Full-length steel cavity prefabricated supporting assembly, cavity supporting structure with full-length steel cavity prefabricated supporting assembly and manufacturing method of full-length steel cavity prefabricated supporting assembly

By using prefabricated support components of long steel cavity in tunnel construction and using a combined structure of arc-shaped steel pipes and composite winding pipes, the problem of insufficient construction complexity and durability in traditional tunnel construction is solved, and high efficiency and low Cost tunnel support effect.

CN118959039APending Publication Date: 2024-11-15NANJING TECH UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410693637.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-05-31
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

In traditional tunnel construction, steel belts are complex in construction, long construction period, high material cost, limited durability, and difficult to adapt to the needs of deep buried working conditions.

Method used

The prefabricated support assembly of the through-length steel cavity is adopted to form the cavity by welding multiple arc steel tubes in parallel, and a arc-shaped composite winding tube and chemical anchor bolt are provided therein. The composite winding tube is fixed with concrete filling and positioning parts. Form a high-strength cavity structure, simplify the processing process and improve the docking strength of the components.

Benefits of technology

It improves the tunnel bearing capacity and durability, reduces material usage and production costs, simplifies the processing process, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118959039A_ABST
    Figure CN118959039A_ABST
Patent Text Reader

Abstract

The invention discloses a full-length steel cavity prefabricated supporting assembly for tunnel reinforcement, a cavity supporting structure with the full-length steel cavity prefabricated supporting assembly and a manufacturing method of the full-length steel cavity prefabricated supporting assembly and relates to the technical field of tunnels, and the full-length steel cavity prefabricated supporting assembly comprises a steel pipe cavity, a plurality of composite winding pipes and a plurality of chemical anchor bolts. Wherein the steel pipe cavity is formed by welding a plurality of arc-shaped steel cavities in parallel; according to the cavity supporting structure, core concrete is filled in a composite winding pipe after a full-length steel cavity prefabricated supporting assembly is assembled in a tunnel, and interlayer concrete is filled between a steel pipe cavity and the composite winding pipe. The composite material pipe is embedded in the interlayer concrete, the composite material pipe restrains the core concrete filled in the composite material pipe, so that the internal strength of the pipe piece is improved in multiple directions, the bearing capacity of the pipe piece prefabricated assembly is improved, and when the pipe piece prefabricated assembly is designed, on the premise that the mechanical property requirements such as the bearing capacity are met, the pipe piece prefabricated assembly can be manufactured more stably. The thickness of the duct piece can be correspondingly reduced, the material consumption is reduced, the material utilization rate is improved, and the weight and production cost of the prefabricated assembly are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] The present invention relates to the technical field of tunnel engineering, and in particular to a through-length steel cavity prefabricated support assembly, a cavity support structure thereof and a manufacturing method thereof. Background Art

[0002] The cavity support structure is composed of prefabricated components of square steel pipes and composite material winding pipes. It is the main assembly component of tunnel construction and is responsible for resisting the pressure of the surrounding soil layer, groundwater pressure and some special loads. As the main support structure in tunnel construction, the quality of the segment support structure is directly related to the overall quality and safety of the tunnel, and affects the bearing capacity, waterproof performance and durability of the tunnel.

[0003] With the continuous development of society, tunnels have developed from shallow buried conditions to deep buried conditions. Traditional steel belt construction is complex, has a long construction period, high material cost, limited durability, heavy weight and poor adaptability. Summary of the invention

[0004] The present invention aims to solve one of the technical problems in the related art to at least a certain extent. To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a through-length steel cavity prefabricated support assembly, a cavity support structure thereof and a manufacturing method thereof, comprising: The through-length steel tube cavity is formed by welding a plurality of identical arc-shaped steel tubes in parallel, wherein a hole is reserved at the three-point point of the middle square steel tube, and the square steel tube at one end of the through-length steel tube cavity is smaller than the square steel tube at the other end along the circumferential direction, but the thickness thereof shall be kept consistent to ensure the strength of the joint and facilitate the jointing between the steel tube cavities in advance.

[0005] Multiple arc-shaped composite wrapped tubes, the arc-shaped composite wrapped tubes should be consistent with the arc length of the steel tube cavity, and like the steel tube cavity, the composite wrapped tube size at one end along the circumferential direction is smaller than the composite wrapped tube size at the other end, but the thickness should be consistent to ensure the strength of the joint and the joint between the composite wrapped tubes in advance. The composite tube should be set in other square steel tubes except for the holes that need to be reserved.

[0006] Concrete, the concrete includes core concrete and sandwich concrete, the core concrete is filled in the internal space of the composite tube, and the sandwich concrete is filled in the space formed by the inside of the non-closed chamber and the outside of the composite tube.

[0007] A plurality of chemical anchor bolts are arranged on the reserved holes of the steel pipe cavity.

[0008] In some embodiments, the composite winding tube is fixed in the cavity of the full-length steel tube by a positioning piece.

[0009] In some embodiments, the positioning member is made of steel.

