Method and system for determining anti-seismic toughness of transformer substation based on data analysis
Through a data analysis method, a directed network graph model of the substation system is established, and the decision-making deployment time and equipment repair priority are determined. Combined with Monte Carlo simulation, the problem of deviation between seismic toughness simulation results and actual values in the existing technology is solved. More accurate seismic toughness assessment and determination of decision-making and deployment time are achieved.
Patent Information
- Application Number
- CN202410997834.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-11-15
AI Technical Summary
The existing seismic toughness determination method based on functional indicators is difficult to accurately reflect the actual situation during the simulation process, resulting in large deviations in decision-making and deployment time and equipment maintenance strategies, and it is impossible to effectively evaluate the seismic toughness of the system.
Using a data analysis method, by defining the functional status and toughness evaluation indicators of the substation system, establishing a directed network graph model, determining the decision-making deployment time and equipment repair priority, and combining the Monte Carlo simulation method, the seismic toughness curve of the substation system is calculated. and evaluate indicators to reduce the deviation between simulation results and actual values.
By quantitatively evaluating the seismic toughness of the substation system, determining the decision-making and deployment time based on the complexity and functional status, a more realistic repair sequence of faulty equipment is generated, which improves the accuracy of the simulation results and reduces the seismic toughness simulation value and the actual value. deviation.
Smart Images

Figure CN118965975A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power system assessment, and in particular to a method and system for determining the seismic toughness of a substation based on data analysis. Background Art
[0002] Seismic resilience is a further deepening and development of seismic design based on performance, which provides a newer and more comprehensive idea for the seismic planning and design of power grid infrastructure, that is, to strive to maintain the necessary functions of the power grid when it is hit by an earthquake disaster, and to achieve rapid recovery of its post-earthquake functions to avoid the huge social impact and economic losses caused by long-term power outages. At this stage, defining, quantifying and realizing the seismic resilience of engineering structures or infrastructure has become a hot topic in international earthquake prevention and disaster reduction and the main direction of future earthquake engineering research and development. At the beginning of the 21st century, the resilience curve based on functional indicators proposed by Bruneau et al. is a highly recognized method for describing quantitative seismic resilience. Compared with the traditional probability-based operational reliability risk assessment, the seismic resilience curve can comprehensively describe the dynamic changes in the system function level before and after an earthquake, and then evaluate the system resilience based on the curve characteristics such as the overall loss of function.
[0003] The existing seismic resilience determination method based on the resilience curve of functional indicators usually uses empirical values to determine the decision-making deployment time, and in the simulation process, the equipment maintenance order is usually assumed to be generated in a random state. However, in the actual process, due to the complexity of the post-earthquake environment and the differences in substation systems, the decision-making deployment time will also vary greatly. In real situations, the equipment maintenance strategy often needs to be adjusted on-site according to the actual situation, which makes the simulated seismic resilience deviate greatly from the actual value. To this end, we propose a method and system for determining the seismic resilience of substations based on data analysis. Summary of the invention
[0004] The main purpose of the present invention is to provide a method and system for determining the seismic resilience of a substation based on data analysis, which can effectively solve the problems in the background technology.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] The method for determining the seismic resilience of a substation based on data analysis includes:
[0007] S1: The functional state F of the substation system is defined as the maximum allowable power transmission and transformation capacity of the substation system, and the resilience assessment index R is the overall functional loss of the substation system after an earthquake.
[0008] S2: A network directed graph model G(V,E) of the substation system is established based on the logical topological relationship between the substation layout and the equipment. The state of the edge E is determined by the working state s of each device in the system. The connectivity state between nodes V is recorded and represented by the connection matrix C[x]. Based on this, a functional relationship F=f(C[s]) is established between the functional state F of the substation system and the equipment state s.
