Construction method for repairing water-rich stratum concrete sump inrush water leakage

Through the construction method of water-rich concrete water collection pit sudden surge and leakage repair in water-rich formations, drainage and grouting technology are used to solve the problem of sudden surge and leakage in water collection pits, achieving simplification of construction, cost saving and structural strength improvement, ensuring long-term waterproofing effect .

CN118958346APending Publication Date: 2024-11-15CHINA MCC17 GRP CO LTD

Patent Information

Application Number
CN202411356586.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-27
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

In underground construction in water-rich areas, sudden water leakage in the water collecting pit is often caused by complex geological conditions, large water pressure, and inadequate construction measures, which affects the construction progress and foundation stability. The traditional repair method is not lasting. The strength and size of the component design cannot be guaranteed.

Method used

The construction method of water-rich formation concrete collecting pit sudden leakage repair and construction, including pumping cleaning, open hole drainage, waterproof sealing, temporary pouring concrete sealing, reverse grouting and infrared thermal imager auxiliary quality control, through drainage pipes and Grouting materials ensure water pressure reduction and structural strength.

Benefits of technology

This method simplifies the construction process, reduces costs and construction periods, ensures repair effect and structural strength, reduces damage to the building, and achieves a long-term waterproofing effect.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention provides a water-rich stratum concrete sump inrush water leakage repairing construction method, and belongs to the technical field of water leakage in water-rich areas, and the method comprises the following steps: S1, pumping water to clean a sump to find a water leakage point, and investigating water burst reasons and conditions in detail; s2, determining a repair construction method according to the on-site water burst pressure; s3, opening holes in the inrush point positions of the foundation pit, and installing a water pipe valve for drainage; s4, waterproof plugging is conducted around the drainage point of the water pipe valve; s5, concrete is temporarily poured in the waterproof plugging range, and the horizontal sealing layer resists the water bearing pressure and the subsequent reverse grouting pressure; s6, reverse grouting is conducted through the drainage pipe, and the grouting quality is controlled in cooperation with an infrared thermal imager; s7, the water leakage condition after repairing is detected, and a waterproof layer is constructed on the downstream face of the foundation pit; the construction technology is simple, the problem is effectively solved, good impermeability is achieved after repairing is completed, and the strength of an original structural member is guaranteed. The water collecting pit is prevented from losing normal use functions, and in addition, adverse effects on the surrounding environment are prevented.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of water leakage in water-rich areas, and in particular relates to a construction method for repairing sudden water leakage in a concrete sump in a water-rich stratum. Background Art

[0002] In underground construction of building projects, sump pits are common facilities used to collect and discharge groundwater. However, under some complex geological conditions, the strata around the sump are rich in water or due to certain factors during the construction process, the sump pits that have been poured may suddenly leak.

[0003] The reasons for sudden water leakage in the sump are, on the one hand, the high groundwater level, the strong permeability of the soil layer, the presence of large pressurized water, and the thin thickness of the raft slab in the sump, which may cause the sump to face greater water pressure and easily cause sudden water leakage. On the other hand, misjudgment of geological conditions during construction, inadequate water-stopping measures, inadequate precipitation, and defects in the foundation pit support structure may all become factors that induce sudden water leakage in the sump. When a sudden water leakage occurs in the sump, it will not only affect the construction progress and quality, but may also lead to a series of problems such as affected foundation stability, instability of the surrounding soil, and ground subsidence, posing a threat to project safety and the surrounding environment.

[0004] With the increasing number of underground projects and the diversification of underground water levels, the sudden leakage of water collection pits has become more complex and diverse. Traditional repair methods include direct plugging, wooden wedge plugging, box plugging, and strong plugging. Their construction techniques may have limitations, such as short-term effects, inability to guarantee the design strength of components, inability to guarantee the design dimensions of the water collection pit drawings after the repair is completed, and difficulty in adapting to complex working conditions.

