Constructional engineering progress management method based on data analysis

By building multi-level dynamic graph models and real-time data analysis, the problems of multi-dimensional data fusion and resource optimization in construction project progress management are solved, efficient and scientific progress management and resource allocation are achieved, and project success rate is improved.

CN118966927APending Publication Date: 2024-11-15SHANDONG BOFA INTELLIGENT TECH CO LTD

Patent Information

Application Number
CN202411455246.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-18
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing construction project progress management methods lack the deep integration of multi-dimensional data, dynamic early warning mechanism and adaptive resource optimization allocation capabilities, resulting in inefficiency and waste of resources.

Method used

Build a multi-level dynamic graph model, collect and clean construction site data, perform critical path analysis, quantify uncertain factors, generate multi-objective optimization decision recommendations, and continuously optimize models and suggestions through real-time feedback loop mechanism.

Benefits of technology

It has achieved scientific and systematic construction project progress management, improved management efficiency, timeliness and accuracy of decision-making, ensured the rational use of resources, and reduced project risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118966927A_ABST
    Figure CN118966927A_ABST
Patent Text Reader

Abstract

The invention discloses a constructional engineering progress management method based on data analysis, and belongs to the technical field of data processing. The method comprises the following steps: step 1, constructing a multi-level dynamic graph model of a construction project to comprehensively represent a project structure and a dependency relationship; step 2, collecting construction site data and carrying out cleaning, standardization and structural processing; step 3, executing key path analysis on multiple scales, identifying and tracking key tasks which change dynamically, and ensuring consistency and accuracy of analysis results; 4, quantifying and simulating uncertain factors and interaction of the uncertain factors, and evaluating potential influence of the uncertain factors on the overall progress of the constructional engineering; step 5, generating decision suggestions under multi-objective optimization based on the multi-level dynamic graph model and the uncertainty analysis result; and step 6, establishing a real-time feedback circulation mechanism, performing comparative analysis on the actual progress in the implementation process and optimization suggestions, continuously collecting construction data, and updating the multi-level dynamic graph model and decision suggestions in time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of data processing, and more specifically, to a construction project progress management method based on data analysis. Background Art

[0002] In the field of construction engineering, project progress management is a key link to ensure timely completion of projects and cost control. Traditional progress management methods mainly rely on manual records and simple chart analysis, which is not only inefficient but also easily affected by human factors, resulting in deviations in project progress and waste of resources. With the increasing scale of construction projects and the continuous advancement of engineering technology, traditional progress management methods have been unable to adapt to the needs of modern construction projects.

[0003] In recent years, data analysis technology has gradually been applied in construction project progress management and has become an important means of optimizing progress management. Through the analysis of multi-dimensional data, project managers can monitor project progress in real time, identify potential risks, and make dynamic adjustments based on actual conditions. These data usually include but are not limited to project construction progress, resource usage, environmental factors, and historical data. Using advanced machine learning algorithms and statistical analysis methods, project progress and potential problems can be predicted more accurately.

[0004] However, although a variety of data analysis tools have been introduced into construction project progress management, existing technologies still face many challenges. For example, how to effectively integrate data from different sources, how to quantify progress deviations in real time, and how to establish a dynamic early warning mechanism are all key factors affecting project management effectiveness. In addition, current progress management methods often lack intelligent decision-making support capabilities and cannot achieve adaptive resource optimization based on real-time data.

[0005] To sum up, how to achieve the deep integration of multi-dimensional data, the establishment of a dynamic early warning mechanism, and the generation of adaptive resource optimization allocation plans in the progress management of construction projects has become a technical problem that needs to be solved urgently. Summary of the invention

[0006] In order to overcome a series of defects in the prior art, the purpose of this application is to provide a construction project progress management method based on data analysis to address the above problems, including the following steps.

[0007] Step 1: Build a multi-level dynamic graph model of the construction project to fully characterize the project structure and dependencies.

[0008] Step 2: Collect construction site data and clean, standardize and structure it to make it conform to the input format requirements of the multi-level dynamic graph model.

[0009] Step 3: Perform critical path analysis at multiple scales to identify and track dynamically changing key tasks and ensure the consistency and accuracy of the analysis results.

[0010] Step 4: Quantify and simulate the uncertainties and their interactions to assess their potential impact on the overall progress of the construction project.

[0011] Step 5: Generate decision recommendations under multi-objective optimization based on the multi-level dynamic graph model and uncertainty analysis results.

[0012] Step 6: Establish a real-time feedback loop mechanism to compare and analyze the actual progress during implementation with the optimization suggestions, continuously collect construction data, and timely update the multi-level dynamic graph model and decision-making suggestions.

[0013] Furthermore, step 1 includes the following steps.

[0014] Determine the main levels of the building project, establish independent but interrelated hierarchical structures, and form a complete hierarchical structure as the basic framework of the dynamic graph model.

[0015] Within each level and between different levels, identify and define the dependencies, sharing, and constraints between tasks, use nodes and edges in graph theory to represent tasks and their relationships, and build the topological structure of a multi-level graph model.

[0016] Add time attributes to each node and edge in the multi-level graph model, including the start and end time of the task, duration, and time dependency, to dynamically reflect the time-varying characteristics of the project, thereby transforming the static multi-level graph into a multi-level dynamic graph model.

[0017] Resource information and constraints are added to the multi-level dynamic graph model and associated with relevant task nodes to achieve resource allocation optimization and constraint satisfaction analysis.

[0018] Create interactive interfaces with real-time data sources for multi-level dynamic graph models, define data input formats, update algorithms, and trigger conditions to dynamically reflect the latest status of the project and improve the timeliness and accuracy of decision-making.

[0019] Use historical project data or simulation data to verify and test the constructed multi-level dynamic graph model to check whether it can accurately represent the project structure, reflect dependencies, and adapt to project changes. Adjust and optimize it according to the test results until it meets project management needs.

[0020] Furthermore, resource information and constraint conditions are added to the multi-level dynamic graph model and associated with relevant task nodes to achieve resource allocation optimization and constraint satisfaction analysis, including the following steps.

[0021] The human resources, equipment resources and material resources involved in construction projects are systematically classified, and the key attributes of each type of resource are defined. At the same time, the measurement units and evaluation indicators of the resources are determined, and quantitative standards for resource attributes are established.

[0022] Analyze and define various constraints, including total resource constraints, time window constraints, technical specification constraints, and site space constraints, and formally describe the constraints and convert them into quantifiable mathematical expressions or logical rules to ensure that the constraints can be accurately identified and processed.

[0023] In the multi-level dynamic graph model, resource requirement attributes are added to each task node, and a functional relationship between resource requirements and task execution parameters is established to achieve a dynamic association between resource allocation and task progress.

[0024] Bring all available resources under unified management to achieve dynamic allocation and scheduling of resources, including designing resource allocation priority rules, resource conflict resolution strategies and resource utilization efficiency evaluation methods to ensure that resources can be used rationally.

[0025] During the resource allocation process, the satisfaction of various constraints is verified in real time. When a constraint violation is found, timely warnings are issued and adjustment suggestions are provided to ensure the feasibility of the resource allocation plan.

[0026] A heuristic algorithm is used to find the optimal resource allocation plan while satisfying various constraints, and a plan evaluation index system is established to provide a quantitative basis for decision-making.

[0027] Furthermore, step 2 includes the following steps.

[0028] Develop a comprehensive data collection plan based on the needs of the multi-level dynamic graph model, including determining the type of data that needs to be collected, selecting appropriate data collection methods and tools, and developing collection frequency and sampling strategies.

[0029] According to the formulated data collection plan, data collection equipment is deployed at the construction site, including installing various sensors, configuring mobile devices and applications, and establishing a data transmission network.

[0030] The collected raw data is preliminarily processed and cleaned, including removing obvious errors or outliers, handling missing data, unifying data formats and units, and performing necessary data conversions.

[0031] The cleaned data is converted into a standardized and structured format to meet the input requirements of the multi-level dynamic graph model, including: converting unstructured data into structured form, normalizing numerical data, and organizing information according to predefined data patterns.

[0032] Perform comprehensive quality checks and validation on the converted data, including statistical analysis to detect potential anomalies, cross-validation of data from different sources to ensure consistency, and comparison with historical data or expert knowledge to verify plausibility.

[0033] The verified data is integrated and mapped to the corresponding nodes and relationships of the multi-level dynamic graph model, and the automatic import and update of data is realized.

[0034] Further, the verified data is integrated and mapped to the corresponding nodes and relationships of the multi-level dynamic graph model, and the automatic import and update of the data is realized, including the following steps.

[0035] Standardized mapping rules are formulated for different types of construction data, and the correspondence between data fields and graph model node attributes is defined in detail, including data type conversion rules, numerical mapping relationships and timestamp processing methods, to ensure that data can be accurately mapped to the correct location in the graph model.

[0036] The verified data is imported into the graph model according to the mapping rules, and data version control and conflict handling mechanisms are implemented to ensure data consistency in the case of concurrent updates.

[0037] By comparing the data timestamp and version number, the specific content that needs to be updated is determined, and the transaction mechanism is used to ensure the atomicity of the update operation. At the same time, a data update log is established to record all update operations.

[0038] Monitor abnormal situations in the data update process in real time, and set up a multi-level alarm mechanism. When an abnormality is found, an alarm will be issued in time and the preset exception handling process will be automatically executed.

[0039] After the data update is completed, the status update calculation of the graph model is triggered, including node status update, relationship attribute recalculation and key indicator derivation, to ensure that the graph model can accurately reflect the latest construction site status.

[0040] Furthermore, the node status update is expressed as: S(N i ,t)=f(T start (N i ),Tend(N i ),D(N i ,t),R(N i ,t)), where S(N i ,t) represents task N i The state at time t; T start (N i )、Tend(N i ) are task N iThe planned start time and the planned end time; D(N i ,t) represents task N i The actual progress at time t; R(N i ,t) represents task N i The resources used at time t; f represents how to update the overall status of the task based on the time, progress, and resource status of the task.

