220kV transformer substation GIS test equipment and test process

Through the integrated and automated GIS test equipment of 220kV substation, the problems of complexity, low efficiency and poor safety of traditional testing methods are solved, and a more efficient and safer testing process is achieved, ensuring the reliability of test results and the safety of equipment.

CN118962305APending Publication Date: 2024-11-15WUHAN HANYUAN JIJI ELECTRIC POWER EQUIP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411199291.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

Traditional GIS testing methods have problems such as complex operation, low efficiency, insufficient accuracy and poor safety, which leads to unreliable test results and may cause equipment damage.

Method used

An integrated and automated 220kV substation GIS testing equipment was designed, including central control components, analysis components, high-voltage components, monitoring components and power supply components. Through automated control and real-time monitoring, comprehensive testing and protection of GIS equipment is achieved.

Benefits of technology

It improves the safety, accuracy and efficiency of the test, ensures the stability and reliability of the test process, reduces human errors, prevents equipment damage, and ensures the safety of personnel and equipment through automatic protection measures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118962305A_ABST
    Figure CN118962305A_ABST
Patent Text Reader

Abstract

The invention provides 220kV transformer substation GIS test equipment and a test process, and relates to the technical field of transformer substation maintenance, and the equipment comprises a central control assembly which is used for controlling the on-off of the whole device; the signal receiving and transmitting end of the analysis assembly is connected with the signal receiving and transmitting end of the central control assembly, and the analysis assembly is used for sampling and monitoring the insulating gas of the GIS equipment of the transformer substation. According to the equipment and the process, automatic control can be realized through the central control assembly, the sensing module acquires key data of GIS equipment in real time, the test accuracy and safety are improved, the analysis assembly accurately monitors the purity of insulating gas, it is ensured that the gas meets requirements, resource waste is reduced, the high-voltage assembly provides adjustable voltage and simulates operation conditions, and the test efficiency is improved. And the equipment is quickly powered off and protected through the high-voltage switch when the high-voltage switch is abnormal, the monitoring assembly monitors the voltage, current and temperature in real time, protection measures are automatically taken, the overall test process covers comprehensive test and optimization, the result is ensured to be reliable, and operation faults are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of transformer substation maintenance, in particular to 220kV transformer substation GIS testing equipment and a testing process. Background Art

[0002] In the power system, 220kV substation GIS (gas insulated switchgear) is an indispensable and important equipment in the power grid. Its performance and safety are directly related to the stable operation of the power system. Since the internal insulating medium of GIS equipment is usually SF6 gas, its reliability under high-voltage operating environment is particularly important. Therefore, it is very necessary to conduct comprehensive and rigorous tests before the GIS equipment is put into use. These tests not only evaluate the insulation performance of GIS equipment under rated voltage and overvoltage conditions, but also ensure the purity of the gas inside the equipment and the electrical performance under high voltage.

[0003] Traditional GIS testing methods mostly rely on manual operation and independent testing equipment, which have problems such as complex operation, low efficiency, and insufficient testing accuracy. In addition, manual operation is prone to human errors, resulting in unreliable test results and even equipment damage. In order to overcome these challenges, this technical solution proposes an integrated and automated 220kV substation GIS testing equipment and its testing process to improve the safety, accuracy and efficiency of the test. Summary of the invention

[0004] The present invention aims to solve the shortcomings existing in the background technology, provide 220kV substation GIS test equipment and test process, and improve the defects of traditional detection schemes that are not reliable and have poor overall accuracy and safety.

[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a 220kV substation GIS test equipment, comprising: a central control component, used to control the opening and closing of the entire device; an analysis component, wherein a signal transceiver end of the analysis component is connected to a signal transceiver end of the central control component, and is used to sample and monitor the insulating gas of the substation GIS equipment; a high-voltage component, wherein the high-voltage component is provided with a high-voltage output end connected to the GIS equipment, and is used to generate high-intensity high-voltage electricity to test the load of the substation; a plurality of monitoring components, wherein the plurality of monitoring components are respectively arranged at the analysis component and the high-voltage component, and are used to monitor the internal operation of the equipment during the inspection process and to provide protection; a power supply component, wherein one side of the power supply component is provided with an external input power line for power input, and the other side of the power supply component is provided with an external output power line, and is used to provide a power supply path for each component.

[0006] Furthermore, the central control component includes: a console, which is used for human-computer interaction and can display data to assist staff control; a sensor module, which is provided with multiple groups, and the multiple groups of sensor modules are respectively arranged in various places in the GIS equipment, for monitoring the status of the GIS equipment during the inspection process, and the sensor module contains a data collector, a voltage sensor, a temperature sensor, a pressure sensor and a humidity sensor, and the signal output ends of the voltage sensor, temperature sensor, pressure sensor and humidity sensor are connected to the signal receiving end of the data collector, and the data collector is signal-connected to the console.

[0007] Furthermore, the analysis component includes: a sampling module, which is composed of a sampling head and a sample delivery tube, and a regulating valve is provided in the middle of the sample delivery tube; a pretreatment system, which contains a filter, a dryer and a pressure reducer, and the top of the filter is connected to the sample delivery tube, and the filter, dryer and pressure reducer are internally conductive; an analysis module, which is composed of a spectrometer and a mass spectrometer, and the sample gas is monitored by the spectrometer and the mass spectrometer in turn; a recovery module, which is a return pipe used to connect the analysis module and guide the detected sample gas to flow back into the GIS equipment.

