Distributed multi-project collaborative scheduling method and system considering multi-skill resource limitation

By constructing a complete mathematical model, designing heuristic algorithms, adaptive variable neighborhood search algorithms, and combining with cooperation negotiation agreements, the problem of multi-project collaborative scheduling with limited multi-skill resources in a distributed environment is solved, and the rational allocation and scheduling of resources is realized. Improve the research and development efficiency of high-end equipment.

CN118967076AInactive Publication Date: 2024-11-15HANGZHOU NORMAL UNIVERSITY
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202411071661.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-11-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology is difficult to effectively carry out multi-project collaborative scheduling with limited multi-skill resources in a distributed environment. Traditional algorithms cannot meet the actual needs of enterprises, especially in the research and development of high-end equipment, involving multi-level tasks and optimized scheduling of multi-skill personnel. .

Method used

A distributed multi-project collaborative scheduling method is proposed to consider the limitations of multi-skill resources. By constructing a complete mathematical model, designing heuristic algorithms and adaptive variable neighborhood search algorithms, and combining cooperation negotiation agreements, the rational allocation of global resources is achieved and Scheduling, optimize the scheduling of distributed multi-mode and multi-skill projects.

Benefits of technology

In a distributed environment, independent decision-making and reasonable allocation of resources for each project are achieved, the completion time of all projects is shortened, the efficiency of equipment research and development is improved, and the optimality of personnel allocation and task sorting is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118967076A_ABST
    Figure CN118967076A_ABST
Patent Text Reader

Abstract

The invention discloses a distributed multi-project collaborative scheduling method and system considering multi-skill resource limitation, and relates to the field of collaborative scheduling, and the scheduling method comprises the steps: obtaining research and development task data of distributed multi-projects; constructing a complete mathematical model of the collaborative scheduling method; designing a heuristic algorithm to generate an initial scheduling scheme S according to the structural property; designing a self-adaptive variable neighborhood search algorithm through an initial solution S generated based on a heuristic algorithm, and generating a final scheduling scheme; and designing a cooperation negotiation protocol, and realizing reasonable allocation and scheduling of global resources. The invention relates to a distributed multi-project cooperative scheduling method and system considering multi-skill resource limitation, each project agent optimizes project scheduling in a local level to minimize completion time of the project, a cooperation method based on multiple agents is provided, and optimal allocation of global resources is realized through an evolution principle of cooperation negotiation, so that the project scheduling efficiency is improved. The equipment research and development efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of collaborative scheduling, and in particular to a distributed multi-project collaborative scheduling method and system considering multi-skill resource constraints. Background Art

[0002] Resource scheduling in a multi-project environment is ubiquitous in project management in modern manufacturing and service industries. Multi-project collaborative scheduling can bring higher benefits to enterprises. It can meet the actual needs of enterprises in R&D, production, project management, etc. The traditional multi-project scheduling problem solves the resource conflict problem by building all project tasks into a super network and sharing all resources and information. It has been widely studied in the field of project scheduling. Due to the rapid development of globalization and the advancement of information technology, project characteristics and resource characteristics may hinder the sharing of resources and information. In response to these situations, a common practice adopted by high-end equipment manufacturing companies or multinational companies is to set up branches in different regions and adopt a dual management mechanism, which can meet local flexible management while maintaining global centralized management. In this decentralized management mechanism, information is not shared among project managers, and in order to maximize their own interests, competition and conflict often arise over limited global shared resources.

[0003] At present, the research on multi-project collaborative scheduling with limited multi-skill resources is still insufficient. The existing literature mainly focuses on the centralized decision-making model of multi-skill multi-project scheduling problems. The traditional project scheduling algorithm can no longer achieve multi-project collaborative scheduling in a distributed environment and meet the actual needs of enterprises. At present, the existing research on multi-project collaborative scheduling has the following problems:

[0004] (1) At present, the research on multi-project collaborative scheduling with limited multi-skill resources is still insufficient. The existing literature mainly focuses on the centralized decision-making model of multi-skill multi-project scheduling problems. In this model, the global decision maker has all the information of multiple projects, thereby realizing the allocation of personnel for all tasks in the project. However, in the process of high-end equipment R&D, multi-level R&D tasks and multi-skill R&D personnel are involved, which requires project managers to hire special resources such as multi-skill personnel to carry out the optimization scheduling of multi-level tasks;

[0005] (2) In addition, in a distributed management environment, there are multiple decision makers between projects and their information is not shared, making centralized scheduling difficult. Traditional project scheduling algorithms can no longer achieve collaborative scheduling of multiple projects in a distributed environment and meet the actual needs of enterprises. Therefore, how to reasonably allocate shared funding budgets among distributed projects and solve the multi-mode and multi-skill collaborative scheduling of each project has important practical application background and theoretical research value. Summary of the invention

[0006] The purpose of the present invention is to provide a distributed multi-project collaborative scheduling method and system considering multi-skill resource constraints, overcome the shortcomings of the prior art, and solve the problems existing in the prior art.

[0007] To solve the above problems, the technical solutions adopted by the present invention are as follows:

[0008] The present invention provides a distributed multi-project collaborative scheduling method considering multi-skill resource constraints, the scheduling method comprising:

[0009] S1: Obtain distributed multi-project R&D task data;

[0010] High-end equipment R&D includes N distributed R&D projects in different geographical locations. Each project is scheduled by a project agent that can make independent decisions, and these projects share the total budget B given by the enterprise. In the distributed environment, each project i (i = 1, 2, ..., N) decomposes the multi-level R&D tasks into J i + 1 non-preemptive meta-R&D task, the first of which is a virtual start task j=0 and the last is a virtual end task j=J i , the R&D department of project i has a total of M i Multi-skilled R&D personnel, where x ijm =1 means employee m can handle R&D task A ij , otherwise 0, for each item i, use o ij To indicate all R&D tasks that can be completed ij The collection of R&D personnel, namely

[0011] S2: Construct a complete mathematical model of the collaborative scheduling method;

[0012] The complete mathematical model includes:

[0013] (1) Local decision-making model for project agents to optimize resource scheduling within projects:

[0014]

[0015]

[0016]

