Production material preparation scheduling method, device and equipment and storage medium
Through automated calculations and scheduling, the problem of inconsistency between material preparation and production plan caused by traditional manual material preparation and scheduling is solved, and the close connection between material preparation and production plan is achieved, production efficiency and resource utilization efficiency are improved, and inventory costs and risks are reduced.
Patent Information
- Application Number
- CN202411025517.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-11-15
AI Technical Summary
Traditional material preparation schedules rely on manual operations, which can easily lead to inconsistent material preparation results with product production plans, resulting in a risk of lower production efficiency and normal operation of the production line.
By obtaining material inventory information and information about the products to be processed in the production line, calculate the required and available time for preparation of each product batch, determine the different working hours of preparation, and automatically schedule the preparation work based on the different working hours to ensure the preparation and production plan. Closely connected.
It effectively reduces the shutdown caused by unfinished material preparation, improves the overall efficiency of the production line, ensures smooth production process, reasonably allocates resources, and reduces inventory costs and risks.
Smart Images

Figure CN118966664A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of production and manufacturing technology, and specifically to a production material preparation scheduling method, device, equipment and storage medium. Background Art
[0002] In modern manufacturing, product material preparation scheduling is a key link to ensure smooth production processes and improve production efficiency. However, traditional material preparation scheduling often relies on manual operations. Although this method is flexible, it also has many shortcomings. Among them, the most important problem is that manual scheduling can easily lead to inconsistencies between material preparation results and product production plans.
[0003] Specifically, when manually scheduling material preparation, operators need to consider multiple complex factors, such as the specific requirements of the production plan, the actual status of the current inventory, and the supplier's delivery time. In this process, operators must accurately grasp every detail to ensure that the material preparation plan matches the production needs. However, due to the limitations of human judgment and memory, this scheduling method that relies on manual labor is often difficult to avoid errors and delays. Once the material preparation results deviate from the product production plan, it may trigger a chain reaction, resulting in a decrease in production efficiency and even affecting the normal operation of the entire production line, causing considerable losses to the company. Summary of the invention
[0004] In view of the above-mentioned shortcomings of the prior art, the present invention provides a production material preparation scheduling method, device, equipment and storage medium to solve the above-mentioned technical problems.
[0005] The present invention provides a production material preparation scheduling method, the method comprising: acquiring inventory information of materials and product information of products to be processed on a production line; scheduling product processing batches based on the product information to obtain the production time of each product batch, performing set processing on each product batch based on the inventory information to obtain the set quantity of each product batch; calculating the set quantity of each product batch and the pre-equipment material working hours to obtain the time required for material preparation of each product batch, and obtaining the available material preparation time of each product batch based on the current time and the production time; determining the difference between the required material preparation time and the available material preparation time as the material preparation difference working hours, and scheduling the material preparation work based on the material preparation difference working hours.
[0006] In one embodiment of the present application, scheduling of product processing batches is performed based on the product information, including: obtaining sub-information of the product information of each batch of products to be processed; determining the scheduling standard quantity of each sub-information based on a preset scheduling rule, and assigning different scheduling coefficients to each type of sub-information; calculating the scheduling standard quantity and the scheduling coefficient to obtain the scheduling index of each product to be processed, so as to schedule the processing batches of each product to be processed based on the scheduling index.
[0007] In one embodiment of the present application, each product batch is processed as a set based on the inventory information, including: obtaining the material type and quantity information on each tray, and automatically matching and extracting the corresponding materials on the tray according to the material list required for each product batch, so as to obtain a first set rate for each product batch; calculating the quantity of materials required for each batch according to the material quantity in the material list and inventory information of each product batch, and extracting the corresponding quantity of materials from the inventory, so as to obtain a second set rate for each product batch.
[0008] In one embodiment of the present application, after obtaining the first completion rate of each product batch, it also includes: treating the product batches whose first completion rate is less than a preset first completion rate threshold as slow production batches; calculating the proportion of the slow production batches in all product batches; when the proportion of the slow production batches is greater than the preset slow production proportion threshold, generating a first material shelving instruction to trigger the material shelving work.
[0009] In one embodiment of the present application, after obtaining the second completeness rate of each product batch, it also includes: treating the product batch whose second completeness rate is less than the preset second completeness rate threshold as a product batch with insufficient materials; if such a product batch with insufficient materials exists, obtaining the insufficient materials information of the product batch with insufficient materials, and sending the insufficient materials information to relevant staff to trigger the procurement or scheduling process.
[0010] In one embodiment of the present application, after obtaining the time required for preparation of each product batch, it also includes: determining the product batches whose preparation time is longer than the preset preparation time threshold as long preparation batches; calculating the proportion of the long preparation batches in all product batches; when the proportion of the long preparation batches is greater than the preset long preparation proportion threshold, generating a second material shelving instruction to trigger the material shelving work.
[0011] In one embodiment of the present application, after determining the difference between the time required for material preparation and the time available for material preparation as the differential working time for material preparation, it also includes: determining the product batch whose differential working time is greater than the preset working time threshold as a relaxed material preparation batch; if the set rate of any relaxed material preparation batch is greater than or equal to the preset third set rate threshold, the relaxed material preparation batch is regarded as a production batch that can be prepared; if the set rate of any relaxed material preparation batch is less than the preset third set rate threshold, the relaxed material preparation batch is regarded as a production batch to be replenished, and the production batch to be replenished needs to be prepared as a set of materials after the materials are put on the shelves.
