction method. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0018] Figure 1 is a schematic diagram of a deep foundation pit area in an embodiment of the present application; Figure 2 It is a schematic diagram of the embodiment of the present application for demonstrating the interlocking structure of the cast-in-place pile and the high-pressure rotary jet pile; Figure 3 It is a structural schematic diagram for showing the first purlin, the first support beam, the first concrete support, the ramp and the plank road in the embodiment of the present application; Figure 4 It is a structural schematic diagram for showing the second purlin, the second support beam, and the second concrete support in the embodiment of the present application; Figure 5 It is a cross-sectional view used to show the structure on the south side of the foundation pit in the embodiment of the present application; Figure 6 It is a cross-sectional view used to show the structure on the east side of the foundation pit in the embodiment of the present application; Figure 7 It is a cross-sectional view used to show the structure on the north side of the foundation pit in the embodiment of the present application; Figure 8 It is a cross-sectional view used to show the structure on the west side of the foundation pit in the embodiment of the present application.

[0019] Figure numerals: 1. column piles; 2. external supporting structure; 21. cast-in-place piles; 22. high-pressure rotary jet piles; 23. crown beam; 3. first supporting beam; 31. first connecting beam; 32. first support; 4. first concrete support; 5. plank road; 6. ramp; 7. second supporting beam; 71. second connecting beam; 72. second support; 8. first purlin; 9. second purlin; 10. steel lattice column; 11. underground first floor slab; 12. underground second floor slab; 13. third purlin; 14. steel diagonal brace; 15. positioning steel plate; 16. second concrete support; 17. west building; 18. north building; 19. pipe gallery and underground pipelines. DETAILED DESCRIPTION

[0020] The following is combined with Figure 1-8 This application is described in further detail.

[0021] The embodiment of the present application discloses a construction method of a large-scale high-position cantilever support system. The construction method of a large-scale high-position cantilever support system comprises the following steps: Reference Figure 1 , exploration and investigation of the surrounding environment and underground structure of the foundation pit. There are pipeline corridors and underground pipelines 19 on the south side of the deep foundation pit area, north side buildings 18 on the north side, west side buildings 17 on the west side, and the original buildings have anchor cables located underground in the foundation pit area. There are no buildings on the east side.

