Vertical transportation method for high-rise fabricated building construction
By using mobile steel operating platforms and cage devices in high-rise buildings, and using signal bells and lifting drop buttons to control the transportation of cages, the safety hazards and low efficiency of aluminum mold support pole transportation in the prior art are solved. It achieves fast, safe and low-cost transportation effects.
Patent Information
- Application Number
- CN202410851624.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-28
- Publication Date
- 2024-11-15
AI Technical Summary
The existing vertical transportation method of aluminum mold support vertical poles has problems such as easily collision and falling out of material transfer holes, high labor intensity, slow transportation, time-consuming and high cost.
Using mobile steel operating platform and cage device, the cage lifting and descending are controlled through signal bells and lifting down buttons. The wire rope and chute technology are used to achieve rapid and safe transportation of aluminum mold support poles, reducing manual operation, reducing labor intensity and cost.
It achieves rapid and safe transportation, reduces labor intensity and cost, and ensures the reliability and safety of construction.
Smart Images

Figure CN118958701A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of high-rise building construction methods, and in particular relates to a vertical transportation method for high-rise assembled building construction. Background Art
[0002] At present, the vertical transportation construction of aluminum formwork support poles is that after the concrete is poured, the casting layer quick-disassembly support frame template is manually transferred to the installation floor through the transfer hole, and the bottom layer of the three-layer quick-disassembly support frame is transferred to the installation floor for stacking and installation through the transfer hole manually or by attaching a lifting and unloading platform. The disadvantages of this transportation method are: it is easy to collide with the transfer hole and fall off to injure people, there are safety hazards, high labor intensity, slow transportation, time-consuming and labor-intensive, and high cost.
[0003] In summary, a vertical transportation method for high-rise prefabricated building construction is proposed in the present invention. Summary of the invention
[0004] In order to solve the above technical problems, the inventors have obtained the technical solution of the present invention through practice and summary. The present invention discloses that the basic concept of the technical solution adopted by the present invention to solve the above technical problems is:
[0005] The purpose of the present invention is to provide a vertical transportation method for high-rise assembled building construction using laminated reinforced thermal insulation composite panels, which is reliable to use, fast to transport, reduces labor intensity, saves time and effort, has obvious effects, is not easy to fall off and injure people, and ensures construction safety.
[0006] The object of the present invention is achieved by: a vertical transportation method for high-rise assembled building construction, comprising the following steps:
[0007] Step 1: Make a mobile steel operating platform
[0008] Measure the length and width of the elevator shaft, and use 12# channel steel and δ3mm patterned steel plate to weld and make a mobile steel operating platform in the elevator shaft; the length and width of the mobile steel operating platform are 50mm smaller than the corresponding dimensions of the elevator shaft;
[0009] Step 2: Make the cage
[0010] The cage of the vertical transport device is welded with φ16mm steel bars and δ3 patterned steel plates, and the cage door is welded with φ16mm steel bars. The height and width of the cage door are 50mm smaller than the elevator shaft opening.
[0011] Step 3: Use a 100mm φ18mm steel pipe to weld to the φ16mm steel bar of the cage at the side door of the elevator shaft opening on the standard floor, and insert a 100mm φ16mm steel bar into the cage door as a hinge;
[0012] Step 4: Pre-embed 50mm×50mm steel plates on the shear walls of the elevator shafts on the first to third standard floors, weld the 50mm×50mm steel plates to the scaffolding steel pipe slide bars, and install the vertical transportation device when the structure is constructed to the third standard floor;
[0013] Step 5, first, install a mobile steel operating platform in the elevator shaft of the first standard floor, install an I-beam crossbeam on the top of the aluminum formwork of the shear wall of the elevator shaft of the fourth standard floor, and hang an electric hoist with a steel wire rope;
[0014] Step 6: The shear walls of the elevator shafts from the first to the third standard floors are welded and connected with scaffolding steel pipe slides, and the scaffolding steel pipe slides are installed at the 50mm×50mm steel plate position;
[0015] The electric hoist on the top of the cage includes a steel wire rope, the end of which is connected to the cage, and channel steel slides are welded on both sides of the cage and greased;
[0016] Step 7: The aluminum formwork support pole loading and unloading personnel on the first standard floor and the operators on the fourth and above standard floors control the lifting of the cage through the signal bell and the lifting and lowering buttons installed at the entrance of the elevator shaft of each standard floor;
[0017] During lifting, the channel steel slides on both sides of the cage slide along the scaffolding steel pipe slide bars connected to the shear wall of the elevator shaft;
[0018] Transport the aluminum formwork support poles to the fourth standard floor, open the cage door, and manually transport them to the floor slab at the elevator shaft entrance;
[0019] When descending, the aluminum mold support poles are removed, the cage door is closed, and the cage is controlled to descend through the signal bell and the lifting and lowering buttons installed at the entrance of the elevator shaft on each standard floor;
[0020] Step 8: When the structure is constructed to the elevator room, the electric hoist, wire rope and I-beam are removed, and the vertical transport device and the mobile steel operating platform are removed simultaneously;
[0021] Step 9: Test the operation and complete the installation.