[0012] The present application provides a production material preparation scheduling device, which includes: an information collection module, which is used to obtain inventory information of materials and product information of products to be processed on the production line; a set processing module, which is used to schedule product processing batches based on the product information to obtain the production time of each product batch, and to perform set processing on each product batch based on the inventory information to obtain the set quantity of each product batch; a material preparation work time calculation module, which is used to calculate the set quantity of each product batch and the pre-equipment material work time to obtain the required time for material preparation of each product batch, and obtain the available time for material preparation of each product batch based on the current time and the production time; a material preparation scheduling module, which is used to determine the difference between the required time for material preparation and the available time for material preparation as the material preparation difference work time, and schedule the material preparation work based on the material preparation difference work time.
[0013] The present application provides an electronic device, including a processor, a memory and a communication bus; the communication bus is used to connect the processor and the memory; the processor is used to execute a computer program stored in the memory to implement the production material preparation scheduling method as described above.
[0014] The present application provides a computer-readable storage medium having a computer program stored thereon, wherein the computer program is used to enable a computer to execute the production material preparation scheduling method as described above.
[0015] Beneficial effects of the present invention: The production material preparation scheduling method proposed in the present invention comprehensively considers the material inventory information and the product information of the products to be processed on the production line, accurately calculates the time required for material preparation for each product batch, and derives the available material preparation time based on the current time and the production time, thereby scheduling the material preparation work. This refined scheduling method can ensure the close connection between the material preparation work and the production plan, thereby effectively reducing the shutdown of the production line due to incomplete material preparation, and significantly improving the overall efficiency of the production line.
[0016] It should be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The drawings herein are incorporated into the specification and constitute a part of the specification, showing embodiments consistent with the present application, and together with the specification, are used to explain the principles of the present application. Obviously, the drawings described below are only some embodiments of the present application, and for those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative work. In the drawings:
[0018] Figure 1 is a schematic diagram of an implementation environment of a production material preparation scheduling method shown in an exemplary embodiment of the present application;
[0019] Figure 2 It is a schematic diagram of the steps of a production material preparation scheduling method shown in an exemplary embodiment of the present application;
[0020] Figure 3 is a schematic diagram of a complete set of processing flow charts shown in an exemplary embodiment of the present application;
[0021] Figure 4 is a block diagram of a production material preparation scheduling device shown in an exemplary embodiment of the present application;
[0022] Figure 5 A schematic diagram of the structure of a computer system suitable for implementing an electronic device of an embodiment of the present application is shown. DETAILED DESCRIPTION
[0023] The following will describe the embodiments of the present invention with reference to the accompanying drawings and preferred embodiments. Those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be understood that the preferred embodiments are only for illustrating the present invention, not for limiting the scope of protection of the present invention.
[0024] It should be noted that the illustrations provided in the following embodiments are only schematic illustrations of the basic concept of the present invention, and thus the drawings only show components related to the present invention rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed arbitrarily, and the component layout may also be more complicated.
[0025] In the following description, numerous details are discussed to provide a more thorough explanation of the embodiments of the present invention. However, it is obvious to those skilled in the art that the embodiments of the present invention can be implemented without these specific details. In other embodiments, well-known structures and devices are shown in the form of block diagrams rather than in detail to avoid making the embodiments of the present invention difficult to understand.
[0026] First of all, it should be explained that production scheduling, also known as production planning scheduling or production dispatching, refers to the reasonable arrangement and scheduling of production tasks through scientific and reasonable methods and means during the production process based on the company's production capacity, order requirements, material supply and other actual conditions.
[0027] Complete set processing refers to a processing method that aims at products that require a combination of multiple parts or components to complete, and ensures that these parts or components can be completed in accordance with the proportion and requirements of product assembly during production, so as to smoothly carry out subsequent assembly work.
[0028] Figure 1 It is a schematic diagram of an implementation environment of a production material preparation scheduling method shown in an exemplary embodiment of the present application.
[0029] like Figure 1 As shown, the implementation environment of the production material preparation scheduling method proposed in this application includes a data acquisition device 101 and a computer device 102, wherein the data acquisition device 101 is used to collect the information of the products to be processed of the production line and the inventory information of the warehouse, and send the collected information of the products to be processed and the inventory information to the computer device 102, and the data acquisition device can be any device or equipment that can be used for information collection, such as a camera, a camera, an infrared sensor, etc., and this application does not impose any restrictions on this; the computer device 102 is used to perform a set of processing on the batch of products to be processed based on the information of the products to be processed and the inventory information collected by the data acquisition device 101, and further based on its inventory information and the information of the products to be processed, so as to calculate the material preparation time of each batch of products based on the results of the set, and then schedule the product material preparation work. Among them, the computer device 102 can be at least one of a desktop graphics processing unit (GPU) computer, a GPU computing cluster, a neural network computer, etc., or it can be an intelligent processor integrated on the current vehicle, and this application does not impose any restrictions on this.