[0005] In order to research and develop more advanced and more effective water collection pit sudden leakage repair technology to cope with the above problems and new challenges and demands, a construction method for repairing water leakage in concrete water collection pits in water-rich strata is proposed. Summary of the invention

[0006] In order to effectively solve the problem of sudden gushing and leakage of water collection pits in water-rich areas of basements, the present invention proposes a method for repairing sudden gushing and leakage of concrete water collection pits in water-rich strata, including the following steps:

[0007] S1. Pump out water and clean the sump to find the leaking point, and investigate the cause and situation of the water inrush in detail;

[0008] S2. Determine the repair construction method according to the on-site water pressure;

[0009] S3. Drill holes at the sudden surge points in the foundation pit and install water pipe valves for drainage;

[0010] S4. Waterproof and seal the drainage points around the water pipe valves;

[0011] S5. Temporary pouring of concrete horizontal sealing layer in the waterproof sealing range to resist water bearing pressure and subsequent reverse grouting pressure;

[0012] S6. Reverse grouting through the drainage tube and use infrared thermal imaging to control the grouting quality;

[0013] S7. Check the water leakage after repair and construct a waterproof layer on the back surface of the foundation pit;

[0014] Preferably, in step S1, a suitable submersible pump is first prepared to pump water from the foundation pit to ensure that the amount of water pumped is greater than the amount of water gushing out, and the gushing water in the sump can be pumped to the working surface at the bottom of the pit and in a balanced state. Garbage in the foundation pit is cleaned up while taking effective safety protection measures. A detailed on-site survey of the leaking point, leaking location, leaking cracks or leaking holes is conducted to analyze the causes of the leak, form an inspection record, and draw a simple map of the leaking point location characteristics.

[0015] Preferably, in step S2, the elevation of the groundwater level in the aquifer is first detected, and the sudden surge pressure of the foundation pit leakage is calculated by theoretical calculation and data simulation. Theoretical calculation can be based on the principle of groundwater dynamics, taking into account the permeability and head height of the aquifer. Data simulation can use computer software to model and simulate the foundation pit and groundwater system to more accurately predict the sudden surge pressure. According to the sudden surge pressure and site conditions, a reasonable drainage scheme is designed. The purpose of drainage is to reduce the head pressure at the sudden surge point, reduce the leakage flow, and finally determine the appropriate size of the drainage pipe and the corresponding grouting scheme. The grouting scheme takes into account factors such as the selection of materials, the arrangement of grouting holes, the grouting amount, and the grouting pressure.

[0016] Preferably, in step S3, the drainage position of the opening at the surge point is accurately determined to ensure the drilling position. According to the surge pressure and the thickness of the foundation pit raft calculated on site, appropriate drilling equipment is selected, and the drilling depth and diameter are reasonably determined to achieve a good drainage effect. After the drilling is completed, the debris in the hole is cleaned up in time to ensure that the drainage channel is smooth. Select a drainage pipe of suitable material and specification (such as a thickened steel pipe, a galvanized pipe) and thread and install the valve at one end of the drainage pipe in advance. During installation, ensure the correctness of the installation direction so that it can be opened and closed normally to achieve the pressure relief function. Insert the end of the drainage pipe without the valve installed into the drainage channel, install a water stop strip at the connection and intersection of the pipeline and the foundation pit structure, and strictly seal it to ensure that there is no water leakage at the gap between the top of the opening hole and the junction of the pipeline. After the drainage pipe is installed, open the pipeline valve to ensure that a large amount of surge water flows out through the pipeline, and there is no obvious surge leakage in the surrounding area of ​​the pipeline.

[0017] Preferably, in step S4, the drainage pipe is first connected to a plastic hose to guide the sudden water in the drainage pipe into a bucket of suitable size, and a suitable water pump is placed in the bucket for drainage treatment. Subsequently, the debris and soil around the drainage pipe and the loose concrete aggregates of the cement slurry without strength are chiseled out, and a horizontal sealing layer is used to seal the leakage range around the drainage pipe with a quick-setting plugging mortar. After the construction is completed, it is ensured that the sudden water in the foundation pit only flows from the drainage pipe into the temporary bucket and is then discharged by the water pump, and there is no water leakage in other parts, and the foundation pit can be kept dry.

[0018] Preferably, in step S5, after the waterproof layer around the drainage pipe solidifies, a temporary concrete thick horizontal bottom seal is constructed on the surface of the drainage pipe to expand to a certain range according to the surge verification pressure in step S2. The quality of the construction is strictly controlled to ensure that the pouring is dense, crack-free and has a certain strength. This temporary concrete construction is used to resist the water bearing pressure and the subsequent reverse grouting pressure. After the grouting is completed and the leak repair effect is achieved, it is dismantled to ensure that the size of the foundation pit is not affected after the repair.