[0041] The relationship attribute recalculation formula is expressed as: A(E ij )=g(S(N i ,t),S(N j ,t),C(E ij ),R shared (E ij ,t)), where A(E ij ) represents task N i and N j Dependency relationship between ij Attributes; S(N j ,t) represents task N j The state at time t; C(E ij ) represents task N i and N j The constraints between shared (E ij ,t) indicates that in task N i and N j The shared resources or constraints between them; g represents how to update the properties of the dependency relationship according to changes in task status, constraints, and shared resources.

[0042] The formula for the derivation of key indicators is: KP(t)=h({S(N i ,t)},{A(E ij )},K), where KP(t) represents the critical path or other key indicators of the project at time t; {S(N i ,t)} represents all tasks N i The state set at time t; {A(E ij )} represents all task dependencies E ij A set of attributes; K represents other indicators related to the overall project progress; h represents how to derive the critical path and other key project progress indicators based on task status, dependencies and other factors.

[0043] Furthermore, step 3 includes the following steps.

[0044] Establish a multi-scale analysis framework and clearly define the various scale levels where critical path analysis is required, including the overall project level, main stage level, sub-project level and single task level.

[0045] For each scale level, its unique time granularity, resource constraints and critical evaluation criteria are determined to ensure that the analysis results at different scales are coordinated and supportive of each other.

[0046] Starting from the highest level, perform critical path analysis level by level and calculate the earliest start time, earliest finish time, latest start time, latest finish time and total float time of each task to identify the characteristics and influencing factors of the critical path and tasks.

[0047] Establish associations between analysis results at different scales, decompose high-level critical paths into low-level tasks, or aggregate low-level critical tasks into high-level critical paths, to ensure that the hierarchical relationships and dependencies between tasks are consistent.

[0048] Establish a dynamic update mechanism to automatically recalculate critical paths and critical tasks based on real-time data, achieve real-time monitoring of critical tasks, and identify new critical tasks in a timely manner.

[0049] Conduct sensitivity and stability analysis on the results of multi-scale critical path analysis, simulate scenarios of changes in task duration and resource fluctuations, observe changes in critical paths, identify tasks or factors that are likely to cause path changes, and provide guidance for risk management and resource optimization.

[0050] The results of the multi-scale critical path analysis are comprehensively verified and checked for consistency. Based on the verification results, the analysis methods and parameters are continuously optimized to improve the overall performance of the multi-scale critical path analysis.

[0051] Furthermore, the earliest start time ES(N i ) is calculated as: , where EF(N j ) represents task N j The earliest end time; P(N i ) represents task N i The set of predecessor tasks, that is, in task N i A task that must be completed before; ∣ is a commonly used symbol in set theory and mathematical logic, representing a set that satisfies certain conditions.

[0052] The earliest end time EF(N i ) is calculated as: EF(N i )=ES(N i )+D(N i ), where ES(N i ) represents task N i The earliest start time of D(N i ) indicates N i duration.

[0053] Latest end time LF(N i ) is calculated as: , where LS(N j ) represents task N j The latest start time of S(N i ) represents task N i The set of subsequent tasks that must wait for task N i Tasks that can only be started after they are completed.

[0054] Latest start time LS(N i ) is calculated as: LS(N i )=LF(N i )-D(N i ).

[0055] Total float time F(N i ) is calculated as: F(N i )=LS(N i )-ES(N i )=LF(N i )-EF(N i ).

[0056] Furthermore, step 4 includes the following steps.

[0057] Comprehensively identify and classify the key uncertainties that affect the progress of construction projects, assess their probability of occurrence and potential impact, and form a list of uncertainties.

[0058] The identified uncertainties are quantified and a probability distribution is assigned to each factor to represent its possible values ​​and probability of occurrence under different circumstances.

[0059] Construct an interaction model between uncertain factors, analyze the relationship between different factors and their mutual influence, and identify and quantify the impact of uncertain factors on the overall progress.

[0060] Monte Carlo simulation is performed based on the quantitative uncertainty factors and interaction model. A large number of possible project schedule results are generated through repeated sampling and calculation, so as to obtain a statistical analysis of the impact of different combinations of uncertain factors.

[0061] Analyze the simulation results, evaluate the potential impact of various uncertainties and their combinations on the overall progress of the construction project, calculate key performance indicators, and identify the factors that have the greatest impact on the progress.

[0062] Furthermore, the influence of uncertain factors on the overall progress is expressed as: G = ∑ k=1 n I k ·C k +∑k=1 n ∑ h=1 n a kh I k ·C h , where G represents the combined impact of all identified uncertainties on the overall progress of the construction project; I k represents the kth uncertainty factor U k The degree of direct impact; k represents the kth uncertainty factor U k The probability of occurrence; a kh represents the interactive influence of the kth uncertainty factor on the hth uncertainty factor; C h Represents the occurrence probability of the hth uncertain factor Uh.

[0063] Furthermore, step 5 includes the following steps.

[0064] Establish a comprehensive multi-objective optimization framework, clearly define key objectives and set appropriate weights and priorities for each objective, while identifying potential conflicts and trade-offs between objectives.

[0065] Based on the multi-level dynamic graphical model and uncertainty analysis results, a comprehensive optimization model is constructed to capture the complexity and dynamic characteristics of the project.

[0066] Run the comprehensive optimization model to generate a set of Pareto optimal solutions, and record the decision variable values, objective function values, and potential implementation strategies corresponding to each Pareto optimal solution.

[0067] Based on the Pareto optimal solution set, decision recommendations including resource reallocation, key task optimization and risk mitigation measures are generated, and the feasibility, potential impact and consistency of each recommendation are comprehensively evaluated.

[0068] Furthermore, based on the Pareto optimal solution set, decision recommendations including resource reallocation, key task optimization, and risk mitigation measures are generated, and the feasibility, potential impact, and consistency of each recommendation are comprehensively evaluated, including the following steps.

[0069] The Pareto optimal solution set is systematically clustered and feature analyzed. Similar solutions are classified and sorted according to their distribution positions and features in the target space. The characteristics of each type of solution are quantitatively and qualitatively analyzed to summarize their common decision-making features and differences.

[0070] For each type of Pareto optimal solution, detailed improvement suggestions are formulated from three dimensions: resource allocation, task plan adjustment, and risk management. These suggestions include determining the types and quantities of key resources that need to be reallocated, identifying key tasks that can be optimized and their specific adjustment plans, and designing corresponding risk mitigation measures. These suggestions are then integrated into a complete decision package to ensure mutual coordination and support between the suggestions.

[0071] Construct a decision proposal evaluation framework, evaluate each decision proposal from three dimensions: technical feasibility, economic feasibility, and management feasibility, set scoring criteria for each dimension and perform quantitative scoring.

[0072] Simulate the implementation effects of various decision recommendations under different project environments and conditions, and evaluate their potential impact on project key performance indicators.

[0073] Conduct consistency analysis between decision-making recommendations, check whether there are conflicts or contradictions between different recommendations, evaluate the synergy and potential impact between the recommendations, and ensure that all recommendations are coordinated and consistent to promote the realization of project goals.

[0074] Based on the evaluation results, decision-making recommendations are prioritized and integrated, and recommendations with higher scores, significant impacts and controllable risks are listed as priority implementation items. At the same time, a phased implementation plan is formulated to clarify the implementation sequence, time nodes and resource requirements of each recommendation, and corresponding monitoring indicators and adjustment mechanisms are designed to ensure that decision-making recommendations can be implemented in an orderly and efficient manner.

[0075] Furthermore, step 6 includes the following steps.

[0076] Compare the actual progress data with the optimization suggestions generated in step 5 to identify progress deviations and assess their potential impact on the overall project progress.

[0077] When the identified deviation exceeds the preset threshold, an alarm is automatically issued and notifications are sent to the corresponding level of management based on the severity of the deviation.

[0078] Automatically update multi-level dynamic graph models and re-evaluate project structures and dependencies based on continuously collected real-time data, either periodically or when significant deviations occur.

[0079] Based on the updated multi-level dynamic graph model and the latest project status, the multi-objective optimization algorithm is re-run to generate revised decision recommendations.

[0080] Compared with the prior art, the present application has the following beneficial effects.

[0081] This application constructs a multi-level dynamic graph model to comprehensively characterize the structure and dependencies of the construction project, combines the cleaning and standardization of field data, performs critical path analysis and identifies dynamic key tasks, further quantifies uncertainties and their interactions, simulates and evaluates the project progress, generates decision recommendations based on multi-objective optimization, and continuously optimizes the model and recommendations through a real-time feedback loop to ensure the timeliness and accuracy of the decision. BRIEF DESCRIPTION OF THE DRAWINGS

[0082] Figure 1 A flow chart of a construction project progress management method based on data analysis disclosed in an embodiment of the present application. DETAILED DESCRIPTION

[0083] In order to make the purpose, technical scheme and advantages of the implementation of the present invention clearer, the technical scheme in the embodiment of the present invention will be described in more detail below in conjunction with the drawings in the embodiment of the present invention. In the drawings, the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions. The described embodiments are part of the embodiments of the present invention, not all of the embodiments.

[0084] Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in the field without making any creative work shall fall within the scope of protection of the present invention.

[0085] The embodiments and directional terms described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be construed as limiting the present invention.

[0086] like Figure 1 As shown, the construction project progress management method based on data analysis includes the following steps.

[0087] Step 1: Build a multi-level dynamic graph model of the construction project to fully characterize the project structure and dependencies.

[0088] Step 2: Collect construction site data and clean, standardize and structure it to make it conform to the input format requirements of the multi-level dynamic graph model.

[0089] Step 3: Perform critical path analysis at multiple scales to identify and track dynamically changing key tasks and ensure the consistency and accuracy of the analysis results.

[0090] Step 4: Quantify and simulate the uncertainties and their interactions to assess their potential impact on the overall progress of the construction project.

[0091] Step 5: Generate decision recommendations under multi-objective optimization based on the multi-level dynamic graph model and uncertainty analysis results.

[0092] Step 6: Establish a real-time feedback loop mechanism to compare and analyze the actual progress during implementation with the optimization suggestions, continuously collect construction data, and timely update the multi-level dynamic graph model and decision-making suggestions.

[0093] The data-based construction project progress management method is a systematic process designed to improve the management efficiency and accuracy of construction projects. The following is a detailed analysis of each step, including the technical effects and their importance in practical application.