[0030] The present application proposes a production material preparation scheduling method, which includes: obtaining all information on products to be processed on the production line on that day and sorting each product batch, obtaining the production start time of each product batch based on the sorting result, processing each product batch as a set based on the initial material inventory data of the material warehouse to obtain the set rate of each product batch, and determining the time required for material preparation of each product batch according to the preset standard material preparation working hours, obtaining the available material preparation time based on the current time and the production start time of each product batch, determining the difference between the available material preparation time and the required material preparation time as the material preparation difference time, and then scheduling the material preparation work based on the material preparation difference time. By scheduling material preparation work, it can ensure that materials are prepared in time before production starts, avoiding production delays caused by insufficient materials or improper preparation, helping to improve the overall production efficiency of the production line and ensure the smooth progress of the production process; moreover, material preparation scheduling can also help companies to reasonably allocate material preparation resources, such as manpower, equipment and time. By accurately calculating the time required for material preparation and the difference in material preparation time, material preparation plans can be arranged more accurately to avoid waste or shortage of resources; in addition, reasonable material preparation scheduling can also reduce unnecessary material inventory backlogs, so that the production management department can prepare materials in an orderly manner according to the scheduling plan, avoid purchasing and storing materials too early or too late, thereby reducing inventory costs and risks.
[0031] like Figure 2As shown, in an exemplary embodiment, the production material preparation scheduling method includes at least steps S210 to S240, which are described in detail as follows:
[0032] Step S210, obtaining the inventory information of the material and the product information of the products to be processed on the production line.
[0033] In one embodiment of the present application, in daily work, in order to monitor the material inventory and the products to be processed on the production line in real time to ensure the smooth progress of the production process, the existing material inventory information including the material name, quantity, location, etc., and the product information of the products to be processed on the production line such as product number, name, and production batch are usually entered into the database system, and the changes in the material inventory can be monitored in real time using sensors and scanning equipment to ensure the accuracy of the data. Therefore, when there are products to be processed on the production line, the product information can be updated through the scanning equipment, including the processing status, estimated completion time, etc. In addition, employees can also query the material inventory information and the product information of the products to be processed on the production line through the user interface, and update the relevant information as needed, such as material outbound and inbound operations, or record the processing progress of the production line products. Similarly, when further data processing is required based on the above-mentioned related data, the relevant inventory data and product information can be directly obtained from the data system.
[0034] Step S220, scheduling product processing batches based on product information to obtain the production time of each product batch, and performing set processing on each product batch based on inventory information to obtain the set quantity of each product batch.
[0035] In one embodiment of the present application, scheduling of product processing batches is performed based on product information, including: obtaining sub-information of the product information of each batch of products to be processed; determining the scheduling standard quantity of each sub-information based on a preset scheduling rule, and assigning different scheduling coefficients to each type of sub-information; calculating the scheduling standard quantity and the scheduling coefficient to obtain the scheduling index of each product to be processed, so as to schedule the processing batches of each product to be processed based on the scheduling index.
[0036] In one embodiment of the present application, first, obtain the product information of each batch of products to be processed from the production management system or database, including but not limited to sub-information such as product type, quantity, delivery deadline, and processing difficulty; and preset scheduling rules according to the actual situation of the enterprise and past experience, such as the urgency of the delivery deadline, the processing complexity of the product type, etc., so as to give different scheduling coefficients to various sub-information (such as delivery deadline, processing difficulty, etc.) to reflect their importance and priority in scheduling. Then, based on the preset scheduling rules, a scheduling standard quantity is calculated for each sub-information of the product to be processed. For example, the more urgent the delivery deadline, the higher the scheduling standard quantity may be. Finally, the scheduling standard quantity of each sub-information is multiplied by the corresponding scheduling coefficient, and then these products are added to obtain the scheduling index of each product to be processed. According to the scheduling index of each product to be processed, it is sorted from high to low to determine the processing batch and order, and the scheduling result is input into the production management system for execution by the production line. It should be noted that the scheduling index takes into account multiple sub-information, so it can more comprehensively reflect the processing priority of the product.
[0037] In a specific embodiment of the present application, the OEM products include product A, product B, and product C. For example, the sub-information and scheduling coefficient of each product are shown in Table 1:
[0038] Table 1
[0039] Product Categories Delivery deadline Term coefficient Processing difficulty Difficulty Order quantity / piece Product A urgent 1.5 medium 1.0 100 Product B generally 1.0 Simple 0.8 150 Product C Loose 0.8 complex 1.2 200
[0040] As shown in Table 1, the delivery deadline, processing difficulty, and order quantity of various products to be processed are different. Therefore, after obtaining the above data information, the scheduling coefficients of delivery deadline, processing difficulty, and order quantity are further set according to the product information. Taking the delivery deadline standard quantity: urgent = 3, general = 2, loose = 1; the processing difficulty standard quantity: complex = 3, medium = 2, simple = 1; the order quantity standard quantity directly uses the number of orders as an example, the calculation formula of the product scheduling index can be obtained as follows:
[0041] Scheduling index = (delivery deadline standard quantity × delivery deadline coefficient) + (processing difficulty standard quantity × processing difficulty coefficient) + order quantity
[0042] Based on the above scheduling index calculation method, the scheduling index of product A is calculated to be 106.5, the scheduling index of product B is 153.8, and the scheduling index of product C is 204.4. Therefore, according to the scheduling index, the processing order is determined as follows: product C (highest index, priority processing), product B (second index), product A (lowest index, last processing). Finally, the scheduling results are communicated to the production line to guide the production line to process the products in the determined order.
[0043] It should be noted that the scheduling method based on the product information proposed in this embodiment can more reasonably arrange the processing batches and sequences of each product to be processed, which not only improves production efficiency, but also ensures that urgent and important orders can be processed first. In addition, by comprehensively considering multiple sub-information, this method makes scheduling more scientific and fair, and reduces the impact of human intervention and subjective judgment. In addition, the above embodiment is only used as an example for explanation. In a specific production process, the category, coefficient setting, and standard quantity setting of its product sub-information can be adaptively adjusted according to the actual production operation requirements, and this application does not impose any restrictions on it.