[0009] S3: Determine the variables related to the simulation process of substation system function loss and restoration, including the earthquake intensity range [a min ,a max ] and the current input earthquake intensity level a, equipment seismic vulnerability curve, equipment repair time distribution model, available repair resources and time step Δt;
[0010] S4: According to the current input earthquake intensity level a and the equipment seismic vulnerability curve, obtain the current state vector s of the equipment in the system d , the current state vector s d Substitute into the functional relationship of step S2 to obtain the current functional status F of the substation system d ;
[0011] S5: According to the current functional status of the substation system F d The complexity of the substation system determines the decision deployment time threshold t max , and the decision deployment time threshold t max Inversely proportional to the current functional status of the substation system F d , which is proportional to the complexity of the substation system. The complexity of the substation system is quantified by the average degree of the logical topological relationship network between devices. The complexity of the substation system is proportional to the average degree of the logical topological relationship network between devices. The calculation formula of the average degree is:
[0012]
[0013] In the formula, It is expressed as the average degree of the logical topological relationship network between devices; k m It is expressed as the number of devices connected to the mth device; M is the total number of devices
[0014] S6: According to the equipment repair time distribution model and the equipment importance, determine the equipment repair priority p, generate the faulty equipment repair order π according to the equipment repair priority, and obtain the repair time of each faulty equipment through random sampling according to the equipment repair time distribution model and corresponding parameters, wherein the faulty equipment repair order value is inversely proportional to the equipment repair priority p;
[0015] The steps for determining the equipment repair priority p include:
[0016] The number of repetitions of the substation system function loss and restoration simulation process is set to Q;
[0017] Get the functional level K of the substation when the i-th device is not repaired during the simulation process ip , and the functional level K' of the substation after the i-th device is repaired ip ;
[0018] Obtain the repair time of the i-th device in the simulation process according to the equipment repair time distribution model;
[0019] Calculate the repair efficiency index P of the i-th device based on the obtained parameters i , the calculation formula is:
[0020]
[0021] According to the network directed graph model of the constructed substation system, the equipment importance evaluation value WD of the i-th equipment is calculated. i ;
[0022] The repair priority evaluation value f of the i-th device is calculated by the following formula i , the calculation formula is:
[0023] f i =αp i +βWD i
[0024] In the formula, α and β are constant coefficients, and 0.3<α<0.7; 0.3<β<0.7; α+β=1;
[0025] The repair priority evaluation value of the equipment obtained is used as the representation of the equipment repair priority p;
[0026] The process of obtaining the importance of the device includes the following steps:
[0027] Obtain all devices connected to the i-th device according to the constructed network directed graph model of the substation system;
[0028] According to the logical topological relationship between the devices, the devices connected to the i-th device are divided into directional devices and directed devices;
[0029] Define the connection relationship between the directional device and the i-th device as a directional edge, and the connection relationship between the directed device and the i-th device as a directed edge;
[0030] The device importance evaluation value of the i-th device is calculated according to the following formula:
[0031]
[0032] Where, WDi N is the device importance evaluation value of the i-th device; (i) It is represented as the set of devices connected to the i-th device in the network directed graph model of the substation system; WD ini It is represented as the sum of the weights of all directed edges of the i-th device; WD outi It is represented as the sum of the weights of all directional edges of the i-th device; w ji It is represented as the weight of the jth directed edge of the ith device; w ij It is represented as the weight of the jth directional edge of the ith device; N in(i) Represented as the set of all devices directed by the i-th device; N out(i) Represented as the set of all directional devices of the i-th device;
[0033] S7: Decompose the function recovery process according to the time step Δt, allocate available repair resources according to the repair order π of the faulty equipment, update the equipment status s and the substation system function status F according to the repair time of the faulty equipment, obtain the substation system function seismic toughness curve, and calculate the corresponding toughness evaluation index R, the calculation formula is:
[0034]
[0035] In the formula, F 0 It is represented by the functional level of the substation before the earthquake; F(t) is represented by the functional level of the substation at time t; t 0 is the time when the earthquake occurred; t e It is the moment when the substation fully recovers its functional level after an earthquake;
[0036] The Monte Carlo simulation method is used to repeat steps S4 to S7, and the statistical values of the resilience evaluation index R, including the mean and variance, are calculated to obtain the quantitative evaluation index value of the seismic resilience of the substation system.