[0022] Reference Figure 2 , Figure 3 , Figure 4 and Figure 5 , construction of the peripheral support structure 2: first, cast-in-place piles 21 are constructed at intervals to surround the foundation pit area, and then two high-pressure rotary jet piles 22 are constructed between two adjacent cast-in-place piles 21 to connect the two adjacent cast-in-place piles 21 to form a cast-in-place pile 21-high-pressure rotary jet pile 22-high-pressure rotary jet pile 22-cast-in-place pile 21 bite structure to enclose and support the deep foundation pit area underground. The diameter of the cast-in-place pile 21 is larger than the high-pressure rotary jet pile 22. After the strength of the cast-in-place pile 21 and the high-pressure rotary jet pile 22 reaches the design strength, the top pile heads of the cast-in-place pile 21 and the high-pressure rotary jet pile 22 are broken. After the clearing and chiseling is completed, the crown beam 23 steel bars are tied and concrete is poured to form the crown beam 23, so as to connect the cast-in-place pile 21 and the high-pressure rotary jet pile 22 into a whole, thereby improving the stability of the peripheral support structure 2; Reference Figure 6 , Figure 7 and Figure 8 , inner support construction, column piles 1 are constructed inside the outer support structure 2 in the deep foundation pit area, the column piles 1 are spaced apart along the periphery of the deep foundation pit area, and steel lattice columns 10 are constructed along the vertical direction on the top of the column piles 1, and the steel lattice columns 10 are lowered and embedded in the top of the column piles 1; Underground main structure construction, refer to Figure 3 , excavate from the ground to the design elevation of the bottom of the crown beam 23 from east to west to the design elevation of the bottom of the first supporting beam 3; from the design elevation of the bottom of the crown beam 23 to the design elevation of the bottom of the first supporting beam 3, excavate from the middle to the north and south sides at the same time, and then carry out the construction of the first surrounding purlin 8, the first supporting beam 3, the first concrete support 4 on the four sides and the plank road 5, the construction ramp 6 connects the first supporting beam 3 and the plank road 5, the first supporting beam 3 includes a first connecting beam 31 and a first support 32 arranged horizontally and vertically, the first support 32 is connected to the first surrounding purlin 8, and the two ends of the first concrete support 4 are respectively connected to the first surrounding purlin 8 and the first connecting beam 31; refer to Figure 3 , some earth-moving machinery and earth-moving transport vehicles are used for construction on the plank road 5, and the other part of the earth-moving machinery is used to excavate and construct under the first support beam 3 to the design elevation of the second support beam 7, and to construct the second enclosure purlin 9 and the second support beam 7. The second support beam 7 includes a second connecting beam 71 and a second support 72 arranged horizontally and vertically. The second support 72 is connected to the second enclosure purlin 9, and the two ends of the second concrete support 16 are respectively connected to the second enclosure purlin 9 and the second connecting beam 71; the second concrete support 16 is constructed on the south and east sides of the deep foundation pit, from the design elevation of the bottom of the second support beam 7 to the design elevation of the base, and excavated from the middle to the north and south sides at the same time, referring to Figure 6 , pre-embed the positioning steel plate 15 in the base, carry out the construction of the third purlin 13, weld and fix the two ends of the steel brace 14 to the third purlin 13 and the positioning steel plate 15, and carry out the steel brace replacement construction on the north side of the deep foundation pit; The bottom plate, outer wall and floor slab are constructed by setting up connected formworks in the bottom plate area and the outer wall area, and pouring concrete at the same time. During this process, a construction space is reserved between the top of the outer wall and the design elevation of the third purlin 13. Then the force transmission belt is constructed. After the concrete strength of the bottom plate and the force transmission belt reaches the design requirements, the second purlin 9, the second support beam 7 and the second concrete support 16 are removed. Figure 5 and Figure 6 Then, the second-floor outer wall and second-floor floor slab 12 are constructed on the south and east sides of the deep foundation pit, the second-floor force transfer belt is backfilled and the force transfer belt is constructed to connect the second-floor floor slab 12 and the peripheral support structure 2, and then the first support beam 3, the first concrete support 4, the first purlin 8 and the steel lattice column 10 are removed. Next, the first-floor outer wall and the first-floor floor slab 11 are constructed on all four sides of the deep foundation pit, and the force transfer belt is constructed to connect the first-floor floor slab 11 and the crown beam 23. No support for the first-floor floor slab 11 is set on the crown beam 23, so that the first-floor floor slab 11 forms a high cantilever structure. Figure 7 Finally, remove the steel support and backfill the force transfer belt to the top elevation of 11 on the underground first floor.

[0023] The implementation principle of the construction method of the large-scale high-position cantilever support system of the embodiment of the present application is as follows: by using cast-in-place piles 21, high-pressure rotary jet piles 22, crown beams 23, first concrete supports 4, second concrete supports 16, negative first floor slabs 11 and negative second floor slabs 12 on the south side of the deep foundation pit adjacent to the pipe gallery and underground pipelines and the east side of the deep foundation pit adjacent to no buildings, the two concrete supports and two-layer floor slab supports reduce the impact on the surrounding buildings, municipal roads and underground pipelines, such as deformation of underground pipelines, and improve the stability of the deep foundation pit support; on the north side of the deep foundation pit adjacent to the buildings The support form of cast-in-place piles 21, high-pressure rotary jet piles 22, crown beams 23, first concrete supports 4, steel braces 14 and negative first floor slabs 11 is adopted. The support form of cast-in-place piles 21, high-pressure rotary jet piles 22, crown beams 23, first concrete supports 4 and negative first floor slabs 11 is adopted for the west side of the deep foundation pit adjacent to the building and the original building has the anchor cable located underground in the foundation pit area. The original buildings and building support structures around the deep foundation pit are used to stabilize the foundation pit structure. While avoiding the original building support structure or the anchor cable left by the building, the construction cost is reduced and the construction efficiency is improved. Unless otherwise defined, the technical terms or scientific terms used in this application shall be the ordinary meaning understood by people with general skills in the field to which this application belongs. The words "first", "second", "third" and similar words used in the specification and claims of this application do not indicate any order, quantity or importance, but are only used to distinguish different components. "One" or "one" and similar words do not indicate quantity restrictions, but indicate the existence of at least one. "Include" or "comprising" and other similar words mean that the elements or objects appearing before "include" or "comprising" include the elements or objects listed after "include" or "comprising" and their equivalents, and do not exclude other elements or objects. "Up", "down", "left", "right", etc. are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.