[0044] In one embodiment of the present application, each product batch is processed as a set based on inventory information, including: obtaining the material type and quantity information on each tray, and automatically matching and extracting the corresponding materials on the tray according to the material list required for each product batch, so as to obtain a first set rate for each product batch; calculating the quantity of materials required for each batch according to the material quantity in the material list and inventory information of each product batch, and extracting the corresponding quantity of materials from the inventory, so as to obtain a second set rate for each product batch.
[0045] In one embodiment of the present application, firstly, a warehouse management system or RFID technology is used to collect the material type and quantity information on each tray in real time, and for each product batch, a list of materials required for its production is input, including detailed information such as material type and quantity, and a feasible set processing algorithm is designed, which can automatically calculate and match the required materials according to the list of materials and real-time inventory information of the product batch. Then the set processing algorithm is run to automatically match and extract the materials required for each product batch, and an extraction instruction is generated according to the algorithm result to guide the staff or automated equipment to take the materials from the corresponding tray. In addition, after the set processing is completed, the matching degree between the materials actually extracted from each product batch and the required materials is counted to calculate the first set rate, that is, the proportion of materials successfully matched during the first set processing, and then the first set rate is analyzed to identify the key factors affecting the set rate, so as to adjust the inventory layout and optimize the set processing algorithm according to the analysis results to improve the first set rate of subsequent batches.
[0046] In a specific embodiment of the present application, taking the products to be processed as 1 set of product X and 1 set of product Y as an example, the bill of materials (BOM) of product X and product Y are shown in Table 2.
[0047] Table 2
[0048]
[0049] In addition, the material information in each tray is shown in Table 3:
[0050] Table 3
[0051]
[0052]
[0053] After obtaining the product BOM shown in Table 2 and the tray information shown in Table 3, the bill of materials of product X and product Y are input into the complete set processing system, and the real-time inventory information of tray 1, tray 2 and tray 3 is obtained through the warehouse management system. Taking the complete set processing rule as "Rule 1: Prioritize the extraction of materials from the tray with the largest inventory quantity. Rule 2: If the material on a certain tray is not enough to meet the demand of a batch, continue to extract from other trays containing the material" as an example, for product X, the system automatically extracts 2 materials A and 3 materials B from tray 1 and 1 material C from tray 2 according to the bill of materials and inventory information; for product Y, the system extracts 4 materials D from tray 2 and 2 materials E from tray 3. It can be obtained that all the required materials of product X are successfully matched, and its first complete set rate is 100%; all the required materials of product Y are also successfully matched, so the first complete set rate of product Y is also 100%.
[0054] It should be noted that during the production process, the inventory changes of the material trays can be continuously monitored and the inventory information can be updated in real time to detect insufficient inventory of a certain material, and the production plan can be adjusted or material procurement can be carried out in a timely manner to ensure the completion rate of subsequent batches.
[0055] In another embodiment of the present application, the bill of materials of each product batch is firstly summarized to clarify the type and quantity of materials required for each batch, and the current inventory quantity of various materials is obtained through the enterprise's inventory management system. Then, for each product batch, the quantity of required materials is calculated based on its bill of materials and current inventory information, and the corresponding quantity of materials is extracted from the inventory based on the calculated material requirements to achieve complete set processing of the products.
[0056] In a specific embodiment of the present application, the products to be processed are product A, product B, and product C as an example, wherein the number of product A to be processed is 100 sets, the number of product B to be processed is 150 sets, and the number of product C to be processed is 200 sets, and the BOM of product A, product B, and product C is shown in Table 4:
[0057] Table 4
[0058] Material A Material B Material C Material D Material E Product A 2pcs 1pcs 3pcs / / Product B / 2pcs / 4pcs / Product C 1pcs / 2pcs / 5pcs
[0059] In addition, the current inventory of material A, material B, material C, material D, and material E is 300pcs, 200pcs, 400pcs, 600pcs, and 900pcs, respectively. Therefore, for each product, according to its bill of materials and inventory data, the maximum number of sets that can be produced is calculated. For product A, a maximum of 100 sets can be produced (limited by material B); product B can produce a maximum of 100 sets (limited by material B); product C can produce a maximum of 150 sets (limited by material A). Therefore, according to the calculated maximum number of sets that can be produced, the corresponding number of materials are extracted from the inventory to facilitate subsequent production. Finally, based on the number of sets and the planned production quantity of each product, the corresponding set rate is calculated. In this embodiment, the set rate of product A is 100%, the set rate of product B is 66.67% (100 / 150), and the set rate of product C is 75% (150 / 200).
[0060] It should be noted that after obtaining the completeness rate of each product, the products with a completeness rate lower than 100% can be further analyzed to find out the bottleneck materials (such as material B and material A in this example), and the production plan can be adjusted or material procurement can be carried out according to the analysis results to improve the completeness rate of subsequent batches.
[0061] It should be noted that the set of rules mentioned in the above embodiments is only for the purpose of illustrative explanation of the entire process and logic, and does not represent the full content or form of the set of rules. In the actual production process, enterprises can formulate more complex and complete sets of rules based on their own production characteristics, material characteristics, product quality requirements, market demand and other factors. These rules may include but are not limited to multiple dimensions such as material matching, storage conditions, and production process optimization, aiming to ensure the efficiency of production, the stability of product quality, and the adaptability to market demand. This application does not impose any restrictions on the specific content and form of the set of rules, and enterprises can flexibly adjust and optimize according to their actual situation to meet the ever-changing market demand and production environment.