[0017]

[0018]

[0019]

[0020]

[0021]

[0022]

[0023] y ijmt ∈{0,1},S ij ≥0

[0024] in, Indicates the Jth item of the i-th item i The completion time of a task, y ijmt represents the decision variable, which converts task A at time t ij When assigned to employee m, it is equal to 1, otherwise it is equal to 0, q ij Indicates o ij The number of R&D personnel in ij Indicates R&D task A ij Pay employees actual wages, ca ij Indicates R&D task A ij Pay employees a standard salary, m represents the capability coefficient of R&D personnel m, d ij Indicates R&D task A ij The actual construction period, da ij Indicates R&D task A ij The standard construction period, S ij Indicates R&D task A ij The start time, f ij Indicates R&D task A ij End time of

[0025] (2) Global decision-making model for resource allocation and coordination among projects by coordination agents:

[0026] min C max

[0027]

[0028]

[0029]

[0030] Among them, C max represents the completion time of all distributed projects, B i represents the budget of the i-th R&D project;

[0031] S3: Based on the structured properties, a heuristic algorithm is designed to generate the initial scheduling solution S;

[0032] According to the two structural properties, a heuristic algorithm is designed to generate a better initial scheduling solution S, which improves the convergence speed and solution quality of the subsequent intelligent optimization algorithm.

[0033] The two structural properties include:

[0034] Property 1: For the distributed multi-R&D project collaborative scheduling sub-problem, consider that the same employee needs to handle two parallel R&D tasks A at the same time ij and A in , and will not exceed the funding budget of project i, in order to minimize the completion time of R&D project i, the project manager needs to prioritize the tasks with the smallest latest completion time;

[0035] Property 2: For a given R&D personnel allocation plan for the distributed multi-R&D project collaborative scheduling sub-problem, when the following conditions are met, the project manager will assign task A on the critical path to ij Assigned R&D personnel m Replaced with a more powerful p n Only in this way can the completion time of project i be effectively shortened;

[0036] S4: Based on the initial solution S generated by the heuristic algorithm, an adaptive variable neighborhood search algorithm is designed to generate the final scheduling solution;

[0037] Design an adaptive variable neighborhood search algorithm that can adaptively change the neighborhood search structure, expand the search range in the neighborhood in the later stage of the algorithm operation, and improve the efficiency of solving distributed multi-mode and multi-skill project scheduling sub-problems of different scales;

[0038] S5: Design cooperative negotiation protocols to achieve reasonable allocation and scheduling of global resources;

[0039] After outputting the optimal solution for each project, design negotiation agreements to achieve a reasonable allocation of global resources;

[0040] The negotiation protocol is a process of solving the global resource allocation problem. Each project agent makes local decisions based on the available budget allocated to it. The project agents make allocations one by one based on the project priority sequence π negotiated in advance, where the funding budget value B of each project i is iIt is determined by the allocation strategy of the project agent in the constraints. It is worth noting that if all project managers choose to share the capital budget under perfect competition instead of cooperating by following the given agreement, each project agent may only obtain the minimum capital budget from the project agent, which can only ensure that each task in project i is allocated to the employee who needs the least salary. At this time, the capital budget is usually not fully utilized, resulting in a longer total project time span; once all project agents choose to cooperate with the project agent, during the negotiation process, each project agent uses the available budget for local scheduling in the order of negotiation, and the project agent will disclose the budget surplus B s , each project manager will shorten the completion time of the project by shortening the duration of tasks that occupy more budget on the critical path, and all agents have no motivation to unilaterally avoid cooperation because they have no way to obtain additional benefits.

[0041] Preferably, the specific steps of the heuristic algorithm in S3 are:

[0042] S31: Calculate all tasks A in project i ij The earliest start time and the latest completion time of these tasks are assigned to the R&D personnel p who need the least salary according to property 2. m ;

[0043] S32: Generate a task list using property 1 and the minimum time difference principle;

[0044] S33: Decode the task list using a serial scheduling generation scheme to obtain the maximum completion time of project i;

[0045] S34: Calculate the critical path of the solution and the total time difference of each task;

[0046] S35: Sort the tasks on the non-critical path in descending order according to the total time difference, and replace the R&D personnel of the tasks on the critical path one by one. If property 2 is satisfied, go to S31; otherwise, output the result.

[0047] Preferably, the specific steps of an adaptive variable neighborhood search algorithm in S4 are:

[0048] S41: using the initial solution S of the heuristic algorithm as the initial solution of the adaptive variable neighborhood search algorithm;

[0049] S42: Set the maximum number of iterations to I max , let k = 1; I = 1;

[0050] S43: When k≤k max , perform k perturbations on the initial solution S and obtain a feasible solution S';

[0051] S44: Perform the kth neighborhood search on the feasible solution S' to obtain the local optimal solution S'';

[0052] S45: When S' is better than S, then S' = S, k = 1, I = I + 1; otherwise k = k + 1, I = I + 1;

[0053] S46: When the number of iterations ends, output S and end the algorithm.

[0054] Preferably, the encoding scheme of the adaptive variable neighborhood search algorithm is: first, for each sub-project, this article adopts a two-dimensional encoding method S = (X, M), where the task dimension vector X = (0, ..., g, ..., n + 1) is used to represent the order of task starts in the scheduling scheme. In project scheduling, the start of all tasks must satisfy the constraints of priority relationships. The employee dimension vector M = (0, ..., m, ..., 0) represents the employee assigned to the task dimension vector, and the decoding method is the classic serial scheduling generation mechanism.

