Sand-carrying reservoir operation scheduling optimization method coupled with anti-regulation and storage engineering
Through the multi-sand reservoir operation scheduling optimization method of coupled reverse storage engineering, the water-sand dynamic model and water supply benefit maximization model are used to coordinate reservoir siltation and water supply demand, and the long-term safe operation and comprehensive benefits of the reservoir are achieved.
Patent Information
- Application Number
- CN202410934207.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2024-11-15
AI Technical Summary
During the high-sand river flow into the reservoir, the reservoir needs to take into account the need to slow down silt and flood control and water supply. The existing technology is difficult to effectively coordinate the contradiction between water supply and sand discharge, resulting in limited water supply capacity.
The multi-sand reservoir operation scheduling optimization method is adopted for the coupled reverse storage engineering. By collecting daily water and sand data, calculating the recurrence rate and runoff mode ratio coefficient, screening typical water and sand scenarios, and using the water and sand dynamics model to calculate the silt volume and silt in the reservoir area Remaining storage capacity, build a water supply benefit maximization model, determine the optimal water storage level and water supply allocation plan, and realize reasonable water and sand scheduling of the main storage-anti-reverse storage compound system.
It effectively resolved the contradiction between reservoir sand discharge and water supply, slowed down reservoir siltation, ensured the demand for Sansheng water supply (production, living, and ecological water supply), and improved the level of water supply guarantee.
Smart Images

Figure CN118966608A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of water conservancy projects and relates to an operation scheduling optimization method for a sand-laden reservoir coupled with a reverse regulation and storage project. Background Art
[0002] The arid areas in northwest my country are short of water resources and have a fragile ecological environment. Reservoirs built on high-sand-content rivers must not only try to slow down siltation, but also take into account flood control and water supply needs. During the period when high-sand-content floods enter the reservoir, in order to reduce siltation in the reservoir area and ensure long-term effective storage capacity, reservoirs are usually mainly used for open discharge and sand discharge. In this way, the water supply capacity will be limited, resulting in a contradiction between water supply and sand discharge. To solve the above problems, a common practice is to build a reverse regulation and storage project. In this way, during the reservoir sediment discharge period, the reverse regulation and storage project can be used for production and living water supply, thereby improving the water supply guarantee rate. Clarifying the mutual feedback process between the reservoir-reverse regulation and storage project and proposing a reasonable water and sediment dispatching method for the reservoir-reverse regulation and storage project composite system are of great significance to ensure the long-term safe operation of the reservoir, maximize the comprehensive benefits, and make full use of water resources in arid areas. Summary of the invention
[0003] The purpose of the present invention is to provide an optimization method for the operation and scheduling of a sediment-rich reservoir coupled with a reverse regulation and storage project, so as to coordinately resolve the contradictions among multiple objectives such as flood discharge and sediment removal, water supply, and ecological water demand during the operation period of the sediment-rich reservoir.
[0004] The technical solution adopted by the present invention is a method for optimizing the operation and dispatching of a sediment-rich reservoir coupled with a reverse regulation and storage project, and the specific operation steps are as follows:
[0005] Step 1: Collect daily water and sediment data, calculate the recurrence rate, runoff, or sediment transport modulus coefficient, and select three typical water and sediment scenarios based on the water and sediment abundance and drought characteristics;
[0006] Step 2: Substitute the typical water-sediment scenarios obtained in step 1 into the water-sediment dynamics model to calculate the water-sediment transport in the reservoir area under different water storage levels, so as to obtain the bed sedimentation elevation Z at the end of the reservoir operation. b , and then by querying the water level-sedimentation storage capacity curve, the sediment deposition amount and remaining storage capacity of the reservoir area under this working condition are obtained;
[0007] Step 3: Taking the remaining storage capacity obtained in step 2 as the adjustment condition, the corresponding maximum water supply, monthly water supply guarantee rate and destruction rate are solved through the water supply benefit maximization model;
[0008] Step 4: Based on the calculation results of steps 2 and 3, determine the operating water level corresponding to the situation where the water supply meets the standard and the siltation is minimized, which is the optimal water storage level.
[0009] The present invention is also characterized in that:
[0010] Step 1 is as follows:
[0011] Step 1.1: Based on the data from the upstream hydrological station in the reservoir area, obtain a long series of daily water and sediment inflow data, with a time scale of no less than ten years;
[0012] Step 1.2: Use the recurrence rate, runoff or sediment transport modulus ratio coefficient to evaluate the water and sediment abundance and drought characteristics; the runoff modulus ratio coefficient refers to the ratio of the annual runoff to the multi-year average net flow of the long sequence, see formula (1); the sediment transport modulus ratio coefficient refers to the ratio of the annual sediment transport to the multi-year average sediment transport of the long sequence, see formula (2); the recurrence rate refers to the percentage of the number of corresponding years within the range of the runoff modulus ratio coefficient or the sediment transport modulus ratio coefficient to the total number of years in the long sequence, see formula (3);
[0013] Runoff modulus ratio coefficient:
[0014] Sand transport modulus coefficient:
[0015] Reproducibility:
[0016] Where P W , P Ws , P are runoff modulus ratio coefficient, sediment transport modulus ratio coefficient, and recurrence rate respectively; W 典型 、Ws 典型 They are annual runoff and annual sediment transport respectively; are the long-term average runoff and sediment transport respectively; N is the total number of years in the long sequence; n i is the number of years within the range of runoff modulus ratio coefficient or sediment transport modulus ratio coefficient;
[0017] Step 1.3: Select three typical water and sediment scenarios based on the water and sediment abundance and drought characteristics;
[0018] ① If the recurrence rate is less than 37.5% and the runoff or sediment transport modulus coefficient is greater than 1.04, it means that the water and sediment characteristics are abundant in water and sediment;
[0019] ② If the recurrence rate is between 37.5% and 62.5%, and the runoff or sediment transport modulus ratio coefficient is between 0.97 and 1.04, it means that the water-sediment characteristics are flat and level;
[0020] ③ The recurrence rate is greater than 62.5% and the runoff or sediment transport modulus coefficient is less than 0.97, indicating that the water and sediment characteristics are low water and low sand.