[0022] In a further technical solution, each building is equipped with one to three sets of vertical transportation devices and mobile steel operating platforms to be used for control of each floor to ensure smooth control;
[0023] In step 9, the vertical transport device and the mobile steel operating platform are inspected, calibrated, and debugged before use. The lifting time of the vertical transport device of the aluminum formwork support poles is controlled to be no more than 1 hour. After confirming that it meets the quality and stability requirements, the aluminum formwork support poles are transported vertically until the construction of each layer of the cast-in-place structure is completed.
[0024] In a further technical solution, in step 9, the verticality error of the scaffolding steel pipe slide bar of the vertical transport device does not exceed the set 4mm, and the electric hoist, wire rope and scaffolding steel pipe slide bar are promptly maintained after the transportation is completed.
[0025] In a further technical solution, the 12# channel steel in the mobile steel operating platform is welded into two sets of triangular lateral frames, one side of which is parallel to the shear wall of the elevator shaft, and a δ3mm patterned steel plate is welded in the middle.
[0026] In a further technical solution, the steel pipe slide bars of the vertical transport device scaffolding are placed vertically, and multiple groups are transported for testing, with the number not less than 6 groups.
[0027] In a further technical solution, an aluminum formwork is set up on the floor slab of the elevator shaft opening, the bottom of the aluminum formwork is detachably connected to the elevator shaft opening, and the top is connected to the I-beam crossbeam.
[0028] Beneficial effects:
[0029] The vertical transportation method for high-rise assembled building construction using laminated reinforced thermal insulation composite panels proposed in the present invention is reliable to use. Because the loading and unloading personnel of the aluminum mold support poles on the first standard floor and the operators on the fourth and above standard floors control the lifting of the cage through the signal bell and the lifting and lowering buttons installed at the opening of the elevator shaft on each standard floor, the transportation time is shortened, and the technical problems of easy collision and falling of the material transfer hole and injuring people, safety hazards, high labor intensity, slow transportation, time-consuming and labor-intensive transportation, and high cost are solved. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0031] Figure 1 It is a schematic diagram of a vertical transportation method for high-rise assembled building construction using stacked reinforced thermal insulation composite panels proposed by the present invention.
[0032] Figure 2 It is a schematic diagram of the AA section of the present invention;
[0033] In the figure: 1. Scaffolding steel pipe slide; 2. Channel steel slide; 3. Cage; 4. 50mm×50mm steel plate; 5. Electric hoist; 6. I-beam steel beam; 7. Mobile steel operating platform; 8. Elevator shaft; 9. Elevator shaft shear wall; 10. Steel wire rope; 11. Aluminum mold support pole; 12. Elevator shaft opening floor; 13. Cage door; 14. 12# channel steel; 15. δ3mm patterned steel plate; 16. φ16mm steel bar; 17. 100mm length φ18mm steel pipe; 18. 100mm length φ16mm steel bar; 19. Signal bell; 20. Lift and lower buttons. DETAILED DESCRIPTION
[0034] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0035] The application principle of the present invention is further described below in conjunction with the accompanying drawings and specific embodiments.