[0062] In addition, the inventory information mentioned in the embodiments of the present application covers the data of multiple key material warehouses, including at least the material inventory information of the IWM system intelligent silo, the IWM system acceptance area, the SAP system return silo, and the MES system MT bulk material area. This information is crucial for the production planning and material management of the enterprise because they reflect the real-time storage situation of materials in different warehouses and areas. However, it should be clear that this is only an exemplary enumeration and does not represent the full scope of inventory information. In actual application scenarios, inventory information may also include other material warehouse data closely related to enterprise production, such as line warehouses, transit warehouses, etc. This application does not impose any specific restrictions on the specific content and scope of the inventory information. In the specific implementation process, it can flexibly define and expand the scope of inventory information according to its own management needs and business processes to ensure efficient and smooth production operations.
[0063] Figure 3 It is a schematic diagram of a complete set of processing flow charts showing an exemplary embodiment of the present application.
[0064] like Figure 3 As shown, after obtaining the inventory information and the material requirements of each product batch, they are processed as a set based on the tray and quantity. Among them, the first set rate is obtained based on the tray set processing, and the production batch with the first set rate less than the preset first set rate threshold is regarded as a delayed production batch. If the proportion of delayed production batches is greater than the preset delayed production ratio threshold, the material shelving work is triggered; the second set rate is obtained based on the material quantity, and the product batch with the second set rate lower than the preset second set rate threshold is regarded as a short-material product batch. When there is a short-material product batch, its short-material information is obtained, and the procurement or scheduling process is triggered based on the short-material information.
[0065] In one embodiment of the present application, after each product batch is processed as a set based on inventory information and the first set rate of each product batch is obtained, it also includes: considering the product batch whose first set rate is less than the preset first set rate threshold as a delayed production batch; calculating the proportion of the delayed production batch in all product batches; when the proportion of the delayed production batch is greater than the preset delayed production ratio threshold, generating a first material shelving instruction to trigger the material shelving work. After the second set rate of each product batch is obtained, it also includes: considering the product batch whose second set rate is less than the preset second set rate threshold as a short-material product batch; if there is a short-material product batch, obtaining the short-material information of the short-material product batch, and sending the short-material information to relevant staff to trigger the procurement or scheduling process.
[0066] In one embodiment of the present application, the system first collects the tray data of each product batch, which includes information such as the type and quantity of the material on each tray, and calculates the first set rate based on the collected tray data, that is, the production readiness of the product is evaluated according to the completeness of the tray configuration. At the same time, the second set rate is calculated based on the statistics of the number of materials to reflect the adequacy of the material inventory. A preset first set rate threshold is set, such as 90%. When the first set rate of a product batch is lower than this threshold, the system will automatically mark the batch as a delayed production batch, and further calculate the proportion of the delayed production batch in all product batches. For example, if there are 100 product batches, of which 10 batches have a first set rate lower than 90%, then the proportion of delayed production batches is 10%. If the proportion of delayed production batches exceeds the system preset delayed production ratio threshold (such as 5%), the system will generate a first material shelf instruction to notify the warehouse to replenish materials to ensure the continuous supply of the production line. Similar to the first set rate, a threshold is also set for the second set rate, such as 100%. When the second set rate of a product batch is lower than this threshold, the batch will be automatically marked as a short-material product batch. Once the short-material product batch is identified, the detailed short-material information of these batches will be obtained immediately, including the type and quantity of the missing materials, etc., and the short-material information will be automatically sent to the staff responsible for procurement or scheduling, so that they can trigger the corresponding procurement or scheduling process in time to solve the material shortage problem.
[0067] In a specific embodiment of the present application, the product to be processed includes five product batches (A, B, C, D, E) as an example, and the product batches are processed as a set based on the material tray and the material quantity, and the set rates of multiple product batches are shown in Table 5:
[0068] Table 5
[0069] Product Batch A Product Batch B Product batch C Product batch D Product Batch E The first set rate 85% 92% 88% 95% 90% The second set rate 98% 100% 96% 93% 97%
[0070] After obtaining the yield rate of each product as shown in Table 5, take the preset first set rate threshold of 90%, the preset delayed production ratio threshold of 30%, and the preset second set rate threshold of 100% as an example. According to this threshold, the first set rate of batch A (85%) and batch C (88%) is lower than 90%, so they are marked as delayed production batches. These two delayed production batches account for 40% of all five batches, which exceeds the preset delayed production ratio threshold of 30%. Then, the first material shelf instruction is generated, requiring the warehouse to replenish the missing materials of batch A and batch C as soon as possible to increase their first set rate to above the threshold. In addition, according to this threshold, only the second set rate of batch B reaches 100%, and the remaining batches are all short of materials. Batches A, C, D and E are further identified as batches of products with insufficient materials, and the detailed insufficient material information of these batches is immediately obtained, and their insufficient material information is sent to the procurement and scheduling departments to trigger the corresponding material replenishment process in time.
[0071] Step S230, calculating the complete set quantity and pre-equipment material man-hours of each product batch to obtain the time required for material preparation of each product batch, and obtaining the available time for material preparation of each product batch based on the current time and the production start time.