[0021] Through the above operation, three typical water and sand years can be screened out from the long series of hydrological data, namely “abundant water and abundant sand, level water and level sand, and dry water and dry sand”.
[0022] Step 2 is as follows:
[0023] The three typical water and sediment scenarios obtained in step 1 are used as the water and sediment conditions for entering the reservoir, and the water and sediment dynamics model is used to calculate the sediment deposition in the reservoir area under a certain maximum water storage level; first, the hydraulic elements are solved according to the water flow control equation, and then the river-reservoir scouring and siltation patterns under the corresponding water flow conditions are deduced according to the sediment control equation, and then the river-reservoir scouring and siltation changes in a long period of time are obtained, and finally the remaining storage capacity is obtained.
[0024] Step 2.1: Select the governing equations for water-sediment dynamics
[0025] ① Water flow equation
[0026] Continuity equation:
[0027] Equations of motion:
[0028] In the formula, Q is the flow rate; A is the cross-sectional area of the water flow; Z is the water level; J is the energy slope; q L is the lateral inflow and outflow of the unit flow, where outflow is positive and inflow is negative; u L is the component of the lateral inlet and outlet flow velocity in the mainstream direction; x is the flow rate;
[0029] ② Sediment equation
[0030] Continuity equation:
[0031] Riverbed deformation equation:
[0032] Where S is the average sediment content of the section; ρ' is the dry bulk density of the sediment; A s is the cross-sectional erosion and deposition area; q s is the lateral inlet and outlet sediment transport rate per unit process; Z b is the bed elevation; t is the time; α is the recovery saturation coefficient; ω is the average vertical sinking velocity; S, S * are the average sediment content of the section and the sediment-carrying capacity of the water flow;
[0033] Step 2.2: Discretize the governing equations of water-sediment dynamics
[0034] The finite difference method is used to discretize the governing equations of water-sediment dynamics, and the river is divided into several sections along the course, so that the water flow in each section is close to uniform flow, and the section numbers increase from downstream to upstream.
[0035] ① Discreteness of water flow equations
[0036] Discrete continuity equation: Q i =Q i+1 -Q Li (8) Discrete equation of motion:
[0037] In the formula, Q Li is the inflow and outflow of the i-th river section, the outflow is positive and the inflow is negative; is the average cross-sectional area of the i-th river section; is the average hydraulic gradient of the ith river section;
[0038] ② Discreteness of sediment equation
[0039] Discrete continuity equation:
[0040] Discrete bed deformation equation:
[0041] In the formula, ΔZ bi is the elevation change of the upper surface erosion and siltation on section i;
[0042] Step 2.3: Define boundary conditions and set time step
[0043] ① The upstream inlet of the computational domain is located in the tailwater area of the reservoir, and the downstream outlet is located at the dam site of the reservoir;
[0044] ② Considering that water and sand are concentrated in the reservoir during the flood season, the time step during this period is set to day; in the non-flood season, the time step is set to ten days;
[0045] Step 2.4: Design multiple groups of operating water levels and set sand removal methods.
[0046] ① Calculate multiple groups of maximum water levels: design multiple groups of operating water levels according to the water level fluctuation range of 0.01 to 0.05 m to avoid missing the "optimal water level". To save the workload of trial calculation, the "operating water level range" can be roughly determined by referring to the normal water level in the reservoir planning and design stage.
[0047] ② Select the sediment discharge scheme in the reservoir planning and design stage as the sediment discharge method;
[0048] Step 2.5: Obtain the amount of sediment deposited in the reservoir
[0049] The three typical water-sediment scenarios obtained in step 1 are respectively substituted into the water-sediment dynamics model as the water-sediment inflow conditions, and the water-sediment transport calculation of the reservoir area under different operating water levels is performed to obtain the bed sedimentation elevation Z at the end of the reservoir operation under different working conditions. b ; Finally, by querying the water level-sedimentation storage capacity curve, the sediment deposition amount and remaining storage capacity of the reservoir under different working conditions are obtained.