[0036] Example 1
[0037] like Figure 1-2As shown, an embodiment of the present invention is a vertical transportation method for high-rise assembled building construction with laminated reinforced thermal insulation composite panels, step 1, making a mobile steel operating platform, measuring the length and width of the elevator shaft 8, using 12# channel steel 14 and δ3mm patterned steel plate 15 for welding to make the elevator shaft mobile steel operating platform 7, the length and width of the mobile steel operating platform 7 are 50mm smaller than the elevator shaft 8, using φ16mm steel bars 16 and δ3mm patterned steel plates 15 for welding to make the vertical transportation device cage 3, using φ16mm steel bars 16 for welding to make the cage door 13, The height and width are 50mm smaller than the elevator shaft 8 opening. The side door of the elevator shaft 8 opening on the standard floor adopts a 100mmφ18 steel pipe 17 welded on the cage 3 steel bar 16. The cage door 13 adopts a 100mmφ16mm steel bar 18 inserted as a hinge. The scaffolding steel pipe sliding rod 150mm×50mm steel plate 4 is embedded and welded in the shear wall 9 of the elevator shaft on the first to third standard floors. The vertical transportation device is installed when the structure is constructed to the third standard floor. First, the mobile steel operating platform 7 is installed in the elevator shaft 8 on the first standard floor, and the shear wall 9 on the elevator shaft on the fourth standard floor is installed. I-beam crossbeam 6 is installed on the top of aluminum formwork of force wall 9, an electric hoist 5 is hung with steel wire rope 10, scaffolding steel pipe slide bar 1 is installed on the shear wall 9 of the first to third standard floors of elevator shaft and welded scaffolding steel pipe slide bar 150mm×50mm steel plate 4, electric hoist 5 steel wire rope 10 is connected to the cage 3 on the top, channel steel slide 2 is welded on both sides of the cage 3, butter is applied, the first standard floor aluminum formwork support pole 11 loading and unloading personnel and the fourth and above standard floor operators control the hoist through the signal bell 19 and the lifting and lowering button 20 installed at the opening of the elevator shaft 8 of each standard floor The cage 3 is lifted. During the lifting, the steel channel chute 2 of the cage 3 slides along the scaffolding steel pipe slide rod 1 firmly connected to the shear wall 9 of the elevator shaft, and the aluminum mold support uprights 11 are transported to the fourth standard floor. The cage door 13 is opened and manually transported to the floor slab 12 of the elevator shaft opening. After the aluminum mold support uprights 11 are unloaded, the cage door 13 is closed, and the cage 3 is controlled to descend by the signal bell 19 and the lifting and lowering buttons 20 installed at the opening of the elevator shaft 8 on each standard floor. The electric hoist 5, wire rope 10 and I-beam crossbeam 6 are removed from the structural construction to the elevator machine room, and the vertical transportation device and the mobile steel operating platform 7 are removed simultaneously.
[0038] Each building can be equipped with one to three sets of vertical transportation devices and mobile steel operating platforms 7 for control of each floor. To ensure smooth control, the vertical transportation devices and mobile steel operating platforms 7 are tested, calibrated, and debugged before use. The lifting time of the vertical transportation device of the aluminum mold support pole 11 is controlled to be no more than 1 hour. After confirming that it meets the quality and stability requirements, the aluminum mold support pole 11 is vertically transported until the cast-in-place structure of each floor is completed. The vertical error of the scaffolding steel pipe slide bar 1 of the vertical transportation device does not exceed the set 4mm. After transportation, the electric hoist 5, wire rope 10, and scaffolding steel pipe slide bar 1 are maintained in time. The 12# channel steel 14 in the mobile steel operating platform 7 is welded into two sets of triangular lateral frames, and one side is parallel to the elevator shaft shear wall 9, and the δ3mm patterned steel plate 15 is welded in the middle. The scaffolding steel pipe slide bar 1 of the vertical transportation device is placed vertically, and multiple groups are transported for testing, and the number is not less than 6 groups. An aluminum formwork is set up on the elevator shaft opening floor 12, and the bottom of the aluminum formwork is detachably connected to the elevator shaft 8 opening, and the top is connected to the I-beam crossbeam 6.
[0039] The vertical transportation method for high-rise assembled building construction using laminated reinforced thermal insulation composite panels proposed in the present invention is reliable to use. Because the loading and unloading personnel of the aluminum mold support poles on the first standard floor and the operators on the fourth and above standard floors control the lifting of the cage through the signal bell and the lifting and lowering buttons installed at the opening of the elevator shaft on each standard floor, the transportation time is shortened, and the technical problems of easy collision and falling of the material transfer hole and injuring people, safety hazards, high labor intensity, slow transportation, time-consuming and labor-intensive transportation, and high cost are solved.
[0040] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be considered exemplary and non-restrictive in all respects, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention.