[0055] The present invention also provides a distributed multi-project collaborative scheduling system considering multi-skill resource constraints, the scheduling system specifically comprising:

[0056] Task data acquisition module, used to obtain distributed multi-project R&D task data;

[0057] High-end equipment R&D includes N distributed R&D projects in different geographical locations. Each project is scheduled by a project agent that can make independent decisions, and these projects share the total budget B given by the enterprise. In the distributed environment, each project i (i = 1, 2, ..., N) decomposes the multi-level R&D tasks into J i + 1 non-preemptive meta-R&D task, the first of which is a virtual start task j=0 and the last is a virtual end task j=J i , the R&D department of project i has a total of M i Multi-skilled R&D personnel, where x ijm =1 means employee m can handle R&D task A ij , otherwise 0, for each item i, use o ij To indicate all R&D tasks that can be completed ij The collection of R&D personnel, namely

[0058] Mathematical model building module, used to build a complete mathematical model of the collaborative scheduling method;

[0059] The complete mathematical model includes:

[0060] (1) Local decision-making model for project agents to optimize resource scheduling within projects:

[0061]

[0062]

[0063]

[0064]

[0065]

[0066]

[0067]

[0068]

[0069]

[0070] y ijmt ∈{0,1},S ij ≥0

[0071] in, Indicates the Jth item of the i-th item i The completion time of a task, t ijmt represents the decision variable, which converts task A at time t ij When assigned to employee m, it is equal to 1, otherwise it is equal to 0, q ij Indicates o ij The number of R&D personnel in ij Indicates R&D task A ij Pay employees actual wages, ca ij Indicates R&D task A ij Pay employees a standard salary, m represents the capability coefficient of R&D personnel m, d ij Indicates R&D task A ij The actual construction period, da ij Indicates R&D task A ij The standard construction period, S ij Indicates R&D task A ij The start time, f ij Indicates R&D task A ij End time of

[0072] (2) Global decision-making model for resource allocation and coordination among projects by coordination agents:

[0073] min C maX

[0074]

[0075]

[0076] B i ≥0,

[0077] Among them, C max represents the completion time of all distributed projects, B i represents the budget of the i-th R&D project;

[0078] The initial scheduling scheme output module is used to design a heuristic algorithm to generate the initial scheduling scheme S according to the structured properties;

[0079] According to the two structural properties, a heuristic algorithm is designed to generate a better initial scheduling solution S, which improves the convergence speed and solution quality of the subsequent intelligent optimization algorithm.

[0080] The two structural properties include:

[0081] Property 1: For the distributed multi-R&D project collaborative scheduling sub-problem, consider that the same employee needs to handle two parallel R&D tasks A at the same time ij and A in , and will not exceed the funding budget of project i, in order to minimize the completion time of R&D project i, the project manager needs to prioritize the tasks with the smallest latest completion time;

[0082] Property 2: For a given R&D personnel allocation plan for the distributed multi-R&D project collaborative scheduling sub-problem, when the following conditions are met, the project manager will assign task A on the critical path to ij Assigned R&D personnel m Replaced with a more powerful p n Only in this way can the completion time of project i be effectively shortened;

[0083] The variable neighborhood search algorithm module is used to design an adaptive variable neighborhood search algorithm based on the initial solution S generated by the heuristic algorithm to generate the final scheduling solution;

[0084] Design an adaptive variable neighborhood search algorithm that can adaptively change the neighborhood search structure, expand the search range in the neighborhood in the later stage of the algorithm operation, and improve the efficiency of solving distributed multi-mode and multi-skill project scheduling sub-problems of different scales;

[0085] The global resource allocation module is used to design cooperative negotiation protocols to achieve reasonable allocation and scheduling of global resources;

[0086] After outputting the optimal solution for each project, design negotiation agreements to achieve a reasonable allocation of global resources;

[0087] The negotiation protocol is a process of solving the global resource allocation problem. Each project agent makes local decisions based on the available budget allocated to it. The project agents make allocations one by one based on the project priority sequence π negotiated in advance, where the funding budget value B of each project i is i It is determined by the allocation strategy of the project agent in the constraints. It is worth noting that if all project managers choose to share the capital budget under perfect competition instead of cooperating by following the given agreement, each project agent may only obtain the minimum capital budget from the project agent, which can only ensure that each task in project i is allocated to the employee who needs the least salary. At this time, the capital budget is usually not fully utilized, resulting in a longer total project time span; once all project agents choose to cooperate with the project agent, during the negotiation process, each project agent uses the available budget for local scheduling in the order of negotiation, and the project agent will disclose the budget surplus B s , each project manager will shorten the completion time of the project by shortening the duration of tasks that occupy more budget on the critical path, and all agents have no motivation to unilaterally avoid cooperation because they have no way to obtain additional benefits.

[0088] Preferably, the specific steps of the heuristic algorithm in the initial scheduling scheme output module are:

[0089] S31: Calculate all tasks A in project i ij The earliest start time and the latest completion time of these tasks are assigned to the R&D personnel p who need the least salary according to property 2. m ;

[0090] S32: Generate a task list using property 1 and the minimum time difference principle;

[0091] S33: Decode the task list using a serial scheduling generation scheme to obtain the maximum completion time of project i;

[0092] S34: Calculate the critical path of the solution and the total time difference of each task;

[0093] S35: Sort the tasks on the non-critical path in descending order according to the total time difference, and replace the R&D personnel of the tasks on the critical path one by one. If property 2 is satisfied, go to S31; otherwise, output the result.

[0094] Preferably, the specific steps of an adaptive variable neighborhood search algorithm in the variable neighborhood search algorithm module are:

[0095] S41: using the initial solution S of the heuristic algorithm as the initial solution of the adaptive variable neighborhood search algorithm;

[0096] S42: Set the maximum number of iterations to I max, let k = 1; I = 1;

[0097] S43: When k≤k max , perform k perturbations on the initial solution S and obtain a feasible solution S';

[0098] S44: Perform the kth neighborhood search on the feasible solution S' to obtain the local optimal solution S'';

[0099] S45: When S' is better than S, then S' = S, k = 1, I = I + 1; otherwise k = k + 1, I = I + 1;

[0100] S46: When the number of iterations ends, output S and end the algorithm.

[0101] Preferably, the encoding scheme of the adaptive variable neighborhood search algorithm is: first, for each sub-project, this article adopts a two-dimensional encoding method S = (X, M), where the task dimension vector X = (0, ..., g, ..., n + 1) is used to represent the order of task starts in the scheduling scheme. In project scheduling, the start of all tasks must satisfy the constraints of priority relationships. The employee dimension vector M = (0, ..., m, ..., 0) represents the employee assigned to the task dimension vector, and the decoding method is the classic serial scheduling generation mechanism.