[0037] A substation seismic resilience determination system based on data analysis, including an indicator definition module, a directed graph model construction module, a simulation process variable acquisition module, and a seismic resilience curve fitting module;
[0038] The indicator definition module is used to define the substation system functional status F and the resilience evaluation index R;
[0039] The directed graph model building module establishes a network directed graph model G(V, E) of the substation system according to the logical topological relationship between the substation layout and the equipment, and establishes a functional relationship F=f(C[s]) between the substation system functional state F and the equipment state s;
[0040] The simulation process variable acquisition module is used to determine the relevant variables of the substation system function loss and recovery simulation process;
[0041] The seismic toughness curve fitting module is used to obtain the functional seismic toughness curve of the substation system and calculate the corresponding toughness evaluation index R. The calculation formula is:
[0042]
[0043] In the formula, F 0 It is represented by the functional level of the substation before the earthquake; F(t) is represented by the functional level of the substation at time t; t 0 is the time when the earthquake occurred; t e It is the moment when the substation fully recovers its functional level after an earthquake;
[0044] The seismic toughness curve fitting module includes a current function status acquisition submodule, a decision deployment time acquisition submodule, a fault equipment repair sequence acquisition submodule, and an equipment status and function status update submodule;
[0045] The current functional state acquisition submodule is used to obtain the current state vector s of the equipment in the system according to the current input earthquake intensity level a and the equipment seismic vulnerability curve d , and the current state vector s d Substitute into the functional relationship of step S2 to obtain the current functional status F of the substation system d ;
[0046] The decision deployment time acquisition submodule is used to obtain the current functional state of the substation system according to the current functional state of the substation system. d The complexity of the substation system determines the decision deployment time threshold t max ;
[0047] The faulty equipment repair order acquisition submodule is used to determine the equipment repair priority p according to the equipment repair time distribution model and the equipment importance, generate the faulty equipment repair order π according to the equipment repair priority, and obtain the repair time of each faulty equipment through random sampling according to the equipment repair time distribution model and corresponding parameters;
[0048] The device status and function status update submodule is used to decompose the function recovery process according to the time step Δt, allocate available repair resources according to the faulty device repair order π, and update the device status s and the substation system function status F according to the repair time of the faulty device;
[0049] The system also includes a memory, a processor, and a computer program stored on the memory and executable on the processor.
[0050] The present invention has the following beneficial effects:
[0051] Compared with the prior art, the technical solution of the present invention defines the functional state F of the substation system as the maximum allowable transmission and transformation capacity of the substation system, and the resilience evaluation index R as the overall functional loss of the substation system after an earthquake. According to the logical topological relationship between the substation layout and the equipment, a network directed graph model G(V,E) of the substation system is established, wherein the state of the edge E is determined by the working state s of each device in the system, and the connectivity state between the nodes V is recorded and represented by the connection matrix C[x]. Based on this, a functional relationship F=f(C[s]) between the functional state F of the substation system and the equipment state s is established, and the earthquake intensity range [a] including the range of the functional state F of the substation system and the equipment state s is determined. min ,a max ] and the current input earthquake intensity level a, the equipment seismic vulnerability curve, the equipment repair time distribution model, the available repair resources and the time step Δt related variables. According to the current input earthquake intensity level a and the equipment seismic vulnerability curve, the current state vector s of the equipment in the system is obtained. d , the current state vector s d Substitute into the function relationship to obtain the current functional status F of the substation system d , and according to the current functional status of the substation system F d The complexity of the substation system determines the decision deployment time threshold t max According to the equipment repair time distribution model and equipment importance, the equipment repair priority p is determined, and the fault equipment repair order π is generated. According to the equipment repair time distribution model and the corresponding parameters, the repair time of each faulty equipment is obtained by random sampling. The functional recovery process is decomposed according to the time step Δt, and the available repair resources are allocated according to the faulty equipment repair order π. According to the repair time of the faulty equipment, the equipment state s and the substation system functional state F are updated to obtain the substation system functional seismic resilience curve, and the corresponding resilience evaluation index R is calculated. The Monte Carlo simulation method is used to repeat the simulation, and the statistical values of the resilience evaluation index R, including the mean and variance, are calculated to obtain the quantitative evaluation index value of the seismic resilience of the substation system. The decision deployment time threshold is determined in combination with the complexity and functional status of the substation, and the faulty equipment repair order is generated based on the equipment importance, so that the simulation results are closer to the real state, thereby effectively reducing the deviation between the simulated value of seismic resilience and the actual value. BRIEF DESCRIPTION OF THE DRAWINGS
[0052] Figure 1 It is a flow chart of the method for determining the seismic toughness of a substation based on data analysis of the present invention;
[0053] Figure 2 It is a structural block diagram of a substation seismic resilience determination system based on data analysis of the present invention;
[0054] Figure 3 Schematic diagram of the seismic toughness curve of the substation system. DETAILED DESCRIPTION
[0055] The present invention will be further described below in conjunction with specific implementation methods, wherein the accompanying drawings are only used for exemplary descriptions and represent only schematic diagrams rather than actual drawings, and should not be understood as limiting the present invention. In order to better illustrate the specific implementation methods of the present invention, some parts of the accompanying drawings may be omitted, enlarged or reduced, and do not represent the size of the actual product.