[0008] Furthermore, the high-voltage component includes: a high-voltage transformer, a rectifier circuit, a high-voltage capacitor and a high-voltage switch, wherein the high-voltage switch is connected in series with the high-voltage transformer, the rectifier circuit and the high-voltage capacitor, wherein the high-voltage transformer also includes: a shell made of an insulating ceramic material as a whole, a magnetic flux ring is arranged inside the shell, a connecting plate is installed on the top of the shell by bolts, and the connecting plate and the magnetic flux ring form a ring loop; a detachable primary coil is provided on one side of the shell, and the primary coil is sleeved on the magnetic flux ring, and a detachable pressurization coil is provided on the other side of the shell, and the pressurization coil is sleeved on the other end of the magnetic flux ring.

[0009] Furthermore, the monitoring component includes: an overvoltage protection module, which is composed of multiple groups of voltage sensors, relays and discharge gaps, and the multiple groups of voltage sensors of the overvoltage protection module are arranged at various locations in the equipment to monitor the internal voltage of the equipment; an overcurrent protection module, which is composed of multiple groups of current sensors, circuit breakers and adjustment resistors, and the multiple groups of current sensors are arranged at various locations of the outer casing of the test equipment to monitor whether the outer casing of the equipment is leaking; a temperature protection module, which is composed of a temperature sensor and an active radiator, and the temperature sensor is arranged inside the equipment to monitor the operating temperature of the equipment.

[0010] Furthermore, the power supply component includes: a power supply module, the power supply module includes a power supply and a power-on wire, power-on wires are provided on both sides of the power supply, and the two power-on wires are respectively connected to two power lines of an external input and an external output; an emergency power-off module, the emergency power-off module is connected to the power supply module signal, and is used to control the emergency shutdown of the power supply module, wherein the emergency power-off module includes a control cavity, a control block is slidably connected inside the control cavity, a power-on block is provided inside the control block, and when the control block is located in the middle of the control cavity, the power-on block and the power-on wire are conductive, a spring is provided between the inner wall of the top of the control cavity and the control block, an electromagnet that repels the control block is provided at the bottom of the control cavity, and the control block is maintained in the middle of the control cavity under the repulsive force of the spring and the electromagnet; a photoelectric monitoring module, the photoelectric monitoring module is used to monitor whether there is anyone entering the internal space, the photoelectric monitoring module includes a circuit board and a plurality of light sensors connected to the port of the circuit board, the circuit board is electrically connected to the electromagnet, and is used to control the start and stop of the electromagnet.

[0011] A 220kV substation GIS test process, the process comprising:

[0012] Step S1: Visually inspect the GIS equipment to be inspected, and conduct a comprehensive inspection of the GIS and test equipment to ensure that the equipment is in normal condition without damage or abnormality;

[0013] Step S2: Perform a withstand voltage test on the GIS through high-voltage components to detect whether it can withstand the rated voltage and overvoltage. Under high voltage, use a partial discharge test system to detect whether there is a discharge phenomenon inside the GIS, and analyze its location and intensity.

[0014] Step S3: Analyze the purity of the insulating gas in the GIS component to ensure that it meets the insulation requirements;

[0015] Step S4: During the inspection process, the voltage, current, partial discharge signal and other data during the test are monitored in real time through the central control component, and the collected data are analyzed to generate a test report to evaluate the insulation performance and reliability of the GIS;

[0016] Step S5: During the inspection process, the voltage, current and temperature in the equipment are monitored in real time through the monitoring component, and the inspection area is monitored through the power supply component. If an abnormality is found, the power supply can be automatically cut off to protect the safety of personnel and equipment;

[0017] Step S6: After monitoring is completed, the problems existing in the GIS are corrected according to the test results, such as replacing the insulating gas, performing internal cleaning, etc., and the corrected GIS is tested again in steps S2 to S5 to ensure that all parameters meet the requirements.

[0018] Furthermore, the step S2 also includes:

[0019] Step S21: activating the high-voltage component through the central control component, the high-voltage transformer starts working, raising the input voltage to the required test voltage level, the rectifier circuit converts the AC power into DC power, and stores the electric energy through the high-voltage capacitor;

[0020] Step S22: Under the control of the control console, the high-voltage component gradually increases the voltage to the set withstand voltage value to simulate the high-voltage condition of the GIS equipment in operation. The voltage sensor monitors the applied voltage value in real time to ensure the accuracy of the test voltage;

[0021] Step S23: Maintain the set withstand voltage value for a certain period of time, and monitor the voltage stability and the response of the equipment through the sensor module. If an abnormality occurs during this process, such as voltage fluctuation or equipment discharge, the central control component will automatically record and issue an alarm through the monitoring component, and the high-voltage switch will quickly cut off the power supply of the high-voltage component to prevent damage.

[0022] Furthermore, the step S3 also includes:

[0023] Step S31: The sampling module is started through the central control component, and the sampling head extracts gas samples from the GIS equipment. The gas enters the pretreatment system through the sample delivery tube, and the flow rate of the sampled gas is controlled by the regulating valve to ensure that the gas sample entering the pretreatment system is stable;

[0024] Step S32: The gas sample first passes through a filter to remove impurities, and then passes through a dryer to remove moisture to ensure that the gas sample is pure and free of interference. At the same time, the gas passes through a pressure reducer to adjust the sample gas pressure to the working range of the spectrum analyzer and the mass spectrometer;

[0025] Step S33: The pre-treated gas sample enters the spectrum analyzer, and the gas composition is analyzed by infrared light or laser to detect the purity of SF6 gas. Then the gas sample enters the mass spectrometer to further analyze the gas composition and identify trace impurities. The data obtained by the analysis is then processed by the central processing unit to obtain a gas purity and composition report, and the results are displayed in real time on the console;

[0026] Step S34: After the detection is completed, the sample gas flows back to the GIS equipment through the return pipe to ensure environmental protection and cost-effectiveness.