[0094] The multi-level dynamic graph model of the construction project in step 1 can fully characterize the project structure and dependencies, and graphically represent the connections and dependencies between various tasks, thus forming a dynamic and updateable network structure. Technically, the model is constructed using graph theory and network analysis methods, so that various elements in the project (such as tasks, resources, time, etc.) can be presented in the form of nodes and edges to ensure the visualization and traceability of information. Step 1 improves the understanding of the overall structure of the project, allowing managers to quickly identify critical paths and potential bottlenecks when facing complex projects, thereby optimizing resource allocation and scheduling. By dynamically updating the graph model, the project management team can grasp the progress of the project in real time, effectively respond to changes, and improve the flexibility and adaptability of the project.

[0095] Step 2 involves the use of sensors, drones, and mobile devices to comprehensively collect data from the construction site, such as personnel progress, material usage, and equipment status. The collected data often has problems such as noise, missing data, and inconsistent formats, so it must be cleaned, standardized, and structured. This process uses data preprocessing techniques such as data cleaning algorithms, outlier detection, and missing value interpolation to ensure that the data meets the input format requirements of the multi-level dynamic graph model. Step 2 can improve the reliability and consistency of the data and ensure that the basic data for subsequent analysis is accurate. In addition, through standardization, data from different sources and formats can be seamlessly integrated, which helps to establish a comprehensive construction data archive and provide a solid foundation for subsequent analysis and decision-making.

[0096] The critical path method (CPM) in step 3 is a project management technique used to determine the shortest time required to complete a project. By performing critical path analysis at multiple scales, dynamically changing critical tasks can be identified and tracked. Step 3 can improve the consistency and accuracy of the analysis results, especially when faced with the complexity and dynamic changes of the project. Multi-scale analysis means analyzing at different levels (such as tasks, stages, and overall projects), which can fully grasp the key nodes and time relationships of the project and promptly identify potential delays and risks. Through dynamically updated critical paths, project managers can allocate resources more effectively, ensure the timely completion of critical tasks, and reduce the risk of project delays.

[0097] Construction projects often face various uncertainties, such as weather changes, supply chain issues, personnel mobility, etc., and the impact of these factors on project progress cannot be ignored. Step 4 aims to quantify and simulate these uncertainties and their interactions to assess their potential impact on the overall progress of the construction project. By building uncertainty models and using simulation techniques (such as Monte Carlo simulation), different uncertainty scenarios can be evaluated and predicted. This step can provide project managers with a quantitative risk assessment to help them understand the specific impact of uncertainty on project progress and develop more scientific response strategies. By simulating different scenarios, we can better prepare for possible risks and reduce emergencies during project implementation.

[0098] Step 5 uses multi-objective optimization algorithms, such as genetic algorithms and particle swarm optimization, to find the best solution in terms of resource use, time scheduling, cost control, etc. This step can provide managers with efficient decision support to ensure the best balance between multiple goals. For example, decision suggestions can minimize costs and optimize resource utilization efficiency while ensuring project progress. In this way, construction plans can be formulated more scientifically, the overall project management level can be improved, and the success rate of the project can be increased.

[0099] Step 6 involves comparing and analyzing the actual progress of the implementation process with the optimization suggestions, collecting construction data in a timely manner, and updating the multi-level dynamic graph model and decision-making suggestions. Through real-time monitoring of construction progress and data analysis, deviations can be quickly identified and construction strategies can be adjusted in a timely manner. This process realizes the closed loop of project management, ensuring that each decision can be based on the latest field data and avoiding decision-making errors caused by information lag. In addition, the real-time feedback mechanism also promotes continuous learning and improvement, and can improve the management efficiency and quality of future projects by summarizing lessons learned.

[0100] To sum up, through the effective implementation of the above steps, scientific and systematic project management can be achieved, and the efficiency and success rate of construction projects can be improved.

[0101] Furthermore, step 1 includes the following steps.

[0102] Determine the main levels of the construction project, establish independent but interrelated hierarchical structures, and form a complete hierarchical structure as the basic framework of the dynamic graph model. This step involves systematic analysis and disassembly of the project to establish independent but interrelated hierarchical structures. Technically, this process can use methods such as the Analytic Hierarchy Process (AHP) to ensure that the constructed hierarchy is clear and logical. By identifying the different levels of the project (such as the overall project, main stages, subtasks, etc.), a complete hierarchical structure is formed, which can clearly show the relationship between the levels. This structure lays the foundation for the dynamic graph model, ensures the reasonable allocation of subsequent tasks and resources, and helps project managers grasp the overall situation in complex projects.

[0103] Within each level and between different levels, identify and define the dependencies, sharing, and constraints between tasks, and use nodes and edges in graph theory to represent tasks and their relationships, thereby building the topological structure of a multi-level graph model. This step uses nodes and edges in graph theory to represent tasks and their relationships, thereby building the topological structure of a multi-level graph model. Nodes represent tasks, while edges represent dependencies between tasks, such as the logical relationship between predecessor tasks and successor tasks. In this way, the interactions and connections between tasks can be intuitively displayed. This process improves the understanding of project tasks, allowing managers to clearly identify critical paths, adjust task scheduling and resource allocation in a timely manner, and optimize project progress.

[0104] Add time attributes to each node and edge in the multi-level graph model, including the start and end time of the task, duration, and time dependencies, to dynamically reflect the time-varying characteristics of the project, thereby transforming the static multi-level graph into a multi-level dynamic graph model. This step uses timestamp and duration data to transform the static multi-level graph into a dynamic multi-level dynamic graph model, which can reflect the time-varying characteristics of the project in real time, allowing managers to more accurately grasp the progress of the project and potential delays. Through dynamic time attributes, more precise progress control can be achieved to ensure that each task is completed on time, thereby improving the efficiency of the overall project.

[0105] Resource information and constraints are added to the multi-level dynamic graph model and associated with relevant task nodes to achieve resource allocation optimization and constraint satisfaction analysis. In this step, each task node can be associated with its required resources, such as manpower, equipment, and materials, while also considering various constraints (such as resource availability, legal and regulatory restrictions, etc.). This process improves the scientificity and rationality of resource management and ensures that the project operates efficiently with limited resources. By optimizing resource allocation, project managers can reduce costs, reduce waste, and improve the overall benefits of the project.

[0106] Create an interactive interface with the real-time data source for the multi-level dynamic graph model, define the data input format, update algorithm and trigger conditions to dynamically reflect the latest status of the project and improve the timeliness and accuracy of decision-making. Creating an interactive interface with the real-time data source for the multi-level dynamic graph model is a key link to improve the timeliness and accuracy of decision-making. This process includes defining the data input format, updating the algorithm and trigger conditions so that the model can dynamically reflect the latest status of the project. Through the input of real-time data, it is possible to obtain timely information on the progress of on-site construction, resource usage, and task completion, so as to make rapid responses and adjustments. This step improves the real-time and flexibility of project management, enabling managers to make effective decisions quickly in a complex and dynamic construction environment and reduce the risks caused by information lags.

[0107] Use historical project data or simulation data to verify and test the constructed multi-level dynamic graph model to check whether it can accurately represent the project structure, reflect dependencies, and adapt to project changes, and adjust and optimize according to the test results until it meets the project management needs. Use historical project data or simulation data to verify and test the constructed multi-level dynamic graph model to ensure that the model can accurately represent the project structure, reflect dependencies, and adapt to project changes. This process can use different verification methods, such as regression testing and sensitivity analysis, to check the performance of the model in different scenarios, and adjust and optimize according to the test results. This step ensures that the constructed model meets the needs of actual project management and improves the adaptability and accuracy of the model. Through continuous verification and optimization, the project management team can ensure that the model always maintains efficient decision-making support capabilities in a complex construction environment, providing strong technical support for the successful implementation of the project.

[0108] In summary, building a multi-level dynamic graph model for a construction project can provide a scientific basis for project progress management through the effective implementation of the above steps. Through a clear hierarchy, clear task relationships, dynamic time attributes, optimized resource allocation, real-time data interaction, and continuous model verification, managers can achieve more efficient and flexible project management, thereby improving the success rate and quality of the overall construction project.

[0109] Furthermore, resource information and constraint conditions are added to the multi-level dynamic graph model and associated with relevant task nodes to achieve resource allocation optimization and constraint satisfaction analysis, including the following steps.

[0110] The human resources, equipment resources and material resources involved in the construction project are systematically classified, and the key attributes of each type of resource are defined. At the same time, the measurement units and evaluation indicators of the resources are determined, and the quantitative standards of resource attributes are established. Before integrating resource information and constraints, it is necessary to first systematically classify the human resources, equipment resources and material resources involved in the construction project. This classification process should take into account the different types, uses and characteristics of resources. Define the key attributes of each type of resource, such as the skill level of human resources, the performance parameters of equipment resources, the specifications and costs of material resources, and determine the measurement units and evaluation indicators of resources. This step can provide clear standards and basis for subsequent resource management, establish quantitative standards for resource attributes, and make resource management more scientific and transparent. Through the clear classification and definition of resources, the availability and demand of resources can be accurately evaluated, thereby providing support for subsequent resource allocation.

[0111] Analyze and define various constraints, including total resource constraints, time window constraints, technical specification constraints, and site space constraints, and formally describe the constraints and convert them into quantifiable mathematical expressions or logical rules to ensure that the constraints can be accurately identified and processed. Analyzing and defining various constraints is an important part of optimizing resource allocation. These constraints can include total resource constraints (such as the maximum available amount of manpower and materials), time window constraints (such as the start and end time of the task), technical specification constraints (such as construction standards and safety requirements), and site space constraints (such as equipment layout and use restrictions). Formalize these constraints and convert them into quantifiable mathematical expressions or logical rules so that they can be accurately identified and processed. This step can establish a strict framework for resource management, ensuring that various constraints are fully considered in the resource allocation process, avoiding resource waste and management failure. Through this quantitative method, the feasibility of resource use can be effectively evaluated to ensure that various standards and requirements are met during planning and execution.