[0056] The specific implementation process of the technical solution of the present invention includes the following steps:
[0057] Step 1: Define the substation system functional status F and resilience evaluation index R;
[0058] The functional state F of the substation system is defined as the maximum allowable power transmission and transformation capacity of the substation system, and the resilience assessment index R is the overall functional loss of the substation system after an earthquake.
[0059] Step 2: According to the substation layout and the logical topological relationship between the devices, a network directed graph model G(V,E) of the substation system is established, where the state of the edge E is determined by the working state s of each device in the system, and the connectivity state between the nodes V is recorded and represented by the connection matrix C[x]. Based on this, a functional relationship F=f(C[s]) is established between the functional state F of the substation system and the device state s.
[0060] Step 3: Determine the variables related to the substation system function loss and restoration simulation process, including the earthquake intensity range [a min ,a max ] and the current input earthquake intensity level a, equipment seismic vulnerability curve, equipment repair time distribution model, available repair resources and time step Δt;
[0061] Step 4: According to the current input earthquake intensity level a and the equipment seismic vulnerability curve, obtain the current state vector s of the equipment in the system d , the current state vector s d Substitute into the functional relationship of step S2 to obtain the current functional status F of the substation system d ;
[0062] Step 5: According to the current functional status of the substation system F d The complexity of the substation system determines the decision deployment time threshold t max ;
[0063] Among them, the decision deployment time threshold t max Inversely proportional to the current functional status of the substation system F d, which is proportional to the complexity of the substation system. The complexity of the substation system is quantified by the average degree of the logical topological relationship network between devices. The complexity of the substation system is proportional to the average degree of the logical topological relationship network between devices. The calculation formula of the average degree is:
[0064]
[0065] In the formula, It is expressed as the average degree of the logical topological relationship network between devices; k m It is expressed as the number of devices connected to the mth device; M is the total number of devices.
[0066] Step 6: According to the equipment repair time distribution model and equipment importance, determine the equipment repair priority p, generate the faulty equipment repair order π according to the equipment repair priority, and obtain the repair time of each faulty equipment through random sampling according to the equipment repair time distribution model and corresponding parameters;
[0067] Among them, the faulty equipment repair order value is inversely proportional to the equipment repair priority p;
[0068] The steps for determining the equipment repair priority p include:
[0069] S611: setting the number of repetitions of the substation system function loss and recovery simulation process to Q;
[0070] S612: Obtain the functional level K of the substation when the i-th device is not repaired during the simulation process ip , and the functional level K' of the substation after the i-th device is repaired ip ;
[0071] S613: Obtaining the repair time of the i-th device in the simulation process according to the device repair time distribution model;
[0072] S614: Calculate the repair efficiency index P of the i-th device according to the acquired parameters i , the calculation formula is:
[0073]
[0074] S615: Calculate the device importance evaluation value WD of the i-th device according to the constructed network directed graph model of the substation system i ;
[0075] S616: Calculate the repair priority evaluation value f of the i-th device by the following formula i , the calculation formula is:
[0076] f i =αp i +βWD i
[0077] In the formula, α and β are constant coefficients, and 0.3<α<0.7; 0.3<β<0.7; α+β=1;
[0078] S617: Using the acquired repair priority evaluation value of the device as a representation of the device repair priority p;
[0079] The process of obtaining the importance of equipment includes the following steps:
[0080] S621: Acquire all devices connected to the i-th device according to the constructed network directed graph model of the substation system;
[0081] S622: Divide the devices connected to the i-th device into directional devices and directed devices according to the logical topological relationship between the devices;
[0082] S623: define the connection relationship between the directional device and the i-th device as a directional edge, and the connection relationship between the directed device and the i-th device as a directed edge;