[0102] Compared with the prior art, the present invention has the following beneficial effects:

[0103] In the distributed environment, the present invention schedules each project by an independent decision-making project agent. These projects share the total budget given by the enterprise, and the budget is reasonably allocated at the global level to minimize the completion time of all projects. At the same time, each project agent also optimizes the project scheduling at the local level to minimize the completion time of the project. A multi-agent-based cooperation method is proposed, which realizes the optimal allocation of global resources and improves the efficiency of equipment research and development through the evolutionary principle of cooperative negotiation.

[0104] The present invention designs a heuristic algorithm, which generates an initial solution by analyzing the structured properties of distributed sub-projects, and quickly solves it through an adaptive variable neighborhood search algorithm. The algorithm effectively solves the problem of multi-mode, multi-skill and multi-project collaborative scheduling in a distributed environment, ensuring the optimal personnel allocation and task sequencing of the project under budget constraints. BRIEF DESCRIPTION OF THE DRAWINGS

[0105] Figure 1 The algorithm flow chart of the distributed multi-project collaborative scheduling method and system considering the constraints of multi-skill resources;

[0106] Figure 2 It is a two-dimensional coding strategy diagram in the adaptive variable neighborhood search algorithm;

[0107] Figure 3Comparison of completion time curves of PSO, BA, TS and AVNS when n=20;

[0108] Figure 4 Comparison of completion time curves of PSO, BA, TS and AVNS when n=40;

[0109] Figure 5 Comparison of completion time curves of PSO, BA, TS and AVNS when n=60;

[0110] Figure 6 Comparison of completion time curves of PSO, BA, TS and AVNS when n=80;

[0111] Figure 7 Comparison of completion time curves of PSO, BA, TS and AVNS when n=100;

[0112] Figure 8 Comparison of completion time curves of PSO, BA, TS and AVNS when n=120. DETAILED DESCRIPTION

[0113] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.

[0114] Considering the distributed multi-project collaborative scheduling method and system under multi-skill resource constraints, the goal is to solve the problem of multi-project collaborative scheduling under multi-resource constraints. The problem is described as follows: high-end equipment R&D includes N distributed R&D projects in different geographical locations. Each project is scheduled by a project agent that can make independent decisions, and these projects share the total budget B given by the enterprise. In the distributed environment, each project i (i = 1, 2, ..., N) decomposes the multi-level R&D tasks into J i + 1 non-preemptive meta-R&D task, the first of which is a virtual start task j=0 and the last is a virtual end task j=J i The R&D department of Project i has a total of M i Multi-skilled R&D personnel, where x ijm =1 means employee m can handle R&D task A ij , otherwise 0, for each item i, use o ij To indicate all R&D tasks that can be completed ij The collection of R&D personnel, namely Different employees have different ability levels, which leads to different durations for the same task. ij and cost c ij, that is, employees with stronger abilities take less time to complete tasks, but need to be paid more wages, where the wages paid for all tasks in project i cannot exceed its budget B i Since the total available budget B for all projects is limited, there is competition among project agents for the limited budget. The coordination agent needs to reasonably allocate the global shared total budget. Therefore, the problem studied includes two levels: the coordination agent makes decisions on the budget allocation problem at the global level to minimize the completion time C of all projects. max Each project agent makes decisions on the project scheduling problem at the local level to minimize the completion time of the project

[0115] Please refer to Figure 1 As shown, this embodiment provides a distributed multi-project collaborative scheduling method considering multi-skill resource constraints, and the scheduling method includes:

[0116] S1: Obtain distributed multi-project R&D task data;

[0117] High-end equipment R&D includes N distributed R&D projects in different geographical locations. Each project is scheduled by a project agent that can make independent decisions, and these projects share the total budget B given by the enterprise. In the distributed environment, each project i (i = 1, 2, ..., N) decomposes the multi-level R&D tasks into J i + 1 non-preemptive meta-R&D task, the first of which is a virtual start task j=0 and the last is a virtual end task j=J i , the R&D department of project i has a total of M i Multi-skilled R&D personnel, where x ijm =1 means employee m can handle R&D task A ij , otherwise 0, for each item i, use o ij To indicate all R&D tasks that can be completed ij The collection of R&D personnel, namely

[0118] S2: Construct a complete mathematical model of the collaborative scheduling method;

[0119] The complete mathematical model includes:

[0120] (1) Local decision-making model for project agents to optimize resource scheduling within projects:

[0121]

[0122]

[0123]

[0124]

[0125]

[0126]

[0127]

[0128]

[0129]

[0130] y ijmt ∈{0,1},S ij ≥0

[0131] in, Indicates the Jth item of the i-th item i The completion time of a task, y ijmt represents the decision variable, which converts task A at time t ij When assigned to employee m, it is equal to 1, otherwise it is equal to 0, q ij Indicates o ij The number of R&D personnel in ij Indicates R&D task A ij Pay employees actual wages, ca ij Indicates R&D task A ij Pay employees a standard salary, m represents the capability coefficient of R&D personnel m, d ij Indicates R&D task A ij The actual construction period, da ij Indicates R&D task A ij The standard construction period, S ij Indicates R&D task A ij The start time, f ij Indicates R&D task A ij End time of

[0132] (2) Global decision-making model for resource allocation and coordination among projects by coordination agents:

[0133] min C max

[0134]

[0135]

[0136] B i ≥0,

[0137] Among them, C max represents the completion time of all distributed projects, B i represents the budget of the i-th R&D project;

[0138] The specific parameter table in the above model is:

[0139] S3: Based on the structured properties, a heuristic algorithm is designed to generate the initial scheduling solution S;

[0140] According to the two structural properties, a heuristic algorithm is designed to generate a better initial scheduling solution S, which improves the convergence speed and solution quality of the subsequent intelligent optimization algorithm.