[0112] In the multi-level dynamic graph model, resource requirement attributes are added to each task node, and a functional relationship between resource requirements and task execution parameters is established to achieve a dynamic association between resource allocation and task progress. This step requires analyzing the specific resources required for each task, including manpower, equipment, and materials, and establishing a functional relationship with these resources in the task node. This association allows project managers to dynamically adjust the allocation and configuration of resources according to the progress of the task, ensuring the effective use of resources and the smooth progress of the task. By combining resource requirement attributes with task execution parameters, the resource requirements of the task can be understood in real time, and then corresponding measures can be taken to optimize resource allocation. This process improves the flexibility and adaptability between tasks and resources, allowing managers to quickly respond to changes and improve construction efficiency in a complex construction environment.

[0113] Integrate all available resources into unified management to achieve dynamic allocation and scheduling of resources, including designing resource allocation priority rules, resource conflict resolution strategies and resource utilization efficiency evaluation methods to ensure that resources can be used reasonably. Integrating all available resources into unified management is the core of ensuring dynamic resource allocation and scheduling. By designing resource allocation priority rules, resource conflict resolution strategies and resource utilization efficiency evaluation methods, resources can be ensured to be used reasonably. This process requires the formulation of clear rules to guide the allocation and scheduling of resources, ensuring that the resource needs of key tasks are met first, while effectively avoiding conflicts and duplication between resources. Dynamic management requires not only real-time monitoring and updating of resources, but also timely adjustment of resource allocation strategies to cope with emergencies at the construction site. Through this systematic management method, the efficiency and rationality of resource use can be improved, thereby reducing construction costs and risks.

[0114] During the resource allocation process, the satisfaction of various constraints is verified in real time. When a constraint violation is found, a warning is issued in time and adjustment suggestions are provided to ensure the feasibility of the resource allocation plan. During the resource allocation process, real-time verification of the satisfaction of various constraints is the key to ensuring the feasibility of the resource allocation plan. When a constraint violation is found, a warning should be issued in time and adjustment suggestions should be provided. This process not only helps to find problems in a timely manner, but also provides decision-making support for managers to help them quickly respond. By monitoring and analyzing data, it is possible to evaluate whether the current resource configuration meets the preset constraints and make necessary adjustments according to the situation. This real-time monitoring improves the flexibility and adaptability of project management, enabling projects to better cope with various challenges in an uncertain construction environment and ensure the dual guarantee of progress and quality.

[0115] Using heuristic algorithms, we can find the optimal resource allocation solution under the premise of meeting various constraints, and establish a solution evaluation index system to provide a quantitative basis for decision-making. This step can not only effectively explore various possibilities of resource allocation, but also find the best resource allocation solution under actual construction conditions through the optimization process of the algorithm. Heuristic algorithms can intelligently schedule resources based on historical data and real-time information to improve resource utilization and project progress. By establishing an evaluation index system, comprehensive decision analysis can be performed based on different goals (such as cost, time, resource utilization, etc.). This step improves the scientificity and rationality of resource allocation, enabling project managers to make more informed choices in a complex decision-making environment.

[0116] In summary, the process of adding resource information and constraints to the multi-level dynamic graph model and associating them with task nodes can achieve the optimization of resource allocation and constraint satisfaction analysis through the effective implementation of each step. Through the classification and quantification of resources, the definition and formalization of constraints, the dynamic association of task resource requirements, unified resource management, and real-time monitoring and optimization, the overall efficiency and success rate of construction projects can be significantly improved, providing solid support for the smooth progress of the project.

[0117] Furthermore, step 2 includes the following steps.

[0118] According to the needs of the multi-level dynamic graph model, a comprehensive data collection plan is formulated, including determining the type of data to be collected, selecting appropriate data collection methods and tools, and formulating collection frequency and sampling strategies. In this step, it is necessary to clarify the type of data to be collected, such as construction progress, resource usage, environmental conditions, worker status, etc. Selecting appropriate data collection methods and tools, such as sensors, mobile devices, drones, etc., is the key to ensuring data accuracy and real-time performance. In addition, a reasonable collection frequency and sampling strategy must be formulated to balance the amount of data with processing efficiency to ensure the real-time and accuracy of the collected data. This step enables data collection to be carried out efficiently through precise planning and design, ensuring that subsequent data analysis and model building are based on a reliable information foundation, and ultimately improving the management level of construction projects.

[0119] According to the formulated data collection plan, data collection equipment is deployed at the construction site, including installing various sensors, configuring mobile devices and applications, and establishing a data transmission network. This step involves the installation and configuration of multiple devices, including sensors, cameras, mobile devices, etc., to achieve comprehensive monitoring of the construction process. Installing sensors can collect environmental data such as temperature, humidity, and vibration in real time. Configuring mobile devices and applications can facilitate workers to enter and feedback data. Establishing a data transmission network ensures that data can be transmitted to the central system in a timely and secure manner. This step improves the comprehensiveness and real-time nature of data collection through the combination of multiple data collection methods, allowing project managers to keep abreast of the dynamic situation of the construction site at any time and provide timely support for subsequent decision-making.

[0120] The collected raw data is preliminarily processed and cleaned, including removing obvious errors or outliers, handling missing data, unifying data formats and units, and performing necessary data conversions. This step includes removing obvious errors or outliers, handling missing data, unifying data formats and units, and performing necessary data conversions. Through these processes, the data quality can be significantly improved, making it more suitable for subsequent analysis and use. This step eliminates noise and inconsistencies through data cleaning, ensuring that subsequent analysis is based on high-quality data, thereby improving the accuracy and reliability of data analysis.

[0121] The cleaned data is converted into a standardized and structured format to meet the input requirements of the multi-level dynamic graph model, including: converting unstructured data into a structured form, normalizing numerical data, and organizing information according to predefined data patterns. This step specifically includes converting unstructured data (such as text, images) into a structured form to facilitate model processing; normalizing numerical data to eliminate the impact of different dimensions; and organizing information according to predefined data patterns. The technical effect of this process is that the structured data form improves the availability and ease of processing of the data, laying a good foundation for subsequent analysis and modeling. At the same time, the standardized data format makes subsequent data processing and analysis more efficient, avoiding complex problems caused by inconsistent data formats.

[0122] Perform a comprehensive quality check and validation on the converted data, including statistical analysis to detect potential anomalies, cross-validation of data from different sources to ensure consistency, and comparison with historical data or expert knowledge to verify rationality. This step includes statistical analysis to detect potential anomalies, cross-validation of data from different sources to ensure consistency, and comparison with historical data or expert knowledge to verify rationality. Through these methods, problems in the data can be identified in a timely manner and adjusted and processed accordingly. This process ensures the accuracy and consistency of the data through strict data quality management, enhances the application value of the data in the multi-level dynamic graph model, and provides a solid foundation for subsequent decision-making.

[0123] The verified data is integrated and mapped to the corresponding nodes and relationships of the multi-level dynamic graph model, and the data is automatically imported and updated. This step can associate various types of data with different tasks, resources and time dimensions in the model, thereby realizing dynamic updates. This process achieves efficient connection between data and models, allowing the multi-level dynamic graph model to reflect the latest status of the construction site in real time, enhancing the timeliness and accuracy of decision-making. At the same time, automated data import and update reduces the need for manual intervention and improves the intelligence level of the system.

[0124] Further, the verified data is integrated and mapped to the corresponding nodes and relationships of the multi-level dynamic graph model, and the automatic import and update of the data is realized, including the following steps.

[0125] Standardized mapping rules are formulated for different types of construction data, and the correspondence between data fields and graph model node attributes is defined in detail, including data type conversion rules, numerical mapping relationships, and timestamp processing methods, to ensure that data can be accurately mapped to the correct location in the graph model. The mapping rules define in detail the correspondence between data fields and graph model node attributes, covering data type conversion rules, numerical mapping relationships, and timestamp processing methods. For example, for construction progress data, it is necessary to clarify its corresponding node attributes in the graph model, such as "task status" and "estimated completion time". This process ensures that data from different sources can be accurately mapped to the correct location in the graph model, thereby avoiding analysis errors caused by inconsistent data. Through standardized mapping rules, data integration becomes systematic, reducing manual intervention and improving the efficiency and accuracy of data processing.

[0126] According to the mapping rules, the verified data is imported into the graph model, and data version control and conflict handling mechanisms are implemented to ensure data consistency in the case of concurrent updates. The data version control in this step ensures the traceability of historical data, allowing project managers to view data change records at any time. At the same time, the conflict handling mechanism takes corresponding measures to ensure data consistency and accuracy when data update conflicts occur by setting priorities, timestamps, etc. This step ensures the security and reliability of the data import process by introducing version control and conflict handling mechanisms, avoids confusion and errors caused by data conflicts, and provides a solid foundation for subsequent data analysis.

[0127] By comparing the data timestamp and version number, the specific content that needs to be updated is determined, and the transaction mechanism is used to ensure the atomicity of the update operation. At the same time, a data update log is established to record all update operations. This step means that during the data update process, either all update operations are completed successfully or no operations are performed, thus avoiding inconsistencies caused by partial updates of the data. At the same time, a data update log is established to record all update operations to provide a basis for subsequent data tracing and troubleshooting. This step enhances the security and traceability of data updates through transaction mechanisms and log records, allowing project managers to comprehensively monitor and manage data changes.

[0128] Real-time monitoring of abnormal situations during data update, and setting up a multi-level alarm mechanism. When an abnormality is found, an alarm is issued in time, and the preset exception handling process is automatically executed. By setting up a multi-level alarm mechanism, an alarm can be issued in time when an abnormality is found, and the preset exception handling process is automatically executed. This mechanism can respond to potential problems quickly and reduce the impact of failures on project progress. For example, if an abnormal value or data inconsistency occurs during the data update process, it will be automatically detected and processed to ensure the accuracy and integrity of the data. This step improves the reliability and intelligence level through real-time monitoring and exception handling, allowing project managers to respond to possible problems in a timely manner and ensure that the management of the construction site is always under control.

[0129] After the data update is completed, the state update calculation of the graph model is triggered, including node status update, relationship attribute recalculation and key indicator derivation, to ensure that the graph model can accurately reflect the latest construction site status. This step can ensure that the graph model can timely reflect the latest construction progress, resource usage and other relevant information, thereby providing accurate decision support for project managers. Through dynamic updates, project managers can grasp the changes on the construction site in real time, quickly adjust the construction plan, optimize resource allocation, and ensure the smooth progress of the project. This step enhances the real-time and accuracy of the multi-level dynamic graph model through state update calculation, making it a powerful tool in project management.