[0050] Step 3 is as follows:
[0051] Under the three typical water and sediment inflow scenarios in step 1, the remaining storage capacity at different operating water levels obtained in step 2 is used as the adjustment condition. By carrying out the optimization calculation of reservoir water supply, the reasonable allocation of water supply between the main reservoir and the counter-regulation reservoir is achieved. The specific operation process is as follows:
[0052] (1) Constructing a water supply benefit maximization model
[0053] The water supply benefit maximization model involves decision variables, objective functions, and constraints;
[0054] ①Decision variables
[0055] Water supply flow x j,t is the decision variable, where j=1, 2 are the reservoir and reverse regulation project respectively; t=1, 2, 3, ···, N is the regulation period;
[0056] ②Objective function
[0057] maxW=∑(x j,t ×Δt) (12)
[0058] Where W is the combined water supply of the reservoir and the reverse regulation and storage project; x j,t is the water supply flow in the tth period; Δt is the time step;
[0059] ③ Constraints
[0060] Water balance: V j,t+1 =V j,t +(Q j,t -x j,t -W j,t -E j,t )×Δt (13)
[0061] Water storage capacity: V j,min ≤V j,t ≤V j,max (14)
[0062] Water supply capacity: x j,t ≤x max (15)
[0063] Equal flow water supply: x j,t =x j,t+1 (16)
[0064] Sand discharge period limit: x 1,t =0 (17)
[0065] Ecological water demand: W j,t ≥W 生态 (18)
[0066] Daily variation of reservoir water level:
[0067] ΔZ≤8m (19)
[0069] Where V j,t and V j,t+1 are the water storage capacity of each reservoir at the beginning of the tth period and the beginning of the t+1th period respectively; Q j,t , W j,t 、E j,t are the inflow, abandoned water flow and loss flow in the tth period respectively; V j,min and V j,max are the minimum and maximum water storage capacity of each reservoir respectively; x max is the design flow of the water supply pipeline; ΔZ is the daily reduction of the water level in the reservoir area;
[0070] (2) Solving the water supply benefit maximization model
[0071] Under different inflow water and sediment conditions, the remaining storage capacity at the end of the reservoir operation is used as the regulating storage capacity. The reservoir water supply allocation plan under a certain operating water level is determined according to the water supply benefit maximization model to obtain the corresponding maximum water supply and monthly water supply guarantee rate and destruction rate; among which, the monthly water supply guarantee rate P and the destruction rate d should meet the relevant requirements, and their definitions are shown in formulas (20) and (21);
[0072] Monthly water supply guarantee rate:
[0073] Destruction rate:
[0074] Where M is the designed water supply period; N is the actual water supply period; W ts W is the designed water supply in the tth period; t is the actual water supply in the tth period.
[0075] The beneficial effects of the present invention are as follows: for reservoirs on sediment-rich rivers, based on multi-objective optimization theory, a reasonable water-sediment dispatching method for a main reservoir-counter-regulation reservoir composite system is proposed, which can effectively solve the contradiction between reservoir sediment discharge and water supply, which has important supporting value for slowing down reservoir siltation and ensuring water supply for production, life, and ecology, and obtains a reservoir operation dispatching optimization method that takes into account the two key requirements of "slowing down reservoir siltation" and "ensuring water supply targets". BRIEF DESCRIPTION OF THE DRAWINGS
[0076] Figure 1 The distribution positions of the Tingkou Reservoir and the Zhongyuangou Counter-Regulation Reservoir in Example 3 of the present invention;
[0077] Figure 2 It is the mutual feedback between the Tingkou Reservoir and the Zhongyuangou counter-regulation reservoir in Example 3 of the present invention;
[0078] Figure 3 It is the relationship curve between the maximum water storage level and the water supply under different working conditions of Example 3 of the present invention. DETAILED DESCRIPTION
[0079] The present invention is further described in detail below in conjunction with embodiments and drawings, but the embodiments of the present invention are not limited thereto.
[0080] Example 1
[0081] The method for optimizing the operation and dispatching of a sediment-rich reservoir in a coupled reverse regulation and storage project of the present invention is as follows:
[0082] Step 1: Collect daily water and sediment data, calculate the recurrence rate, runoff, or sediment transport modulus coefficient, and select three typical water and sediment scenarios based on the water and sediment abundance and drought characteristics;
[0083] Step 2: Substitute the typical water-sediment scenarios obtained in step 1 into the water-sediment dynamics model to calculate the water-sediment transport in the reservoir area under different water storage levels, so as to obtain the bed sedimentation elevation Z at the end of the reservoir operation. b , and then by querying the water level-sedimentation storage capacity curve, the sediment deposition amount and remaining storage capacity of the reservoir area under this working condition are obtained;
[0084] Step 3: Taking the remaining storage capacity obtained in step 2 as the adjustment condition, solve the corresponding maximum water supply and the monthly water supply guarantee rate and destruction rate;
[0085] Step 4: Based on the calculation results of steps 2 and 3, determine the operating water level corresponding to the situation where the water supply meets the standard and the siltation is minimized, which is the optimal water storage level.
[0086] Example 2
[0087] Based on Example 1,
[0088] Step 1 is as follows:
[0089] Step 1.1: Based on the data from the upstream hydrological station in the reservoir area, obtain a long series of daily water and sediment inflow data, with a time scale of no less than ten years;
[0090] Step 1.2: Use the recurrence rate, runoff or sediment transport modulus ratio coefficient to evaluate the water and sediment abundance and drought characteristics; the runoff modulus ratio coefficient refers to the ratio of the annual runoff to the multi-year average net flow of the long sequence, see formula (1); the sediment transport modulus ratio coefficient refers to the ratio of the annual sediment transport to the multi-year average sediment transport of the long sequence, see formula (2); the recurrence rate refers to the percentage of the number of corresponding years within the range of the runoff modulus ratio coefficient or the sediment transport modulus ratio coefficient to the total number of years in the long sequence, see formula (3);
[0091] Runoff modulus ratio coefficient:
[0092] Sand transport modulus coefficient:
[0093] Reproducibility:
[0094] Where P W , P Ws , P are runoff modulus ratio coefficient, sediment transport modulus ratio coefficient, and recurrence rate respectively; W 典型 、Ws 典型 They are annual runoff and annual sediment transport respectively; are the long-term average runoff and sediment transport respectively; N is the total number of years in the long sequence; n i is the number of years within the range of runoff modulus ratio coefficient or sediment transport modulus ratio coefficient;
[0095] Step 1.3: Select three typical water and sediment scenarios based on the water and sediment abundance and drought characteristics;
[0096] If the recurrence rate is less than 37.5% and the runoff or sediment transport modulus ratio coefficient is greater than 1.04, it means that the water and sediment characteristics are abundant in water and sediment;
[0097] If the recurrence rate is between 37.5% and 62.5% and the runoff or sediment transport modulus ratio coefficient is between 0.97 and 1.04, it means that the water-sediment characteristics are flat and level;
[0098] A recurrence rate greater than 62.5% and a runoff or sediment transport modulus coefficient less than 0.97 indicate that the water-sediment characteristics are low water and low sand.