[0141] The two structural properties include:

[0142] Property 1: For the distributed multi-R&D project collaborative scheduling sub-problem, consider that the same employee needs to handle two parallel R&D tasks A at the same time ij and A in , and will not exceed the funding budget of project i, in order to minimize the completion time of R&D project i, the project manager needs to prioritize the tasks with the smallest latest completion time;

[0143] Property 2: For a given R&D personnel allocation plan for the distributed multi-R&D project collaborative scheduling sub-problem, when the following conditions are met, the project manager will assign task A on the critical path to ij Assigned R&D personnel m Replaced with a more powerful p n Only in this way can the completion time of project i be effectively shortened;

[0144] The specific steps of the heuristic algorithm in S3 are:

[0145] S31: Calculate all tasks A in project i ij The earliest start time and the latest completion time of these tasks are assigned to the R&D personnel p who need the least salary according to property 2. m ;

[0146] S32: Generate a task list using property 1 and the minimum time difference principle;

[0147] S33: Decode the task list using a serial scheduling generation scheme to obtain the maximum completion time of project i;

[0148] S34: Calculate the critical path of the solution and the total time difference of each task;

[0149] S35: Sort the tasks on the non-critical path in descending order according to the total time difference, and replace the R&D personnel of the tasks on the critical path in sequence. If property 2 is satisfied, go to S31; otherwise, output the result;

[0150] The encoding method in S33 is as follows Figure 2 shown.

[0151] S4: Based on the initial solution S generated by the heuristic algorithm, an adaptive variable neighborhood search algorithm is designed to generate the final scheduling solution;

[0152] Design an adaptive variable neighborhood search algorithm that can adaptively change the neighborhood search structure, expand the search range in the neighborhood in the later stage of the algorithm operation, and improve the efficiency of solving distributed multi-mode and multi-skill project scheduling sub-problems of different scales;

[0153] The specific steps of the adaptive variable neighborhood search algorithm in S4 are:

[0154] S41: using the initial solution S of the heuristic algorithm as the initial solution of the adaptive variable neighborhood search algorithm;

[0155] S42: Set the maximum number of iterations to I max , let k = 1; I = 1;

[0156] S43: When k≤k max , perform k perturbations on the initial solution S and obtain a feasible solution S';

[0157] S44: Perform the kth neighborhood search on the feasible solution S' to obtain the local optimal solution S'';

[0158] S45: When S' is better than S, then S' = S, k = 1, I = I + 1; otherwise k = k + 1, I = I + 1;

[0159] S46: When the number of iterations ends, output S and end the algorithm;

[0160] The encoding scheme of the adaptive variable neighborhood search algorithm is as follows: first, for each sub-project, this paper adopts a two-dimensional encoding method S = (X, M), where the task dimension vector X = (0, ..., g, ..., n + 1) is used to represent the order in which tasks start in the scheduling scheme. In project scheduling, the start of all tasks must satisfy the constraints of priority relationships. The employee dimension vector M = (0, ..., m, ..., 0) represents the employee assigned to the task dimension vector. The decoding method is the classic serial scheduling generation mechanism.

[0161] S5: Design cooperative negotiation protocols to achieve reasonable allocation and scheduling of global resources;

[0162] After outputting the optimal solution for each project, design negotiation agreements to achieve a reasonable allocation of global resources;

[0163] The negotiation protocol is a process of solving the global resource allocation problem. Each project agent makes local decisions based on the available budget allocated to it. The project agents make allocations one by one based on the project priority sequence π negotiated in advance, where the funding budget value B of each project i is i It is determined by the allocation strategy of the project agent in the constraints. It is worth noting that if all project managers choose to share the capital budget under perfect competition instead of cooperating by following the given agreement, each project agent may only obtain the minimum capital budget from the project agent, which can only ensure that each task in project i is allocated to the employee who needs the least salary. At this time, the capital budget is usually not fully utilized, resulting in a longer total project time span; once all project agents choose to cooperate with the project agent, during the negotiation process, each project agent uses the available budget for local scheduling in the order of negotiation, and the project agent will disclose the budget surplus B s , each project manager will shorten the completion time of the project by shortening the duration of tasks that occupy more budget on the critical path, and all agents have no motivation to unilaterally avoid cooperation because they have no way to obtain additional benefits.

[0164] This embodiment also provides a distributed multi-project collaborative scheduling system considering multi-skill resource constraints, and the scheduling system specifically includes:

[0165] Task data acquisition module, used to obtain distributed multi-project R&D task data;

[0166] High-end equipment R&D includes N distributed R&D projects in different geographical locations. Each project is scheduled by a project agent that can make independent decisions, and these projects share the total budget B given by the enterprise. In the distributed environment, each project i (i = 1, 2, ..., N) decomposes the multi-level R&D tasks into J i + 1 non-preemptive meta-R&D task, the first of which is a virtual start task j=0 and the last is a virtual end task j=J i , the R&D department of project i has a total of M i Multi-skilled R&D personnel, where x ijm =1 means employee m can handle R&D task A ij , otherwise 0, for each item i, use o ij To indicate all R&D tasks that can be completed ij The collection of R&D personnel, namely

[0167] Mathematical model building module, used to build a complete mathematical model of the collaborative scheduling method;

[0168] The complete mathematical model includes:

[0169] (1) Local decision-making model for project agents to optimize resource scheduling within projects:

[0170]

[0171]

[0172]

[0173]

[0174]

[0175]

[0176]

[0177]

[0178]

[0179] y ijmt ∈{0,1},S ij ≥0

[0180] in, Indicates the Jth item of the i-th item i The completion time of a task, t ijmt represents the decision variable, which converts task A at time t ij When assigned to employee m, it is equal to 1, otherwise it is equal to 0, q ij Indicates o ij The number of R&D personnel in ij Indicates R&D task A ij Pay employees actual wages, ca ij Indicates R&D task A ij Pay employees a standard salary, m represents the capability coefficient of R&D personnel m, d ij Indicates R&D task A ij The actual construction period, da ij Indicates R&D task A ij The standard construction period, S ij Indicates R&D task A ij The start time, f ij Indicates R&D task A ij End time of

[0181] (2) Global decision-making model for resource allocation and coordination among projects by coordination agents:

[0182] min Cmax

[0183]

[0184]

[0185] B i ≥0,

[0186] Among them, C max represents the completion time of all distributed projects, B i represents the budget of the i-th R&D project;

[0187] The initial scheduling scheme output module is used to design a heuristic algorithm to generate the initial scheduling scheme S according to the structured properties;

[0188] According to the two structural properties, a heuristic algorithm is designed to generate a better initial scheduling solution S, which improves the convergence speed and solution quality of the subsequent intelligent optimization algorithm.