[0024] The above are all optional embodiments of the present application, and are not intended to limit the protection scope of the present application. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A construction method for a large high-position cantilever support system. Features: The following steps are involved: Construction of external support structure: Carry out cast-in-place piles and high-pressure jet grouting piles to enclose the foundation pit area, and carry out cap beam construction to connect the tops of cast-in-place piles and high-pressure jet grouting piles; Inner support construction, column pile construction is carried out in the foundation pit area, and steel lattice column construction is carried out in the vertical direction on the top of the column pile; For the construction of the underground main structure, the earthwork is excavated to the design elevation of the bottom of the first supporting beam, and the first purlin construction, the first supporting beam construction, the first concrete support construction on the four sides and the plank road construction are carried out. The earthwork is excavated to the design elevation of the second supporting beam, and the second purlin construction and the second supporting beam construction are carried out. For the position without nearby buildings and supporting structures, the second concrete support construction is carried out. The earthwork is excavated to the design elevation of the base, and the steel support replacement construction is carried out for at least one position with the original building / its supporting structure nearby; Construction of the base plate, exterior wall and floor slab, construction of the base plate and exterior wall, construction of the force transfer belt, after the concrete strength of the base plate and the force transfer belt reaches the design requirements, remove the second purlin, the second supporting beam and the second concrete support, and then carry out the construction of the second-basement exterior wall and the second-basement floor slab, backfill the second-basement force transfer belt and construct the force transfer belt to connect the second-basement floor slab and the outer supporting structure, and then remove the first supporting beam, the first concrete support, the first purlin and the steel lattice column, and then carry out the construction of the first-basement exterior wall and the first-basement floor slab, construct the force transfer belt to connect the first-basement floor slab and the crown beam, and finally remove the steel support and backfill the force transfer belt to the top elevation of the first-basement floor slab.

2. The construction method of the large-scale high-position cantilever support system according to claim 1, Features: The construction of cast-in-place piles and high-pressure jet-jet piles comprises the following steps: First, cast-in-place pile construction is carried out at intervals to surround the foundation pit area, and then at least one high-pressure rotary jet pile construction is carried out between two adjacent cast-in-place piles to connect the two adjacent cast-in-place piles.

3. The construction method of the large-scale high-position cantilever support system according to claim 1, Features: The crown beam construction comprises the following steps: The tops of the cast-in-place piles and high-pressure rotary jet piles are demolished and after clearing, the crown beam reinforcement is tied and concrete is poured to form the crown beam.

4. The construction method of the large-scale high-position cantilever support system according to claim 1, Features: During the excavation of the foundation pit area, the excavation is carried out in zones and layers. The foundation pit area is divided into four zones according to four directions. The foundation pit area is divided into four layers along its depth direction according to the design elevation of the bottom of the crown beam, the design elevation of the bottom of the first supporting beam, and the design elevation of the bottom of the second supporting beam, and excavated in sequence.

5. The construction method of the large-scale high-position cantilever support system according to claim 1, Features: The first support beam includes a first connecting beam and a first support arranged horizontally and vertically, the first support is connected to the first surrounding purlin, and the two ends of the first concrete support are respectively connected to the first surrounding purlin and the first connecting beam; the second support beam includes a second connecting beam and a second support arranged horizontally and vertically, the second support is connected to the second surrounding purlin, and the two ends of the second concrete support are respectively connected to the second surrounding purlin and the second connecting beam.

6. The construction method of the large-scale high-position cantilever support system according to claim 1, Features: The base is pre-buried with a positioning steel plate, and the steel brace replacement construction includes the following steps: constructing the third perimeter purlin, and fixing the two ends of the steel brace to the third perimeter purlin and the positioning steel plate respectively.

7. The construction method of the large-scale high-position cantilever support system according to claim 6, Features: The base plate and exterior wall construction includes setting up connected formwork for the base plate area and the exterior wall area, and pouring concrete at the same time. During this process, a construction space is reserved between the top of the exterior wall and the third purlin.

8. The construction method of the large-scale high-position cantilever support system according to claim 1, Features: The location of the steel support replacement construction is where the foundation pit is close to the location of the building.

9. The construction method of the large-scale high-position cantilever support system according to claim 1, Features: One end of the steel lattice column close to the column pile is embedded in the top of the column pile.

10. The construction method of the large-scale high-position cantilever support system according to claim 1, Features: The first supporting beam is provided with a ramp for connecting the plank road.