[0130] In summary, integrating and mapping the verified data to the corresponding nodes and relationships of the multi-level dynamic graph model and realizing the automatic import and update of data is a complex and systematic process. The efficient implementation of each step not only improves the accuracy and reliability of data processing, but also provides strong support for the progress management of construction projects, enabling project managers to make scientific decisions in a dynamically changing environment and promote the smooth progress of the project.

[0131] Furthermore, the node status update is expressed as: S(N i ,t)=f(T start (N i ),Tend(N i ),D(N i ,t),R(N i ,t)), where S(N i ,t) represents task N i The state at time t; T start (N i )、Tend(N i ) are task N i The planned start time and the planned end time of D(N i ,t) represents task N i The actual progress at time t; R(N i ,t) represents task N i The resources used at time t; f represents how to update the overall status of the task based on the time, progress, and resource status of the task. The node status update formula allows managers to monitor and evaluate the status of tasks in real time, thereby quickly identifying potential delays or resource shortages. By dynamically updating the node status, resource allocation can be adjusted in a timely manner and the construction sequence can be optimized to ensure that the project proceeds as planned. For example, if the actual progress of a task lags behind the planned progress, the completion of the task can be facilitated by adjusting resource allocation or work arrangements. This real-time feedback mechanism enables project management to be more flexible in dealing with uncertainties and improve the overall efficiency of the project.

[0132] The relationship attribute recalculation formula is expressed as: A(E ij )=g(S(N i ,t),S(N j ,t),C(E ij ),R shared (E ij ,t)), where A(E ij ) represents task N i and N j Dependency relationship between ij Attributes; S(N j ,t) represents task N j The state at time t; C(E ij ) represents task N i and N j The constraints between shared (E ij ,t) indicates that in task N i and N j The resources or constraints shared between tasks; g represents how to update the dependency attributes according to the changes in task status, constraints, and shared resources. By recalculating the relationship attributes, project managers can update the dependencies between tasks in real time to reflect changes in task status. For example, if task N i The progress of task N is delayed, which will affect j By dynamically recalculating the properties of dependencies, it is possible to identify tasks that need to be processed first, thereby optimizing the overall project schedule. This approach enhances project flexibility and enables managers to respond to dynamically changing construction environments.

[0133] The formula for the derivation of key indicators is: KP(t)=h({S(N i ,t)},{A(E ij )},K), where KP(t) represents the critical path or other key indicators of the project at time t; {S(N i ,t)} represents all tasks N i The state set at time t; {A(E ij )} represents all task dependencies E ijThe key indicators are a set of attributes; K represents other indicators related to the overall progress of the project; and h represents how to derive the critical path and other key project progress indicators based on task status, dependencies, and other factors. By deriving key indicators, it is possible to identify which tasks are most critical to the overall progress of the project, and take timely measures to ensure the smooth completion of these key tasks. For example, if a task on the critical path is delayed, managers can quickly adjust resource allocation or scheduling plans to prevent the delay from affecting the overall project progress. In this way, project managers can dynamically evaluate the progress of the project and make quick decisions when necessary to reduce risks and increase the success rate of the project.

[0134] Furthermore, step 3 includes the following steps.

[0135] Establish a multi-scale analysis framework and clearly define the various scale levels that require critical path analysis, including the overall project level, the main stage level, the sub-project level, and the single task level. This hierarchical approach allows you to develop corresponding strategies and plans for different analysis needs and problems. The analysis at the overall project level is a global perspective that can grasp the macro progress and resource allocation of the project; the main stage level helps to identify the key nodes and milestones of each stage; the sub-project level can deeply analyze the construction status of each sub-division and discover potential bottlenecks or problems; and the analysis at the single task level focuses on the execution of specific tasks. Through this structured approach, you can effectively grasp the overall status of the project, improve the scientificity and pertinence of decision-making, and provide a basis for subsequent detailed analysis.

[0136] For each scale level, determine its unique time granularity, resource constraints and critical evaluation criteria to ensure that the analysis results at different scales are coordinated and supported. This step ensures that the analysis results between different levels are coordinated and consistent. For example, the overall project level may focus on the time granularity of weeks or months, while the single task level can be refined to hours or minutes. Resource constraints include human, material and financial constraints. Managers must find a balance between the availability of resources and the needs of the project. In addition, the setting of critical evaluation criteria such as the impact of tasks and resource consumption rates not only helps the project team identify priority tasks, but also effectively prevents potential risks. Through such standardized settings, the analysis results at each level can form a closed loop to ensure the smooth transmission and sharing of information, thereby improving the efficiency of overall project management.

[0137] Starting from the highest level, perform critical path analysis step by step, and calculate the earliest start time, earliest end time, latest start time, latest end time and total float time of each task, identify the characteristics and influencing factors of critical paths and tasks. This analysis process not only reveals the dependencies between tasks, but also identifies which tasks are critical to the project schedule, thus providing a basis for the priority allocation of resources. Through dynamic critical path calculation, you can clearly see the time pressure points of the project, so as to carry out risk management and scheduling more targetedly. This step can reflect the dynamic changes of the project in real time and update the critical path in time, so that project managers can quickly respond to potential problems and challenges to ensure the smooth progress of the project.

[0138] Establish the association between the analysis results of different scales, decompose the high-level critical path into low-level tasks, or aggregate the low-level critical tasks into the high-level critical path, to ensure the consistency of the hierarchical relationship and dependency between tasks. This process ensures the consistency of the hierarchical relationship and dependency between tasks. By decomposing the high-level critical path into low-level tasks, managers can deeply understand the mutual influence between tasks. In addition, reverse aggregation of low-level critical tasks to high-level critical paths can ensure the consistency between the overall goals of the project and specific tasks. This hierarchical analysis enables the project team to effectively coordinate between different levels to ensure that all tasks work towards a common goal. This step significantly improves the transparency and information sharing of project management, and reduces the management risks caused by information asymmetry.

[0139] Establish a dynamic update mechanism to automatically recalculate critical paths and key tasks based on real-time data, realize real-time monitoring of key tasks, and identify new key tasks in a timely manner. By real-time monitoring of the progress of key tasks, new key tasks can be quickly identified, and plans and resource allocations can be adjusted in a timely manner based on the latest progress data. This mechanism not only improves the ability to respond to emergencies, but also ensures the achievement of project goals. The implementation of the dynamic update mechanism closely combines real-time data with the analysis process, making the decision-making process of project management more scientific and efficient. This step realizes closed-loop control of project management through continuous monitoring and feedback, thereby effectively reducing project risks and improving the success rate.

[0140] Conduct sensitivity and stability analysis on the results of multi-scale critical path analysis, simulate scenarios of task duration changes and resource fluctuations, observe changes in critical paths, identify tasks or factors that are prone to path changes, and provide guidance for risk management and resource optimization. This process helps identify tasks or factors that are prone to path changes, and provides guidance for risk management and resource optimization. The implementation of sensitivity analysis not only reveals the most critical tasks and risk points in the project, but also provides data-based decision support for project managers. By simulating different scenarios, possible challenges can be foreseen in advance, so that corresponding preventive measures can be taken. This step improves the foresight of project management, enabling managers to make more robust decisions in a dynamic environment.

[0141] The results of the multi-scale critical path analysis are fully verified and checked for consistency. Based on the verification results, the analysis methods and parameters are continuously optimized to improve the overall performance of the multi-scale critical path analysis. This process requires cross-validation of the analysis results at different levels to ensure the accuracy and consistency of the information. By continuously optimizing the analysis methods and parameters, the overall performance of the multi-scale critical path analysis can be improved based on the verification results. This step improves the trust and transparency of project management by establishing a rigorous verification mechanism, allowing all stakeholders to trust the analysis results more and make more confident choices in project decision-making. Through these systematic steps, project managers can effectively improve the execution and efficiency of the project and ensure the successful implementation of construction projects.

[0142] Furthermore, the earliest start time ES(N i ) is calculated as: , where EF(N j ) represents task N j The earliest end time; P(N i ) represents task N i The set of predecessor tasks, that is, in task N i The task that must be completed before; | is a commonly used symbol in set theory and mathematical logic, representing a set that satisfies a certain condition. This means that task N i The earliest start time of a task depends on the completion time of all its predecessor tasks. By selecting the latest finish time of the predecessor tasks as the start time of the current task, all dependencies are respected. This calculation can help project managers clearly understand which tasks can be started and when, so as to optimize resource allocation and work scheduling and prevent delays caused by improper time scheduling between tasks.

[0143] The earliest end time EF(N i ) is calculated as: EF(N i )=ES(N i )+D(Ni ), where ES(N i ) represents task N i The earliest start time of D(N i ) indicates N i By adding the earliest start time of a task to its duration, the earliest end time of the task can be quickly calculated, providing basic data for project scheduling, allowing the project team to evaluate the completion of each task and make adjustments in the overall timeline. This method ensures a logical order between tasks and reduces potential conflicts caused by improper task order.

[0144] Latest end time LF(N i ) is calculated as: , where LS(N j ) represents task N j The latest start time of S(N i ) represents task N i The set of subsequent tasks that must wait for task N i The core of this formula is to ensure that after task N is completed, i Before the completion time, all subsequent tasks that depend on it can be started on time. By calculating the latest start time of all subsequent tasks, we can determine the time when task N i The latest completion time of the project is calculated, thus providing an effective time constraint for the overall progress of the project. This calculation is crucial for dealing with the risk of project delays and can effectively support time management.

[0145] Latest start time LS(N i ) is calculated as: LS(N i )=LF(N i )-D(N i By subtracting the task duration from the late finish time, the project manager can calculate the task N i The latest time that a task can be started without affecting the start of subsequent tasks. This calculation helps set task priorities, allowing project teams to schedule tasks appropriately, minimize the risk of delays, and improve overall project efficiency.

[0146] Total float time F(N i ) is calculated as: F(N i )=LS(N i )-ES(N i )=LF(N i )-EF(N i). Total float is a key indicator of task flexibility, which indicates the amount of time a task can be delayed without affecting the overall progress of the project. By calculating the difference between the latest start time and the earliest start time (or the difference between the latest finish time and the earliest finish time), you can understand the time margin of the task. This indicator is important for priority adjustment, resource allocation and risk management. If the total float time of a task is zero, it means that the task is a critical task and any delay will directly affect the completion time of the project.