[0019] Preferably, in step S6, reverse grouting is performed after the concrete horizontal seal reaches a certain strength, and the grouting material uses ordinary silicate cement, which has good strength and anti-seepage function and early strength function. During grouting, the grouting coverage of the foundation pit raft is observed with an infrared thermal imager to dynamically adjust the grouting pressure, and the grouting of all the gaps of the raft slab in the sump is completed by observing the infrared thermal imager, and the pressure is maintained for a certain period of time. After the grouting slurry solidifies, the pressure is released to end the grouting construction.

[0020] Preferably, in step S7, after the preliminary repair is completed, the repair effect is checked by direct observation to observe whether there are cracks and traces of water seepage on the surface, and then the leakage point is observed for a period of time. After the sudden surge repair is completed, the temporary horizontal sealing layer concrete at the repair point is removed to expose the sealed grouting pipeline, and the grouting iron pipe is cut along the back water surface of the foundation pit by gas cutting. After the cutting is completed, ensure that the end of the grouting pipe and the internal solidified cement slurry are in the same plane as the back water surface of the sump structure. Finally, the back water surface of the foundation pit is painted with a reinforced waterproof layer, and a cement-based penetrating crystalline waterproof coating that can penetrate into the concrete to play a good waterproof and self-repairing role is applied within the range of the sudden surge repair point. After the coating construction is completed, the inner wall of the foundation pit is painted with 20 thick 1:2 cement mortar plus 5% waterproofing agent, and the layers are smoothed and polished. After the final setting is completed and a hydrophobic film is formed on the surface, continue to maintain it.

[0021] Beneficial Effects

[0022] The method of repairing sudden surges in water-rich layer collection pits is to open holes for drainage. Its construction process is relatively simple, the amount of work is small and the cost is low. Compared with the traditional method of using pipe wells to first lower the water level and then repair, it saves a lot of costs to a certain extent and shortens the construction period.

[0023] The grouting material used in the water-rich layer sump sudden surge repair method is ordinary Portland cement PI 62.5 (R). Its raw materials are relatively easy to obtain and the cost is relatively low. It has good strength and anti-seepage functions and also has early strength function, which ensures the strength of the sump structural components while repairing the leakage problem. The grouting process of ordinary Portland cement is relatively simple, does not require the use of special grouting equipment and technology, and the construction is convenient and quick.

[0024] In the water-rich layer collection pit sudden surge repair method, the use of infrared thermal imaging devices to assist in controlling the grouting quality can achieve the purpose of rapid and accurate leak-stopping and repair grouting while reducing unnecessary damage to buildings. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0026] The application principle of the present invention is further described below in conjunction with specific embodiments.

[0027] Example 1

[0028] A construction method for repairing sudden water leakage in a concrete water collection pit in a water-rich stratum comprises the following steps:

[0029] S1. Prepare a suitable submersible pump to pump water from the foundation pit. Ensure that the pumping volume is greater than the gushing volume, and that the gushing water in the sump can be pumped to the working surface at the bottom of the pit and in a balanced state. Clean up the garbage in the foundation pit while taking effective safety protection measures. Conduct a detailed on-site survey of the leaking point, leaking location, leaking cracks or leaking holes, analyze the causes of the leak, form an inspection record, and draw a simple map of the leaking point location characteristics.

[0030] S2. Observe and measure the elevation of the groundwater level in the aquifer, and calculate the sudden surge pressure of the foundation pit through theoretical calculation and data simulation. Theoretical calculation can be based on the principle of groundwater dynamics, taking into account the permeability of the aquifer and the head height. Data simulation can use computer software to model and simulate the foundation pit and groundwater system to more accurately predict the sudden surge pressure. According to the sudden surge pressure and site conditions, a reasonable drainage plan is designed. The purpose of drainage is to reduce the head pressure at the sudden surge point and reduce the leakage flow. Finally, the appropriate size of the drainage pipe and the corresponding grouting plan are determined. The grouting plan takes into account factors such as material selection, grouting hole layout, grouting volume, and grouting pressure.

[0031] S3. Accurately determine the location of the drainage hole at the surge point and ensure the drilling position. According to the surge pressure and the thickness of the foundation pit raft calculated in step S2, select appropriate drilling equipment. The drilling construction depth is 200cm and the hole diameter is DN40. After the drilling is completed, clean up the debris in the hole in time to ensure a smooth drainage channel. Select a DN32 galvanized pipe as the drainage pipe. One end of the drainage pipe is pre-threaded to install the valve. During installation, ensure the correctness of the installation direction so that it can be opened and closed normally to achieve the pressure relief function. Insert the end of the drainage pipe without the valve installed into the drainage channel, and install a water stop strip at the connection and intersection of the pipeline and the foundation pit structure for strict sealing to ensure that there is no water leakage in the gap between the top of the hole and the junction of the pipeline. After the drainage pipe is installed, open the pipeline valve to ensure that a large amount of surge water flows out through the pipeline, and there is no obvious surge leakage in the surrounding area of ​​the pipeline.