[0027] Furthermore, the step S5 further includes:

[0028] Step S51: During the test, the monitoring component continuously monitors the voltage, current and temperature in the equipment. The voltage sensor and the current sensor monitor the voltage and current of the high-voltage component and the GIS equipment respectively. The temperature sensor monitors the operating temperature inside the equipment.

[0029] Step S52: The data from all sensors are transmitted to the data collector through the sensor module and transmitted to the central control unit in real time for analysis. If abnormal data is detected, the system will immediately trigger the corresponding protection device;

[0030] Step S53: When an overvoltage or overcurrent condition is detected, the overvoltage protection module and the overcurrent protection module will quickly cut off the high voltage power supply or reduce the current by adjusting the resistance to prevent damage to the device;

[0031] Step S54: When the temperature protection module detects that the temperature inside the device is abnormally high, it will immediately start the active radiator to cool it down and suspend the test if necessary;

[0032] Step S55: If a serious abnormal situation is detected, the monitoring component will notify the operator through the console and automatically interrupt the test. If the situation is critical, such as leakage in the equipment casing or someone mistakenly enters the test area, the photoelectric monitoring module will trigger the emergency power-off module to quickly cut off the power supply to ensure on-site safety.

[0033] The present invention provides a 220kV substation GIS test equipment and test process, which has the following beneficial effects:

[0034] The advantages of the present invention are that, firstly, the present technical solution realizes the automatic control of the whole test process through the central control component, the console provides a human-computer interaction interface, the operator can conveniently start and stop the test, and monitor and adjust the test process in real time, and multiple groups of sensor modules are distributed in various key positions of the GIS equipment, which can collect and transmit the operation data of the equipment in real time, which not only reduces the workload of the operator, but also improves the accuracy of the test, ensuring that the test process is safer and more stable;

[0035] Secondly, through the analysis component, this technical solution can accurately monitor the purity of the insulating gas inside the GIS equipment. After sampling, pretreatment and analysis, the gas sample is ensured to meet the insulation requirements. This process can not only timely detect and eliminate gas impurities that may affect the insulation performance, but also effectively reduce the gas loss during the test process through the recovery module, reduce environmental pollution, and achieve efficient use of resources;

[0036] Third, the high-voltage components provide an adjustable high-voltage power supply, which can simulate the high-voltage conditions that GIS equipment may encounter in actual operation. Through the high-voltage transformer and rectifier circuit, the high-voltage components can accurately control and maintain the voltage level required for the test. When an abnormal situation occurs during the test, the high-voltage switch can quickly cut off the power supply to prevent equipment damage and ensure the safety of the test process.

[0037] Fourthly, by monitoring the overvoltage protection module, overcurrent protection module and temperature protection module in the components, it provides a full range of equipment protection functions, monitors the voltage, current and temperature of the equipment in real time, and once an abnormality is detected, the system can automatically take corresponding protection measures, such as cutting off the power supply or reducing the current, to prevent the equipment from overloading, overheating or other dangerous situations. In addition, the power supply component provides a stable power supply and has an emergency power-off function, which can protect the safety of equipment and operators in an emergency.

[0038] Fifth, the test process proposed in this technical solution covers the complete process from equipment inspection, pressure resistance test, gas monitoring to problem correction. Through steps S2-S6, the equipment is continuously optimized in multiple tests and adjustments to ultimately ensure that all parameters meet the requirements. Such process design effectively improves the reliability and authority of the test results and reduces the possibility of failure after the equipment is put into operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 It is a schematic diagram of the overall structure of the present invention.

[0040] Figure 2 It is a working schematic diagram of the central control component of the present invention.

[0041] Figure 3 It is a working schematic diagram of the power supply component of the present invention.

[0042] Figure 4 It is a schematic diagram of the monitoring component structure of the present invention.

[0043] Figure 5 It is a schematic diagram of the structure of the analysis component of the present invention.

[0044] Figure 6 It is a schematic diagram of the high-voltage transformer structure of the present invention.

[0045] Figure 7 It is a schematic diagram of the structure of the power supply component of the present invention.

[0046] Figure 1-7In: 1- central control component; 110- control console; 120- sensor module; 2- analysis component; 210- sampling module; 211- sampling head; 212- sample delivery tube; 213- regulating valve; 220- pretreatment system; 221- filter; 222- dryer; 223- pressure reducer; 230- analysis module; 231- spectrum analyzer; 232- mass spectrometer; 240- recovery module; 241- return pipe; 3- high voltage component; 310- high voltage transformer; 311- primary coil; 312- pressurized coil; 313- magnetic conduction ring ;314-connecting board;320-rectifier circuit;330-high-voltage capacitor;340-high-voltage switch;4-monitoring component;410-overvoltage protection module;420-overcurrent protection module;430-temperature protection module;5-power supply component;510-power supply module;511-power supply;512-power line;520-emergency power-off module;521-control chamber;522-control block;523-power-on block;524-spring;525-electromagnet;530-photoelectric monitoring module;531-circuit board;532-light sensor. DETAILED DESCRIPTION

[0047] The technical solutions in the embodiments of the present application will be described clearly and completely below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present application.

[0048] The disclosure below provides many different embodiments or examples to realize the different structures of the present application. In order to simplify the disclosure of the present application, the parts and settings of specific examples are described below. Of course, they are only examples, and the purpose is not to limit the present application. In addition, the present application can repeat reference numbers and / or reference letters in different examples, and this repetition is for the purpose of simplification and clarity, which itself does not indicate the relationship between the various embodiments and / or settings discussed. In addition, the various specific processes and material examples provided by the present application, but those of ordinary skill in the art can appreciate the application of other processes and / or the use of other materials.