[0083] S624: Calculate the device importance evaluation value of the i-th device according to the following formula:
[0084]
[0085] Where, WD i N is the device importance evaluation value of the i-th device; (i) It is represented as the set of devices connected to the i-th device in the network directed graph model of the substation system; WD ini It is represented as the sum of the weights of all directed edges of the i-th device; WD outi It is represented as the sum of the weights of all directional edges of the i-th device; w ji It is represented as the weight of the jth directed edge of the ith device; w ij It is represented as the weight of the jth directional edge of the ith device; N in(i) Represented as the set of all devices directed by the i-th device; N out(i) Represented as the set of all directional devices of the i-th device;
[0086] Step 7: Decompose the function recovery process according to the time step Δt, allocate available repair resources according to the repair order π of the faulty equipment, update the equipment status s and the substation system function status F according to the repair time of the faulty equipment, and obtain the substation system function seismic toughness curve, as shown in Figure 3 As shown, the corresponding toughness evaluation index R is calculated, and the calculation formula is:
[0087]
[0088] In the formula, F 0 It is represented by the functional level of the substation before the earthquake; F(t) is represented by the functional level of the substation at time t; t 0 is the time when the earthquake occurred; t e It is the moment when the substation fully recovers its functional level after an earthquake;
[0089] Step 8: Repeat steps 4 to 7 using the Monte Carlo simulation method to calculate the statistical values of the resilience evaluation index R, including the mean and variance, and obtain the quantitative evaluation index value of the seismic resilience of the substation system.
[0090] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A method for determining the seismic toughness of a substation based on data analysis, characterized in that: include: S1: The functional state F of the substation system is defined as the maximum allowable power transmission and transformation capacity of the substation system, and the resilience assessment index R is the overall functional loss of the substation system after an earthquake. S2: A network directed graph model G(V,E) of the substation system is established based on the logical topological relationship between the substation layout and the equipment. The state of the edge E is determined by the working state s of each device in the system. The connectivity state between nodes V is recorded and represented by the connection matrix C[x]. Based on this, a functional relationship F=f(C[s]) is established between the functional state F of the substation system and the equipment state s. S3: Determine the variables related to the simulation process of substation system function loss and restoration, including the earthquake intensity range [a min ,a max ] and the current input earthquake intensity level a, equipment seismic vulnerability curve, equipment repair time distribution model, available repair resources and time step Δt; S4: According to the current input earthquake intensity level a and the equipment seismic vulnerability curve, obtain the current state vector s of the equipment in the system d , the current state vector s d Substitute into the functional relationship of step S2 to obtain the current functional status F of the substation system d ; S5: According to the current functional status of the substation system F d The complexity of the substation system determines the decision deployment time threshold t max ; S6: According to the equipment repair time distribution model and the importance of the equipment, determine the equipment repair priority p, generate the faulty equipment repair order π according to the equipment repair priority, and obtain the repair time of each faulty equipment through random sampling according to the equipment repair time distribution model and corresponding parameters; S7: Decompose the function recovery process according to the time step Δt, allocate available repair resources according to the repair order π of the faulty equipment, update the equipment status s and the substation system function status F according to the repair time of the faulty equipment, obtain the substation system function seismic toughness curve, and calculate the corresponding toughness evaluation index R, the calculation formula is: Where F0 represents the functional level of the substation before the earthquake; F(t) represents the functional level of the substation at time t; t0 is the time when the earthquake occurs; t e It is the moment when the substation’s functional level is fully restored after an earthquake.