[0147] Furthermore, step 4 includes the following steps.

[0148] Comprehensively identify and classify the key uncertainties that affect the progress of construction projects, assess their probability of occurrence and potential impact, and form a list of uncertainties. This step analyzes factors that may lead to progress deviations from multiple perspectives, such as weather changes, delayed material supply, labor shortages, technical failures, construction plan adjustments, etc. Through systematic classification, these uncertainties are divided into different categories, such as external environmental factors, internal management factors, technical factors, etc. This process helps project managers better understand the overall situation that affects the progress of the project and provides a framework for subsequent quantification and analysis. At the same time, different categories of factors can correspond to different management strategies to enhance the flexibility of the project in dealing with uncertainty.

[0149] The identified uncertainties are quantified, and a probability distribution is assigned to each factor to represent its possible values ​​and probability of occurrence under different circumstances. Through quantification, the impact of each uncertain factor becomes measurable, and its potential impact on the construction period can be represented by a specific numerical value. For example, weather factors can be quantified by the number of rainy days and the temperature fluctuation range, and supply chain delays can be represented by the number of delay days. Subsequently, a probability distribution (such as normal distribution, uniform distribution) is assigned to each uncertain factor to represent the value range and probability of occurrence of the factor under different circumstances. This process provides a data basis for subsequent simulation and analysis, and makes uncertainty management more scientific and operational.

[0150] Construct an interaction model between uncertain factors, analyze the relationship between different factors and their mutual influence, and identify and quantify the impact of uncertain factors on the overall progress. The purpose of constructing an interaction model between uncertain factors is to further analyze the mutual influence between various factors and their combined impact on the overall progress. For example, a delay in material supply may affect the construction progress, but if bad weather or human resource shortages occur at the same time, the impact of the delay may be amplified. By building an interaction model, it is possible to analyze how these factors work together to form a complex impact on the project progress. This process not only reveals the independent impact of each factor, but also reveals their interrelationships, allowing project managers to more fully understand the multidimensional impact of uncertainty on the project progress and formulate corresponding mitigation measures.

[0151] Monte Carlo simulation is performed based on the quantitative uncertainty factors and interaction model, and a large number of possible project progress results are generated through repeated sampling and calculation, so as to obtain a statistical analysis of the impact of different combinations of uncertain factors. Monte Carlo simulation generates multiple possible results of project progress by repeatedly sampling the probability distribution of each uncertain factor. This step can generate a large number of progress prediction scenarios and perform statistical analysis on project progress under different combinations of uncertain factors. Through a large number of simulation runs, it is possible to have a more accurate prediction of the combined impact of uncertain factors and obtain a progress estimate range covering multiple possibilities. This provides a basis for flexible project management and allows early action under uncertain conditions.

[0152] Analyze the simulation results, evaluate the potential impact of various uncertain factors and their combinations on the overall progress of the construction project, calculate key performance indicators, and identify the factors that have the greatest impact on the progress. By analyzing a large number of simulation results, it is possible to determine which factors are the main risk points in progress management, so that resources can be allocated to high-risk tasks or stages in priority. This process not only improves the accuracy of project progress forecasts, but also provides specific action guidelines for risk management. Based on this result, project managers can formulate emergency plans, adjust resource allocation, and optimize construction plans in a timely manner to reduce the risk of project progress being affected by uncertain factors.

[0153] In summary, through the above series of steps, construction project progress management has shifted from passive response to active prediction and optimization. The comprehensive identification, quantification and establishment of interactive models of uncertain factors provide a solid foundation for subsequent simulations, while the application of Monte Carlo simulation provides project managers with clear means of progress assessment and risk identification. Finally, through in-depth analysis of the simulation results, the key factors that have the greatest impact on the progress can be effectively identified, helping the project team optimize resources, reduce risks, and increase project success rates. This series of steps can significantly improve the accuracy and efficiency of project management in actual operations, and provide strong technical support for the smooth progress of construction projects.

[0154] Furthermore, the influence of uncertain factors on the overall progress is expressed as: G = ∑ k=1 n I k ·C k +∑ k=1 n ∑ h=1 n a kh I k ·C h , where G represents the combined impact of all identified uncertainties on the overall progress of the construction project; I k represents the kth uncertainty factor U k The degree of direct impact; k represents the kth uncertainty factor U k The probability of occurrence; a kh represents the interactive influence of the kth uncertainty factor on the hth uncertainty factor; C h represents the probability of occurrence of the hth uncertainty factor Uh. In this way, the combined impact of uncertainties can be assessed more accurately, especially when the interrelationships between these factors are complex. By analyzing direct impacts and interactions, the most critical uncertainties can be prioritized and effective countermeasures can be formulated, thereby optimizing the project schedule management strategy. This formulaic evaluation method provides quantitative support for project risk management and decision-making, helping to identify potential risks in advance and formulate corresponding mitigation measures.

[0155] Furthermore, step 5 includes the following steps.

[0156] Establish a comprehensive multi-objective optimization framework, clearly define key objectives and set appropriate weights and priorities for each objective, while identifying potential conflicts and trade-offs between objectives. Construction projects often involve multiple conflicting objectives, such as minimizing costs, shortening construction time, maximizing resource utilization, etc. By setting weights and priorities, the optimization framework can weigh the conflicts between various objectives and ensure that the most important objectives are given priority. For example, in an emergency project, the construction time may be more important than the cost, so the weight of shortening the construction time will be higher. The construction of this framework helps project managers make balanced decisions between multiple objectives and ensure that the decision results meet the overall needs of the project.

[0157] Based on the multi-level dynamic graph model and uncertainty analysis results, a comprehensive optimization model is constructed to capture the complexity and dynamic characteristics of the project. By combining uncertainty analysis, the comprehensive optimization model can take into account the impact of uncertain factors on resources and progress in the actual project process. For example, external factors such as uncertainty in resource supply and weather changes may lead to dynamic adjustments to the project schedule. By introducing a multi-level dynamic graph model, the comprehensive optimization model can capture dynamic changes at different levels (such as the overall project, stage, and task level) to achieve comprehensive modeling of project complexity. This process provides accurate and flexible data support for subsequent optimization calculations, effectively improving the model's ability to adapt to complexity and variability.

[0158] Run the comprehensive optimization model to generate a Pareto optimal solution set, and record the decision variable values, objective function values, and potential implementation strategies corresponding to each Pareto optimal solution. A Pareto optimal solution means that while keeping one goal unchanged, it is impossible to obtain better results on other goals. By generating multiple Pareto optimal solutions, decision makers can be provided with a variety of feasible solutions covering different resource allocations and task arrangements. For example, in the Pareto solution set, some solutions may give priority to shortening the construction period, but sacrifice some cost-effectiveness; while other solutions extend the project duration while ensuring low costs. This approach gives project managers more room for choice when faced with different trade-offs, allowing them to make more flexible decisions.

[0159] Based on the Pareto optimal solution set, decision recommendations including resource reallocation, key task optimization and risk mitigation measures are generated, and the feasibility, potential impact and consistency of each recommendation are comprehensively evaluated. This process helps to transform theoretical optimization results into practical and executable strategic recommendations. By evaluating the feasibility and potential impact of each recommendation, we can have a clearer understanding of the actual impact of different decisions on the project, especially the effects of resource reallocation and key task optimization. The generation and evaluation of decision recommendations ensure that when facing a complex and changing project environment, the project execution plan can be flexibly adjusted according to different risks and goals to maximize the possibility of project success.

[0160] In summary, step 5 can comprehensively improve the decision support capability of project management by establishing a multi-objective optimization framework, building a comprehensive optimization model, generating a Pareto optimal solution set, and generating detailed decision recommendations. Step 5 enables project management to transition from traditional static planning to a dynamic, multi-objective optimization stage, and can cope with complex uncertainties and conflicting goals in engineering.

[0161] Furthermore, based on the Pareto optimal solution set, decision recommendations including resource reallocation, key task optimization, and risk mitigation measures are generated, and the feasibility, potential impact, and consistency of each recommendation are comprehensively evaluated, including the following steps.

[0162] Systematic clustering and feature analysis are performed on the Pareto optimal solution set. Similar solutions are classified and sorted according to their distribution positions and features in the target space. The characteristics of each type of solution are quantitatively and qualitatively analyzed to summarize their common decision-making features and differences. By systematically clustering and feature analysis of the Pareto optimal solution set, the distribution law of the optimal solution in the target space can be understood more effectively. Different solutions correspond to different resource allocations, construction schedules, and risk management solutions, and cluster analysis helps to extract solutions with similar features from a large number of solutions. Quantitative and qualitative analysis of each type of solution can summarize the common features and key differences of the solution set, laying the foundation for the subsequent generation of decision recommendations. This classification method improves the efficiency of analysis and ensures that decision makers can more specifically choose solutions suitable for different project scenarios without losing insight due to complex Pareto solution sets.

[0163] For each type of Pareto optimal solution, detailed improvement suggestions are formulated from the perspective of resource allocation, task plan adjustment, and risk management, including determining the types and quantities of key resources that need to be reallocated, identifying key tasks that can be optimized and their specific adjustment plans, and designing corresponding risk mitigation measures. These suggestions are then integrated into a complete decision package to ensure mutual coordination and support between the suggestions. Resource reallocation can ensure that key resources are used efficiently, and task plan adjustment can further improve the overall progress and efficiency of the project by optimizing task sequence and resource allocation. Risk mitigation measures provide response strategies based on the specific uncertainties of the project. The three suggestions are integrated into a coordinated decision package to ensure that they can support and enhance each other and reduce potential conflicts caused by decentralized decision-making. This step ensures that the improvement suggestions are overall coordinated, so that the key tasks and resource utilization of the project can be optimized in dynamic changes.

[0164] Construct a decision proposal evaluation framework, evaluate each decision proposal from three dimensions: technical feasibility, economic feasibility, and management feasibility, set scoring criteria for each dimension and perform quantitative scoring. Technical feasibility evaluation can determine whether the plan can be implemented under existing conditions, economic feasibility focuses on the balance between project costs and benefits, and management feasibility focuses on the difficulty of implementing the proposal and possible obstacles. By setting scoring criteria and quantifying each dimension, the transparency and objectivity of the evaluation process can be ensured. This approach helps managers clearly understand the strengths and weaknesses of each plan, ensure that well-thought-out decisions are made, and thus maximize benefits with limited resources.