[0099] The typical water and sediment scenarios obtained in step 1 are used as the water and sediment conditions for entering the reservoir, and the water and sediment dynamics model is used to calculate the sediment deposition in the reservoir area under a certain maximum water storage level; first, the hydraulic elements are solved according to the water flow control equation, and then the river-reservoir scouring and siltation patterns under the corresponding water flow conditions are deduced according to the sediment control equation, and then the river-reservoir scouring and siltation changes in a long period of time are obtained, and finally the remaining storage capacity is obtained.
[0100] Step 2 is as follows:
[0101] Step 2.1: Select the governing equations for water-sediment dynamics
[0102] ① Water flow equation
[0103] Continuity equation:
[0104] Equations of motion:
[0105] In the formula, Q is the flow rate; A is the cross-sectional area of the water flow; Z is the water level; J is the energy slope; q L is the lateral inflow and outflow of the unit flow, where outflow is positive and inflow is negative; uL is the component of the lateral inlet and outlet flow velocity in the mainstream direction; x is the flow rate;
[0106] ② Sediment equation
[0107] Continuity equation:
[0108] Riverbed deformation equation:
[0109] Where S is the average sediment content of the section; ρ' is the dry bulk density of the sediment; A s is the cross-sectional erosion and deposition area; q s is the lateral inlet and outlet sediment transport rate per unit process; Z b is the bed elevation; t is the time; α is the recovery saturation coefficient; ω is the average vertical sinking velocity; S, S * are the average sediment content of the section and the sediment-carrying capacity of the water flow;
[0110] Step 2.2: Discretize the governing equations of water-sediment dynamics
[0111] The finite difference method is used to discretize the governing equations of water-sediment dynamics, and the river is divided into several sections along the course, so that the water flow in each section is close to uniform flow, and the section numbers increase from downstream to upstream.
[0112] ① Discreteness of water flow equations
[0113] Discrete continuity equation: Q i =Q i+1 -Q Li (8) Discrete equation of motion:
[0114] In the formula, Q Li is the inflow and outflow of the i-th river section, the outflow is positive and the inflow is negative; is the average cross-sectional area of the i-th river section; is the average hydraulic gradient of the ith river section;
[0115] ② Discreteness of sediment equation
[0116] Discrete continuity equation:
[0117] Discrete bed deformation equation:
[0118] In the formula, ΔZ bi is the elevation change of the upper surface erosion and siltation on section i;
[0119] Step 2.3: Define boundary conditions and set time step
[0120] ① The upstream inlet of the computational domain is located in the tailwater area of the reservoir, and the downstream outlet is located at the dam site of the reservoir;
[0121] ② Considering that water and sand are concentrated in the reservoir during the flood season, the time step during this period is set to day; in the non-flood season, the time step is set to ten days;
[0122] Step 2.4: Design multiple groups of operating water levels and set sand removal methods.
[0123] ① Calculate multiple groups of maximum water levels: design multiple groups of operating water levels according to the water level fluctuation range of 0.01 to 0.05 m to avoid missing the "optimal water level". To save the workload of trial calculation, the "operating water level range" can be roughly determined by referring to the normal water level in the reservoir planning and design stage.
[0124] ② Select the sediment discharge scheme in the reservoir planning and design stage as the sediment discharge method;
[0125] Step 2.5: Obtain the amount of sediment deposited in the reservoir
[0126] The three typical water-sediment scenarios obtained in step 1 are respectively substituted into the water-sediment dynamics model as the water-sediment inflow conditions, and the water-sediment transport calculation of the reservoir area under different operating water levels is performed to obtain the bed sedimentation elevation Z at the end of the reservoir operation under different working conditions. b ; Finally, by querying the water level-sedimentation storage capacity curve, the sediment deposition amount and remaining storage capacity of the reservoir under different working conditions are obtained.