[0032] S4. First, connect the drainage pipe to a plastic hose to guide the sudden water in the drainage pipe into a temporarily prepared bucket, and put a suitable drainage pump in the bucket for drainage treatment. Then, remove the debris and soil around the drainage pipe and the loose concrete aggregates of the cement slurry without strength, and use quick-setting plugging mortar to seal the leakage area around the drainage pipe with a 2-3cm thick horizontal sealing layer. After the construction is completed, ensure that the sudden water in the foundation pit flows from the drainage pipe into the temporary bucket and is discharged by the water pump. There is no leakage in other parts and the foundation pit can remain dry.

[0033] S5. After the waterproof layer around the drainage pipe solidifies, a 30cm thick temporary concrete (micro-expansion C30, P6) horizontal bottom cover is constructed based on the surge verification pressure in step S2 and the surface is expanded 20cm. The construction quality is strictly controlled to ensure that the pouring is dense, crack-free and has a certain strength. This temporary concrete construction is used to resist the water bearing pressure and the subsequent reverse grouting pressure. After the grouting is completed and the leak repair effect is achieved, it will be dismantled to ensure that the size of the foundation pit is not affected after the repair.

[0034] S6. After the concrete horizontal seal reaches 75% strength, reverse grouting is carried out. Ordinary Portland cement PI 62.5 (R) is used as the grouting material. During grouting, the grouting coverage of the foundation pit raft is observed with an infrared thermal imager to dynamically adjust the grouting pressure. The grouting of all the gaps of the raft slab leaking from the sump is completed by observing the infrared thermal imager, and the pressure is maintained for 10 hours. After the grouting slurry is finally set, the pressure is released to end the grouting construction.

[0035] S7. After the initial repair is completed, check the repair effect. Use direct observation to observe whether there are cracks and traces of water seepage on the surface, and then continue to detect for a period of time to observe whether there are any abnormalities at the leakage point. After the foundation pit sudden surge repair is completed, the temporary horizontal sealing layer concrete at the repair point is removed to expose the sealed grouting pipeline. Use gas cutting to cut off the grouting iron pipe along the back water surface of the foundation pit. After the cutting is completed, ensure that the end of the grouting pipe and the internal solidified cement slurry are in the same plane as the back water surface of the sump structure. Finally, the back water surface of the foundation pit is painted with a reinforced waterproof layer, and a cement-based penetrating crystalline waterproof coating that can penetrate into the concrete and play a good waterproof and self-repairing role is applied within the range of the sudden surge repair point. After the coating construction is completed, the inner wall of the foundation pit is painted with 20 thick 1:2 cement mortar plus 5% waterproofing agent, and the surface is smoothed and polished in layers. After the final setting is completed, a hydrophobic film is formed on the surface and continued maintenance can be performed.

[0036] Among them, the certain time and certain intensity in this embodiment need to be considered in formulating a sudden surge blocking plan. It is related to the soil quality in the actual area and the concrete materials used, and specific data cannot be given.

[0037] Embodiment 2

[0038] A construction method for repairing sudden water leakage in a concrete water collection pit in a water-rich stratum comprises the following steps:

[0039] S1. Prepare a suitable submersible pump to pump water from the foundation pit. Ensure that the pumping volume is greater than the gushing volume, and that the gushing water in the sump can be pumped to the working surface at the bottom of the pit and in a balanced state. Clean up the garbage in the foundation pit while taking effective safety protection measures. Conduct a detailed on-site survey of the leaking point, leaking location, leaking cracks or leaking holes, analyze the causes of the leak, form an inspection record, and draw a simple map of the leaking point location characteristics.

[0040] S2. Observe and measure the elevation of the groundwater level in the aquifer, and calculate the sudden surge pressure of the foundation pit through theoretical calculation and data simulation. Theoretical calculation can be based on the principle of groundwater dynamics, taking into account the permeability of the aquifer and the head height. Data simulation can use computer software to model and simulate the foundation pit and groundwater system to more accurately predict the sudden surge pressure. According to the sudden surge pressure and site conditions, a reasonable drainage plan is designed. The purpose of drainage is to reduce the head pressure at the sudden surge point and reduce the leakage flow. Finally, the appropriate size of the drainage pipe and the corresponding grouting plan are determined. The grouting plan takes into account factors such as material selection, grouting hole layout, grouting volume, and grouting pressure.