[0165] Simulate the implementation effects of various decision suggestions under different project environments and conditions, and evaluate their potential impact on the project's key performance indicators. Through simulation, the potential impact of various solutions on key performance indicators (such as construction period, cost and quality) can be evaluated in advance, and possible bottlenecks and problems can be identified. This process effectively reduces the risk of decision-making, because decision makers can adjust plans in advance based on simulation results to avoid major impacts caused by uncertainties or unexpected situations in actual implementation. This step can provide management with a visual, data-driven tool to better predict and manage future changes in the project.

[0166] Conduct consistency analysis between decision suggestions, check whether there are conflicts or contradictions between different suggestions, evaluate the synergy and potential impact between the suggestions, and ensure that all suggestions are coordinated to promote the realization of project goals. This step can identify potential conflicts and avoid duplication of resources or contradictions between different strategies. At the same time, by evaluating the synergy of each suggestion, managers can further optimize decisions and improve the overall effectiveness of implementing multiple suggestions in combination. This step ensures that different decision-making plans can be effectively integrated under a unified framework, avoiding increased uncertainty or decreased efficiency in project execution due to lack of coordination.

[0167] According to the evaluation results, the decision suggestions are prioritized and integrated and optimized, and suggestions with high scores, significant impacts, and controllable risks are listed as priority implementation items. At the same time, a phased implementation plan is formulated to clarify the implementation sequence, time nodes, and resource requirements of each suggestion, and corresponding monitoring indicators and adjustment mechanisms are designed to ensure that the decision suggestions can be implemented in an orderly and efficient manner. This step ensures the effective allocation and use of resources by establishing a phased implementation plan to clarify the execution time nodes and resource requirements of each suggestion. At the same time, corresponding monitoring indicators and adjustment mechanisms are designed to ensure that the progress, cost, and quality of the implementation process of the suggestions can be tracked and fed back in real time. In this way, not only can the efficient implementation of decision suggestions be guaranteed, but also the strategy can be adjusted in time during the project progress to minimize the risks in implementation.

[0168] In summary, through the processes of system clustering, three-dimensional optimization, feasibility assessment, and consistency analysis, a comprehensive multi-objective optimization decision support mechanism is provided. It can provide a reliable basis for decision-making in the complex and dynamic environment of construction projects, while ensuring that these suggestions can be effectively implemented in reality. This process provides an efficient and scientific decision-making tool for construction project management, and improves the overall management level and success rate of the project.

[0169] Furthermore, step 6 includes the following steps.

[0170] Compare the actual progress data with the optimization suggestions generated in step 5 to identify progress deviations and assess their potential impact on the overall project progress. This process helps to identify progress deviations in a timely manner, thereby assessing their potential impact on the overall project progress. By comparing actual data with planned data, delays or advances in task execution can be effectively detected. This step provides a real-time feedback mechanism for project managers to ensure early detection and response to deviations.

[0171] When the identified deviation exceeds the preset threshold, an alarm is automatically issued, and notifications are sent to managers at the corresponding level based on the severity of the deviation. Minor deviations may only require the knowledge of the project manager, while serious deviations may require intervention from senior management. This mechanism ensures the timeliness and effectiveness of project risk management, reducing project delays or resource waste caused by delayed response. This step improves the responsiveness of project management and ensures that deviations can be handled quickly, thereby reducing their negative impact on the overall project.

[0172] Based on the real-time data collected continuously, the multi-level dynamic graph model is automatically updated regularly or when major deviations occur, and the project structure and dependencies are re-evaluated. The multi-level dynamic graph model captures the complexity and dependencies of the project and can be dynamically adjusted to reflect the latest task status, resource allocation, and risk factors. The updated model can more accurately reflect the current operation of the project and ensure that the optimization algorithm can make decisions based on the latest information. This step enables the project management system to adapt to changes in the project execution process and maintain the foresight and accuracy of decision-making by dynamically updating the model.

[0173] Based on the updated multi-level dynamic graph model and the latest project status, the multi-objective optimization algorithm is re-run to generate revised decision recommendations. This process ensures that the optimization recommendations can be adjusted according to the actual project progress and the latest external conditions to provide real-time optimal solutions. By combining real-time data and the latest model, the optimization algorithm can generate the Pareto optimal solution again and propose specific improvement measures to ensure that the project is still moving towards the optimal goal. This step ensures the dynamic and flexible nature of the project management strategy, allowing the project to quickly adjust to various uncertainties.

[0174] In summary, a closed-loop feedback mechanism is formed by comparing actual progress data with optimization suggestions, issuing deviation alerts, dynamically updating multi-level models, and re-running optimization algorithms. This process ensures that the project management system can make adaptive adjustments based on the latest progress, reduce the impact of progress deviations, and provide support for continuous optimization of the project. Through real-time monitoring and continuous optimization, it can ensure that the project can still proceed as expected in a complex and uncertain environment, improving the intelligence and agility of project management.

[0175] Finally, it should be pointed out that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them. Although the present invention has been described in detail with reference to the above embodiments, a person skilled in the art should understand that the technical solutions described in the above embodiments can still be modified, or some of the technical features can be replaced by equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A construction project progress management method based on data analysis, characterized in that: The following steps are involved: Step 1: Build a multi-level dynamic graph model of the construction project to fully characterize the project structure and dependencies; Step 2: Collect construction site data and perform cleaning, standardization and structure processing to make it conform to the input format requirements of the multi-level dynamic graph model; Step 3: Perform critical path analysis at multiple scales to identify and track dynamically changing key tasks and ensure the consistency and accuracy of the analysis results; Step 4: Quantify and simulate uncertainties and their interactions to assess their potential impact on the overall progress of the construction project; Step 5: Generate decision suggestions under multi-objective optimization based on the multi-level dynamic graph model and uncertainty analysis results; Step 6: Establish a real-time feedback loop mechanism to compare and analyze the actual progress during implementation with the optimization suggestions, continuously collect construction data, and timely update the multi-level dynamic graph model and decision-making suggestions.

2. The construction project progress management method based on data analysis according to claim 1 is characterized in that: Step 1 includes the following steps: Determine the main levels of the building project, establish independent but interrelated hierarchical structures, and form a complete hierarchical structure as the basic framework of the dynamic graph model; Identify and define the dependencies, sharing, and constraints between tasks within each level and between different levels, and use nodes and edges in graph theory to represent tasks and their relationships, and build the topological structure of a multi-level graph model; Add time attributes to each node and edge in the multi-level graph model, including the start and end time, duration, and time dependency of the task, to dynamically reflect the characteristics of the project changing over time, thereby transforming the static multi-level graph into a multi-level dynamic graph model; Add resource information and constraints to the multi-level dynamic graph model and associate them with relevant task nodes to achieve resource allocation optimization and constraint satisfaction analysis; Create interactive interfaces with real-time data sources for multi-level dynamic graph models, define data input formats, update algorithms, and trigger conditions to dynamically reflect the latest status of the project and improve the timeliness and accuracy of decision-making; Use historical project data or simulation data to verify and test the constructed multi-level dynamic graph model to check whether it can accurately represent the project structure, reflect dependencies, and adapt to project changes. Adjust and optimize it according to the test results until it meets project management needs.

3. The construction project progress management method based on data analysis according to claim 2 is characterized in that: Resource information and constraints are added to the multi-level dynamic graph model and associated with relevant task nodes to achieve resource allocation optimization and constraint satisfaction analysis, including the following steps: Systematically classify the human resources, equipment resources and material resources involved in construction projects, define the key attributes of each type of resource, determine the measurement units and evaluation indicators of the resources, and establish quantitative standards for resource attributes; Analyze and define various constraints, including total resource constraints, time window constraints, technical specification constraints, and site space constraints, and formalize the constraints and convert them into quantifiable mathematical expressions or logical rules to ensure that the constraints can be accurately identified and processed; In the multi-level dynamic graph model, resource requirement attributes are added to each task node, and a functional relationship between resource requirements and task execution parameters is established to achieve dynamic association between resource allocation and task progress; Bring all available resources under unified management to achieve dynamic resource allocation and scheduling, including designing resource allocation priority rules, resource conflict resolution strategies, and resource utilization efficiency evaluation methods to ensure that resources can be used reasonably; Verify the satisfaction of various constraints in real time during the resource allocation process. When a constraint violation is found, issue a warning and provide adjustment suggestions in a timely manner to ensure the feasibility of the resource allocation plan. A heuristic algorithm is used to find the optimal resource allocation plan while satisfying various constraints, and a plan evaluation index system is established to provide a quantitative basis for decision-making.

4. The construction project progress management method based on data analysis according to claim 1 is characterized in that: Step 2 includes the following steps: Develop a comprehensive data collection plan based on the needs of the multi-level dynamic graph model, including determining the type of data to be collected, selecting appropriate data collection methods and tools, and developing collection frequency and sampling strategies; Deploy data collection equipment at the construction site according to the developed data collection plan, including installing various sensors, configuring mobile devices and applications, and establishing a data transmission network; Perform preliminary processing and cleaning of the collected raw data, including removing obvious errors or outliers, handling missing data, unifying data formats and units, and performing necessary data conversions; Convert the cleaned data into a standardized and structured format to meet the input requirements of the multi-level dynamic graph model, including: converting unstructured data into structured form, normalizing numerical data, and organizing information according to predefined data patterns; Conduct comprehensive quality checks and validation of converted data, including statistical analysis to detect potential anomalies, cross-validation of data from different sources to ensure consistency, and comparison with historical data or expert knowledge to verify plausibility; The verified data is integrated and mapped to the corresponding nodes and relationships of the multi-level dynamic graph model, and the automatic import and update of data is realized.