[0049] The embodiment of the present application provides a 220kV substation GIS test equipment and test process. The 220kV substation GIS test equipment and test process can realize automatic control through the central control component. The sensor module collects key data of the GIS equipment in real time to improve the accuracy and safety of the test. The analysis component accurately monitors the purity of the insulating gas to ensure that the gas meets the requirements and reduce resource waste. The high-voltage component provides an adjustable voltage, simulates the operating conditions, and quickly cuts off the power to protect the equipment in abnormal situations through the high-voltage switch. The monitoring component monitors the voltage, current and temperature in real time and automatically takes protective measures. The overall test process covers comprehensive testing and optimization to ensure reliable results and reduce operational failures. The 220kV substation GIS test equipment and test process are described in detail below. It should be noted that the description order of the following embodiments is not intended to limit the preferred order of the embodiments.

[0050] The present application is described in detail below in conjunction with the accompanying drawings and specific implementation methods. Figure 1-7 In this embodiment, a 220kV substation GIS test equipment is provided, including: a central control component 1, which is used to control the opening and closing of the entire device; an analysis component 2, wherein the signal transceiver end of the analysis component 2 is connected to the signal transceiver end of the central control component 1, and is used to sample and monitor the insulating gas of the substation GIS equipment; a high-voltage component 3, wherein the high-voltage component 3 is provided with a high-voltage output end connected to the GIS equipment, and is used to generate high-intensity high-voltage electricity to test the load of the substation; multiple groups of monitoring components 4, wherein the multiple groups of monitoring components 4 are respectively arranged at the analysis component 2 and the high-voltage component 3, and are used to monitor the internal operation of the equipment during the inspection process and to provide protection; a power supply component 5, wherein one side of the power supply component 5 is provided with an external input power line for power input, and the other side of the power supply component 5 is provided with an external output power line, which is used to provide power supply paths for each component.

[0051] Furthermore, the central control component includes: a console 110, which is used for human-computer interaction and can display data to assist staff control; a sensor module 120, which is provided with multiple groups, and the multiple groups of sensor modules 120 are respectively arranged in various places in the GIS equipment, for monitoring the status of the GIS equipment during the inspection process. The sensor module 120 contains a data collector, a voltage sensor, a temperature sensor, a pressure sensor and a humidity sensor. The signal output ends of the voltage sensor, the temperature sensor, the pressure sensor and the humidity sensor are connected to the signal receiving end of the data collector, and the signal connection between the data collector and the console 110 is established.

[0052] During use, the console 110 is used for human-computer interaction. The operator can start or stop the entire test process through the console and monitor the test data in real time. At the same time, the sensor module 120 can be used to monitor the status of the equipment in real time through the connected data collector. Each sensor including voltage, temperature, pressure, and humidity sensors will transmit data to the data collector, which will then be transmitted to the console for processing and display, thereby improving the safety and accuracy of the test process. The operator can monitor the status of the equipment in real time through the console, and promptly discover and handle abnormal situations. The arrangement of multiple sets of sensors makes equipment monitoring more comprehensive, ensuring the stability and reliability of GIS equipment during testing.

[0053] Further, the analysis component 2 includes: a sampling module 210, which is composed of a sampling head 211 and a sample delivery tube 212, and a regulating valve 213 is provided in the middle of the sample delivery tube 212; a pretreatment system 220, which contains a filter 221, a dryer 222 and a pressure reducer 223, and the top of the filter 221 is connected to the sample delivery tube 212, and the filter 221, the dryer 222 and the pressure reducer 223 are internally connected; an analysis module 230, which is composed of a spectrometer 231 and a mass spectrometer 232, and the sample gas is monitored by the spectrometer 231 and the mass spectrometer 232 in turn; a recovery module 240, which is a return pipe 241, which is used to connect the analysis module 230 and guide the sample gas after detection to flow back to the GIS device;

[0054] During use, a gas sample is extracted from the GIS device through the sampling head, and the sample gas is transmitted to the pretreatment system through the sample delivery tube 212. The regulating valve 213 in the middle controls the gas flow. Then, the gas sample is processed by the filter 221, the dryer 222 and the pressure reducer 223, and then enters the analysis module for component analysis. The gas sample is successively subjected to detailed component analysis by the spectrometer 231 and the mass spectrometer 232. The data is transmitted to the console 110 for processing. Finally, the analyzed gas sample is returned to the GIS device through the return pipe 241 to avoid gas waste. The above process ensures the accuracy of gas sample analysis, removes impurities and moisture through the pretreatment system, ensures the purity and reliability of gas analysis, and at the same time, utilizes the gas recovery function to effectively reduce the test cost, reduce environmental pollution, and achieve efficient use of resources.

[0055] Further, the high-voltage component includes: a high-voltage transformer 310, a rectifier circuit 320, a high-voltage capacitor 330 and a high-voltage switch 340, wherein the high-voltage switch 340 is connected in series with the high-voltage transformer 310, the rectifier circuit 320 and the high-voltage capacitor 330, wherein the high-voltage transformer 310 also includes: a shell made of an insulating ceramic material as a whole, a magnetic flux ring 313 is arranged inside the shell, a connecting plate 314 is installed on the top of the shell by bolts, and the connecting plate 314 and the magnetic flux ring 313 form a ring loop; a detachable primary coil 311 is arranged on one side of the shell, and the primary coil 311 is sleeved on the magnetic flux ring 313, and a detachable pressurizing coil 312 is arranged on the other side of the shell, and the pressurizing coil 312 is sleeved on the other end of the magnetic flux ring 313;

[0056] During use, the input low voltage is increased to the required high voltage level through the high voltage transformer 310, and then the alternating current is converted into direct current through the rectifier circuit 320, and the energy is stored through the high voltage capacitor 330. The current after the transformation is passed through the GIS equipment for withstand voltage monitoring. When an accident occurs during the monitoring process, it can be quickly disconnected through the high voltage switch 340. The high voltage component 3 provides a stable and adjustable high voltage power supply, which can accurately simulate the high voltage conditions that the GIS equipment may encounter during operation, ensuring the reliability and safety of the equipment. The high voltage switch 340 provides a fast disconnection function, which can immediately interrupt the power supply when an abnormal situation is detected to avoid equipment damage;

[0057] Specifically, since the high-voltage coil as a whole is a component with a high load, it needs to be maintained or replaced frequently. When the high-voltage coil needs to be maintained or replaced, the connecting plate 314 can be removed by bolts, and the pressure coil 312 and the original coil 311 can be taken out from the high-voltage transformer 310 for maintenance, thereby improving the maintenance convenience of the device.

