Whole-process water cut-off construction method for deep foundation pit engineering

By using water conduit pipe drainage fertilizer troughs in deep foundation pit projects and setting up precast concrete covers, the problem of waterproof coil damage caused by water accumulation in basement exterior walls and foundation pit edges in deep foundation pit projects is solved, and the construction quality is improved and shorten the construction period and reduce quality problems in concrete construction.

CN118958344APending Publication Date: 2024-11-15THE THIRD CONSTR OF CHINA CONSTR EIGHTH ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411285147.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

During the construction of deep foundation pit projects, water accumulation in the fertilizer grooves on the basement exterior wall and the edge of the foundation pit leads to the damage of the waterproof coil of the basement floor, and frequent pumping during subsequent construction is difficult to control, affecting the waterproof quality, and the water accumulation of the base plate erodes the raft after the pouring belt of the base plate Plate steel bars lead to construction difficulties and degradation of quality.

Method used

Use water conduit pipes to introduce water between the basement exterior wall and the edge of the foundation pit into the water collection pit, and discharge it through a water pump. Prefabricated concrete cover plates are installed to prevent garbage from entering. Prefabricated prefabricated concrete exterior wall foundation pit fertilizer trough is backfilled in advance, and the basement is to be connected with the basement. The main structure is constructed simultaneously to reduce water accumulation and construction time.

Benefits of technology

Effectively reduce the damage to waterproof coils by fertilization tanks, improve construction quality, shorten construction period, reduce quality problems in concrete construction, such as water seepage caused by cold joints and weak areas, and improve the construction of concrete with post-pouring tape Quality and waterproofing effect of basement floor.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958344A_ABST
    Figure CN118958344A_ABST
Patent Text Reader

Abstract

The invention provides a whole-process water break construction method for deep foundation pit engineering, which relates to the technical field of deep foundation pit engineering construction and comprises the steps of first earth excavation, first concrete structure construction, tower crane installation, second earth excavation, basement bottom plate construction, fat groove earth backfilling and the like. According to the method, quality control over basement bottom plate waterproof roll construction can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of deep foundation pit engineering construction, in particular to a full-process water-cutting construction method for deep foundation pit engineering. Background Art

[0002] In the construction of civil engineering, the construction of deep foundation pit projects is of top priority, and it is also one of the most dangerous sub-projects, which has attracted the attention of civil engineering practitioners. In the construction process of deep foundation pit projects, the water-cutting construction of deep foundation pit projects is a crucial link. The accumulation of water in the fertilizer trough between the outer wall of the basement and the edge of the foundation pit will cause damage to the waterproof membrane of the basement floor. At the same time, in the subsequent construction of the basement outer wall waterproof membrane and insulation layer, it is also necessary to pump water frequently, which makes the construction of the basement floor waterproof membrane difficult, which is not conducive to the quality control of waterproof construction, and also causes repeated pumping operations, which is time-consuming and laborious. The accumulated water in the bottom slab post-casting strip will also corrode the exposed raft slab steel bars. At the same time, because the raft slab steel bars are dense, the accumulated water is difficult to clean, and it cannot be removed even before the concrete construction of the post-casting strip. The accumulated water here will weaken the waterproof capacity of the post-casting strip and reduce the quality of concrete construction. Summary of the invention

[0003] In view of the above-mentioned prior art, the present invention proposes a method for cutting off water during the whole process of deep foundation pit construction.

[0004] The present invention provides a method for cutting off water during the whole process of deep foundation pit construction, which comprises the following steps: S1. Excavation of the first earthwork: excavation of the first trestle earthwork, the earthwork of the tower crane foundation and the earthwork of the trestle columns, and construction of the trestle columns; S2. Construction of the first concrete structure: Construction of the first trestle concrete structure and tower crane foundation concrete structure; S3, tower crane installation: excavate the first layer except the trestle area and install the tower crane; S4, second earthwork excavation: carry out the hoisting construction of the first layer of prefabricated assembled concrete exterior wall, the earthwork excavation of the second trestle area, the construction of the second trestle concrete structure, and the earthwork excavation of the rest of the second trestle area in sequence; S5. Construction of basement slab: After pouring the basement slab cushion layer on the upper end of the soil layer at the bottom of the foundation pit, the concrete construction of the external guide wall of the concrete outer wall is carried out, and the fertilizer trough area is formed between the external guide wall of the concrete outer wall and the foundation pit retaining piles; the waterproof membrane of the basement slab is laid, and the water pipes connecting the fertilizer trough area and the post-casting belt area are pre-buried inside the basement slab, and then the concrete structure of the basement slab is constructed; S6. Backfilling of the fertilizer trough: Partial backfilling of the fertilizer trough area is carried out, and the backfilling height is lower than the outer guide wall of the concrete outer wall. The second layer of prefabricated assembled concrete outer wall is hoisted and constructed, and the vertical reinforced concrete columns at the outer wall connection are cast on the inner side of the second layer of prefabricated assembled concrete outer wall. The basement outer wall waterproofing membrane and insulation layer are constructed in sequence on the outer side of the second layer of prefabricated assembled concrete outer wall, and the earth backfilling between the basement outer wall and the fertilizer trough at the edge of the foundation pit is carried out.