5. The construction project progress management method based on data analysis according to claim 4 is characterized in that: Integrate and map the verified data to the corresponding nodes and relationships of the multi-level dynamic graph model, and realize automatic import and update of data, including the following steps: Formulate standardized mapping rules for different types of construction data, and define in detail the correspondence between data fields and graph model node attributes, including data type conversion rules, numerical mapping relationships, and timestamp processing methods, to ensure that data can be accurately mapped to the correct location in the graph model; Import the verified data into the graph model according to the mapping rules, and implement data version control and conflict handling mechanisms to ensure data consistency in the case of concurrent updates; By comparing the data timestamp and version number, the specific content that needs to be updated is determined, and the transaction mechanism is used to ensure the atomicity of the update operation. At the same time, a data update log is established to record all update operations; Real-time monitoring of abnormal situations during data update, and setting up a multi-level alarm mechanism to issue an alarm in time when an abnormality is found, and automatically execute the preset abnormality handling process; After the data update is completed, the status update calculation of the graph model is triggered, including node status update, relationship attribute recalculation and key indicator derivation, to ensure that the graph model can accurately reflect the latest construction site status.

6. The construction project progress management method based on data analysis according to claim 5 is characterized in that: The node status update is expressed as: S(N i ,t)=f(T start (N i ),Tend(N i ),D(N i ,t),R(N i ,t)), where S(N i ,t) represents task N i The state at time t; T start (N i )、Tend(N i ) are task N i The planned start time and the planned end time of D(N i ,t) represents task N i The actual progress at time t; R(N i ,t) represents task N i The resources used at time t; f represents how to update the overall status of the task based on the time, progress, and resource status of the task; The relationship attribute recalculation formula is expressed as: A(E ij )=g(S(N i ,t),S(N j ,t),C(E ij ),R shared (E ij ,t)), where A(E ij ) represents task N i and N j Dependency relationship between ij Attributes; S(N j ,t) represents task N j The state at time t; C(E ij ) represents task N i and N j The constraints between shared (E ij ,t) indicates that in task N i and N j The resources or constraints shared between them; g represents how to update the properties of the dependency relationship according to changes in task status, constraints, and shared resources; The formula for the derivation of key indicators is: KP(t)=h({S(N i ,t)},{A(E ij )},K), where KP(t) represents the critical path or other key indicators of the project at time t; {S(N i ,t)} represents all tasks N i The state set at time t; {A(E ij )} represents all task dependencies E ij A set of attributes; K represents other indicators related to the overall project progress; h represents how to derive the critical path and other key project progress indicators based on task status, dependencies and other factors.

7. The construction project progress management method based on data analysis according to claim 1 is characterized in that: Step 3 includes the following steps: Establish a multi-scale analysis framework and clearly define the various scales at which critical path analysis is required, including the overall project level, major phase level, sub-project level, and single task level; For each scale level, determine its unique time granularity, resource constraints and critical evaluation criteria to ensure that the analysis results at different scales are coordinated and supportive of each other; Starting from the highest level, perform critical path analysis level by level and calculate the earliest start time, earliest finish time, latest start time, latest finish time and total float time of each task to identify the characteristics and influencing factors of the critical path and tasks; Establish associations between analysis results at different scales, decompose high-level critical paths into low-level tasks, or aggregate low-level critical tasks into high-level critical paths, to ensure that the hierarchical relationships and dependencies between tasks are consistent; Establish a dynamic update mechanism to automatically recalculate critical paths and critical tasks based on real-time data, achieve real-time monitoring of critical tasks, and identify new critical tasks in a timely manner; Conduct sensitivity and stability analysis on the results of multi-scale critical path analysis, simulate scenarios of task duration changes and resource fluctuations, observe changes in critical paths, identify tasks or factors that are likely to cause path changes, and provide guidance for risk management and resource optimization; The results of the multi-scale critical path analysis are comprehensively verified and checked for consistency. Based on the verification results, the analysis methods and parameters are continuously optimized to improve the overall performance of the multi-scale critical path analysis.

8. The construction project progress management method based on data analysis according to claim 7 is characterized in that: Earliest start time ES(N i ) is calculated as: , where EF(N j ) represents task N j The earliest end time; P(N i ) represents task N i The set of predecessor tasks, that is, in task N i The task that must be completed before; ∣ is a commonly used symbol in set theory and mathematical logic, indicating a set that satisfies a certain condition; The earliest end time EF(N i ) is calculated as: EF(N i )=ES(N i )+D(N i ), where ES(N i ) represents task N i The earliest start time of D(N i ) indicates N i Duration of Latest end time LF(N i ) is calculated as: , where LS(N j ) represents task N j The latest start time of S(N i ) represents task N i The set of subsequent tasks that must wait for task N i Tasks that can only be started after completion; Latest start time LS(N i ) is calculated as: LS(N i )=LF(N i )-D(N i ); Total float time F(N i ) is calculated as: F(N i )=LS(N i )-ES(N i )=LF(N i )-EF(N i ).

9. The construction project progress management method based on data analysis according to claim 1 is characterized in that: Step 4 includes the following steps: Comprehensively identify and classify the key uncertainties that affect the progress of construction projects, assess their probability of occurrence and potential impact, and form a list of uncertainties; Quantify the identified uncertainties and assign a probability distribution to each factor to represent its possible values ​​and probability of occurrence under different circumstances; Construct an interaction model between uncertain factors, analyze the relationship between different factors and their mutual influence, and identify and quantify the impact of uncertain factors on the overall progress; Monte Carlo simulation is performed based on the quantitative uncertainty factors and interaction models. A large number of possible project schedule results are generated through repeated sampling and calculation, so as to obtain statistical analysis of the impact of different combinations of uncertain factors. Analyze the simulation results, evaluate the potential impact of various uncertainties and their combinations on the overall progress of the construction project, calculate key performance indicators, and identify the factors that have the greatest impact on the progress.

10. The construction project progress management method based on data analysis according to claim 9 is characterized in that: The influence of uncertain factors on the overall progress is expressed by the formula: G=∑ k=1 n I k ·C k +∑ k=1 n ∑ h=1 n a kh I k ·C h , where G represents the combined impact of all identified uncertainties on the overall progress of the construction project; I k represents the kth uncertainty factor U k The degree of direct impact; k represents the kth uncertainty factor U k The probability of occurrence; a kh represents the interactive influence of the kth uncertainty factor on the hth uncertainty factor; C h Represents the occurrence probability of the hth uncertain factor Uh.

11. The construction project progress management method based on data analysis according to claim 1 is characterized in that: Step 5 includes the following steps: Establish a comprehensive multi-objective optimization framework, clearly define key objectives and set appropriate weights and priorities for each objective, while identifying potential conflicts and trade-offs between objectives; Based on the multi-level dynamic graph model and uncertainty analysis results, a comprehensive optimization model is constructed to capture the complexity and dynamic characteristics of the project; Run the comprehensive optimization model to generate a Pareto optimal solution set, and record the decision variable values, objective function values, and potential implementation strategies corresponding to each Pareto optimal solution; Based on the Pareto optimal solution set, decision recommendations including resource reallocation, key task optimization and risk mitigation measures are generated, and the feasibility, potential impact and consistency of each recommendation are comprehensively evaluated.

12. The construction project progress management method based on data analysis according to claim 11 is characterized in that: Based on the Pareto optimal solution set, decision recommendations including resource reallocation, key task optimization, and risk mitigation measures are generated, and the feasibility, potential impact, and consistency of each recommendation are fully evaluated, including the following steps: Perform systematic clustering and feature analysis on the Pareto optimal solution set, classify similar solutions according to their distribution positions and features in the target space, conduct quantitative and qualitative analysis on the characteristics of each type of solution, and summarize their common decision-making features and differences; For each type of Pareto optimal solution, detailed improvement suggestions are formulated from three dimensions: resource allocation, task plan adjustment, and risk management. These suggestions include determining the types and quantities of key resources that need to be reallocated, identifying key tasks that can be optimized and their specific adjustment plans, and designing corresponding risk mitigation measures. These suggestions are then integrated into a complete decision package to ensure mutual coordination and support between the suggestions. Construct a decision proposal evaluation framework, evaluate each decision proposal from three dimensions: technical feasibility, economic feasibility, and management feasibility, set scoring criteria for each dimension, and perform quantitative scoring; Simulate the implementation effects of various decision recommendations under different project environments and conditions, and evaluate their potential impact on project key performance indicators; Conduct consistency analysis among decision-making recommendations, check whether there are conflicts or contradictions between different recommendations, evaluate the synergy and potential impact among the recommendations, and ensure that all recommendations are coordinated and consistent to promote the realization of project goals; Based on the evaluation results, decision-making recommendations are prioritized and integrated, and recommendations with higher scores, significant impacts and controllable risks are listed as priority implementation items. At the same time, a phased implementation plan is formulated to clarify the implementation sequence, time nodes and resource requirements of each recommendation, and corresponding monitoring indicators and adjustment mechanisms are designed to ensure that decision-making recommendations can be implemented in an orderly and efficient manner.

13. The construction project progress management method based on data analysis according to claim 1 is characterized in that: Step 6 includes the following steps: Compare the actual progress data with the optimization suggestions generated in step 5, identify progress deviations and assess the potential impact of the deviations on the overall project progress; When the identified deviation exceeds the preset threshold, an alarm is automatically issued and notifications are sent to the corresponding level of management based on the severity of the deviation; Automatically update multi-level dynamic graph models and re-evaluate project structures and dependencies based on continuously collected real-time data, either periodically or when significant deviations occur; Based on the updated multi-level dynamic graph model and the latest project status, the multi-objective optimization algorithm is re-run to generate revised decision recommendations.

Citation Information

Patent Citations

  • Multi-system cooperative system and method for production process control of discrete manufacturing enterprises

    CN104331767A

  • Constructional engineering project cost management method based on critical path fuzzy earned value analysis method

    CN115578072A

  • Intelligent fire-fighting resource dynamic scheduling and management method and system based on Internet of Things

    CN117709739A

  • Highway construction optimization method and system based on big data

    CN117710156A

  • Project management monitoring method and system based on multi-stage analysis

    CN117787434A

Cited By

  • Project progress analysis system based on artificial intelligence statistics

    CN119205036A

  • Collaborative optimization allocation method and system for air route resources

    CN119479383A

  • Production project implementation progress intelligent statistical analysis method and system

    CN119578806A

  • Environmental impact assessment method based on building management

    CN119761992A

  • BIM-based traffic engineering construction progress and resource management optimization system

    CN119809554A