[0058] Furthermore, the monitoring component 4 includes: an overvoltage protection module 410, which is composed of multiple groups of voltage sensors, relays and discharge gaps, and the multiple groups of voltage sensors of the overvoltage protection module 410 are arranged at various places in the equipment to monitor the internal voltage of the equipment; an overcurrent protection module 420, which is composed of multiple groups of current sensors, circuit breakers and regulating resistors, wherein the multiple groups of current sensors are arranged at various places of the outer shell of the test equipment to monitor whether the outer shell of the equipment is leaking; a temperature protection module 430, which is composed of a temperature sensor and an active heat sink, wherein the temperature sensor is arranged inside the equipment to monitor the operating temperature of the equipment;

[0059] During use, the overvoltage protection module 410 monitors the voltage condition inside the equipment in real time through the voltage sensor, and the relay and the discharge gap ensure that the power supply is quickly cut off in the case of overvoltage. The overcurrent protection module 420 monitors the current condition of the equipment casing through the current sensor, and the circuit breaker and the regulating resistor can reduce the current or cut off the power supply in the case of overcurrent. The temperature protection module 430 temperature sensor monitors the temperature inside the equipment, and the active radiator automatically cools down when the temperature rises abnormally. The above process can provide multi-level safety protection measures for the inspection process, ensuring a quick response in the case of overvoltage, overcurrent or abnormal temperature to protect the safety of equipment and personnel. At the same time, the real-time monitoring and automatic protection functions of the monitoring component 4 are used to improve the safety and stability of the entire test process.

[0060] Furthermore, the power supply component 5 includes: a power supply module 510, the power supply module 510 includes a power supply 511 and a power-on wire 512, the power supply 511 is provided with power-on wires 512 on both sides, and the two power-on wires 512 are respectively connected to two power lines of an external input and an external output; an emergency power-off module 520, the emergency power-off module 520 is connected to the power supply module 510 signal, and is used to control the emergency shutdown of the power supply module 510, wherein the emergency power-off module 520 includes a control cavity 521, and a control block 522 is slidably connected inside the control cavity 521, and a power-on block 523 is provided inside the control block 522, and when the control block 522 is located in the middle of the control cavity 521, the power-on block 523 is connected to the electric wire 512, a spring 524 is arranged between the inner wall of the top of the control cavity 521 and the control block 522, an electromagnet 525 is arranged at the bottom of the control cavity 521 to repel the control block 522, and the control block 522 is maintained in the middle of the control cavity 521 under the repulsive force of the spring 524 and the electromagnet 525; a photoelectric monitoring module 530, the photoelectric monitoring module 530 is used to monitor whether there is anyone entering the internal space, the photoelectric monitoring module 530 includes a circuit board 531 and a plurality of light sensors 532 connected to the port of the circuit board 531, the circuit board 531 is electrically connected to the electromagnet 525, and is used to control the start and stop of the electromagnet 525;

[0061] During use, the power supply 511 and the power line 512 are used to conduct and connect the circuit. In the state of conduction and connection, the electromagnet 525 can physically maintain the connection of the control block 522 and the power block 523 to the circuit. When the light sensor 532 detects that someone has mistakenly entered the detection area, the circuit board 531 controls the electromagnet 525 to be turned off, so that the spring 524 pushes the control block 522 to move and cut off the connection of the power line 512, and quickly completes the circuit cutting.

[0062] Through the above process, the power supply module 510 is used to provide a stable power supply for each component to ensure the normal operation of the test equipment. The photoelectric monitoring module 530 is used to continuously monitor the safety of the test area to ensure that the power-off mechanism can be triggered in time in an emergency. When an emergency situation such as leakage or accidental entry of a person is detected, the photoelectric monitoring module 530 can be triggered to quickly cut off the power supply. The above components provide a stable power supply path to ensure the normal operation of each component. The emergency power-off function is used to improve the safety of the equipment, and the power supply can be quickly cut off in dangerous situations to protect the equipment and operators.

[0063] A 220kV substation GIS test process, the process includes:

[0064] Step S1: Visually inspect the GIS equipment to be inspected, and conduct a comprehensive inspection of the GIS and test equipment to ensure that the equipment is in normal condition without damage or abnormality. Before the test begins, visual inspection and equipment status confirmation are performed to ensure that the GIS equipment and test equipment are in normal working condition. This process effectively prevents test failures caused by equipment damage or abnormal conditions, and improves the reliability of the entire test process;

[0065] Step S2: Perform a withstand voltage test on the GIS through the high-voltage component 3 to detect whether it can withstand the rated voltage and overvoltage. Under high voltage, use the partial discharge test system to detect whether there is a discharge phenomenon inside the GIS, and analyze its location and intensity. Perform a withstand voltage test on the GIS through the high-voltage component 3 to simulate the high-voltage conditions that the equipment may encounter in actual operation. Combined with the partial discharge test system, the discharge phenomenon inside the GIS and its specific location can be accurately detected. This process can effectively evaluate the insulation performance of the GIS and ensure the safety and stability of the equipment in actual operation.