[0041] S3. Accurately determine the location of the drainage hole at the surge point and ensure the drilling position. According to the surge pressure and the thickness of the foundation pit raft calculated in step S2, select appropriate drilling equipment. The drilling construction depth is 200cm and the hole diameter is DN40. After the drilling is completed, clean up the debris in the hole in time to ensure a smooth drainage channel. Select a DN32 galvanized pipe as the drainage pipe. One end of the drainage pipe is pre-threaded to install the valve. During installation, ensure the correctness of the installation direction so that it can be opened and closed normally to achieve the pressure relief function. Insert the end of the drainage pipe without the valve installed into the drainage channel, and install a water stop strip at the connection and intersection of the pipeline and the foundation pit structure for strict sealing to ensure that there is no water leakage in the gap between the top of the hole and the junction of the pipeline. After the drainage pipe is installed, open the pipeline valve to ensure that a large amount of surge water flows out through the pipeline, and there is no obvious surge leakage in the surrounding area of ​​the pipeline.

[0042] S4. If a small amount of sudden water leakage is still found around the drainage pipe after the above steps are completed, the original sudden water leakage point drilling size is changed on site to enlarge the drainage pipe, or a set of drainage pipes is added next to the original drainage pipe. After the drainage pipe is changed, the water bearing pressure around the pipe becomes smaller and there is no obvious sudden water leakage.

[0043] S5. First, connect the drainage pipe to a plastic hose to guide the sudden water in the drainage pipe into a temporarily prepared bucket, and put a suitable drainage pump in the bucket for drainage treatment. Then, remove the debris and soil around the drainage pipe and the loose concrete aggregates of the cement slurry without strength, and use quick-setting plugging mortar to seal the leakage area around the drainage pipe with a 2-3cm thick horizontal sealing layer. After the construction is completed, ensure that the sudden water in the foundation pit flows from the drainage pipe into the temporary bucket and is discharged by the water pump. There is no leakage in other parts and the foundation pit can be kept dry.

[0044] S6. After the waterproof layer around the drainage pipe solidifies, a 30cm thick temporary concrete (micro-expansion C30, P6) horizontal bottom cover is constructed based on the surge verification pressure in step S2 and the surface is expanded 20cm. The construction quality is strictly controlled to ensure that the pouring is dense, crack-free and has a certain strength. This temporary concrete construction is used to resist the water bearing pressure and the subsequent reverse grouting pressure. After the grouting is completed and the leak repair effect is achieved, it will be dismantled to ensure that the size of the foundation pit is not affected after the repair.

[0045] S7. After the concrete horizontal seal reaches 75% strength, reverse grouting construction is carried out. Ordinary Portland cement PI 62.5 (R) is used as the grouting material. During grouting, the grouting coverage of the foundation pit raft slab is observed with an infrared thermal imager to dynamically adjust the grouting pressure. The grouting of all the gaps of the raft slab leaking from the sump is completed by observing the infrared thermal imager, and the pressure is maintained for 10 hours. After the grouting slurry is finally set, the pressure is released to end the grouting construction.

[0046] S8. After the initial repair is completed, check the repair effect. Use direct observation to observe whether there are cracks and traces of water seepage on the surface, and then continue to detect for a period of time to observe whether there are any abnormalities at the leakage point. After the foundation pit sudden surge repair is completed, the temporary horizontal sealing layer concrete at the repair point is removed to expose the sealed grouting pipeline. Use gas cutting to cut off the grouting iron pipe along the back water surface of the foundation pit. After the cutting is completed, ensure that the end of the grouting pipe and the internal solidified cement slurry are in the same plane as the back water surface of the sump structure. Finally, the back water surface of the foundation pit is painted with a reinforced waterproof layer, and a cement-based penetrating crystalline waterproof coating that can penetrate into the concrete and play a good waterproof and self-repairing role is applied within the range of the sudden surge repair point. After the coating construction is completed, the inner wall of the foundation pit is painted with 20 thick 1:2 cement mortar plus 5% waterproofing agent, and the surface is smoothed and polished in layers. After the final setting is completed, a hydrophobic film is formed on the surface and continued maintenance can be performed.