[0189] The two structural properties include:

[0190] Property 1: For the distributed multi-R&D project collaborative scheduling sub-problem, consider that the same employee needs to handle two parallel R&D tasks A at the same time ij and A in , and will not exceed the funding budget of project i, in order to minimize the completion time of R&D project i, the project manager needs to prioritize the tasks with the smallest latest completion time;

[0191] Property 2: For a given R&D personnel allocation plan for the distributed multi-R&D project collaborative scheduling sub-problem, when the following conditions are met, the project manager will assign task A on the critical path to ij Assigned R&D personnel m Replaced with a more powerful p n Only in this way can the completion time of project i be effectively shortened;

[0192] The specific steps of the heuristic algorithm in the initial scheduling scheme output module are:

[0193] S31: Calculate all tasks A in project i ij The earliest start time and the latest completion time of these tasks are assigned to the R&D personnel p who need the least salary according to property 2. m ;

[0194] S32: Generate a task list using property 1 and the minimum time difference principle;

[0195] S33: Decode the task list using a serial scheduling generation scheme to obtain the maximum completion time of project i;

[0196] S34: Calculate the critical path of the solution and the total time difference of each task;

[0197] S35: Sort the tasks on the non-critical path in descending order according to the total time difference, and replace the R&D personnel of the tasks on the critical path one by one. If property 2 is satisfied, go to S31; otherwise, output the result.

[0198] The variable neighborhood search algorithm module is used to design an adaptive variable neighborhood search algorithm based on the initial solution S generated by the heuristic algorithm to generate the final scheduling solution;

[0199] Design an adaptive variable neighborhood search algorithm that can adaptively change the neighborhood search structure, expand the search range in the neighborhood in the later stage of the algorithm operation, and improve the efficiency of solving distributed multi-mode and multi-skill project scheduling sub-problems of different scales;

[0200] The specific steps of an adaptive variable neighborhood search algorithm in the variable neighborhood search algorithm module are as follows:

[0201] S41: using the initial solution S of the heuristic algorithm as the initial solution of the adaptive variable neighborhood search algorithm;

[0202] S42: Set the maximum number of iterations to I max , let k = 1; I = 1;

[0203] S43: When k≤k max , perform k perturbations on the initial solution S and obtain a feasible solution S';

[0204] S44: Perform the kth neighborhood search on the feasible solution S' to obtain the local optimal solution S'';

[0205] S45: When S' is better than S, then S' = S, k = 1, I = I + 1; otherwise k = k + 1, I = I + 1;

[0206] S46: When the number of iterations ends, output S and end the algorithm;

[0207] The encoding scheme of the adaptive variable neighborhood search algorithm is as follows: first, for each sub-project, this paper adopts a two-dimensional encoding method S = (X, M), where the task dimension vector X = (0, ..., g, ..., n + 1) is used to represent the order in which tasks start in the scheduling scheme. In project scheduling, the start of all tasks must satisfy the constraints of priority relationships. The employee dimension vector M = (0, ..., m, ..., 0) represents the employee assigned to the task dimension vector. The decoding method is the classic serial scheduling generation mechanism.

[0208] The global resource allocation module is used to design cooperative negotiation protocols to achieve reasonable allocation and scheduling of global resources;

[0209] After outputting the optimal solution for each project, design negotiation agreements to achieve a reasonable allocation of global resources;

[0210] The negotiation protocol is a process of solving the global resource allocation problem. Each project agent makes local decisions based on the available budget allocated to it. The project agents make allocations one by one based on the project priority sequence π negotiated in advance, where the funding budget value B of each project i is i It is determined by the allocation strategy of the project agent in the constraints. It is worth noting that if all project managers choose to share the capital budget under perfect competition instead of cooperating by following the given agreement, each project agent may only obtain the minimum capital budget from the project agent, which can only ensure that each task in project i is allocated to the employee who needs the least salary. At this time, the capital budget is usually not fully utilized, resulting in a longer total project time span; once all project agents choose to cooperate with the project agent, during the negotiation process, each project agent uses the available budget for local scheduling in the order of negotiation, and the project agent will disclose the budget surplus B s , each project manager will shorten the completion time of the project by shortening the duration of tasks that occupy more budget on the critical path, and all agents have no motivation to unilaterally avoid cooperation because they have no way to obtain additional benefits.

[0211] like Figure 3-8 As shown in the figure, the convergence curves of AVNS, PSO, BA and TS in 6 examples are shown. For small-scale cases, such as n=20, 40, 60, the convergence effects of PSO, BA and TS are not much different from AVNS. However, as the problem scale increases, such as n=100, 120, 150, these three algorithms tend to fall into local optimality and usually obtain poor scheduling solutions. In contrast, AVNS can jump out of local convergence and continue to find a better solution. According to the above experimental results, it can be inferred that the designed AVNS has obvious advantages in both solution quality and algorithm convergence.

[0212] Based on the above analysis, it can be shown that the adaptive variable neighborhood search algorithm (AVNS) can efficiently solve the distributed multi-project collaborative scheduling problem.