[0010] In some embodiments, the composite winding tube is fixedly disposed at the center of the through-length steel tube chamber.

[0011] In some embodiments, the cross-section of the composite wound tube is circular.

[0012] In some embodiments, two ends of the composite winding tube are flush with two ends of the full-length steel tube cavity in the circumferential direction.

[0013] In some embodiments, the reserved hole is reserved on the square steel tube in the middle of the steel tube cavity and is located at the three-point point of a section of the arc-shaped square steel tube.

[0014] In some embodiments, the prefabricated segment support structure is formed by assembling a plurality of prefabricated segment support components through the seams.

[0015] On the other hand, the present invention provides a segment support structure, which is assembled by a plurality of the segment prefabricated components through seams or staggered seams.

[0016] (1) Prefabricated curved square steel pipes and curved composite winding pipes; (2) welding the arc-shaped square steel tubes in parallel to form a steel tube cavity, (3) Fixing the composite winding tube at the center position of each square steel tube in the steel tube cavity through a positioning piece.

[0017] Compared with the prior art, the present invention has the following beneficial effects: The present invention buries the composite wrapped pipe in the sandwich concrete. The composite wrapped pipe constrains the core concrete filled inside, so that the internal strength of the pipe segment is improved in multiple directions, thereby improving the bearing capacity of the pipe segment prefabricated assembly. When designing the pipe segment prefabricated assembly, the thickness of the pipe segment can be reduced accordingly while meeting the requirements of mechanical properties such as bearing capacity, thereby achieving the effect of reducing material consumption, improving material utilization, and reducing production costs.

[0018] The cavity of the through-length steel cavity assembly of the present invention is formed by welding several arc-shaped square steel pipes, which reduces The difficulty in the processing of the full-length steel cavity assembly has improved the efficiency of processing and manufacturing. When reserving holes, only the square steel tube in the middle of the full-length steel tube cavity is opened, and the composite winding tube is not set on the square steel tube with the hole. This can ensure that the strength of the composite winding tube is not destroyed.

[0019] The present invention prefabricates the full-length steel pipe cavity assembly in a factory, transports it to the site for installation, and finally injects concrete, which can greatly improve efficiency.

[0020] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention and implement it according to the contents of the specification, the following is a detailed description of the preferred embodiments of the present invention in conjunction with the accompanying drawings. The specific implementation of the present invention is given in detail by the following embodiments and their accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings: Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present invention; Figure 2 This is a schematic diagram of a prefabricated assembly of a through-length steel tube cavity according to an embodiment of the present invention; Figure 3 This is a schematic diagram of a joint of a prefabricated assembly of a through-length steel tube cavity in an embodiment of the present invention; Figure 4 Schematic diagram of a composite material winding tube in an embodiment of the present invention; Figure 5 Schematic diagram of a composite wound pipe joint in an embodiment of the present invention; DETAILED DESCRIPTION

[0022] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0023] In the description of the embodiments of the present invention, it should be noted that if the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. appear, the directions or positional relationships indicated are based on the directions or positional relationships shown in the drawings, or are the directions or positional relationships in which the invented product is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0024] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be connected, detachably connected, or integrated; it can be mechanically connected or electrically connected; it can be directly connected or indirectly connected through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0025] The following describes a through-length steel cavity prefabricated support assembly, a cavity support structure thereof, and a manufacturing method thereof according to an embodiment of the present invention with reference to the accompanying drawings.

[0026] As shown in the figure, the prefabricated support assembly of the through-length steel pipe cavity of the present invention includes a steel cavity composed of a plurality of square steel pipes, a plurality of composite winding pipes, and chemical anchor bolts.

[0027] The steel tube cavity is formed by welding a plurality of identical arc-shaped square steel tubes in parallel. When manufacturing the square steel tube, one end of the square steel tube is smaller than the other end along the circumferential direction, but the thickness must be kept consistent to ensure the strength of the butt joint and facilitate the butt joint between the steel tube cavities in advance. The number of square steel tubes in the full-length steel tube cavity is determined according to the specific design. The square steel tubes with reserved holes are not provided with composite material winding tubes, and the square steel tubes with reserved holes need to be symmetrically distributed to ensure uniform force.

[0028] The composite winding tube is fixed in the closed chamber by a positioning piece, the positioning piece is made of steel, the cross section of the composite winding tube is circular, and the two ends of the composite winding tube are flush with the circumference of the through-length steel tube cavity.

[0029] The chemical anchor bolts fix the through-length steel tube cavity prefabricated component on the tunnel wall so that the through-length steel tube cavity prefabricated component and the tunnel wall are tightly fitted.

[0030] After the installation of three sections of multiple full-length steel pipe cavity prefabricated components, grouting is started at the grouting port with a high-pressure pump truck. After the high-performance mortar flows out from the outlet for a few minutes, the outlet is sealed. After the interlayer concrete and core concrete are poured, the roadbed is refilled to seal the grouting port and the outlet.

[0031] A ring of shield segments is assembled from three standard 90° full-length steel pipe cavity prefabricated components.