[0047] Embodiment 3

[0048] A construction method for repairing sudden water leakage in a concrete water collection pit in a water-rich stratum comprises the following steps:

[0049] S1. Prepare a suitable submersible pump to pump water from the foundation pit. Ensure that the pumping volume is greater than the gushing volume, and that the gushing water in the sump can be pumped to the working surface at the bottom of the pit and in a balanced state. Clean up the garbage in the foundation pit while taking effective safety protection measures. Conduct a detailed on-site survey of the leaking point, leaking location, leaking cracks or leaking holes, analyze the causes of the leak, form an inspection record, and draw a simple map of the leaking point location characteristics.

[0050] S2. Observe and measure the elevation of the groundwater level in the aquifer, and calculate the sudden surge pressure of the foundation pit through theoretical calculation and data simulation. Theoretical calculation can be based on the principle of groundwater dynamics, taking into account the permeability of the aquifer and the head height. Data simulation can use computer software to model and simulate the foundation pit and groundwater system to more accurately predict the sudden surge pressure. According to the sudden surge pressure and site conditions, a reasonable drainage plan is designed. The purpose of drainage is to reduce the head pressure at the sudden surge point and reduce the leakage flow. Finally, the appropriate size of the drainage pipe and the corresponding grouting plan are determined. The grouting plan takes into account factors such as material selection, grouting hole layout, grouting volume, and grouting pressure.

[0051] S3. Accurately determine the location of the drainage hole at the surge point and ensure the drilling position. According to the surge pressure and the thickness of the foundation pit raft calculated in step S2, select appropriate drilling equipment. The drilling construction depth is 200cm and the hole diameter is DN40. After the drilling is completed, clean up the debris in the hole in time to ensure a smooth drainage channel. Select a DN32 galvanized pipe as the drainage pipe. One end of the drainage pipe is pre-threaded to install the valve. During installation, ensure the correctness of the installation direction so that it can be opened and closed normally to achieve the pressure relief function. Insert the end of the drainage pipe without the valve installed into the drainage channel, and install a water stop strip at the connection and intersection of the pipeline and the foundation pit structure for strict sealing to ensure that there is no water leakage in the gap between the top of the hole and the junction of the pipeline. After the drainage pipe is installed, open the pipeline valve to ensure that a large amount of surge water flows out through the pipeline, and there is no obvious surge leakage in the surrounding area of ​​the pipeline.

[0052] S4. First, connect the drainage pipe to a plastic hose to guide the sudden water in the drainage pipe into a temporarily prepared bucket, and put a suitable drainage pump in the bucket for drainage treatment. Then, remove the debris and soil around the drainage pipe and the loose concrete aggregates of the cement slurry without strength, and use quick-setting plugging mortar to seal the leakage area around the drainage pipe with a 2-3cm thick horizontal sealing layer. After the construction is completed, ensure that the sudden water in the foundation pit flows from the drainage pipe into the temporary bucket and is discharged by the water pump. There is no leakage in other parts and the foundation pit can remain dry.

[0053] S5 In the above steps, the leakage range around the drainage pipe is sealed with a horizontal layer of quick-setting waterproof mortar. After plugging the leakage, it is found that there is slight water seepage on the surface. The bottom of the foundation pit cannot be guaranteed to be absolutely dry. Apply a flexible waterproof coating reinforcement layer on the surface of the quick-setting waterproof mortar and the 20cm range outside. Apply a layer of polyurethane waterproof coating with excellent elasticity, high and low temperature resistance and outstanding waterproof effect. Use a brush to apply it twice with a coating thickness of 1-1.5mm. After the waterproof coating is applied, observe the surface water-stopping effect.

[0054] S6. After the waterproof mortar and waterproof coating construction around the drainage pipe is completed, check that there is no more water leakage on the foundation pit surface. According to the sudden surge verification pressure in step S2, a 30cm thick temporary concrete (micro-expansion C30, P6) horizontal bottom sealing construction is carried out within a range of 20cm on the surface. The construction quality is strictly controlled to ensure that the pouring is dense, crack-free and has a certain strength. This temporary concrete construction is used to resist the water bearing pressure and the subsequent reverse grouting pressure. After the grouting is completed and the leak repair effect is achieved, it will be dismantled to ensure that the size of the foundation pit is not affected after the repair.