[0213] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. Considering the distributed multi-project collaborative scheduling method under the constraints of multi-skill resources, the characteristics are as follows: The scheduling method comprises: S1: Obtain distributed multi-project R&D task data; High-end equipment R&D includes N distributed R&D projects in different geographical locations. Each project is scheduled by a project agent that can make independent decisions, and these projects share the total budget B given by the enterprise. In the distributed environment, each project i (i = 1, 2, ..., N) decomposes the multi-level R&D tasks into J i + 1 non-preemptive meta-R&D task, the first of which is a virtual start task j=0 and the last is a virtual end task j=J i , the R&D department of project i has a total of M i Multi-skilled R&D personnel, where x ijm =1 means employee m can handle R&D task A ij , otherwise 0, for each item i, use o ij To indicate all R&D tasks that can be completed ij The collection of R&D personnel, namely S2: Construct a complete mathematical model of the collaborative scheduling method; The complete mathematical model includes: (1) Local decision-making model for project agents to optimize resource scheduling within projects: and ijmt ∈{0,1},S ij ≥0 in, Indicates the Jth item of the i-th item i The completion time of a task, y ijmt represents the decision variable, which converts task A at time t ij When assigned to employee m, it is equal to 1, otherwise it is equal to 0, q ij Indicates o ij The number of R&D personnel in ij Indicates R&D task A ij Pay employees actual wages, ca ij Indicates R&D task A ij Pay employees a standard salary, m represents the capability coefficient of R&D personnel m, d ij Indicates R&D task A ij The actual construction period, da ij Indicates R&D task A ij The standard construction period, S ij Indicates R&D task A ij The start time, f ij Indicates R&D task A ij End time of (2) Global decision-making model for resource allocation and coordination among projects by coordination agents: my C max Among them, C max represents the completion time of all distributed projects, B i represents the budget of the i-th R&D project; S3: Based on the structured properties, a heuristic algorithm is designed to generate the initial scheduling solution S; According to the two structural properties, a heuristic algorithm is designed to generate a better initial scheduling solution S, which improves the convergence speed and solution quality of the subsequent intelligent optimization algorithm. The two structural properties include: Property 1: For the distributed multi-R&D project collaborative scheduling sub-problem, consider that the same employee needs to handle two parallel R&D tasks A at the same time ij and A in , and will not exceed the funding budget of project i, in order to minimize the completion time of R&D project i, the project manager needs to prioritize the tasks with the smallest latest completion time; Property 2: For a given R&D personnel allocation plan for the distributed multi-R&D project collaborative scheduling sub-problem, when the following conditions are met, the project manager will assign task A on the critical path to ij Assigned R&D personnel m Replaced with a more powerful p n Only in this way can the completion time of project i be effectively shortened; S4: Based on the initial solution S generated by the heuristic algorithm, an adaptive variable neighborhood search algorithm is designed to generate the final scheduling solution; Design an adaptive variable neighborhood search algorithm that can adaptively change the neighborhood search structure, expand the search range in the neighborhood in the later stage of the algorithm operation, and improve the efficiency of solving distributed multi-mode and multi-skill project scheduling sub-problems of different scales; S5: Design cooperative negotiation protocols to achieve reasonable allocation and scheduling of global resources; After outputting the optimal solution for each project, design negotiation agreements to achieve a reasonable allocation of global resources; The negotiation protocol is a process of solving the global resource allocation problem. Each project agent makes local decisions based on the available budget allocated to it. The project agents make allocations one by one based on the project priority sequence π negotiated in advance, where the funding budget value B of each project i is i It is determined by the allocation strategy of the project agent in the constraints. It is worth noting that if all project managers choose to share the capital budget under perfect competition instead of cooperating by following the given agreement, each project agent may only obtain the minimum capital budget from the project agent, which can only ensure that each task in project i is allocated to the employee who needs the least salary. At this time, the capital budget is usually not fully utilized, resulting in a longer total project time span; once all project agents choose to cooperate with the project agent, during the negotiation process, each project agent uses the available budget for local scheduling in the order of negotiation, and the project agent will disclose the budget surplus B s , each project manager will shorten the completion time of the project by shortening the duration of tasks that occupy more budget on the critical path, and all agents have no motivation to unilaterally avoid cooperation because they have no way to obtain additional benefits.

2. The distributed multi-project collaborative scheduling method considering multi-skill resource constraints according to claim 1 is characterized in that: The specific steps of the heuristic algorithm in S3 are: S31: Calculate all tasks A in project i ij The earliest start time and the latest completion time of these tasks are assigned to the R&D personnel p who need the least salary according to property 2. m ; S32: Generate a task list using property 1 and the minimum time difference principle; S33: Decode the task list using a serial scheduling generation scheme to obtain the maximum completion time of project i; S34: Calculate the critical path of the solution and the total time difference of each task; S35: Sort the tasks on the non-critical path in descending order according to the total time difference, and replace the R&D personnel of the tasks on the critical path one by one. If property 2 is satisfied, go to S31; otherwise, output the result.

3. The distributed multi-project collaborative scheduling method considering multi-skill resource constraints according to claim 1 is characterized in that: The specific steps of the adaptive variable neighborhood search algorithm in S4 are: S41: using the initial solution S of the heuristic algorithm as the initial solution of the adaptive variable neighborhood search algorithm; S42: Set the maximum number of iterations to I max , let k = 1; I = 1; S43: When k≤k max , perform k perturbations on the initial solution S and obtain a feasible solution S'; S44: Perform the kth neighborhood search on the feasible solution S' to obtain the local optimal solution S''; S45: When S' is better than S, then S' = S, k = 1, I = I + 1; otherwise k = k + 1, I = I + 1; S46: When the number of iterations ends, output S and end the algorithm.

4. The distributed multi-project collaborative scheduling method and system considering multi-skill resource constraints according to claim 1 is characterized in that: The encoding scheme of the adaptive variable neighborhood search algorithm is as follows: first, for each sub-project, this paper adopts a two-dimensional encoding method S = (X, M), where the task dimension vector X = (0, ..., g, ..., n+1) is used to represent the order in which tasks start in the scheduling scheme. In project scheduling, the start of all tasks must satisfy the constraints of priority relationships. The employee dimension vector M = (0, ..., m, ..., 0) represents the employee assigned to the task dimension vector. The decoding method is the classic serial scheduling generation mechanism.