[0127] Step 3 is as follows:
[0128] Under the three typical water and sediment inflow scenarios in step 1, the remaining storage capacity at different operating water levels obtained in step 2 is used as the adjustment condition. By carrying out the optimization calculation of reservoir water supply, the reasonable allocation of water supply between the main reservoir and the counter-regulation reservoir is achieved. The specific operation process is as follows:
[0129] (2) Constructing a water supply benefit maximization model
[0130] The water supply benefit maximization model involves decision variables, objective functions, and constraints;
[0131] ①Decision variables
[0132] Water supply flow x j,t is the decision variable, where j=1, 2 are the reservoir and reverse regulation project respectively; t=1, 2, 3, ···, N is the regulation period;
[0133] ②Objective function
[0134] maxW=∑(x j,t ×Δt) (12)
[0135] Where W is the combined water supply of the reservoir and the reverse regulation and storage project; xj,t is the water supply flow in the tth period; Δt is the time step;
[0136] ③ Constraints
[0137] Water balance: V j,t+1 =V j,t +(Q j,t -x j,t -W j,t -E j,t )×Δt (13)
[0138] Water storage capacity: V j,min ≤V j,t ≤V j,max (14)
[0139] Water supply capacity: x j,t ≤x max (15)
[0140] Equal flow water supply: x j,t =x j,t+1 (16)
[0141] Sand discharge period limit: x 1,t =0 (17)
[0142] Ecological water demand: W j,t ≥W 生态 (18)
[0143] Daily variation of reservoir water level:
[0144] ΔZ≤8m (19)
[0146] Where V j,t and V j,t+1 are the water storage capacity of each reservoir at the beginning of the tth period and the beginning of the t+1th period respectively; Q j,t , W j,t 、E j,t are the inflow, abandoned water flow and loss flow in the tth period respectively; V j,min and V j,max are the minimum and maximum water storage capacity of each reservoir respectively; x max is the design flow of the water supply pipeline; ΔZ is the daily reduction of the water level in the reservoir area;
[0147] (2) Solving the water supply benefit maximization model
[0148] Under different inflow water and sediment conditions, the remaining storage capacity at the end of the reservoir operation is used as the regulating storage capacity. The reservoir water supply allocation plan under a certain operating water level is determined according to the water supply benefit maximization model to obtain the corresponding maximum water supply and monthly water supply guarantee rate and destruction rate; among which, the monthly water supply guarantee rate P and the destruction rate d should meet the relevant requirements, and their definitions are shown in formulas (20) and (21);
[0149] Monthly water supply guarantee rate:
[0150] Destruction rate:
[0151] Where M is the designed water supply period; N is the actual water supply period; W ts W is the designed water supply in the tth period; t is the actual water supply in the tth period.
[0152] Example 3
[0153] The present invention discloses an optimization method for operation and dispatching of a sediment-rich reservoir coupled with a reverse regulation and storage project, which is used to solve the contradiction between sediment discharge and water supply in sediment-rich reservoirs in arid areas of Northwest China. In order to verify the feasibility of the present invention, the Tingkou Reservoir and the Zhongyuangou reverse regulation and storage project are taken as examples for calculation.
[0154] Tingkou Water Conservancy Project is located 2 km upstream from the mouth of Heihe River, a first-level tributary of Jinghe River in Changwu County, Xianyang City (see Figure 1 ), including Tingkou Reservoir, Zhongyuangou Counter-regulation and Storage Project and Water Transmission and Distribution Project. Among them, the dam type of Tingkou Reservoir is a homogeneous earth dam with a total storage capacity of 247 million m 3 The normal water storage level is 893.0m; the dam type of Zhongyuangou counter-regulation reservoir is a homogeneous earth dam with a total storage capacity of 9.86 million m 3 , Xingli reservoir capacity 7 million m 3 , the normal water level is 920.3m; the number of installed units of the counter-regulation pump station is 3, and the maximum pumping flow is 1.1m 3 / s, net head 62.0m. The water conservancy hub is mainly used for industrial and urban water supply, and also has benefits such as flood control and power generation. In order to adapt to the sandy characteristics of the Heihe River, the Tingkou Reservoir is used in a "storing clear water and discharging turbid water" manner, that is, there is a sediment discharge period. Due to the limited water supply capacity of the Tingkou Reservoir during the sediment discharge period and the dry season, a reverse regulation and storage project was built at the mouth of the Zhongyuangou ditch to achieve joint water supply from the two reservoirs, greatly improving the water supply security level in the area. The mutual feedback process between the Tingkou Reservoir and the Zhongyuangou reverse regulation reservoir is as follows Figure 2 shown.
[0155] The optimization process of water and sediment dispatching mode of Tingkou Reservoir coupled with Zhongyuangou counter-regulation reservoir is as follows:
[0156] Step 1: Select representative series of incoming water and sand
[0157] (1) Collecting long-term daily water and sediment data
[0158] Gansu Province plans to build two reservoirs, Xinji and Pankou, upstream of the Tingkou Water Conservancy Project, with an annual total water supply of 22 million m 3 The construction of the two reservoirs will inevitably have a certain impact on the flood control and water supply scheduling of the Tingkou Reservoir. However, the water and sediment data used in the planning and design stage of the Tingkou Reservoir did not take into account the impact of the two reservoirs, and therefore could not truly reflect the future water and sediment conditions of the Tingkou Reservoir. In response to this problem, the following method was used to calculate the daily water and sediment process of the Tingkou Reservoir (1954-2014) considering the impact of the two reservoirs.
[0159] ① Daily water and sediment process without considering the impact of the two reservoirs
[0160] Tingkou Hydrological Station is located downstream of Tingkou Reservoir, and its water and sediment data can basically serve as the water and sediment conditions for Tingkou Reservoir. However, Tingkou Station lacks water and sediment data from 2009 to 2014, so it is necessary to interpolate and extend the water and sediment series of Tingkou Station. Here, Zhanghe Hydrological Station is used as a reference station. First, the ratio of "the catchment area of Tingkou Station and the catchment area of Zhanghe Station" is obtained by the area analogy method, and then the water and sediment series of Zhanghe Station from 2009 to 2014 is multiplied by the proportional coefficient to obtain the daily water and sediment process of Tingkou Station from 2009 to 2014. Finally, combined with the existing measured data of Tingkou Station, the daily water and sediment process of Tingkou Station from 1954 to 2014 without considering the influence of the two reservoirs is obtained.