[0055] S7. After the concrete horizontal seal reaches 75% strength, reverse grouting construction is carried out. Ordinary Portland cement PI 62.5 (R) is used as the grouting material. During grouting, the grouting coverage of the foundation pit raft slab is observed with an infrared thermal imager to dynamically adjust the grouting pressure. The grouting of all the gaps of the raft slab leaking from the sump is completed by observing the infrared thermal imager, and the pressure is maintained for 10 hours. After the grouting slurry is finally set, the pressure is released to end the grouting construction.

[0056] S8. After the initial repair is completed, check the repair effect. Use direct observation to observe whether there are cracks and traces of water seepage on the surface, and then continue to detect for a period of time to observe whether there are any abnormalities at the leakage point. After the foundation pit sudden surge repair is completed, the temporary horizontal sealing layer concrete at the repair point is removed to expose the sealed grouting pipeline. Use gas cutting to cut off the grouting iron pipe along the back water surface of the foundation pit. After the cutting is completed, ensure that the end of the grouting pipe and the internal solidified cement slurry are in the same plane as the back water surface of the sump structure. Finally, the back water surface of the foundation pit is painted with a reinforced waterproof layer, and a cement-based penetrating crystalline waterproof coating that can penetrate into the concrete and play a good waterproof and self-repairing role is applied within the range of the sudden surge repair point. After the coating construction is completed, the inner wall of the foundation pit is painted with 20 thick 1:2 cement mortar plus 5% waterproofing agent, and the surface is smoothed and polished in layers. After the final setting is completed, a hydrophobic film is formed on the surface and continued maintenance can be performed.

[0057] Working principle: Drainage through holes in water-rich soil sump In order to provide a pressure relief drainage channel for the sudden leakage point of the sump, reduce the water bearing pressure inside the sump, and reduce the leakage pressure around the sudden leakage point, the leakage point around the drainage pipe can be waterproofed and blocked first, and all the water from the sudden leakage point can be drained into the pipe. Subsequently, reverse grouting is performed on the drainage pipe, and good grouting materials are used, and an auxiliary infrared thermal imager is used during the grouting process to control the grouting quality, so that a good repair effect can be achieved in the end.

[0058] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be considered exemplary and non-restrictive in all respects, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention.

[0059] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A construction method for repairing sudden water leakage in a concrete sump in a water-rich stratum, characterized in that: The following steps are involved: S1. Pump out water and clean the sump to find the leaking point, and investigate the cause and situation of the water inrush in detail; S2. Determine the repair construction method based on the on-site water pressure; S3. Drill holes at the sudden surge points in the foundation pit and install water pipe valves for drainage; S4. Waterproof and seal the drainage points around the water pipe valves; S5. Temporary pouring of concrete in the waterproof sealing area, with the horizontal sealing layer resisting the water bearing pressure and subsequent reverse grouting pressure; S6. Reverse grouting through the drainage tube and use infrared thermal imaging to control the grouting quality; S7. Check the water leakage after repair and construct a waterproof layer on the back water surface of the foundation pit.

2. The method for repairing sudden water leakage in a concrete water collection pit in a water-rich stratum according to claim 1 is characterized in that: In step S1, a suitable submersible pump is first prepared to pump water from the foundation pit, ensuring that the amount of water pumped is greater than the amount of water gushing out, and that the water gushing out of the sump can be pumped to the working surface at the bottom of the pit and is in a balanced state; Clean up the garbage in the foundation pit while taking effective safety protection measures; Conduct a detailed on-site survey of leaking points, leaking locations, leaking cracks or leaking hole characteristics, analyze the causes of the leak, form an inspection record and draw a simple map of the leaking point location characteristics.

3. A construction method for repairing sudden water leakage in a concrete sump in a water-rich stratum according to claim 1, characterized in that: In step S2, the groundwater level of the aquifer is first detected, and the sudden surge pressure of the foundation pit leakage is calculated by theoretical calculation method and data simulation method; The theoretical calculation is based on the principles of groundwater dynamics, taking into account the permeability of the aquifer and the water head height; Data simulation uses computer software to model and simulate foundation pits and groundwater systems to accurately predict surge pressures; Design a reasonable drainage plan based on surge pressure and site conditions; Finally, determine the appropriate size of drainage pipes and corresponding grouting scheme; When combining the grouting scheme, at least the selection of materials, arrangement of grouting holes, grouting volume, and grouting pressure should be considered.