[0005] Preferably, in S1, the pier columns are lattice columns.

[0006] Preferably, in S5, a precast concrete cover plate is installed at the post-cast zone area, and a lower angle iron is provided at the bottom of the precast concrete cover plate.

[0007] Preferably, in S6, the lower inner side of the prefabricated assembled concrete exterior wall is sequentially provided with grouting holes, a water-stop steel plate and a waterproof rubber strip, and the lower outer side of the prefabricated assembled concrete exterior wall is sequentially provided with a lower node reserved groove, a reinforced waterproof coating at the joint, an upward part of the basement floor waterproof membrane, a basement exterior wall waterproof membrane and an insulation layer.

[0008] Preferably, in S6, waterstop steel plates are provided at the top of the precast and assembled concrete exterior wall and the bottom of the upper beam of the basement exterior wall, reserved steel bars for the upper part of the precast and assembled concrete exterior wall are provided at the top of the precast and assembled concrete exterior wall, and reserved steel bars for the lower part of the basement exterior wall area beam are provided at the bottom of the upper beam of the basement exterior wall.

[0009] Compared with the prior art, the beneficial effects of the present invention are as follows: the present invention proposes a method for cutting off water during the whole process of deep foundation pit engineering, which guides the water between the outer wall of the basement and the edge of the foundation pit and the water accumulated in the post-casting strip into the sump through a water guide pipe, and draws it out through a water pump, thereby reducing the damage of the fertilizer tank water to the waterproofing membrane of the basement floor, and improving the quality control of the construction of the waterproofing membrane of the basement floor. A precast concrete cover plate is set at the post-casting strip to prevent garbage from entering, improve the construction quality of the post-casting strip concrete, and reduce the possibility of water leakage in the basement floor after the concrete construction at the post-casting strip. The foundation pit fertilizer tank is backfilled in advance through the precast assembled concrete outer wall, which is carried out simultaneously with the construction of the main structure of the basement, shortening the construction period. At the same time, the precast assembled concrete outer wall reduces the quality problems that may occur during the construction of cast-in-place concrete, such as cold joints and weak areas caused by discontinuous concrete pouring and loose vibration. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 It is a schematic diagram of the first earth excavation in an embodiment of the present invention.

[0011] Figure 2 It is a schematic diagram of the construction of the first concrete structure in an embodiment of the present invention.

[0012] Figure 3 It is a schematic diagram of the installation of a tower crane in an embodiment of the present invention.

[0013] Figure 4-Figure 6 Schematic diagram of the second earth excavation in an embodiment of the present invention.

[0014] Figure 7-Figure 9 It is a schematic diagram of the basement floor construction in an embodiment of the present invention.

[0015] Figure 10-12 It is a schematic diagram of backfilling the fertilizer trough in an embodiment of the present invention.

[0016] Fig.13 It is a detailed diagram of the lower nodes of the prefabricated assembled exterior wall in an embodiment of the present invention.

[0017] Fig.14 It is a detailed diagram of the upper nodes of the prefabricated assembled exterior wall in an embodiment of the present invention.

[0018] Fig.15 This is a detailed diagram of the concrete cover slab node at the post-cast zone of the basement floor in an embodiment of the present invention.