2. The method for determining the seismic toughness of a substation based on data analysis according to claim 1, characterized in that: The method further comprises: The Monte Carlo simulation method is used to repeat steps S4 to S7, and the statistical values of the resilience evaluation index R, including the mean and variance, are calculated to obtain the quantitative evaluation index value of the seismic resilience of the substation system.
3. The method for determining the seismic toughness of a substation based on data analysis according to claim 1, characterized in that: The steps for determining the equipment repair priority p include: The number of repetitions of the substation system function loss and restoration simulation process is set to Q; Get the functional level K of the substation when the i-th device is not repaired during the simulation process ip , and the functional level K' of the substation after the i-th device is repaired ip ; Obtain the repair time of the i-th device in the simulation process according to the equipment repair time distribution model; Calculate the repair efficiency index P of the i-th device based on the obtained parameters i , the calculation formula is: According to the network directed graph model of the constructed substation system, the equipment importance evaluation value WD of the i-th equipment is calculated. i ; The repair priority evaluation value f of the i-th device is calculated by the following formula i , the calculation formula is: f i =αp i +βWD i In the formula, α and β are constant coefficients, and 0.3<α<0.7; 0.3<β<0.7; α+β=1; The repair priority evaluation value of the equipment obtained is used as the representation of the equipment repair priority p.
4. The method for determining the seismic toughness of a substation based on data analysis according to claim 1, characterized in that: The process of obtaining the importance of the device includes the following steps: Obtain all devices connected to the i-th device according to the constructed network directed graph model of the substation system; According to the logical topological relationship between the devices, the devices connected to the i-th device are divided into directional devices and directed devices; Define the connection relationship between the directional device and the i-th device as a directional edge, and the connection relationship between the directed device and the i-th device as a directed edge; The device importance evaluation value of the i-th device is calculated according to the following formula: Where, WD i N is the device importance evaluation value of the i-th device; (i) It is represented as the set of devices connected to the i-th device in the network directed graph model of the substation system; WD ini It is represented as the sum of the weights of all directed edges of the i-th device; WD outi It is represented as the sum of the weights of all directional edges of the i-th device; w ji It is represented as the weight of the jth directed edge of the ith device; w ij It is represented as the weight of the jth directional edge of the ith device; N in(i) Represented as the set of all devices directed by the i-th device; N out(i) Represented as the set of all directional devices of the i-th device.
5. The method for determining the seismic toughness of a substation based on data analysis according to claim 1, characterized in that: The repair order value of the faulty device is inversely proportional to the device repair priority p.
6. The method for determining the seismic toughness of a substation based on data analysis according to claim 1, characterized in that: Decision deployment time threshold t max Inversely proportional to the current functional status of the substation system F d , which is proportional to the complexity of the substation system.
7. The method for determining the seismic toughness of a substation based on data analysis according to claim 1 or 6, characterized in that: The complexity of the substation system is quantitatively characterized by the average degree of the logical topological relationship network between devices. The complexity of the substation system is proportional to the average degree of the logical topological relationship network between devices. The calculation formula of the average degree is: Where K represents the average degree of the logical topology network between devices; k m It is expressed as the number of devices connected to the mth device; M is the total number of devices.