[0066] Step S3: Analyze the purity of the insulating gas in the GIS using the analysis component 2 to ensure that it meets the insulation requirements. Analyze the purity of the insulating gas in the GIS using the analysis component 2 to ensure that the gas meets the insulation requirements. Through precise gas composition analysis, gas impurities that may affect the insulation effect are discovered and eliminated in a timely manner, further ensuring the insulation performance of the GIS equipment.

[0067] Step S4: During the inspection process, the voltage, current, partial discharge signal and other data in the test process are monitored in real time through the central control component 1, and the collected data are analyzed to generate a test report to evaluate the insulation performance and reliability of the GIS. During the test process, the voltage, current and partial discharge signal and other data are monitored in real time through the central control component 1, and analyzed and reported. This real-time monitoring and data analysis not only improves the accuracy of the test, but also provides timely feedback information for the operator, facilitating timely adjustment and optimization of the test process;

[0068] Step S5: During the inspection process, the voltage, current and temperature in the device are monitored in real time through the monitoring component 4, and the inspection area is monitored through the power supply component 5. If an abnormal situation is found, the power supply can be automatically cut off to protect the safety of personnel and equipment. The voltage, current and temperature of the device are monitored in real time through the monitoring component 4 and the power supply component 5, and the power supply is automatically cut off when an abnormal situation is detected. Such an automatic protection mechanism effectively prevents risks such as overheating, overvoltage, overcurrent, etc. of the device, ensuring the safety of personnel and equipment during the test process;

[0069] Step S6: After the monitoring is completed, the problems existing in the GIS are corrected according to the test results, such as replacing the insulating gas, performing internal cleaning, etc., and the corrected GIS is tested again in steps S2 to S5 to ensure that all parameters meet the requirements. After the test is completed, the GIS equipment with problems is corrected according to the test results, and retested to ensure that the corrected equipment meets all test requirements. This step ensures the reliability and accuracy of the test results, making the final test conclusion more authoritative.

[0070] Furthermore, step S2 also includes:

[0071] Step S21: Activate the high-voltage component through the central control component 1, the high-voltage transformer 310 starts to work, increases the input voltage to the required test voltage level, the rectifier circuit 320 converts the AC power into DC power, and stores the electric energy through the high-voltage capacitor 330;

[0072] Step S22: Under the control of the console 110, the high-voltage component gradually increases the voltage to the set withstand voltage value to simulate the high-voltage condition of the GIS equipment in operation. The voltage sensor monitors the applied voltage value in real time to ensure the accuracy of the test voltage.

[0073] Step S23: Maintain the set withstand voltage value for a certain period of time, and monitor the voltage stability and the response of the equipment through the sensor module 120. If an abnormality occurs during this process, such as voltage fluctuation or equipment discharge, the central control component 1 will automatically record and issue an alarm through the monitoring component, and the high-voltage switch 340 will quickly cut off the power supply of the high-voltage component 3 to prevent damage.

[0074] Through the above steps, the whole process of high voltage testing is controlled and has automatic protection function, which ensures the safety and effectiveness of the test. At the same time, it can quickly respond to and handle abnormal situations that may occur during the test to protect the equipment from damage.

[0075] Furthermore, step S3 also includes:

[0076] Step S31: The sampling module is started through the central control component, and the sampling head 211 extracts gas samples from the GIS equipment. The gas enters the pretreatment system through the sample delivery tube 212, and the regulating valve 213 is used to control the flow of the sampled gas to ensure that the gas sample entering the pretreatment system is stable;

[0077] Step S32: The gas sample first passes through the filter 221 to remove impurities, and then passes through the dryer 222 to remove moisture to ensure that the gas sample is pure and free of interference. At the same time, the gas passes through the pressure reducer 223 to adjust the sample gas pressure to the working range of the spectrum analyzer and the mass spectrometer;

[0078] Step S33: The pre-treated gas sample enters the spectrum analyzer 231, and the gas composition is analyzed by infrared light or laser to detect the purity of SF6 gas. Then the gas sample enters the mass spectrometer 232 to further analyze the gas composition and identify trace impurities. The data obtained by the analysis is then processed by the central processing unit to obtain a gas purity and composition report, and the results are displayed in real time on the console 110;

[0079] Step S34: After the detection is completed, the sample gas flows back to the GIS equipment through the return pipe 241 to ensure environmental protection and cost-effectiveness.

[0080] The above steps ensure high accuracy of gas analysis, and the pretreatment system 220 filters impurities and moisture to provide reliable analysis results.

[0081] Furthermore, step S5 further includes:

[0082] Step S51: During the test, the monitoring component 4 continuously monitors the voltage, current and temperature conditions in the equipment. The voltage sensor and the current sensor monitor the voltage and current conditions of the high-voltage component and the GIS equipment respectively. The temperature sensor monitors the operating temperature inside the equipment.

[0083] Step S52: The data of all sensors are transmitted to the data collector through the sensor module 120, and transmitted to the central control unit CCU in real time for analysis. If abnormal data such as overvoltage, overcurrent, and overheating are detected, the system will immediately trigger the corresponding protection device;

[0084] Step S53: When an overvoltage or overcurrent condition is detected, the overvoltage protection module 410 and the overcurrent protection module 420 will quickly cut off the high voltage power supply or reduce the current by adjusting the resistance to prevent damage to the device;

[0085] Step S54: When the temperature protection module 430 detects that the temperature inside the device is abnormally high, it will immediately start the active radiator to cool it down and suspend the test if necessary;

[0086] Step S55: If a serious abnormal situation is detected, the monitoring component 4 will notify the operator through the console 110 and automatically interrupt the test. If the situation is critical, such as leakage of the equipment casing or someone mistakenly enters the test area, the photoelectric monitoring module 530 will trigger the emergency power-off module 520 to quickly cut off the power supply to ensure on-site safety.