[0161] ② Daily water and sediment process considering the influence of the two reservoirs
[0162] The monthly water volume process of Tingkou Station from 1975 to 2008 considering the influence of the two reservoirs is known. Based on the assumption that "only the water volume of the two reservoirs is deducted while the sediment volume remains unchanged",
[0163] a. Calculate the ratio between the "monthly average water volume process from 1975 to 2008 considering the impact of the two reservoirs" and the "monthly average water volume process from 1975 to 2008 without considering the impact of the two reservoirs", and then multiply the "daily runoff process from 1975 to 2008 in step ①" by the proportional coefficient to perform equal time scaling to obtain the daily water and sediment process from 1975 to 2008 considering the impact of the two reservoirs;
[0164] b. Using the proportional coefficient between the “multi-year average runoff from 1975 to 2008 considering the impact of the two reservoirs” and the “multi-year average runoff from 1975 to 2008 without considering the impact of the two reservoirs”, the “daily runoff process without considering the impact of the two reservoirs” in the two periods of 1954 to 1974 and 2009 to 2014 were scaled to obtain the corresponding daily water and sediment process.
[0165] c. Combining steps a and b, the daily water and sediment inflow process from 1954 to 2014 (a total of 61 years) considering the impact of the two reservoirs is obtained.
[0166] (2) Screening of representative series of water and sand entering the reservoir
[0167] Three typical water and sediment scenarios of "abundant sediment in high water, flat sediment in low water, and low sediment in low water" were selected from the long series of water and sediment from 1954 to 2014 as the water and sediment conditions for entering the reservoir. First, the runoff (or sediment transport) modulus ratio coefficient of each year was calculated, and then the annual variation curve of the runoff (or sediment transport) modulus ratio coefficient was drawn. Then, referring to the standards in Table 1, the water and sediment characteristic combinations that met the requirements of the recurrence rate and runoff (or sediment transport) modulus ratio coefficient were selected. The specific results are shown in Table 2.
[0168] Table 1
[0169]
[0170] Table 2
[0171]
[0172] Step 2: Calculation of sediment erosion and deposition
[0173] The water-sediment dynamics model was used to calculate the silt scouring and silting under different inflow conditions (see Table 2). Referring to the plan in the planning and design stage, the sediment discharge method of Tingkou Reservoir was set as "sediment discharge during flood season". Specifically, during the flood season from July to August, when the inflow is greater than 30m 3 / s and the sand content is greater than 50kg / m 3 When the reservoir is at low water level or empty, the reservoir is open for sediment discharge. When the water and sediment entering the reservoir do not meet the immediate sediment discharge conditions, the reservoir is stored and used; during the flood season from September to June of the following year, the reservoir can be used to discharge sediment by taking advantage of the high-sediment-content flood entering the reservoir under the premise of meeting the water supply. Considering that the water and sediment enter the reservoir area from July to September during the flood season, the time step of this period is set to days, while in the non-flood season from October to June of the following year, the time step is set to ten days. Through sediment scouring and sedimentation calculation, the riverbed sedimentation elevation after the reservoir is operated at a certain maximum water storage level under different inflow water and sediment conditions can be obtained. By querying the water level-sedimentation storage capacity curve of Tingkou Reservoir, the sediment deposition amount and remaining storage capacity of the reservoir area under this working condition can be obtained. In order to save space, only the sediment deposition amount and remaining storage capacity under different maximum water storage levels after the initial operation of the reservoir for one year under the flood and sediment scenario are shown here, as shown in Table 3.
[0174] Table 3
[0175]
[0176] Step 3: Optimize the maximum water supply of the reservoir
[0177] The constructed objective function of "maximizing the water supply benefit of the composite system" (i.e., formula (12)) is used to carry out the optimization calculation of water allocation. The water-sediment series obtained in step 1 and the remaining storage capacity obtained in step 2 are taken as known conditions. Based on the principle of water balance and under the "mutual feedback between reservoirs and reverse regulation and storage projects", the water supply of each reservoir is reasonably allocated according to the constraints (i.e., formulas (13) to (19)). The water supply method follows the principle of "priority water supply from Tingkou Reservoir, auxiliary water supply from counter-regulation reservoir, and priority to ecological water use". Specifically: ① If the maximum water supply of Tingkou Reservoir in a certain period of time is greater than the actual water demand of the water supply object, then Tingkou Reservoir will directly "supply water on demand", and at the same time, the counter-regulation reservoir will extract and store the surplus water in Tingkou Reservoir according to the pumping capacity of the pumping station. This is because the monthly net flow of Tingkou Reservoir is unevenly distributed throughout the year, so as much surplus water as possible in the flood season should be pumped into the counter-regulation reservoir; ② If the water supply capacity of Tingkou Reservoir in a certain period of time is less than the actual water demand of the water supply object, water will be supplied first according to the water supply limit of Tingkou Reservoir, and the insufficient part will be supplemented by the counter-regulation reservoir; ③ The designed monthly water supply guarantee rate is ≥90% and the maximum damage depth is ≤20%; ④ In dry years, water supply is given priority after the flood season without considering the sediment discharge of the camera-induced abnormal density flow; ⑤ Restrict the pumping pipeline (maximum pumping flow 1.1m 3 / s) The sediment content in the water body, that is, the sediment content in the water body shall not exceed 8kg / m 3 , otherwise stop pumping. By carrying out runoff regulation calculations, the maximum water supply of the composite system under different working conditions can be obtained. To save space, only the maximum water supply, water supply guarantee rate and damage depth under different maximum water levels after the initial operation of the reservoir for one year under the flood and sediment scenario are shown here (see Table 3), where the water supply target is set at 30 million m 3 .