8. A substation seismic resilience determination system based on data analysis, characterized in that: It includes indicator definition module, directed graph model construction module, simulation process variable acquisition module, and seismic toughness curve fitting module; The indicator definition module is used to define the substation system functional state F and the resilience evaluation index R, wherein the substation system functional state F is defined as the maximum allowable power transmission and transformation capacity of the substation system, and the resilience evaluation index R is the overall functional loss of the substation system after an earthquake; The directed graph model building module establishes a network directed graph model G(V, E) of the substation system according to the logical topological relationship between the substation layout and the equipment, wherein the state of the edge E is determined by the working state s of each device in the system, and the connectivity state between the nodes V is recorded and represented by the connection matrix C[x], based on which the functional relationship F=f(C[s]) between the substation system functional state F and the equipment state s is established; The simulation process variable acquisition module is used to determine the variables related to the substation system function loss and recovery simulation process, including the earthquake intensity range [a min ,a max ] and the current input earthquake intensity level a, equipment seismic vulnerability curve, equipment repair time distribution model, available repair resources and time step Δt; The seismic toughness curve fitting module is used to obtain the functional seismic toughness curve of the substation system and calculate the corresponding toughness evaluation index R. The calculation formula is: Where F0 represents the functional level of the substation before the earthquake; F(t) represents the functional level of the substation at time t; t0 is the time when the earthquake occurs; t e It is the moment when the substation fully recovers its functional level after an earthquake; The seismic toughness curve fitting module includes a current function status acquisition submodule, a decision deployment time acquisition submodule, a fault equipment repair sequence acquisition submodule, and an equipment status and function status update submodule; The current functional state acquisition submodule is used to obtain the current state vector s of the equipment in the system according to the current input earthquake intensity level a and the equipment seismic vulnerability curve d , and the current state vector s d Substitute into the functional relationship of step S2 to obtain the current functional status F of the substation system d ; The decision deployment time acquisition submodule is used to obtain the current functional state of the substation system according to the current functional state of the substation system. d The complexity of the substation system determines the decision deployment time threshold t max , where the decision deployment time threshold t max Inversely proportional to the current functional status of the substation system F d , which is proportional to the complexity of the substation system. The complexity of the substation system is quantitatively characterized by the average degree of the logical topological relationship network between devices. The complexity of the substation system is proportional to the average degree of the logical topological relationship network between devices. The calculation formula of the average degree is: Where K represents the average degree of the logical topology network between devices; k m It is expressed as the number of devices connected to the mth device; M is the total number of devices; The faulty equipment repair order acquisition submodule is used to determine the equipment repair priority p according to the equipment repair time distribution model and the equipment importance, generate the faulty equipment repair order π according to the equipment repair priority, and obtain the repair time of each faulty equipment by random sampling according to the equipment repair time distribution model and corresponding parameters, wherein the faulty equipment repair order value is inversely proportional to the equipment repair priority p, and the equipment importance acquisition process includes the following steps: Obtain all devices connected to the i-th device according to the constructed network directed graph model of the substation system; According to the logical topological relationship between the devices, the devices connected to the i-th device are divided into directional devices and directed devices; Define the connection relationship between the directional device and the i-th device as a directional edge, and the connection relationship between the directed device and the i-th device as a directed edge; The device importance evaluation value of the i-th device is calculated according to the following formula: Where, WD i N is the device importance evaluation value of the i-th device; (i) It is represented as the set of devices connected to the i-th device in the network directed graph model of the substation system; WD ini It is represented as the sum of the weights of all directed edges of the i-th device; WD outi It is represented as the sum of the weights of all directional edges of the i-th device; w ji It is represented as the weight of the jth directed edge of the ith device; w ij It is represented as the weight of the jth directional edge of the ith device; N in(i) Represented as the set of all devices directed by the i-th device; N out(i) Represented as the set of all directional devices of the i-th device; The steps for determining the equipment repair priority p include: The number of repetitions of the substation system function loss and restoration simulation process is set to Q; Get the functional level K of the substation when the i-th device is not repaired during the simulation process ip , and the functional level K' of the substation after the i-th device is repaired ip ; Obtain the repair time of the i-th device in the simulation process according to the equipment repair time distribution model; Calculate the repair efficiency index P of the i-th device based on the obtained parameters i , the calculation formula is: According to the network directed graph model of the constructed substation system, the equipment importance evaluation value WD of the i-th equipment is calculated. i ; The repair priority evaluation value f of the i-th device is calculated by the following formula i , the calculation formula is: f i =αp i +βWD i In the formula, α and β are constant coefficients, and 0.3<α<0.7; 0.3<β<0.7; α+β=1; The repair priority evaluation value of the equipment obtained is used as the representation of the equipment repair priority p The device status and function status update submodule is used to decompose the function recovery process according to the time step Δt, allocate available repair resources according to the faulty device repair order π, and update the device status s and the substation system function status F according to the repair time of the faulty device.
9. The substation seismic resilience determination system based on data analysis according to claim 8, characterized in that: The system further comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the steps of the method according to any one of claims 1 to 7 are implemented.
Citation Information
Cited By
Method and system for optimizing post-earthquake repair sequence of transformer substation
CN122222328A