[0087] The above steps achieve real-time monitoring and automatic protection mechanisms, greatly improving the safety and reliability of the equipment and reducing the risk of human intervention. At the same time, the emergency power-off function protects personnel and equipment in critical situations and avoids possible major accidents.

[0088] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0089] The above is a detailed introduction to a 220kV substation GIS test equipment and test process provided in the embodiments of the present application. This article uses specific examples to illustrate the principles and implementation methods of the present application. The description of the above embodiments is only used to help understand the technical solution and its core idea of ​​the present application; ordinary technicians in this field should understand that: they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some of the technical features therein with equivalents; and these modifications or replacements do not make the essence of the corresponding technical solution deviate from the scope of the technical solution of the embodiments of the present application.

Claims

1. A 220kV substation GIS test equipment, characterized in that: include: A central control component (1), used to control the opening and closing of the entire device; An analysis component (2), wherein a signal transceiver end of the analysis component (2) is connected to a signal transceiver end of the central control component (1) and is used for sampling and monitoring insulating gas of a substation GIS device; A high-voltage component (3), wherein the high-voltage component (3) is provided with a high-voltage output terminal connected to the GIS device and is used to generate high-intensity high-voltage electricity to test the load of the substation; A plurality of monitoring components (4), wherein the plurality of monitoring components (4) are respectively arranged at the analysis component (2) and the high-voltage component (3), and are used to monitor the internal operation of the equipment during the inspection process and to provide protection; A power supply component (5), wherein one side of the power supply component (5) is provided with an external input power line for power input, and the other side of the power supply component (5) is provided with an external output power line for providing a power supply path for each component.

2. The 220kV substation GIS test equipment according to claim 1, characterized in that: The central control component includes: A control console (110), used for human-computer interaction and capable of displaying data to assist staff in control; A sensor module (120), wherein the sensor module (120) is provided in a plurality of groups, and the plurality of groups of the sensor modules (120) are respectively arranged at various locations in the GIS device, and are used to monitor the status of the GIS device during the inspection process; the sensor module (120) internally comprises a data collector, a voltage sensor, a temperature sensor, a pressure sensor, and a humidity sensor; the signal output ends of the voltage sensor, the temperature sensor, the pressure sensor, and the humidity sensor are connected to the signal receiving end of the data collector, and the data collector is signal-connected to the console (110).

3. The 220kV substation GIS test equipment according to claim 1, characterized in that: The analysis component (2) comprises: A sampling module (210), the sampling module (210) consisting of a sampling head (211) and a sample delivery tube (212), the sampling head (211) being connected to one end of the sample delivery tube (212), and a regulating valve (213) being provided in the middle of the sample delivery tube (212); A pretreatment system (220), wherein the pretreatment system (220) comprises a filter (221), a dryer (222) and a pressure reducer (223), wherein the filter (221), the dryer (222) and the pressure reducer (223) are arranged in the same container, wherein the filter (221) is connected to the sample delivery tube (212), and wherein the filter (221), the dryer (222) and the pressure reducer (223) are internally connected to each other; An analysis module (230), wherein the analysis module (230) is composed of a spectrometer (231) and a mass spectrometer (232), and the sample gas is monitored by the spectrometer (231) and the mass spectrometer (232) in sequence; The recovery module (240) is a return pipe (241) used to connect the analysis module (230) and guide the sample gas after detection to flow back to the GIS device.

4. The 220kV substation GIS test equipment according to claim 1, characterized in that: The high-voltage component comprises: a high-voltage transformer (310), a rectifier circuit (320), a high-voltage capacitor (330) and a high-voltage switch (340), wherein the high-voltage switch (340) is connected in series with the high-voltage transformer (310), the rectifier circuit (320) and the high-voltage capacitor (330), and the high-voltage transformer (310) further comprises: A shell made of insulating ceramic material as a whole, a magnetic flux ring (313) is arranged inside the shell, a connecting plate (314) is installed on the top of the shell by bolts, and the connecting plate (314) and the magnetic flux ring (313) form a ring loop; A detachable primary coil (311) is provided on one side of the shell, and the primary coil (311) is sleeved on the magnetic conduction ring (313). A detachable pressurizing coil (312) is provided on the other side of the shell, and the pressurizing coil (312) is sleeved on the other end of the magnetic conduction ring (313).

5. The 220kV substation GIS test equipment according to claim 1, characterized in that: The monitoring component (4) comprises: An overvoltage protection module (410), the overvoltage protection module (410) being composed of a plurality of groups of voltage sensors, relays and discharge gaps, the plurality of groups of voltage sensors of the overvoltage protection module (410) being arranged at various locations in the device and used to monitor the internal voltage of the device; An overcurrent protection module (420), the overcurrent protection module (420) comprising a plurality of groups of current sensors, circuit breakers and regulating resistors, wherein the plurality of groups of current sensors are respectively arranged at various locations of the housing of the test equipment, and are used to monitor whether the housing of the equipment has leakage; A temperature protection module (430) is composed of a temperature sensor and an active radiator, wherein the temperature sensor is arranged inside the device and is used to monitor the operating temperature of the device.