[0178] Step 4: Determine the reservoir operation scheduling plan
[0179] Based on the calculation results of step 2 and step 3, the siltation and maximum water supply under different maximum water storage levels are analyzed and compared. The maximum water storage level corresponding to the conditions that meet multiple objectives such as "water supply meets the standard, water supply guarantee rate meets the standard, damage depth is safe, and reservoir siltation is minimal" is selected as the optimal operating water level. The sediment discharge method and water supply allocation plan behind it are reasonable water and sediment scheduling modes. According to Table 3, for the initial operation of the reservoir under the conditions of abundant water and sediment for one year, the water supply target of 30 million m3 can be met. 3 , the monthly water supply guarantee rate is ≥90% and the maximum damage depth is ≤20%, and the maximum water storage level with the minimum siltation is 867.7m (that is, the optimal water storage level or the optimal operating water level). That is to say, under this operating water level, the reservoir can not only meet the water supply demand to the maximum extent, but also minimize the siltation.
[0180] Based on the above method, Table 4 summarizes the scouring and silting, water supply conditions and optimal operating water levels corresponding to different water and sediment conditions and different water supply targets. Figure 3 The relationship curve between the optimal water storage level and the available water volume under different working conditions is plotted. It can be seen that under the same water supply target, the richer the water and sediment conditions, the larger the corresponding optimal water storage level, but the difference in their values is not obvious. Therefore, the optimal water storage level corresponding to the limit state of abundant water and abundant sediment can be used as the reservoir operating water level threshold; that is, no matter what the water and sediment conditions are, as long as the optimal water storage level of the reservoir reaches 867.7m, 871.0m, and 884.4m respectively, it can meet the 30 million m 3 40 million m 3 , 50 million m 3 The water supply target is achieved. In addition, the siltation in the reservoir area is minimal under this water level condition. According to the above analysis, the optimal operating water level can not only effectively delay reservoir siltation, but also meet the water supply requirements to the maximum extent. The sediment discharge principle (see step 2 of embodiment 2) and water supply principle (see step 3 of embodiment 2) behind it can be regarded as a reasonable water and sediment scheduling mode.
[0181] Table 4
[0182]
[0183] The above description is only a partial implementation case of the present invention. The application of the present invention is not limited to this specific implementation. All specific extensions of the method of the present invention, without departing from the scope of protection of the present invention and the claims, are within the protection scope of the present invention.
Claims
1. A method for optimizing the operation and dispatching of a sediment-rich reservoir coupled with a reverse regulation and storage project, characterized in that: The details are as follows: Step 1: Collect daily water and sediment data, calculate the recurrence rate, runoff, or sediment transport modulus coefficient, and select three typical water and sediment scenarios based on the water and sediment abundance and drought characteristics; Step 2: Substitute the typical water-sediment scenarios obtained in step 1 into the water-sediment dynamics model to calculate the water-sediment transport in the reservoir area under different water storage levels, so as to obtain the bed sedimentation elevation Z at the end of the reservoir operation. b , and then by querying the water level-sedimentation storage capacity curve, the sediment deposition amount and remaining storage capacity of the reservoir area under this working condition are obtained; Step 3: Taking the remaining storage capacity obtained in step 2 as the adjustment condition, solve the corresponding maximum water supply and the monthly water supply guarantee rate and destruction rate; Step 4: Based on the calculation results of steps 2 and 3, determine the operating water level corresponding to the situation where the water supply meets the standard and the siltation is minimized, which is the optimal water storage level.
2. The method for optimizing the operation and dispatching of a sediment-rich reservoir for a coupled reverse regulation and storage project according to claim 1, characterized in that: Step 1 is as follows: Step 1.1: Based on the data from the upstream hydrological station in the reservoir area, obtain a long series of daily water and sediment inflow data, with a time scale of no less than ten years; Step 1.2: Use the recurrence rate, runoff or sediment transport modulus ratio coefficient to evaluate the water and sediment abundance and drought characteristics; the runoff modulus ratio coefficient refers to the ratio of the annual runoff to the multi-year average net flow of the long sequence, see formula (1); the sediment transport modulus ratio coefficient refers to the ratio of the annual sediment transport to the multi-year average sediment transport of the long sequence, see formula (2); the recurrence rate refers to the percentage of the number of corresponding years within the range of the runoff modulus ratio coefficient or the sediment transport modulus ratio coefficient to the total number of years in the long sequence, see formula (3); Runoff modulus ratio coefficient: Sand transport modulus coefficient: Reproducibility: Where P W , P Ws , P are runoff modulus ratio coefficient, sediment transport modulus ratio coefficient, and recurrence rate respectively; W 典型 、Ws 典型 They are annual runoff and annual sediment transport respectively; are the long-term average runoff and sediment transport respectively; N is the total number of years in the long series; n i is the number of years within the range of runoff modulus ratio coefficient or sediment transport modulus ratio coefficient; Step 1.3: Select three typical water and sediment scenarios based on the water and sediment abundance and drought characteristics; If the recurrence rate is less than 37.5% and the runoff or sediment transport modulus ratio coefficient is greater than 1.04, it means that the water and sediment characteristics are abundant in water and sediment; If the recurrence rate is between 37.5% and 62.5% and the runoff or sediment transport modulus ratio coefficient is between 0.97 and 1.04, it means that the water-sediment characteristics are flat and level; A recurrence rate greater than 62.5% and a runoff or sediment transport modulus coefficient less than 0.97 indicate that the water-sediment characteristics are low water and low sand.
3. The method for optimizing the operation and dispatching of a sediment-rich reservoir for a coupled reverse regulation and storage project according to claim 1, characterized in that: The typical water and sediment scenarios obtained in step 1 are used as the water and sediment conditions for entering the reservoir, and the water and sediment dynamics model is used to calculate the sediment deposition in the reservoir area under a certain maximum water storage level; first, the hydraulic elements are solved according to the water flow control equation, and then the river-reservoir scouring and siltation patterns under the corresponding water flow conditions are deduced according to the sediment control equation, and then the river-reservoir scouring and siltation changes in a long period of time are obtained, and finally the remaining storage capacity is obtained.