[0019] In the figure, 1, earthwork of the first trestle; 2, earthwork of the tower crane foundation; 3, earthwork of the trestle column; 4, earthwork excavator; 5, earthwork transport vehicle; 6, pile driver; 7, concrete structure of the first trestle; 8, concrete structure of the tower crane foundation; 9, concrete pump truck; 10, concrete tank truck; 11, earthwork of the first floor except the trestle area; 12, tower crane; 13, prefabricated assembled concrete exterior wall of the first floor; 14, earthwork of the second trestle area; 15, concrete structure of the second trestle; 16, earthwork of the rest of the second floor except the trestle area; 17, basement floor cushion; 18, external guide wall of the concrete exterior wall; 19, foundation pit retaining piles; 20, soil layer at the bottom of the foundation pit; 21 is the waterproof membrane of the basement floor; 22, fertilizer Trough area; 23. Post-casting zone area; 24. Water guide pipe; 25. Basement floor concrete structure; 26. Second-floor precast assembled concrete exterior wall; 27. Vertical reinforced concrete column at the exterior wall connection; 28. Basement exterior wall waterproofing membrane; 29. ​​Insulation layer; 30. Basement exterior wall and foundation pit edge fertilizer trough; 31. Grouting hole; 32. Waterstop steel plate; 33. Reserved groove at the lower node; 34. Strengthen waterproof coating at the joint; 35. Upturned part of the basement floor waterproofing membrane; 37. Waterproof rubber strip; 38. Upper beam of basement exterior wall; 39. Reserved steel bars at the upper part of precast assembled concrete exterior wall; 40. Reserved steel bars at the lower part of the beam in the basement exterior wall area; 41. Lower angle iron; 42. Precast concrete cover plate. DETAILED DESCRIPTION

[0020] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific embodiments.

[0021] Example: Figure 1-Figure 15 As shown, a method for cutting off water during the whole process of deep foundation pit construction includes the following steps: S1. First earthwork excavation: Figure 1 As shown, an earthmoving machine 4, an earthmoving transport vehicle 5 and a pile driver 6 are used to excavate the first trestle earthwork 1, the tower crane foundation earthwork 2 and the trestle column earthwork 3, and to construct the trestle columns, which are lattice columns.

[0022] S2. Construction of the first concrete structure: Figure 2 As shown, a concrete pump truck 9 and a concrete tank truck 10 are used to construct the first trestle concrete structure 7 and the tower crane foundation concrete structure 8.

[0023] S3. Tower crane installation: Figure 3 As shown, the first layer of earthwork 11 is excavated except for the trestle area and a tower crane 12 is installed.

[0024] S4, Second earthwork excavation: Figure 4-Figure 6 As shown, the first layer of prefabricated assembled concrete outer wall 13 is hoisted, the second trestle area earthwork 14 is excavated, the second trestle concrete structure 15 is constructed, and the second trestle area other than the trestle area is excavated 16.

[0025] S5. Basement floor construction: Figure 7-Figure 9 As shown, after pouring the basement floor cushion layer 17 on the upper end of the soil layer 20 at the bottom of the foundation pit, the concrete construction of the external guide wall 18 of the concrete outer wall is carried out, and the fertilizer trough area 22 is formed between the external guide wall 18 of the concrete outer wall and the foundation pit retaining pile 19; the basement floor waterproofing membrane 21 is laid, and the water guide pipe 24 connected to the fertilizer trough area 22 and the post-casting zone area 23 in the basement floor is pre-buried, and the basement floor concrete structure 25 is constructed; as shown in FIG. Fig.15 As shown, a precast concrete cover plate 42 is installed at the post-cast zone area 23 , and a lower angle iron 41 is provided at the bottom of the precast concrete cover plate 42 .

[0026] S6. Backfilling of fertilizer trough: Figure 10-12 As shown, the fertilizer trough area 22 is partially backfilled, and the backfill height is lower than the outer guide wall 18 of the concrete outer wall. The second-layer prefabricated assembled concrete outer wall 26 is hoisted and constructed, and the vertical reinforced concrete column 27 at the outer wall connection is cast on the inner side of the second-layer prefabricated assembled concrete outer wall 26. The basement outer wall waterproof membrane 28 and the insulation layer 29 are sequentially constructed on the outer side of the second-layer prefabricated assembled concrete outer wall 26, and the earth backfill is carried out between the basement outer wall and the fertilizer trough 30 at the edge of the foundation pit.

[0027] Among them, Fig.13 As shown, the lower inner side of the prefabricated assembled concrete exterior wall is provided with grouting holes 31, a water stop steel plate 32 and a waterproof rubber strip 37 in sequence, and the lower outer side of the prefabricated assembled concrete exterior wall is provided with a lower node reserved groove 33, a reinforced waterproof coating 34 at the joint, an upward part 35 of the basement floor waterproof membrane, a basement exterior wall waterproof membrane 28 and an insulation layer 29 in sequence.