6. The 220kV substation GIS test equipment according to claim 1, characterized in that: The power supply component (5) comprises: A power supply module (510), the power supply module (510) comprising a power supply (511) and a power supply line (512), the power supply (511) being provided with power supply lines (512) on both sides, and the two power supply lines (512) being respectively connected to two power supply lines of an external input and an external output; An emergency power-off module (520) is connected to the power module (510) by signal and is used to control the power module (510) to be shut off in an emergency, wherein the emergency power-off module (520) comprises a control cavity (521), a control block (522) is slidably connected inside the control cavity (521), a power-on block (523) is provided inside the control block (522), and the control block (522) is located in the control cavity. When the control chamber (521) is in the middle, the power block (523) is connected to the power line (512), a spring (524) is arranged between the inner wall of the top of the control chamber (521) and the control block (522), and an electromagnet (525) is arranged at the bottom of the control chamber (521) to repel the control block (522). The control block (522) is maintained in the middle of the control chamber (521) under the repulsive force of the spring (524) and the electromagnet (525); A photoelectric monitoring module (530) is used to monitor whether anyone enters the internal space. The photoelectric monitoring module (530) comprises a circuit board (531) and a plurality of light sensors (532) connected to ports of the circuit board (531). The circuit board (531) is electrically connected to the electromagnet (525) to control the start and stop of the electromagnet (525).

7. A 220kV substation GIS test process, characterized in that: The 220kV substation GIS test equipment described in any one of claims 1 to 6 is used, and the process includes: Step S1: Visually inspect the GIS equipment to be inspected, and conduct a comprehensive inspection of the GIS and test equipment to ensure that the equipment is in normal condition without damage or abnormality; Step S2: Performing a withstand voltage test on the GIS through the high voltage component (3) to detect whether it can withstand the rated voltage and overvoltage, and detecting whether there is a discharge phenomenon inside the GIS through a partial discharge test system under high voltage, and analyzing its location and intensity; Step S3: using the analysis component (2) to analyze the purity of the insulating gas in the GIS to ensure that it meets the insulation requirements; Step S4: During the inspection process, the central control component (1) monitors the voltage, current, partial discharge signal and other data in the test process in real time, analyzes the collected data, generates a test report, and evaluates the insulation performance and reliability of the GIS; Step S5: During the inspection process, the voltage, current and temperature in the device are monitored in real time through the monitoring component (4), and the inspection area is monitored through the power supply component (5). If an abnormality is found, the power supply can be automatically cut off to protect the safety of personnel and equipment; Step S6: After monitoring is completed, the problems existing in the GIS are corrected according to the test results, such as replacing the insulating gas, performing internal cleaning, etc., and the corrected GIS is tested again in steps S2 to S5 to ensure that all parameters meet the requirements.

8. The 220kV substation GIS test process according to claim 7 is characterized in that: The step S2 also includes: Step S21: activating the high-voltage component (3) through the central control component (1) to start the high-voltage transformer (310) to increase the input voltage to the required test voltage level, and the rectifier circuit (320) converts the alternating current into direct current, and stores the electric energy through the high-voltage capacitor (330) for backup; Step S22: under the control of the control console (110), the high-voltage component gradually increases the voltage to the set withstand voltage value, simulating the high-voltage condition of the GIS equipment in operation, and the voltage sensor monitors the applied voltage value in real time to ensure the accuracy of the test voltage; Step S23: Maintain the set withstand voltage value for a certain period of time, and monitor the voltage stability and the response of the device through the sensor module (120). If an abnormality occurs during this process, such as voltage fluctuation or device discharge, the central control component (1) will automatically record and issue an alarm through the monitoring component, and quickly cut off the power supply of the high-voltage component (3) through the high-voltage switch (340) to prevent damage.

9. The 220kV substation GIS test process according to claim 7 is characterized in that: The step S3 also includes: Step S31: The collection module is started through the central control component (1), and the sampling head (211) extracts a gas sample from the GIS device. The gas enters the pretreatment system through the sample delivery tube (212), and the flow rate of the sampled gas is controlled by the regulating valve (213) to ensure that the gas sample entering the pretreatment system is stable; Step S32: The gas sample first passes through a filter (221) to remove impurities, and then passes through a dryer (222) to remove moisture to ensure that the gas sample is pure and free of interference. At the same time, the gas passes through a pressure reducer (223) to adjust the sample gas pressure to within the working range of the spectrum analyzer (231) and the mass spectrometer (232); Step S33: the pre-treated gas sample enters the spectrum analyzer (231), and the gas composition is analyzed by infrared light or laser to detect the purity of SF6 gas. Then the gas sample enters the mass spectrometer (232), and the gas composition is further analyzed to identify trace impurities. The data obtained by the analysis is then processed by the central processing unit to obtain a gas purity and composition report, and the results are displayed in real time on the console (110); Step S34: After the detection is completed, the sample gas flows back to the GIS equipment through the return pipe (241), ensuring environmental protection and cost-effectiveness.

10. The 220kV substation GIS test process according to claim 7, characterized in that: The step S5 further comprises: Step S51: During the test, the monitoring component (4) continuously monitors the voltage, current and temperature conditions in the device. The voltage sensor and the current sensor monitor the voltage and current conditions of the high-voltage component and the GIS device respectively. The temperature sensor monitors the operating temperature inside the device. Step S52: The data of all sensors are transmitted to the data collector through the sensor module (120), and transmitted to the control console (110) in real time for analysis. When an abnormal state is detected, the system will immediately trigger the corresponding protection device; Step S53: When an overvoltage or overcurrent condition is detected, the overvoltage protection module (410) and the overcurrent protection module (420) will quickly cut off the high voltage power supply or reduce the current by adjusting the resistance to prevent damage to the device; Step S54: When the temperature protection module (430) detects that the temperature inside the device is abnormally high, it will immediately start the active radiator to cool down the temperature. If the temperature continues to rise, the test will be interrupted; Step S55: When an abnormality is detected during the test, the monitoring component (4) will notify the operator through the console (110) and automatically interrupt the test. When the device casing leaks electricity or someone mistakenly enters the test area, the photoelectric monitoring module (530) will trigger the emergency power-off module (520) to quickly cut off the power supply to ensure on-site safety.