4. A construction method for repairing sudden water leakage in a concrete sump in a water-rich stratum according to claim 1, characterized in that: In the step S3, the location of the drainage hole at the surge point is accurately determined to ensure the drilling position; Select appropriate drilling equipment according to the surge pressure and foundation pit raft thickness verified on site, and reasonably determine the drilling depth and diameter to achieve a good drainage effect; After drilling is completed, clean up the debris in the hole in time to ensure smooth drainage channel; Select a drainage tube of suitable material and specification, and thread one end of the drainage tube to install the valve in advance; during installation, ensure the correct installation direction so that it can be opened and closed normally to achieve the pressure relief function; Insert the end of the drainage pipe without the valve into the drainage channel, install water stop strips at the joints between the pipe and the foundation pit structure to strictly seal the joints, and ensure that no water seepage occurs at the gap between the top of the opening and the junction of the pipe; After the drainage pipe is installed, open the pipe valve to ensure that a large amount of sudden water flows out through the pipe and there is no obvious sudden leakage in the surrounding area of ​​the pipe.

5. A construction method for repairing sudden water leakage in a concrete sump in a water-rich stratum according to claim 1, characterized in that: In step S4, the drainage pipe is first connected to a plastic hose, and the sudden water in the drainage pipe is introduced into a bucket of suitable size, and a suitable water pump is placed in the bucket for drainage treatment; Then loosen the debris, soil and cement slurry around the drainage pipe, remove the concrete aggregate, and use quick-setting plugging mortar to seal the leakage area around the drainage pipe with a horizontal seal layer; After the construction is completed, ensure that the sudden water gushing out of the foundation pit only flows into the temporary water bucket from the drainage pipe and is then discharged through the water pump. There is no water leakage in other parts and the foundation pit remains dry.

6. A construction method for repairing sudden water leakage in a concrete sump in a water-rich stratum according to claim 1, characterized in that: In step S5, after the waterproof layer around the drainage pipe is solidified, temporary concrete thick horizontal bottom sealing construction is carried out on the surface of the drainage pipe according to the surge verification pressure in step S2; Strict quality control during construction to ensure that the pouring is dense and crack-free; This temporary concrete construction is used to resist water bearing pressure and subsequent reverse grouting pressure. It will be dismantled after the grouting is completed to achieve the leak repair effect, ensuring that the size of the foundation pit is not affected after the repair.

7. A construction method for repairing sudden water leakage in a concrete sump in a water-rich stratum according to claim 1, characterized in that: In step S6, after the concrete horizontal sealing layer reaches a specified strength, reverse grouting construction is performed; Ordinary Portland cement is used as grouting material; During grouting, use an infrared thermal imager to observe the grouting coverage of the foundation pit raft slab and dynamically adjust the grouting pressure. Use the infrared thermal imager to observe the completion of grouting of all the gaps in the leaking raft slab in the sump, and maintain a steady pressure. After the grouting slurry solidifies, release the pressure to end the grouting construction.

8. A construction method for repairing sudden water leakage in a concrete sump in a water-rich stratum according to claim 1, characterized in that: In step S7, the preliminary repair is completed, and the repair effect is checked by directly observing whether there are cracks or water seepage marks on the surface; Then, continue to check and observe whether there is any abnormality at the leakage point; After the sudden surge repair of the foundation pit is completed, the temporary horizontal sealing layer concrete at the repair point is removed to expose the blocked grouting pipe; the grouting iron pipe is cut along the back water surface of the foundation pit by gas cutting, and the cutting is completed to ensure that the end of the grouting pipe and the internal solidified cement slurry are in the same plane as the back water surface of the sump structure; Finally, a reinforced waterproof layer is applied to the backwater surface of the foundation pit, and a cement-based penetrating crystalline waterproof coating that can penetrate into the concrete and play a good waterproof and self-repairing role is applied within the scope of the sudden surge repair point; After the coating construction is completed, the inner wall of the foundation pit is painted with 20mm thick 1:2 cement mortar plus 5% waterproofing agent, and smoothed in layers. After the final setting, a hydrophobic film is formed on the surface, and then continued maintenance is required.

Citation Information

Patent Citations

  • Video guiding type grouting construction method

    CN111636711A

  • Comprehensive emergency rescue method for water leakage dangerous case of subway foundation pit

    CN115094928A

  • Treatment method for large-flow confined water inrush of foundation pit

    CN117702789A

Cited By

  • Construction method for metro tunnel leakage water treatment by using bi-component nano acrylate grouting and leaking stoppage material

    CN121654454A