[0072] In one embodiment of the present application, after obtaining the time required for preparation of each product batch, it also includes: determining the product batches whose preparation time is longer than the preset preparation time threshold as long preparation batches; calculating the proportion of long preparation batches in all product batches; when the proportion of long preparation batches is greater than the preset long preparation proportion threshold, generating a second material shelving instruction to trigger the material shelving work.
[0073] In one embodiment of the application, the products to be processed include batch A (number of complete sets: 100 sets), batch B (number of complete sets: 150 sets), and batch C (number of complete sets: 200 sets), and the preparation time for each set of products is: batch A requires 0.5 minutes for each set, batch B requires 0.4 minutes for each set, and batch C requires 0.6 minutes for each set. The required preparation time for each product batch is calculated as follows:
[0074] Batch A: 100 sets x 0.5 minutes / set = 50 minutes,
[0075] Batch B: 150 sets x 0.4 minutes / set = 60 minutes,
[0076] Batch C: 200 sets x 0.6 minutes / set = 120 minutes
[0077] Then, the set pre-equipment material preparation time threshold is 60 minutes, and the product batch exceeding this threshold is determined as a long-term preparation batch, and the preset long-term preparation ratio threshold is 25%. When the ratio of the long-term preparation batch exceeds this threshold, the system will generate a second material shelf instruction as an example. In this embodiment, only the preparation time required for batch C (120 minutes) exceeds the preset threshold, so it is marked as a long-term preparation batch; then, considering that there are currently three product batches, one of which is a long-term preparation batch, the proportion of long-term preparation batches in all product batches is 33.33%, which exceeds the preset 25% threshold. Therefore, the second material shelf instruction is immediately generated and sent to the warehouse management system to trigger the material shelf work to ensure that the materials of batch C can be prepared in time. In addition, the second material shelf instruction can also be pushed to the relevant staff so that the relevant staff can further promote the relevant work of material shelving.
[0078] It should be noted that based on the material preparation method proposed in this implementation, the long-term material preparation batch (Batch C) was identified in a timely manner, and the material shelving work was triggered when its proportion exceeded the preset threshold. This not only helps to avoid production delays, but also improves the efficiency and response speed of material management, thereby saving time and cost for the enterprise.
[0079] Step S240: determine the difference between the time required for material preparation and the time available for material preparation as the material preparation differential working time, and schedule the material preparation work based on the material preparation differential working time.
[0080] In one embodiment of the present application, after determining the difference between the time required for material preparation and the time available for material preparation as the differential working time for material preparation, it also includes: determining the product batches whose differential working time is greater than the preset working time threshold as the relaxed material preparation batches; if the set rate of any relaxed material preparation batches is greater than or equal to the preset third set rate threshold, the relaxed material preparation batches are regarded as the production batches that can be prepared; if the set rate of any relaxed material preparation batches is less than the preset third set rate threshold, the relaxed material preparation batches are regarded as the production batches to be replenished, and the production batches to be replenished need to wait until the materials are put on the shelves before preparing the sets of materials.
[0081] In one embodiment of the present application, the products to be processed include three different product batches: batch A, batch B and batch C. According to the calculation, the time required for batch A to prepare materials is 10 hours, and the time available for preparation is 15 hours, so the difference in preparation time for batch A is 5 hours; the time required for batch B to prepare materials is 8 hours, and the time available for preparation is 6 hours, so the difference in preparation time for batch B is -2 hours; the time required for batch C to prepare materials is 12 hours, and the time available for preparation is 14 hours, so the difference in preparation time for batch C is 14-12=2 hours. Assuming that the preset working time threshold is 3 hours, only the difference in working time between batch A and batch C is greater than this threshold, so they are determined as slack preparation batches. Further check the completion rates of these two relaxed preparation batches. Assuming that the preset third completion rate threshold is 80%, the completion rate of batch A is 85%, and the completion rate of batch C is 75%. Then batch A is regarded as a production batch that can be prepared, and batch C is regarded as a production batch to be supplemented, which needs to wait for the materials to be put on the shelves before the complete set of materials can be prepared. It should be noted that in this embodiment, batch A is determined as a production batch that can be prepared, and preparation of materials can be started immediately, while batch C is determined as a production batch to be supplemented due to insufficient completion rate, and needs to wait for further material replenishment. Batch B is not included in the production plan considered this time because the preparation difference working hours do not reach the preset threshold.
[0082] In addition, it should be noted that the material preparation plan proposed in this embodiment, by comprehensively considering the different material preparation hours and the set rate, can reasonably allocate resources and give priority to the production of product batches with sufficient material preparation, thereby improving production efficiency; at the same time, by setting a set rate threshold, quality control is carried out before production to reduce production risks.
[0083] Finally, it should be noted that the production material preparation scheduling method proposed in this application has the following advantages. First, by comprehensively considering the material inventory information and the product information of the products to be processed on the production line, the time required for material preparation for each product batch can be accurately calculated, and the available time for material preparation can be obtained based on the current time and the production time. This refined scheduling method can ensure the close connection between material preparation work and production plan, thereby effectively reducing the shutdown phenomenon of production line due to incomplete material preparation, and significantly improving the overall efficiency of the production line. Second, by processing each product batch in a set, the number of sets of each batch can be accurately obtained, which helps enterprises to allocate and utilize resources more reasonably, not only to avoid waste of materials, but also to ensure the stability of material supply in the production process, and further improve the utilization efficiency of resources. Third, scheduling material preparation work based on the material preparation difference working hours enables enterprises to flexibly adjust the material preparation plan according to the actual production situation, which helps enterprises to deal with emergencies, such as supplier delivery delays, inventory changes, etc., thereby maintaining the stable operation of the production line. Fourth, through the automated scheduling system, the company can grasp the material preparation progress and production plan of each product batch in real time, which helps the management make more informed decisions and improve overall management efficiency. Fifth, refined material preparation scheduling can reduce unnecessary shutdowns and material waste, thereby reducing production costs. At the same time, by optimizing resource utilization and improving production efficiency, the company can further reduce the production cost per unit product and enhance market competitiveness. In summary, the production material preparation scheduling method proposed in the application significantly improves the production efficiency of the production line, optimizes resource utilization, enhances production flexibility, improves management efficiency, and effectively reduces production costs through precise calculation and intelligent scheduling.