[0028] like Fig.14 As shown, the top of the prefabricated assembled concrete exterior wall and the bottom of the upper beam 38 of the basement exterior wall are both provided with water-stop steel plates 32, the top of the prefabricated assembled concrete exterior wall is provided with prefabricated assembled concrete exterior wall upper reserved steel bars 39, and the bottom of the upper beam 38 of the basement exterior wall is provided with basement exterior wall area beam lower reserved steel bars 40.

[0029] The construction method of this embodiment pre-buries a water pipe in the basement floor to drain the water accumulated in the fertilizer tank and the post-casting zone, thereby reducing the damage caused by the water accumulated in the deep foundation pit to the basement waterproofing membrane and raft slab steel bars. In the normal construction process, it is necessary to wait until the basement main body is fully constructed before the basement exterior wall waterproofing membrane construction, insulation layer construction and fertilizer tank backfilling process can be carried out. This embodiment can backfill the fertilizer tank in advance after the basement raft foundation is poured and the prefabricated assembled concrete exterior wall is prefabricated, and the construction is carried out simultaneously with the basement main body, shortening the construction period.

[0030] The above are only implementation modes of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent schemes made using the contents of the present invention specification, directly or indirectly applied in other related technical fields, are also within the patent protection scope of the present invention.

Claims

1. A method for cutting off water during the whole process of deep foundation pit construction, characterized in that: The steps include: S1. Excavation of the first earthwork: excavation of the first trestle earthwork, the earthwork of the tower crane foundation and the earthwork of the trestle columns, and construction of the trestle columns; S2. Construction of the first concrete structure: Construction of the first trestle concrete structure and tower crane foundation concrete structure; S3, tower crane installation: excavate the first layer except the trestle area and install the tower crane; S4, second earthwork excavation: carry out the hoisting construction of the first layer of prefabricated assembled concrete exterior wall, the earthwork excavation of the second trestle area, the construction of the second trestle concrete structure, and the earthwork excavation of the rest of the second trestle area in sequence; S5. Construction of basement slab: After pouring the basement slab cushion layer on the upper end of the soil layer at the bottom of the foundation pit, the concrete construction of the external guide wall of the concrete outer wall is carried out, and the fertilizer trough area is formed between the external guide wall of the concrete outer wall and the foundation pit retaining piles; the waterproof membrane of the basement slab is laid, and the water pipes connecting the fertilizer trough area and the post-casting belt area are pre-buried inside the basement slab, and then the concrete structure of the basement slab is constructed; S6. Backfilling of the fertilizer trough: Partial backfilling of the fertilizer trough area is carried out, and the backfilling height is lower than the outer guide wall of the concrete outer wall. The second layer of prefabricated assembled concrete outer wall is hoisted and constructed, and the vertical reinforced concrete columns at the outer wall connection are cast on the inner side of the second layer of prefabricated assembled concrete outer wall. The basement outer wall waterproofing membrane and insulation layer are constructed in sequence on the outer side of the second layer of prefabricated assembled concrete outer wall, and the earth backfilling between the basement outer wall and the fertilizer trough at the edge of the foundation pit is carried out.

2. The method for cutting off water supply during the whole process of deep foundation pit construction as claimed in claim 1, characterized in that: In S1, the trestle columns are lattice columns.

3. The method for cutting off water supply during the whole process of deep foundation pit construction as claimed in claim 1 or 2, characterized in that: In S5, a precast concrete cover plate is installed at the post-cast zone area, and a lower angle iron is provided at the bottom of the precast concrete cover plate.

4. The method for cutting off water supply during the whole process of deep foundation pit construction as claimed in claim 1 or 2, characterized in that: In S6, the lower inner side of the prefabricated assembled concrete exterior wall is provided with grouting holes, water-stop steel plates and waterproof rubber strips in sequence, and the lower outer side of the prefabricated assembled concrete exterior wall is provided with lower node reserved grooves, reinforced waterproof coatings at joints, the upper folded part of the basement floor waterproof membrane, the basement exterior wall waterproof membrane and the insulation layer in sequence.

5. The method for cutting off water supply during the whole process of deep foundation pit construction as claimed in claim 1 or 2, characterized in that: In S6, waterstop steel plates are provided at the top of the precast and assembled concrete exterior wall and at the bottom of the upper beam of the basement exterior wall, reserved steel bars for the upper part of the precast and assembled concrete exterior wall are provided at the top of the precast and assembled concrete exterior wall, and reserved steel bars for the lower part of the basement exterior wall area beam are provided at the bottom of the upper beam of the basement exterior wall.