4. The method for optimizing the operation and dispatching of a sediment-rich reservoir for a coupled reverse regulation and storage project according to claim 3 is characterized in that: Step 2 is as follows: Step 2.1: Select the governing equations for water-sediment dynamics ① Water flow equation Continuity equation: Equations of motion: In the formula, Q is the flow rate; A is the cross-sectional area of the water flow; Z is the water level; J is the energy slope; q L is the lateral inflow and outflow of the unit flow, where outflow is positive and inflow is negative; u L is the component of the lateral inlet and outlet flow velocity in the mainstream direction; x is the flow rate; ② Sediment equation Continuity equation: Riverbed deformation equation: In the formula, S is the average sediment content of the section; ρ' is the dry bulk density of the sediment; A s is the cross-sectional scouring and silting area; q s is the lateral inlet and outlet sediment transport rate per unit process; Z b is the bed elevation; t is the time; α is the recovery saturation coefficient; ω is the vertical average sinking velocity; S, S * are the average sediment content of the section and the sediment-carrying capacity of the water flow; Step 2.2: Discretize the governing equations of water-sediment dynamics The finite difference method is used to discretize the governing equations of water-sediment dynamics, and the river is divided into several sections along the course, so that the water flow in each section is close to uniform flow, and the section numbers increase from downstream to upstream. ① Discreteness of water flow equations Discrete continuity equation: Q i =Q i+1 -Q Li (8) Discrete equations of motion: In the formula, Q Li is the inflow and outflow of the i-th river section, the outflow is positive and the inflow is negative; is the average cross-sectional area of the i-th river section; is the average hydraulic gradient of the ith river section; ② Discreteness of sediment equation Discrete continuity equation: Discrete bed deformation equation: In the formula, ΔZ bi is the elevation change of the upper surface erosion and siltation on section i; Step 2.3: Define boundary conditions and set time step ① The upstream inlet of the computational domain is located in the tailwater area of the reservoir, and the downstream outlet is located at the dam site of the reservoir; ② Considering that water and sand are concentrated in the reservoir during the flood season, the time step during this period is set to day; in the non-flood season, the time step is set to ten days; Step 2.4: Design multiple groups of operating water levels and set sand removal methods. ① Calculate multiple groups of maximum water storage levels: design multiple groups of operating water levels according to the water level fluctuation range of 0.01 to 0.05 m; ② Select the sediment discharge scheme in the reservoir planning and design stage as the sediment discharge method; Step 2.5: Obtain the amount of sediment deposited in the reservoir The three typical water-sediment scenarios obtained in step 1 are respectively substituted into the water-sediment dynamics model as the water-sediment inflow conditions, and the water-sediment transport calculation of the reservoir area under different operating water levels is performed to obtain the bed sedimentation elevation Z at the end of the reservoir operation under different working conditions. b ; Finally, by querying the water level-sedimentation storage capacity curve, the sediment deposition amount and remaining storage capacity of the reservoir under different working conditions are obtained.
5. The method for optimizing the operation and dispatching of a sediment-rich reservoir for a coupled reverse regulation and storage project according to claim 4 is characterized in that: Step 3 is as follows: Under the three typical water and sediment inflow scenarios in step 1, the remaining storage capacity at different operating water levels obtained in step 2 is used as the adjustment condition. By carrying out the optimization calculation of reservoir water supply, the reasonable allocation of water supply between the main reservoir and the counter-regulation reservoir is achieved. The specific operation process is as follows: (3) Constructing a water supply benefit maximization model The water supply benefit maximization model involves decision variables, objective functions, and constraints; ①Decision variables Water supply flow x j,t is the decision variable, where j=1, 2 are the reservoir and reverse regulation project respectively; t=1, 2, 3, ···, N is the regulation period; ②Objective function max W=∑(x j,t ×Δt) (12) Where W is the combined water supply of the reservoir and the reverse regulation and storage project; x j,t is the water supply flow in the tth period; Δt is the time step; ③ Constraints Water balance: V j,t+1 =V j,t +(Q j,t -x j,t -W j,t -E j,t )×Δt (13) Water storage capacity: V j,min ≤V j,t ≤V j,max (14) Water supply capacity: x j,t ≤x max (15) Equal flow water supply: x j,t =x j,t+1 (16) Sand discharge period limit: x 1,t =0 (17) Ecological water demand: W j,t ≥W 生态 (18) Daily variation of reservoir water level: ΔZ≤8m (19) Where V j,t and V j,t+1 are the water storage capacity of each reservoir at the beginning of the tth period and the beginning of the t+1th period respectively; Q j,t , W j,t 、E j,t are the inflow, abandoned water flow and loss flow in the tth period respectively; V j,min and V j,max are the minimum and maximum water storage capacity of each reservoir respectively; x max is the design flow of the water supply pipeline; ΔZ is the daily reduction of the water level in the reservoir area; (2) Solving the water supply benefit maximization model Under different inflow water and sediment conditions, the remaining storage capacity at the end of the reservoir operation is used as the regulating storage capacity. The reservoir water supply allocation plan under a certain operating water level is determined according to the water supply benefit maximization model to obtain the corresponding maximum water supply and monthly water supply guarantee rate and destruction rate; among them, the monthly water supply guarantee rate P and the destruction rate d should meet the relevant requirements, and their definitions are shown in formulas (20) and (21); Monthly water supply guarantee rate: Destruction rate: Where M is the designed water supply period; N is the actual water supply period; W ts W is the designed water supply in the tth period; t is the actual water supply in the tth period.