[0084] Figure 4 is a block diagram of a production material preparation scheduling device shown in an exemplary embodiment of the present application. The device can be applied to Figure 1 The device may also be applicable to other exemplary implementation environments and specifically configured in other devices, and this embodiment does not limit the implementation environment to which the device is applicable.
[0085] like Figure 4 As shown, the exemplary production material preparation scheduling device includes: an information collection module 410 , a set processing module 420 , a material preparation man-hour calculation module 430 , and a material preparation scheduling module 440 .
[0086] Among them, the information collection module 410 is used to obtain the inventory information of materials and the product information of the products to be processed on the production line; the set processing module 420 is used to schedule the product processing batches based on the product information to obtain the production time of each product batch, and to perform set processing on each product batch based on the inventory information to obtain the number of sets of each product batch; the material preparation time calculation module 430 is used to calculate the number of sets of each product batch and the pre-equipment material time to obtain the time required for material preparation of each product batch, and to obtain the available time for material preparation of each product batch based on the current time and the production time; the material preparation scheduling module 440 is used to determine the difference between the time required for material preparation and the available time for material preparation as the material preparation difference time, and schedule the material preparation work based on the material preparation difference time.
[0087] It should be noted that the production material preparation scheduling device provided in the above embodiment and the production material preparation scheduling method provided in the above embodiment belong to the same concept, wherein the specific manner in which each module and unit performs the operation has been described in detail in the method embodiment and will not be repeated here. In actual application, the production material preparation scheduling device provided in the above embodiment can distribute the above functions to different functional modules as needed, that is, divide the internal structure of the device into different functional modules to complete all or part of the functions described above, and this is not limited here.
[0088] An embodiment of the present application also provides an electronic device, comprising: one or more processors; a storage device for storing one or more programs, and when the one or more programs are executed by the one or more processors, the electronic device implements the production material preparation scheduling method provided in the above-mentioned embodiments.
[0089] Figure 5 The structure diagram of the computer system suitable for implementing the electronic device of the embodiment of the present application is shown. It should be noted that: Figure 5 The computer system 500 of the electronic device shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.
[0090] like Figure 5As shown, the computer system 500 includes a central processing unit (CPU) 501, which can perform various appropriate actions and processes according to the program stored in the read-only memory (ROM) 502 or the program loaded from the storage part 508 to the random access memory (RAM) 503, such as executing the method described in the above embodiment. In the RAM 503, various programs and data required for system operation are also stored. The CPU 501, the ROM 502 and the RAM 503 are connected to each other through the bus 504. The input / output (I / O) interface 505 is also connected to the bus 504.
[0091] The following components are connected to the I / O interface 505: an input section 506 including a keyboard, a mouse, etc.; an output section 507 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker; a storage section 508 including a hard disk, etc.; and a communication section 509 including a network interface card such as a LAN (Local Area Network) card, a modem, etc. The communication section 509 performs communication processing via a network such as the Internet. A drive 510 is also connected to the I / O interface 505 as needed. A removable medium 511, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 510 as needed so that a computer program read therefrom is installed into the storage section 508 as needed.
[0092] In particular, according to an embodiment of the present application, the process described above with reference to the flowchart can be implemented as a computer software program. For example, an embodiment of the present application includes a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program includes a computer program for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from a network through a communication section 509, and / or installed from a removable medium 511. When the computer program is executed by a central processing unit (CPU) 501, various functions defined in the system of the present application are executed.
[0093] It should be noted that the computer-readable medium shown in the embodiment of the present application can be a computer-readable signal medium or a computer-readable storage medium or any combination of the above two. The computer-readable storage medium can be, for example, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media can include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM), a flash memory, an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present application, a computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, wherein a computer-readable computer program is carried. This propagated data signal can take a variety of forms, including but not limited to an electromagnetic signal, an optical signal, or any suitable combination of the above. A computer-readable signal medium may also be any computer-readable medium other than a computer-readable storage medium, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. A computer program contained on a computer-readable medium may be transmitted using any appropriate medium, including but not limited to: wireless, wired, etc., or any suitable combination of the above.
[0094] The flowchart and block diagram in the accompanying drawings illustrate the possible architecture, functions and operations of the system, method and computer program product according to various embodiments of the present application. Wherein, each box in the flowchart or block diagram can represent a module, a program segment, or a part of the code, and the above-mentioned module, program segment, or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram or flowchart, and the combination of boxes in the block diagram or flowchart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.
[0095] The units involved in the embodiments described in this application may be implemented by software or hardware, and the units described may also be set in a processor. The names of these units do not, in some cases, constitute limitations on the units themselves.
[0096] Another aspect of the present application also provides a computer-readable storage medium on which a computer program is stored. When the computer program is executed by a processor of a computer, the computer executes the production material preparation scheduling method as described above. The computer-readable storage medium may be included in the electronic device described in the above embodiment, or may exist independently without being assembled into the electronic device.