[0032] The method for manufacturing a through-length steel tube cavity prefabricated component is used to manufacture the through-length steel tube cavity prefabricated component of the present invention, comprising the following steps: (1) Prefabricate the same curved square steel tube and composite winding tube; (2) Weld the same arc-shaped square steel pipe into a full-length steel pipe cavity. Note that it should be welded through rather than spot welded. After welding, make a hole in the square steel pipe; (3) The composite winding tube is fixedly arranged at the center position in the cavity of the full-length steel tube segment by means of a positioning piece; In step (1), the square steel tube size at one end of the through-length steel tube cavity is smaller than that at the other end along the circumferential direction, but the thickness thereof shall be kept consistent to ensure the strength of the butt joint and facilitate the butt joint between the steel tube cavities in advance. The number of square steel tubes in the through-length steel tube cavity is determined according to the specific design. The square steel tube with reserved holes is not provided with a composite material winding tube, and the square steel tube with reserved holes shall be symmetrically distributed to ensure uniform force. The composite tube may be an FRP tube, which is a fiber-reinforced composite material having the characteristics of high circumferential tensile strength, large circumferential tensile modulus, good corrosion resistance and durability.

[0033] In step (2), the composite tube is fixed at the center of the closed chamber by a positioning member, wherein the positioning member can be made of steel. The composite tube is placed at the center of the closed chamber to avoid abnormal damage to the specimen during the stress process due to improper arrangement of the composite tube.

[0034] After the prefabricated pipe segment components are manufactured, they are transported to the construction site, fixed and assembled by bolts, and after installation, concrete can be poured inside the cavity interlayer and the composite winding pipe.

[0035] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.

[0036] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A full-length steel cavity prefabricated support assembly, characterized in that: include: The steel tube cavity is formed by welding a plurality of identical arc-shaped square steel tubes in parallel. A hole needs to be reserved in the middle square steel tube of the steel tube cavity to facilitate fixation in the tunnel. The square steel tube at one end of the steel tube cavity is smaller than the square steel tube at the other end along the circumferential direction, but the thickness thereof should be kept consistent to ensure the strength of the joint and facilitate the jointing between the steel tube cavities in advance. Multiple arc-shaped composite wrapped tubes, the arc-shaped composite wrapped tubes should be consistent with the arc length of the steel tube cavity, and like the steel tube cavity, the composite wrapped tube size at one end along the circumferential direction is smaller than the composite wrapped tube size at the other end, but the thickness should be consistent to ensure the strength of the joint and the joint between the composite wrapped tubes in advance. The composite tube should be set in other square steel tubes except for the holes that need to be reserved. Concrete, the concrete includes core concrete and sandwich concrete, the core concrete is filled in the internal space of the composite tube, and the sandwich concrete is filled in the space formed by the inside of the non-closed chamber and the outside of the composite tube. A plurality of chemical anchor bolts are arranged on the reserved holes of the steel pipe cavity.

2. A through-length steel cavity prefabricated support assembly according to claim 1, characterized in that: The composite winding tube is fixed in the steel tube chamber by a positioning piece.

3. A through-length steel cavity prefabricated support assembly according to claim 2, characterized in that: The positioning piece is made of steel.

4. The prefabricated support assembly for a through-length steel cavity according to claim 2 is characterized in that: The composite winding tube is fixedly arranged at the center of the steel tube chamber.

5. The prefabricated support assembly for a through-length steel cavity according to claim 4 is characterized in that: The cross section of the composite tube is circular.

6. The full-length steel cavity prefabricated support assembly according to claim 1, characterized in that: The two ends of the composite winding tube are flush with the two ends of the steel tube cavity in the circumferential direction.

7. The full-length steel cavity prefabricated support assembly according to claim 1, characterized in that: The reserved holes should be reserved on the steel pipe cavity and the square steel pipe with the reserved holes should be symmetrical along the length direction of the steel pipe, and the position should be located at the three-point point of a section of arc-shaped square steel pipe.

8. The full-length steel cavity prefabricated support assembly according to claim 1, characterized in that: The chemical anchor bolts must be strong enough to fix the steel pipe cavity on the tunnel and fit perfectly in the tunnel.

9. A cavity support structure, characterized in that: The cavity support structure comprises a plurality of the through-length steel cavity prefabricated support assemblies as described in any one of claims 1 to 8. The cavity support structure is formed by assembling the plurality of the through-length steel cavity prefabricated support assemblies through seams in a tunnel and then pouring core concrete and interlayer concrete.

10. A method for manufacturing a prefabricated support assembly of a through-length steel cavity, characterized in that: The method is applicable to the prefabricated support assembly of a through-length steel cavity as described in any one of claims 1 to 8, comprising the following steps: (1) Prefabricated curved square steel pipes and curved composite winding pipes; (2) welding the arc-shaped square steel tubes in parallel to form a steel tube cavity, (3) Fixing the composite winding tube at the center position of each square steel tube in the steel tube cavity through a positioning piece.