[0041] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A vertical transportation method for high-rise assembled building construction, It is characterized in that The following steps are involved: Step 1: Make a mobile steel operating platform The length and width of the elevator shaft (8) are measured, and a movable steel operating platform (7) in the elevator shaft is manufactured by welding 12# channel steel (14) and δ3mm patterned steel plate (15); and the length and width of the movable steel operating platform (7) are 50mm smaller than the corresponding dimensions of the elevator shaft (8); Step 2: Make the cage A cage (3) of a vertical transport device is made by welding φ16 mm steel bars (16) and δ3 patterned steel plates (15), and a cage door (13) is made by welding φ16 mm steel bars (16), and the height and width of the cage door are 50 mm smaller than the opening of the elevator shaft (8); Step 3, a 100mm φ18mm steel pipe (17) is welded to the φ16mm steel bar (16) of the cage (3) at the side door of the opening of the standard floor elevator shaft (8), and a 100mm φ16mm steel bar (18) is inserted into the cage door (13) as a hinge; Step 4, pre-embed 50mm×50mm steel plates (4) on the elevator shaft shear walls (9) of the first to third standard floors, weld the 50mm×50mm steel plates (4) to the scaffolding steel pipe slide bars (1), and start installing the vertical transportation device when the structure is constructed to the third standard floor; Step 5, first, install a movable steel operating platform (7) in the elevator shaft (8) of the first standard floor, install an I-beam crossbeam (6) on the top of the aluminum mold of the shear wall (9) of the elevator shaft of the fourth standard floor, and hang an electric hoist (5) with a steel wire rope (10); Step 6, the first to third standard floors of the elevator shaft shear wall (9) are welded and connected with the scaffolding steel pipe slide rod (1), and the scaffolding steel pipe slide rod (1) is installed at the position of the 50mm×50mm steel plate (4); The electric hoist (5) on the top of the cage (3) includes a steel wire rope (10), the end of which is connected to the cage (3), and channel steel slide grooves (2) are welded on both sides of the cage (3) and greased; Step 7, the loading and unloading personnel of the aluminum mold support pole (11) of the first standard floor and the operating personnel of the fourth standard floor and above control the lifting of the cage (3) through the signal bell (19) and the lifting and lowering buttons (20) installed at the opening of the elevator shaft (8) of each standard floor; During lifting, the channel steel slideways (2) on both sides of the cage (3) slide along the scaffolding steel pipe slide bars (1) connected to the elevator shaft shear wall (9); The aluminum mold support pole (11) is transported to the fourth standard floor, the cage door (13) is opened, and the aluminum mold support pole (11) is manually transported to the elevator shaft opening floor (12); When descending, the aluminum mold support pole (11) is removed, the cage door (13) is closed, and the cage (3) is controlled to descend through the signal bell (19) and the lifting and lowering buttons (20) installed at the opening of the elevator shaft (8) on each standard floor; Step 8, when the structure is constructed to the elevator room, the electric hoist (5), the steel wire rope (10) and the I-beam crossbeam (6) are removed, and the vertical transport device and the mobile steel operating platform (7) are removed simultaneously; Step 9: Test the operation and complete the installation.
2. A vertical transportation method for high-rise assembled building construction according to claim 1, It is characterized in that Each building is equipped with one to three sets of vertical transportation devices and mobile steel operating platforms (7) for control of each floor to ensure smooth control; In step 9, the vertical transport device and the mobile steel operating platform (7) are inspected, calibrated, and debugged before use, and the lifting time of the vertical transport device of the aluminum formwork support pole (11) is controlled to be no more than 1 hour. After confirming that it meets the quality and stability requirements, the aluminum formwork support pole (11) is vertically transported until the construction of each layer of the cast-in-place structure is completed.
3. A vertical transportation method for high-rise assembled building construction according to claim 2, It is characterized in that In step 9, the vertical error of the scaffolding steel pipe slide bar (1) of the vertical transport device does not exceed the set 4mm, and the electric hoist (5), the wire rope (10) and the scaffolding steel pipe slide bar (1) are promptly maintained after the transport is completed.
4. A vertical transportation method for high-rise assembled building construction according to claim 2, It is characterized in that The 12# channel steel (14) in the mobile steel operating platform (7) is welded into two sets of triangular lateral frames, one side of which is parallel to the elevator shaft shear wall (9), and a δ3mm patterned steel plate (15) is welded in the middle.
5. A vertical transportation method for high-rise assembled building construction according to claim 2, It is characterized in that The vertical transport device scaffolding steel pipe slide bars (1) are placed vertically, and multiple groups are transported for testing, with the number not less than 6 groups. According to the vertical transportation method for high-rise assembled building construction described in claim 2, It is characterized in that An aluminum formwork is set on the elevator shaft opening floor (12), the bottom of the aluminum formwork is detachably connected to the elevator shaft (8) opening, and the top is connected to the I-beam crossbeam (6).
Citation Information
Patent Citations
Two-to-one suspension ratio construction hoist arranged on elevator shaft traction machine and operation method thereof
CN110228743A
Lifting equipment using steel structure elevator shaft as vertical transportation channel
CN210480526U
Safety protection system for vertical transportation cage in hoistway
CN220664609U
Built-in type material lift
CN2635636Y
Lift device for transfering cold forming product
KR1020180024276A