[0097] Another aspect of the present application also provides a computer program product or a computer program, which includes a computer instruction stored in a computer-readable storage medium. A processor of a computer device reads the computer instruction from the computer-readable storage medium, and the processor executes the computer instruction, so that the computer device executes the production material preparation scheduling method provided in each of the above embodiments.
[0098] The above embodiments are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. Anyone familiar with the technology may modify or change the above embodiments without violating the spirit and scope of the present invention. Therefore, all equivalent modifications or changes made by a person of ordinary skill in the art without departing from the spirit and technical ideas disclosed by the present invention shall still be covered by the claims of the present invention.
Claims
1. A production material preparation scheduling method, characterized in that: The method comprises: Obtain inventory information of materials and product information of products to be processed on the production line; Scheduling product processing batches based on the product information to obtain the production time of each product batch, and performing set processing on each product batch based on the inventory information to obtain the set quantity of each product batch; Calculate the number of sets and pre-equipment time of each product batch to get the time required for material preparation of each product batch, and get the available time for material preparation of each product batch based on the current time and production time; The difference between the required material preparation time and the available material preparation time is determined as the material preparation difference working time, and the material preparation work is scheduled based on the material preparation difference working time.
2. The production material preparation scheduling method according to claim 1, characterized in that: Scheduling product processing batches based on the product information includes: Obtain sub-information of product information of each batch of products to be processed; Determine the scheduling standard quantity of each sub-information based on the preset scheduling rules, and assign different scheduling coefficients to each sub-information; The scheduling standard quantity and the scheduling coefficient are calculated to obtain a scheduling index for each product to be processed, so as to schedule the processing batches of each product to be processed based on the scheduling index.
3. The production material preparation scheduling method according to claim 1, characterized in that: The batches of products are processed as a set based on the inventory information, including: Obtain the type and quantity information of materials on each tray, and automatically match and extract the corresponding materials on the tray according to the bill of materials required for each product batch to obtain the first set rate of each product batch; According to the material quantity in the bill of materials and inventory information of each product batch, the quantity of materials required for each batch is calculated, and the corresponding quantity of materials is extracted from the inventory to obtain the second set rate of each product batch.
4. The production material preparation scheduling method according to claim 3, characterized in that: After obtaining the first set rate of each product batch, it also includes: A product batch whose first set rate is less than a preset first set rate threshold is regarded as a delayed production batch; Calculate the proportion of the delayed production batch in all product batches; When the proportion of delayed production batches is greater than a preset delayed production proportion threshold, a first material shelving instruction is generated to trigger the material shelving work.
5. The production material preparation scheduling method according to claim 3, characterized in that: After obtaining the second set rate of each product batch, it also includes: A product batch whose second set rate is less than a preset second set rate threshold is regarded as a product batch with insufficient materials; If there is a batch of products with insufficient materials, the insufficient materials information of the batch of products with insufficient materials is obtained, and the insufficient materials information is sent to relevant staff to trigger a procurement or scheduling process.
6. The production material preparation scheduling method according to any one of claims 1 to 5, characterized in that: After obtaining the time required for preparing materials for each product batch, it also includes: The product batches whose material preparation time is longer than the pre-preparation material preparation time threshold are identified as long-term material preparation batches; Calculate the proportion of the long-term preparation batches in all product batches; When the proportion of long-time material preparation batches is greater than a preset long-time material preparation proportion threshold, a second material shelving instruction is generated to trigger the material shelving work.
7. The production material preparation scheduling method according to any one of claims 1 to 5, characterized in that: After determining the difference between the material preparation time required and the material preparation time available as the material preparation difference working time, the method further includes: The product batch whose differential working time is greater than the preset working time threshold is determined as a relaxed material preparation batch; If the completion rate of any relaxed stock preparation batch is greater than or equal to the preset third completion rate threshold, the relaxed stock preparation batch is regarded as a batch that can be prepared for production; If the completion rate of any relaxed material preparation batch is less than the preset third completion rate threshold, the relaxed material preparation batch will be regarded as a production batch to be supplemented, and the production batch to be supplemented needs to be prepared as a set of materials after the materials are put on the shelves.
8. A production material preparation scheduling device, characterized in that: The device comprises: The information collection module is used to obtain the inventory information of materials and the product information of the products to be processed on the production line; A complete set processing module, used to schedule product processing batches based on the product information to obtain the production time of each product batch, and to perform complete set processing on each product batch based on the inventory information to obtain the complete set quantity of each product batch; The material preparation time calculation module is used to calculate the number of sets of each product batch and the material preparation time to obtain the time required for material preparation of each product batch, and obtain the available time for material preparation of each product batch based on the current time and production time; The material preparation scheduling module is used to determine the difference between the material preparation time required and the material preparation time available as the material preparation difference working time, and schedule the material preparation work based on the material preparation difference working time.
9. An electronic device, characterized in that: It comprises a processor, a memory and a communication bus; the communication bus is used to connect the processor and the memory; the processor is used to execute the computer program stored in the memory to implement the production material preparation scheduling method as described in any one of claims 1-7.
10. A computer-readable storage medium, characterized in that: A computer program is stored thereon, and the computer program is used to enable a computer to execute the production material preparation scheduling method as described in any one of claims 1-7.
Citation Information
Cited By
Automatic steel bar production and control method and system
CN119536193A