5. Consider a distributed multi-project collaborative scheduling system with limited multi-skill resources, characterized by: The scheduling system specifically includes: Task data acquisition module, used to obtain distributed multi-project R&D task data; High-end equipment R&D includes N distributed R&D projects in different geographical locations. Each project is scheduled by a project agent that can make independent decisions, and these projects share the total budget B given by the enterprise. In the distributed environment, each project i (i = 1, 2, ..., N) decomposes the multi-level R&D tasks into J i + 1 non-preemptive meta-R&D task, the first of which is a virtual start task j=0 and the last is a virtual end task j=J i , the R&D department of project i has a total of M i Multi-skilled R&D personnel, where x ijm =1 means employee m can handle R&D task A ij , otherwise 0, for each item i, use o ij To indicate all R&D tasks that can be completed ij The collection of R&D personnel, namely Mathematical model building module, used to build a complete mathematical model of the collaborative scheduling method; The complete mathematical model includes: (3) Local decision-making model for project agents to optimize resource scheduling within projects: and ijmt ∈{0,1},S ij ≥0 in, Indicates the Jth item of the i-th item i The completion time of a task, y ijmt represents the decision variable, which converts task A at time t ij When assigned to employee m, it is equal to 1, otherwise it is equal to 0, q ij Indicates o ij The number of R&D personnel in ij Indicates R&D task A ij Pay employees actual wages, ca ij Indicates R&D task A ij Pay employees a standard salary, m represents the capability coefficient of R&D personnel m, d ij Indicates R&D task A ij The actual construction period, da ij Indicates R&D task A ij The standard construction period, S ij Indicates R&D task A ij The start time, f ij Indicates R&D task A ij End time of (4) Global decision-making model for resource allocation and coordination among projects by coordination agents: my C max Among them, C max represents the completion time of all distributed projects, B i represents the budget of the i-th R&D project; The initial scheduling scheme output module is used to design a heuristic algorithm to generate the initial scheduling scheme S according to the structured properties; According to the two structural properties, a heuristic algorithm is designed to generate a better initial scheduling solution S, which improves the convergence speed and solution quality of the subsequent intelligent optimization algorithm. The two structural properties include: Property 1: For the distributed multi-R&D project collaborative scheduling sub-problem, consider that the same employee needs to handle two parallel R&D tasks A at the same time ij and A in , and will not exceed the funding budget of project i, in order to minimize the completion time of R&D project i, the project manager needs to prioritize the tasks with the smallest latest completion time; Property 2: For a given R&D personnel allocation plan for the distributed multi-R&D project collaborative scheduling sub-problem, when the following conditions are met, the project manager will assign task A on the critical path to ij Assigned R&D personnel m Replaced with a more powerful p n Only in this way can the completion time of project i be effectively shortened; The variable neighborhood search algorithm module is used to design an adaptive variable neighborhood search algorithm based on the initial solution S generated by the heuristic algorithm to generate the final scheduling solution; Design an adaptive variable neighborhood search algorithm that can adaptively change the neighborhood search structure, expand the search range in the neighborhood in the later stage of the algorithm operation, and improve the efficiency of solving distributed multi-mode and multi-skill project scheduling sub-problems of different scales; The global resource allocation module is used to design cooperative negotiation protocols to achieve reasonable allocation and scheduling of global resources; After outputting the optimal solution for each project, design negotiation agreements to achieve a reasonable allocation of global resources; The negotiation protocol is a process of solving the global resource allocation problem. Each project agent makes local decisions based on the available budget allocated to it. The project agents make allocations one by one based on the project priority sequence π negotiated in advance, where the funding budget value B of each project i is i It is determined by the allocation strategy of the project agent in the constraints. It is worth noting that if all project managers choose to share the capital budget under perfect competition instead of cooperating by following the given agreement, each project agent may only obtain the minimum capital budget from the project agent, which can only ensure that each task in project i is allocated to the employee who needs the least salary. At this time, the capital budget is usually not fully utilized, resulting in a longer total project time span; once all project agents choose to cooperate with the project agent, during the negotiation process, each project agent uses the available budget for local scheduling in the order of negotiation, and the project agent will disclose the budget surplus B s , each project manager will shorten the completion time of the project by shortening the duration of tasks that occupy more budget on the critical path, and all agents have no motivation to unilaterally avoid cooperation because they have no way to obtain additional benefits.

6. The distributed multi-project collaborative scheduling system considering multi-skill resource constraints according to claim 5 is characterized in that: The specific steps of the heuristic algorithm in the initial scheduling scheme output module are: S31: Calculate all tasks Ai in project i j The earliest start time and the latest completion time of these tasks are assigned to the R&D personnel p who need the least salary according to property 2. m ; S32: Generate a task list using property 1 and the minimum time difference principle; S33: Decode the task list using a serial scheduling generation scheme to obtain the maximum completion time of project i; S34: Calculate the critical path of the solution and the total time difference of each task; S35: Sort the tasks on the non-critical path in descending order according to the total time difference, and replace the R&D personnel of the tasks on the critical path one by one. If property 2 is satisfied, go to S31; otherwise, output the result.

7. The distributed multi-project collaborative scheduling system considering multi-skill resource constraints according to claim 5 is characterized in that: The specific steps of an adaptive variable neighborhood search algorithm in the variable neighborhood search algorithm module are as follows: S41: using the initial solution S of the heuristic algorithm as the initial solution of the adaptive variable neighborhood search algorithm; S42: Set the maximum number of iterations to I max , let k = 1; I = 1; S43: When k≤k max , perform k perturbations on the initial solution S and obtain a feasible solution S′; S44: Perform the kth neighborhood search on the feasible solution S′ to obtain the local optimal solution S″; S45: When S″ is better than S, then S″=S, k=1, I=I+1; otherwise k=k+1, I=I+1; S46: When the number of iterations ends, output S and end the algorithm.

8. The distributed multi-project collaborative scheduling system considering multi-skill resource constraints according to claim 5 is characterized by: The encoding scheme of the adaptive variable neighborhood search algorithm is as follows: first, for each sub-project, this paper adopts a two-dimensional encoding method S = (X, M), where the task dimension vector X = (0, ..., g, ..., n+1) is used to represent the order in which tasks start in the scheduling scheme. In project scheduling, the start of all tasks must satisfy the constraints of priority relationships. The employee dimension vector M = (0, ..., m, ..., 0) represents the employee assigned to the task dimension vector. The decoding method is the classic serial scheduling generation mechanism.

Citation Information

Cited By

  • Public testing resource scheduling method based on multi-level random characteristic particle swarm optimization

    CN119647890A

  • Enterprise management optimization method and system of big data enabling ERP

    CN120087557A

  • Enterprise management optimization methods and systems empowered by big data ERP

    CN120087557B